ID TaskTask Name Duration Start Finish % Predecessors

Mode Complete

1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21 0%
2 0%
3 POWER ISLAND 0%
4 Boiler 0%
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20 0%
6 Boiler Pressure Part Fabrication 0%
7 Drum HT 0%
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20 0%
9 Boiler Steam Drum Fitting Installation 0%
10 Boiler Main Tubes Installation 0%
11 Signages 0%
12 Boiler Non-Pressure Parts 0%
13 Boiler Structure, platform 0%
14 Boiler Structure Delivery 0%
15 Boiler Structure erection Wed 9/30/20 0%
16 Boiler House Top Structure Fabrication 0%
17 Boiler House Top Structure Delivery 0%
18 Boiler House Top Structure Erection 0%
19 Boiler House Roofing installation 0%
20 Blowdown Tank(M) 0%
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20 0%
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20 0% 21
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20 0%
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 11
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20 0% 24
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20 0% 25FF
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20 0%
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20 0%
29 Installation 0%
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20 0%
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20 0%
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20 0% 31
33 Flash Tank 0%
34 Flash tank assembly delivery Wed 9/30/20 0%
35 Flash tank assembly installation 0%
36 Flash tank fittings installation 0%
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20 0%
38 Boiler Site Installation Wed 9/30/20 0%
39 Structure & Frame 0%
40 Travelling Grate, Hopper 0%
41 Travelling Grate/Stoker Installation 0%
42 Ash Hopper (under Stoker) Installation 0%
43 Ash Conveyor Plinth 0%
44 Ash Conveyor Delivery 0%
45 Ash Conveyor Installation 0%
46 Refractory Application 0%
47 Temperory support, Drum Lift, Alignment, Securing 0%
48 Generating Tube (818 tubes) Mon 9/7/20 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 12
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

49 Header set up, waterwall, Superheater 0%


50 1st Superheater Tubes Installation c/w Headers 0%
51 1st Superheater Fitting Installation 0%
52 2nd Superheater Tubes Installation c/w Headers 0%
53 2nd Superheater Fitting Installation 0%
54 Downcomers Installation 0%
55 Water Tubes & Membran Wall Installation 0%
56 Economizer, Steam connection pipes, supports 0%
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20 0%
58 Economizer assembly installation 0%
59 Economizer fitting installation 0%
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer 0%
61 Deaerator fitting installation 0%
62 CBD assembly Delivery 0%
63 CBD system installation 0%
64 CBD fittings installation 0%
65 Dust Collector Casing & accessories Wed 9/30/20 0%
66 Assemble fly ash dust collector frame assembly 0%
67 Dust Collector Inner pipe Outside Pipe Installation 0%
68 Dust Collector Guide Vane Damper Installation 0%
69 Rotary valve , hopper and casing Installation 0%
70 Steam Piping Installation c/w Insulation 0%
71 Air Duct Installation c/w Insulation 0%
72 Gas Duct Installation c/w Insulation 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 13
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

73 Accessories/fitings Installation 0%
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20 0%
75 Insulation and Boiler Outer Casing Application 0%
76 Boiler Outer Casing Finishing Paint Works 0%
77 Grating Installation 0%
78 HandRail Installation 0%
79 Sootblower Assembly Delivery 0%
80 Install Sootblower Frames and Hangers 0%
81 Assemble Long Retractable Sootblowers parts including 0%
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including 0%
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and 0%
drain valves
84 Install sootblower fittings 0%
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20 0%
86 Fuel Feeder Delivery 0%
87 Fuel Feeder Installation 0%
88 Service Silo Delivery 0%
89 Service Silo Installation 0%
90 Boiler Draft System Wed 9/30/20 0%
91 FD/ID Fans,Air Heater,Ducting Site Installation 0%
92 ID FAN 0%
93 Centering & Levelling 0%

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 14
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

94 Anchor Bolt Cementing 0%


95 Base Grouting 0%
96 Upper Casing Installation 0%
97 Suction Cone Installation 0%
98 Inlet Damper Installation 0%
99 Primary Force Draft Fan 0%
100 Centering & Levelling 0%
101 Anchor Bolt Cementing 0%
102 Base Grouting 0%
103 Upper Casing Installation 0%
104 Suction Cone Installation 0%
105 Inlet Damper Installation 0%
106 Silencer Installation 0%
107 Secondary Force Draft Fan 0%
108 Centering & Levelling 0%
109 Anchor Bolt Cementing 0%
110 Base Grouting 0%
111 Upper Casing Installation 0%
112 Suction Cone Installation 0%
113 Inlet Damper Installation 0%
114 Silencer Installation 0%
115 Chimney & CEMS 0%
116 Chimney Delivery Tue 9/15/20 0%
117 Chimney Stack Site Installation 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 15
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

