Preparations:
(1) Prior to Dry-docking, information from Head Office must be
taken the estimated Dry-docking time, duration and whether annual dry
docking or special dry docking.
(2) Preliminary purpose "repair list" both for ship yard and
ship's staffs must be compiled.
(3) It according to the condition of machinery and under the
list of survey item.
On dry dock
To present at the bottom survey carried out by the class surveyor
with C/E; captain; C/O& ship repair manager.
Inspections & checks to be made all the jobs performed shipyard &
ship's staff .All the measurements & readings to be taken & recorded.
Assist Classification surveyor's visits and his subsequent surveys.
All repaired machinery parts measurement to be taken and recorded
after completion.
Stern tube wear down limits to be checked whether within limit or
not.
Rudder pintle wear down and jumping clearance limits to be checked
whether within limit or not.
As soon as after completion of docking repair, all sea valves must
be inspected very thoroughly for leakage.
As soon as dry-dock has filled up water and all the sea chests are
immersed properly, all the generator engines to be run and test, after
satisfaction, shore power to be cut off and own power to be cut in,
the time also to be recorded.
All leakage and abnormality to be corrected before leaving dry
dock.
M.E crank shaft deflection readings to be taken and recorded again
and compare with before ones to check any dispute.
3 G.E.K (January – 1993) QUES: 1