Professional Documents
Culture Documents
Introduction To Air-Insulated Substations: Koji Kawakita
Introduction To Air-Insulated Substations: Koji Kawakita
10
Koji Kawakita
Contents
10.1 Site Location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145
10.2 Site Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145
10.3 Conceptual Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 146
10.4 Project Management Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 147
An air-insulated substation (AIS) is one where the main circuit potential is insulated
from the ground by air using porcelain or composite insulators and/or bushings. AIS
is fully composed from air-insulated technology components such as circuit brea-
kers, disconnecting switches (disconnectors), surge arrestors, instrument trans-
formers, power transformers, capacitors, busbars, and so on, and the components
are connected to each other by stranded flexible conductors, tubes, or buried power
cables. AIS is the most common type of substation, accounting for more than 70% of
substations all over the world.
Therefore, electrical engineers are recommended to develop a good understand-
ing of AIS design before learning about gas-insulated switchgear (GIS) and mixed
technology switchgear (MTS), which are developed based on AIS technologies. The
pros and cons of using either AIS, GIS, or MTS technologies are described in
CIGRE technical brochure #390 and in Part D.
This Part B describes the issues to be considered in the design and construction of
a new AIS substation. Figure 10.1 shows the general work flow for establishment of
any new substation and applies also to GIS and MTS as well as AIS.
K. Kawakita (*)
Engineering Strategy and Development, Chubu Electric Power Co., Inc., Nagoya, Japan
e-mail: Kawakita.Kouji@chuden.co.jp
IS NO
REINFORCEMENT
REQUIRED?
YES
CONSIDER
IS A NEW NO OTHER MEANS
SUBSTATION
OF
TECHNICAL, REQUIRED?
REINFORCEMENT
ENVIRONMENTAL AND
COMMERCIAL POLICY YES
PREPARE
PRELIMINARY * GENERAL LOCATION,
PLANS * LINE DIRECTIONS, END
SOIL INVESTIGATIONS,
TRANSPORT ROUTES.
DETERMINE
GENERAL
SITE
DESIGN
LOCATION
DETERMINE
SPECIFIC EXACT SITE
DESIGN LOCATION
& ORIENTATION
PREPARE
MAIN DETERMINE
CONNECTIONS SUBSTATION
& PROTECTION LAYOUT
DIAGRAM
PREPARE
CARRY OUT
CIRCUIT
CIVIL DESIGN
DIAGRAMS
WORK
& SOFTWARE
PREPARE END
WIRING
CIVIL
DIAGRAMS
WORKS
& CABLE
SCHEDULE
INSTALL TEST,
PLANT & COMMISSION,
EQUIPMENT TAKEOVER
The choice of a site location for a new substation is a compromise between technical,
economic, environmental, and administrative factors.
In simple terms the problem is often to find the most suitable location within a
geographic region where the substation can be built, given the total number of
circuits, the destination of the lines, and the rated nominal power of the transformers.
Typically, in the whole region, climate and altitude are almost the same, but
technical and environmental factors vary depending on the site location.
The first step is to locate the range of possible sites, which are as level as possible,
with enough available area, at reasonable cost; with acceptable access for heavy
transport, within the general required location; and without any major restrictions on
line corridors, where the substation can be erected with minimum environmental
impact.
It is often advantageous to locate sites near to existing line corridors or even at
crossing points. Sometimes such places simply do not exist, and the choice will be
confined to places that have only some of the above characteristics.
Once the possible sites have been located, an analysis is then made for all the
technical and environmental aspects of each one, including costs, potential environ-
mental impacts, and the preventive or corrective measures that can be taken to avoid
or reduce them. It is also necessary to assess the likely social acceptance of the
project.
This analysis then provides the criteria for deciding on the most suitable substa-
tion site, bearing in mind the degree of feasibility and the project cost of each
alternative. If no suitable site is found, the process may be reinitiated within another
general area.
Further information about site location is given in CIGRE technical brochure
#161.
In the choice of a site layout for a substation, the number of outgoing lines or feeders
of different voltage levels, the number of main transformers, the required busbar
configurations, and the possibility of future extension as well as compensating
equipment options need to be considered carefully, not only for the original instal-
lation period but also for the needs of the future. It should be noted that the lifetime
of the substation may extend beyond 50 years.
It is very important to allow sufficient space for future extension. Sophisticated
network planning may be needed to estimate the necessary reserve space to
accommodate the ultimate substation layout. If no better design approach exists,
then allowing 100% reserve of outgoing feeders may be used as an estimate. The
space required depends essentially on the present and future function of the
substation.
146 K. Kawakita
The conceptual design establishes the key parameters for the substation, and so
careful attention must be paid at this design stage to ensure that the design
addresses the key concerns of all stakeholders. The conceptual design should
reflect the general business development guidelines and maintenance strategies
of the network operator and should be deduced project-wise from a long-term
orientated company template.
From another viewpoint, conceptual engineering should lay down all the basic
specifications that have a major influence on network cost, network reliability,
and societal acceptance. On the other hand, conceptual engineering should also
offer the opportunity to stimulate competition among the potential service pro-
viders and should offer the network owner the flexibility to either carry out the
detail engineering in-house or to outsource it, depending on the availability of
resources.
10 Introduction to Air-Insulated Substations 147
• Basic elements
• Functions of the network
• Types of substation
• Structure of a substation
• Parameters determined by the network
• Main equipment parameters
• Fault clearing time with respect to system requirements
• Planning of a substation
• General location
• Extent of the substation
• Busbar configurations
• Fault current levels
• Neutral point earthing
• Control in general
• Protection in general
• Maintenance requirements
• Typical switching arrangements
• Service continuity
• Choice of switching arrangements
During the normal execution of a substation project, these three points may not
always be planned or performed in series since the work is done by many concerned
people and restrictions of social requirements or regulation may apply. In the course
of the project, there could be many natural gaps between planned activities and
actual work sequence. A good project management plan must account for such gaps
and for out-of-sequence activities. The challenge in project execution is to
148 K. Kawakita
consistently find a suitable way to minimize the gaps in activities and move the
project forward smoothly.
Project management requires clear understanding, imagining, and evaluation of
any influences that may arise due to out-of-sequence events for the above three key
points. In such instances, the success of the project depends on the ability to take
leadership and realign the project team efforts to the most effective path. When it is
difficult to determine the effective path, the priority of events should always be
considered in the order of flow/time/engineering.
More information about project management planning is given in CIGRE tech-
nical brochure 439. Although this brochure deals with turnkey projects, the basic
concept is applicable to all types of substation projects.