118 Lifting, Centering & Levelling 0%


119 Anchor Bolt Tightening 0%
120 Erection 0%
121 CEMS COMPLETE Tue 9/22/20 0%
122 Steam Turbogenerator 0%
123 STG Site Installation 0%
124 Gland Sealing Condenser installation 0%
125 Reducton gear installation 0%
126 Alignment 0%
127 Oil unit installation 0%
128 Prefab pipes & Turbine cover installation 0%
129 Observation Gantry Fabrication 0%
130 Observation Gantry Installation 0%
131 Staircase & railing Fabrication 0%
132 Staircase & railing Installation 0%
133 Structure Erection 0%
134 Roofing Installation 0%
135 Cladding Installation 0%
136 Gutter Installation 0%
137 Floor Finishing 0%
138 Louvers Installation 0%
139 Overhead crane Installation 0%
140 ST-GB-GEN Lifting 0%
141 ST Centering & Levelling 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 16
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

142 Gearbox Centering & Levelling 0%


143 Generator Centering & Levelling 0%
144 STG Anchor Bolt Cementing 0%
145 STG Base Grouting 0%
146 ST - GB Alignment 0%
147 GB - Generator Alignment 0%
148 ST Piping Installation 0%
149 ST Insulation 0%
150 Lube Oil Unit Lifting 0%
151 Lube Oil Unit Centering & Levelling 0%
152 Lube Oil Unit Anchor Bolt Cementing 0%
153 Lube Oil Unit Base Grouting 0%
154 Steam Air Ejector Delivery 0%
155 Steam Air Ejector Installation 0%
156 Turbine Control Panel Installation (TCP) 0%
157 Cable Installation 0%
158 BALANCE OF PLANT 0%
159 Cooling Water System 0%
160 Vacumn Surface Condenser & Auxiliary 0%
161 VSC Factory Acceptance Test 0%
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20 0%
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20 0% 162
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20 0% 162
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20 0% 162
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 17
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20 0% 162
167 Air Cool Heat Exchanger 0%
168 Heat Exchanger Delivery Mon 9/7/20 0%
169 Heat Exchanger Site Installation 0%
170 ACHE Lifting & Positioning 0%
171 Main Cooling Water Pump Plinth 0%
172 Main Cooling Water Pump Delivery Wed 9/30/20 0%
173 Main Cooling Water Pump Installation 0%
174 Main Cooling Water Pump Anchor Bolt Cementing 0%
175 Main Cooling Water Pump Base Grouting 0%
176 Main Cooling Water Piping 0%
177 Main Cooling Water Valves/Fitting Installation 0%
178 Cooling Tower 0%
179 Cooling Tower Delivery Mon 9/28/20 0%
180 Cooling Tower Site Installation 0%
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20 0%
182 Auxiliary Cooling Water Pump Installation 0%
183 ESP 1 day Sat 9/12/20 Sat 9/12/20 0%
184 ESP Delivery Sat 9/12/20 0%
185 ESP Site Installation 0%
186 ESP Structure/parts Delivery 0%
187 ESP Steel Support Structure Erection and Assembly 0%
188 Install Collecting & Emitting Plates/Electrode 0%
189 Install Rapping Hammer and Accessories 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 18
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

190 Install Inner and Outer Casing 0%


191 Install Ash Hopper 0%
192 Install Rotary Valves 0%
193 Install Transformer Rectifiers 0%
194 Install Inlet and Outlet Expansion Joint 0%
195 Install Inlet and Outlet Dampers 0%
196 Install gratings and railings 0%
197 Install all accessories and Fittings 0%
198 Fuel Handling And Ash Delivery System 0%
199 Fuel Handling 0%
200 Conveyor 0%
201 Fuel Handling Delivery Thu 10/1/20 0%
202 Fuel Handling Site Installation 0%
203 Fuel Conveyor (FC-2&3) Delivery 0%
204 Fuel Conveyor (FC-2&3) Installation 0%
205 Silo Diverter Valve Delivery 0%
206 Silo Diverter Valve Installation 0%
207 Silo Conveyor Structure Delivery 0%
208 Silo Conveyor Delivery (SC - 1&2) 0%
209 Silo Conveyor Structure Erection 0%
210 Silo Conveyor Installation (SC - 1&2) 0%
211 Biomass Silos 0%
212 Biomass Silo Delivery 0%
213 Biomass Silo Site Installation 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 19
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

214 Fuel Silo#1 Delivery Fri 9/25/20 0%


215 Fuel Silo#1 Installation 0%
216 Fuel Silo#2 Delivery 0%
217 Fuel Silo#2 Installation 0%
218 Fuel Silo#1 Rotor Delivery 0%
219 Fuel Silo#1 Rotor Installation 0%
220 Fuel Silo#2 Rotor Delivery 0%
221 Fuel Silo#2 Rotor Installation 0%
222 Ash System 0%
223 Ash Tank, Conveyor Design & Engineering 0%
224 Ash Tank, conveyor Manufacturing 0%
225 Ash Tank Delivery Thu 10/15/20 0%
226 Ash Tank Site Installation 0%
227 Bottom Ash Tank Design & Engineering 0%
228 Bottom Ash Tank, conveyor Manufacturing 0%
229 Bottom Ash Tank Delivery Thu 10/15/20 0%
230 Bottom Ash Tank Site Installation 0%
231 Structure Delivery 0%
232 Structure erection 0%
233 Tank Lifting/Installation 0%
234 Rotary valve installation 0%
235 Ash Conveyor Delivery 0%
236 Ash Conveyor Structure Delivery 0%
237 Ash Conveyor Structure Erection 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 20
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

238 Ash Conveyor Installation 0%


239 Screw Conveyor Delivery 0%
240 Screw Conveyor Structure Delivery 0%
241 Screw Conveyor Structure Erection 0%
242 Screw Conveyor Installation 0%
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20 0%
244 Pumps Delivery Wed 9/30/20 0%
245 Pumps Site Installation 0%
246 Demin Water System 0%
247 Demin System 0%
248 Demin Water System Design & Engineering 0%
249 Demin Water System Manufacturing 0%
250 Demin Water System Delivery Tue 9/15/20 0%
251 Booster Pump Delivery 0%
252 Activated Carbon Filter Delivery 0%
253 Cation Exchange Filter Delivery 0%
254 Anion Exchange Filter Delivery 0%
255 HCL Tank Delivery 0%
256 NaOH Tank Delivery 0%
257 Boiler Compound Tank Delivery 0%
258 pH Chemical Tank Delivery 0%
259 Oxygen Scavenger Tank Delivery 0%
260 Anti Slime Tank Delivery 0%
261 Anti Scale Tank Delivery 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 21
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

262 pH Metering Pump Delivery 0%


263 Make Up Water Pump Delivery 0%
264 Demin Water Make Up Pump Delivery 0%
265 HP Boiler Dosing Pump Delivery 0%
266 LP Boiler Dosing Pump Delivery 0%
267 Anti Slime Dosing Pump Delivery 0%
268 Anti Scale Dosing Pump Delivery 0%
269 Demin Water System Site Installation 0%
270 Booster Pump Installation 0%
271 Activated Carbon Filter Installation 0%
272 Cation Exchange Filter Installation 0%
273 Anion Exchange Filter Installation 0%
274 HCL Tank Installation 0%
275 NaOH Tank Installation 0%
276 Boiler Compound Tank Installation 0%
277 pH Chemical Tank Installation 0%
278 Oxygen Scavenger Tank Installation 0%
279 Anti Slime Tank Installation 0%
280 Anti Scale Tank Installation 0%
281 pH Metering Pump Installation 0%
282 Make Up Water Pump Installation 0%
283 Demin Water Make Up Pump Installation 0%
284 HP Boiler Dosing Pump Installation 0%
285 LP Boiler Dosing Pump Installation 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 22
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

286 Anti Slime Dosing Pump Installation 0%


287 Anti Scale Dosing Pump Installation 0%
288 Demin Tank Design & Engineering 0%
289 Demin Tank Manufacturing 0%
290 Demin Tank Delivery Tue 9/15/20 0%
291 Demin Tank Site Installation 0%
292 Neutralization Tank Delivery 0%
293 Neutralization Tank Installation 0%
294 Valves/Fitting Installation 0%
295 Raw Water System 0%
296 Raw Water Tank Design & Engineering 0%
297 Raw Water Tank Manufacturing 0%
298 Raw Water Tank Delivery Tue 9/15/20 0%
299 Raw Water Tank Site Installation 0%
300 Neutralization System 0%
301 Plant Neutralization System Design & Engineering 0%
302 Plant Neutralization System Manufacturing 0%
303 Neutralizing System Delivery Wed 9/30/20 0%
304 Site Installation 0%
305 Diesel Oil Tank 0%
306 Diesel Oil Tank Design & Engineering 0%
307 Diesel Oil Tank Manufacturing 0%
308 Diesel Oil Tank Delivery 0%
309 Diesel Oil Tank Site Installation 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 23
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

310 Plant Engineering & Interconnection Piping 0%


311 Plant Interconnecting Pipes Design & Engineering 0%
312 Instrumentation engineering 0%
313 Instrumentation Manufacturing 0%
314 Plant Interconnecting Pipes Manufacturing 0%
315 Instrumentation Delivery Wed 9/30/20 0%
316 Plant Interconnecting Pipes Delivery Sun 9/27/20 0%
317 Site Installation Mon 10/5/20 0%
318 Power Island Electrical System 0%
319 Power Island Electrical System Design & Engineering 0%
320 Panel & Switch gear Manufacturing 0%
321 Material procurement 0%
322 Equipment & accessories delivery Sun 10/4/20 0%
323 Site Installation 0%
324 Grid Interconnection System (GIS) 0%
325 Electrical System Design & Engineering 0%
326 Transformer, Switch Gear, Equipment Manufacturing 0%
327 Plant Electrical System Delivery 0%
328 33kV & 11kV Cable Installation 0%
329 Sub station & Plant Site installation 0%
330 DCS 0%
331 DCS Delivery Wed 9/23/20 0%
332 DCS Site Installation 0%
333 Compressed Air System 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 24
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

334 Air Dryer Compressor Delivery Fri 9/25/20 0%


335 Air Dryer Compressor Site Installation 0%
336 Overhead Crane 0%
337 Overhead Crane Design & Engineering 0%
338 Overhead Crane Manufacturing 0%
339 Overhead Crane Delivery Fri 9/25/20 0%
340 Overhead Crane Site Installation 0%
341 CIVIL, STRUCTURAL & BUILDING 0%
342 Civil and Structural Work 0%
343 Turbine Hall & Switchboard Room 0%
344 GROUND FLOOR SLAB AND APRON 0%
345 FRAME 0%
346 Frame, column, 2nd Floor 0%
347 Column 0%
348 Upper floor beam 0%
349 Overhead Crane 0%
350 UPPER FLOOR 0%
351 STAIRCASES, STEPS AND FINISHES 0%
352 ROOFS Sun 9/13/20 0%
353 Roofing/Cladding,Structure 0%
354 ROOF TRUSSES 0%
355 Gutter 0%
356 Purlin 0%
357 ROOF COVERING 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 25
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

358 rainwater down pipe 0%


359 soffit of flat roof 0%
360 WALL Fri 9/18/20 0%
361 brickwall 0%
362 External wall cladding 0%
363 External wall louvres cladding 0%
364 External shera board wall cladding 0%
365 iron purlin 0%
366 WINDOWS AND VENTS Fri 9/25/20 0%
367 FRAME 0%
368 Glass 0%
369 louvres window 0%
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20 0%
371 Door 0%
372 Hinges 0%
373 Lockset 0%
374 door stopper 0%
375 Sliding Door 0%
376 FLOOR FINISHES Fri 9/25/20 0%
377 cement render 0%
378 WALL FINISHES 0%
379 plaster 0%
380 CEILING FINISHES 0%
381 skim coat 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 26
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

382 gypsum board ceiling 0%


383 HANDRAILS AND BALUSTRADINGS 0%
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20 0%
385 MISCELLANEOUS 0%
386 SURFACE WATER DRAINAGE Wed 9/30/20 0%
387 ANTI-TERMITE TREATMENT 0%
388 ANTI-CLIMBED WALL Sat 10/10/20 0%
389 MCC Panel Room 0%
390 Staircase 0%
391 Door Installation Fri 9/25/20 0%
392 Wall Painting Fri 9/25/20 0%
393 Air Conditioner Installation 0%
394 Lighting Installation 0%
395 MCC Cabinets Delivery Wed 9/30/20 0%
396 MCC Cabinets Installation 0%
397 Cable Installation 0%
398 Main Switch Board Room 0%
399 Wall Painting 0%
400 Door Installation 0%
401 Floor Finishing (Power Flout) 0%
402 Air Conditioner Installation Sat 10/10/20 0%
403 Lighting Installation Sat 10/10/20 0%
404 Switch Boards Delivery 0%
405 Switch Boards Installation 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 27
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

406 Cables Installation 0%


407 Batery Room 0%
408 Wall Plastering 0%
409 Wall Painting 0%
410 Door Installation 0%
411 Floor Finishing (Power Flout) 0%
412 Wiring & Lighting Installation Sat 10/10/20 0%
413 Battery Delivery Thu 9/17/20 0%
414 Battery Installation 0%
415 Switch Gear Room 0%
416 Wall Painting 0%
417 Door Installation 0%
418 Floor Finishing (Power Flout) 0%
419 Air Conditioner Installation Sat 10/10/20 0%
420 Lighting Installation Sat 10/10/20 0%
421 Switch Gear 11kV Delivery Wed 9/30/20 0%
422 Switch Gear Installation 0%
423 Cables Installation 0%
424 Transformer Yard 0%
425 Roof column fabrication 0%
426 Roof Truss Fabrication 0%
427 Roof column Installation 0%
428 Roof Truss Installation 0%
429 Roofing installation 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 28
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

430 Anti-climb Fencing Installation 0%


431 Transformer Installation 0%
432 Cables Installation 0%
433 GIS - Pole Erection (Plant to PPU Naka) 0%
434 GIS - Cable Installation (Plant to PPU Naka) 0%
435 Control Room 0%
436 Brick Works Sat 9/12/20 0%
437 Wall Plastering Tue 9/22/20 0%
438 Wall Painting 0%
439 Door Installation 0%
440 Window Installation 0%
441 Floor Finishing (Tile) 0%
442 Ceiling Finishing 0%
443 Air Conditioner Installation Sat 10/10/20 0%
444 Lighting Installation Sat 10/10/20 0%
445 DCS System Delivery 0%
446 DCS System Installation 0%
447 Vacum Surface Condenser Floor 0%
448 Toilet 0%
449 VSC Delivery 0%
450 VSC Exhaust Duct Installation 0%
451 VSC Bellow Installation 0%
452 VSC Lifting to Base 0%
453 VSC Centering & Levelling 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 29
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

454 VSC Base Grouting 0%


455 Gland Condenser Delivery 0%
456 Gland Condenser Lifting to Base 0%
457 Gland Condenser Centering & Levelling 0%
458 Gland Condenser Anchor Bolt Cementing 0%
459 Gland Condenser Base Grouting 0%
460 Condensate Pump Delivery 0%
461 Condenser Pump Installation 0%
462 Condensate Pump Centering & Levelling 0%
463 Condensate Pump Alignment 0%
464 Condensate Pump Anchor Bolt Cementing 0%
465 Condensate Pump Base Grouting 0%
466 Air Compressor Delivery 0%
467 Air Filter Delivery 0%
468 Air Dryer Delivery 0%
469 Air Receiver Tank Delivery 0%
470 Air Compressor Installation 0%
471 Air Filter Installation 0%
472 Air Dryer Installation 0%
473 Air Receiver Tank Installation 0%
474 Accessories/Fitting Installation 0%
475 Compressed air piping Installation 0%
476 Demin Water Plant 0%
477 Foundation c/w apron & ramp 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 30
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

478 ROOFS Sun 9/13/20 0%


479 Roofing/Cladding 0%
480 ROOF TRUSSES 0%
481 Purlin 0%
482 ROOF COVERING 0%
483 Gutter & Downpipe Installation 0%
484 WALL Fri 9/18/20 0%
485 Wall/window/ceilings finishes 0%
486 External wall cladding 0%
487 Painting 0%
488 WINDOWS AND VENTS Fri 9/25/20 0%
489 Fixed glass panel window 0%
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20 0%
491 roller shutter 0%
492 FLOOR FINISHES Fri 9/25/20 0%
493 Floor Finishing (Power Flout) 0%
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20 0%
495 Miscellaneous 0%
496 SURFACE WATER DRAINAGE Wed 9/30/20 0%
497 Wiring & Lighting Installation Fri 10/9/20 0%
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20 0%
499 BOP SPARES DELIVERY Wed 9/30/20 0%
500 0%
501 NON-POWER ISLAND 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 31
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

502 CIVIL, STRUCTURAL & BUILDING 0%


503 Earth Work 0%
504 Slope Boundary (Re-Design & Re-Work) 0%
505 Retaining Wall-2 0%
506 Turfing 0%
507 Concrete Drains 0%
508 Civil and Structural Work 0%
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20 0%
510 GROUND FLOOR SLAB AND APRON 0%
511 Foundation c/w apron & ramp 0%
512 Conveyor Pit c/w Finishing 0%
513 Fuel Receiving Hopper Delivery 0%
514 Fuel Receiving Hopper Installation 0%
515 Fuel Conveyor (FC - 1A&1B) Delivery 0%
516 Fuel Conveyor (FC - 1A&1B) Installation 0%
517 ROOFS Wed 9/16/20 0%
518 Gutter 0%
519 Purlin 0%
520 ROOF COVERING 0%
521 Roofing/Cladding 0%
522 WALL 0%
523 BRICKWORK 0%
524 Wall Plastering 0%
525 External wall cladding 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 32
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

526 Painting 0%
527 WINDOWS AND VENTS 0%
528 ALUMINIUM LOUVRES WINDOW 0%
529 FLOOR FINISHES 0%
530 WALL FINISHES 0%
531 MISCELLANEOUS 0%
532 TRENCHES 0%
533 SURFACE WATER DRAINAGE 0%
534 External & Perimeter 0%
535 Architectural Finishes 0%
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20 0%
537 Water Tank (for Rain Water Harvesting) 0%
538 Wiring & Lighting Installation 0%
539 Hose Reel 0%
540 Sprinkler 0%
541 Administration Office Mon 9/21/20 0%
542 GROUND FLOOR SLAB AND APRON 0%
543 apron 0%
544 cable trench 0%
545 ramp 0%
546 FRAME 0%
547 Water tank plinth 0%
548 STAIRCASES, STEPS, RAMPS AND FINISHES 0%
549 SKIM COATING 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 33
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

550 ROOFS 0%
551 Trusses 0%
552 Purlin 0%
553 ROOF COVERING 0%
554 rainwater down pipe 0%
555 roof slab 0%
556 WALL 0%
557 Plaster 0%
558 Partition/Dry Wall Installation 0%
559 WINDOWS AND VENTS 0%
560 FRAME 0%
561 Glass 0%
562 DOOR INCLUDING IRONMONGERY 0%
563 DOOR 0%
564 door stopper 0%
565 hinges 0%
566 lockset 0%
567 sliding door 0%
568 FLOOR FINISHES 0%
569 floor tiles 0%
570 WALL FINISHES 0%
571 plaster 0%
572 wall tiles 0%
573 Painting 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 34
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

574 CEILING FINISHES 0%


575 skim coat 0%
576 gypsum board 0%
577 ceiling lining 0%
578 paint 0%
579 SANITARY APPLIANCES 0%
580 Pedestal water closet 0%
581 wash hand basin 0%
582 handicap basin 0%
583 Hand spray bidet 0%
584 tissue holder 0%
585 shower rose 0%
586 bib tap 0%
587 soap dispenser 0%
588 grab rail 0%
589 swing-up support rail 0%
590 Mirror 0%
591 Floor drainer 0%
592 trash bin 0%
593 scupper drain 0%
594 counter top 0%
595 toilet cubicle 0%
596 HANDRAILS AND BALUSTRADINGS 0%
597 MISCELLANEOUS 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 35
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

598 Mild steel grillwork 0%


599 SURFACE WATER DRAINAGE 0%
600 Architectural Finishes 0%
601 Mechanical & Electrical 0%
602 External & Perimeter 0%
603 Wiring 0%
604 Air Conditioner Installation 0%
605 Lighting Installation 0%
606 Plant Storage 0%
607 Foundation c/w apron & ramp 0%
608 ROOFS 0%
609 Roofing/Cladding 0%
610 ROOF TRUSSES 0%
611 Purlin 0%
612 ROOF COVERING 0%
613 Gutter & Downpipe Installation 0%
614 WALL 0%
615 Brickwall 0%
616 Wall Plastering 0%
617 Painting 0%
618 WINDOWS AND VENTS 0%
619 Lintol 0%
620 Fixed glass louvres window 0%
621 DOOR INCLUDING IRONMONGERY 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 36
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

622 Lintol 0%
623 DOOR 0%
624 roller shutter 0%
625 FLOOR FINISHES 0%
626 Floor Finishing (Power Flout) 0%
627 WALL FINISHES 0%
628 Wall/window/ceilings finishes 0%
629 Plaster 0%
630 MISCELLANEOUS 0%
631 Miscellaneous 0%
632 SURFACE WATER DRAINAGE 0%
633 Wiring & Lighting Installation 0%
634 Guardhouse 0%
635 ROOFS 0%
636 Roofing/Cladding 0%
637 ROOF TRUSSES 0%
638 Purlin 0%
639 ROOF COVERING 0%
640 WALL 0%
641 Wall/window/ceilings finishes 0%
642 WINDOWS AND VENTS 0%
643 Frame 0%
644 Fixed glass louvres window 0%
645 Fixed glass panel window 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 37
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

646 DOOR INCLUDING IRONMONGERY 0%


647 Door 0%
648 hinges 0%
649 lockset 0%
650 door stopper 0%
651 coat hook 0%
652 FLOOR FINISHES 0%
653 Apron 0%
654 Tiles 0%
655 WALL FINISHES 0%
656 Plaster 0%
657 Tiles 0%
658 CEILING FINISHES 0%
659 cement board 0%
660 SANITARY APPLIANCES 0%
661 water closet 0%
662 Floor drainer 0%
663 Mirror 0%
664 bib tap 0%
665 shower rose 0%
666 tissue holder 0%
667 Hand spray bidet 0%
668 MISCELLANEOUS 0%
669 SURFACE WATER DRAINAGE 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 38
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

670 Wiring 0%
671 Lighting Installation 0%
672 Compact Sub 0%
673 Cable Trenches c/w Finishing 0%
674 Signages 0%
675 Meter Kiosk 0%
676 Incoming Cable from TNB 0%
677 Outgoing Cabble to MSB 0%
678 Diesel Tank 0%
679 Bund Wall 0%
680 Diesel Pump Plinth 0%
681 Diesel Tank Delivery 0%
682 Diesel Tank Installation 0%
683 Diesel Pump Delivery 0%
684 Diesel Pump Installation 0%
685 Diesel Genset Delivery 0%
686 Diesel Genset Installation 0%
687 Main Junction Modification 0%
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit 0%
689 RSA Stage 4 (Part 2) - Work Zone Audit 0%
690 RSA Stage 4 (Part 3) - Re-Opening 0%
691 RSA Stage 5 - Operational 0%
692 New Additional Lane 0%
693 Kerb 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 39
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

694 Resurface Existing Road 0%


695 Reconstruct Existing Road 0%
696 Road Marking & Furniture 0%
697 External Work 0%
698 Roadwork 0%
699 Surface Water Drainage 0%
700 Water Reticulation 0%
701 Sewerage System 0%
702 Fencing & Gate 0%
703 Flag Poles 0%
704 Catchment Pond 0%
705 Meter Room, PPU NAKA 0%
706 Meter Installation 0%
707 Misscellanous 0%
708 Landscape 0%
709 Fence Base 0%
710 Chain Link Fence Installation 0%
711 Sliding Gate Installation 0%
712 Flag Poles Base Construction 0%
713 GI Flag Poles Installation 0%
714 MECHANICAL & ELECTRICAL (M&E) 0%
715 Non-Plant Mechanical Services 0%
716 Weighbridge 0%
717 Weigh Bridge Design & Engineering 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 40
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

718 Weigh Bridge Manufacturing 0%


719 Weigh Bridge Delivery 0%
720 Weigh Bridge Site Installation 0%
721 Fire Fighting System 0%
722 Hose Reel System 0%
723 Fire Detection And Alarm System 0%
724 Clean Agent & Co2 Fire Extinguisher 0%
725 Portable Fire Extinguisher 0%
726 Hydrant System 0%
727 Sign And Notice 0%
728 ACMV System 0%
729 SPLIT UNIT AIR CONDITIONING SYSTEM 0%
730 Indoor/Outdoor Unit 0%
731 Copper Pipe 0%
732 Condensate Pipe 0%
733 ELECTRICAL 0%
734 GRID INTERCONNECTION 0%
735 PRELIMINARY WORK 0%
736 Document to submit for IOD 0%
737 Test result of interconnection facilities 0%
738 Power quality report 0%
739 To do protection setting on site 0%
740 Reliability Report (RR) 0%
741 Certificate for competent person for shutdown & testing 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 41
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

742 TRANSFORMER 0%
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV 0%
744 List of Testing 0%
745 Method of Statement for Testing 0%
746 Cert for competent person to test 0%
747 Connection to Grid 0%
748 Testing and commissioning (SAT) 0%
749 Earthing 0%
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV 0%
751 List of Testing to Submit 0%
752 Method of Statement for Testing 0%
753 Cert for competent person to test 0%
754 Cable Termination 0%
755 Connection to plant 0%
756 Testing and commissioning (SAT) 0%
757 Earthing 0%
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA) 0%
759 Cable Termination 0%
760 Installation/coupling 0%
761 List of testing to submit 0%
762 Method of Statement for testing 0%
763 Testing and commissioning (SAT) 0%
764 Earthing 0%
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER) 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 42
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

766 Cable Termination 0%


767 List of testing to submit 0%
768 Method of Statement for testing 0%
769 Testing and commissioning (SAT) 0%
770 Earthing 0%
771 REMOTE CONTROL PANEL (RCP) 0%
772 Cable Termination 0%
773 Fibre Termination 0%
774 List of testing to submit 0%
775 Method of Statement for testing 0%
776 Testing and commissioning (SAT) 0%
777 Earthing 0%
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER) 0%
779 Supply to the site 0%
780 Panel Installation 0%
781 Cable Termination 0%
782 List of testing to submit 0%
783 Method of Statement for testing 0%
784 Testing and commissioning (SAT) 0%
785 Earthing 0%
786 REMOTE TERMINAL UNIT (RTU) 0%
787 Supply & Install 0%
788 Cable Termination 0%
789 Fibre Termination 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 43
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

790 List of testing to submit 0%


791 Method of Statement for testing 0%
792 Testing and commissioning (SAT) 0%
793 Earthing 0%
794 FIBRE FROM PLANT TO PPU NAKA 0%
795 Fibre Termination 0%
796 List of testing to submit 0%
797 Method of Statement for testing 0%
798 Testing and commissioning (SAT) 0%
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM) 0%
800 Supply & Install 0%
801 List of testing to submit 0%
802 Method of Statement for testing 0%
803 Testing and commissioning (SAT) 0%
804 Earthing 0%
805 33KV METERING PANEL AT CONSUMER SITE 0%
806 Supply & Install 0%
807 Testing and commissioning (SAT) 0%
808 Earthing 0%
809 FIBER TERMINATION PATCH FOR GRID 0%
810 Supply & Install 0%
811 Testing and commissioning (SAT) 0%
812 OTDR result 0%
813 POWER CABLE 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 44
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV) 0%


815 Installation 3 phase straight joint c/w boding kit 0%
816 Installation normal single phase straigh joint for cable 0%
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka 0%
818 Cert for cable tester 0%
819 Testing and commissioning (SAT) 0%
820 VLF test & other tests 0%
821 1C X 185MM2 XLPE AI CABLE (33KV) 0%
822 Supply to the site 0%
823 Intallation cable tray/ladders and other accesorries 0%
824 Inside Majunaka Substation 0%
825 Inside PPU Naka 0%
826 Burried direct ground with sand bending, excavation 0%
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated 0%
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund 0%
829 Along road shoulder & tarcamadam road 0%
830 lay & terminate to 33kV GIS c/w other accesorries 0%
831 lay & terminate to 11kV AIS c/w other accesorries 0%
832 lay & terminate to 11/33kv transformer c/w other accesorries 0%
833 Cert for cable tester 0%
834 VLF test & other tests 0%

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 45
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV) 0%


836 Supply to the site 0%
837 Intallation cable tray/ladders and other accesorries 0%
838 From 11kV panel to 12.5MVA transfomer 0%
839 lay & terminate to 11kV AIS c/w other accesorries 0%
840 lay & terminate to 11/33kv transformer c/w other accesorries 0%
841 Cert for cable tester 0%
842 VLF test & other tests 0%
843 Low Voltage 0%
844 MAIN SWITCH BOARD (MSB) 0%
845 Supply to the site 0%
846 Installation in Majunaka Substation 0%
847 Cable termination incoming and outgoing 0%
848 Method of statement for testing c/w test form and tester certificate 0%
849 Site acceptence test for ; 0%
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB 0%
851 MSB A c/w breaking capacity 65kA, 1600A ACB 0%
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole 0%
Auto Transfer Switch (ATS)
853 MSB C 0%
854 415V MOTOR CONTROL CENTER (MCC) 0%
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20 0%
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20 0%
857 Cable Termination 0%

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 46
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

858 List of testing to submit 0%


859 Method of statement for testing c/w test form and tester certificate 0%
860 Method of Statement for testing 0%
861 Testing and commissioning (SAT) 0%
862 Earthing 0%
863 SUB SWITCHBOARD (SSB) 0%
864 Supply and deliver to the site 0%
865 Install SSB c/w overcurrent & earth leakage relay and other 0%
accessories for;
866 2 SSB at building pentadbiran and tarbin 0%
867 18 unit Distribution Board (DB) in Majunaka Plant 0%
868 2 unit isolators at cold water system and DG control system 0%
869 Street lighting Feeder Pillar 0%
870 1600A Generator connection box 0%
871 Meter Kiosk c/w plint and all else accessories as per TNB specification 0%
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes 0%
873 Earthing 0%
874 GENERATOR SET 0%
875 STANDBY 750KVA GENSET 0%
876 Supply and deliver to the site 0%
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable 0%
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable 0%
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 47
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

879 Install fuel piping 0%


880 Earthing system 0%
881 Install 24 hours fuel tank 0%
882 24V nickel cadmium 0%
883 Testing and commsioning 0%
884 STANDBY 1000KVA GENSET 0%
885 Supply, lay and terminate cable from Genset to AMF 0%
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable 0%
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable 0%
from Genset to the MAB 1
888 Install fuel piping 0%
889 Earthing system 0%
890 Install 10,000 litre fuel tank 0%
891 24V nickel cadmium 0%
892 Testing and commsioning 0%
893 SUBMAIN LV CABLING 0%
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to 0%
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C 0%
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1 0%
897 Install floor penetration fire barrier of BOMBA 0%
898 All outgoing cable from; 0%

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 48
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

899 MSB A to all Sub-DB 0%


900 MSB B to all Sub-DB 0%
901 MSB C to all Sub-DB 0%
902 SSB Tarbin 0%
903 SSB Pentadbiran 0%
904 Testing and commsioning 0%
905 SUB-CIRCUIT & SMALL POWER WIRING 0%
906 To wireup all lighting, sso, and other equipment 0%
907 To supply and install conduit and trunking system 0%
908 To supply and install underfloor ducting system 0%
909 ELECTRICAL FITTINGS 0%
910 Supply all fiting to all buiding 0%
911 LIGHTNING PROTECTION SINGLE DOME 0%
912 To install lighting protection 0%
913 EARTHING 0%
914 To install Earthing protection 0%
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM 0%
916 To supply street lighting / compound lighting system 0%
917 To install street lighting / compound lighting system 0%
918 TNC 0%
919 0%
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20 0%
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20 0%
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20 0% 38FF
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 49
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20 0% 922FF-3 days
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20 0% 923FS+3 days
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20 0% 924
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20 0% 925
927 Plant DOSH Inspection 0%
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20 0%
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20 0%
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20 0%
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20 0%
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20 0%
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20 0%
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20 0%
935 ACW System 4 days Wed 10/7/20Sat 10/10/20 0%
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20 0%
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20 0%
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20 0% 928
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20 0%
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20 0% 939
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20 0% 940
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20 0% 941
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20 0% 942
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20 0% 943
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20 0%
946 Plant Performance Test 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 50
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

947 Plant Reliability Run (RR) 0%


948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20 0%
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu 0%
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu 0%
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20 0%
952 Review documents 0%
953 Line walk at the plant 0%
954 AT&PA activities at the plant 0%
955 AT&PA Report preparation and submission 0%
956 Review and approve AT&PA report 0%
957 Upload AT&PA report in the e-FiT system 0%
958 Approval and issuance of FiTCD letter Sat 11/14/20 0%
959 0%
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP) 0%
961 Borang F1 0%
962 Bomba Inspection 0%
963 Defect List 0%
964 Operation and Maintenance Manual with As-Built Dwg 0%
965 2.5% of the 5% retention sum 0%
966 0%
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21 0%

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 51
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

968 G1 : KERJA-KERJA TANAH 0%


969 G2 : PEMANCANGAN TANDA 0%
970 G3 : ASAS TAPAK 0%
971 G4 : STRUKTUR 0%
972 G5 : PERPAIPAN AIR DALAMAN 0%
973 G6 : PERPAIPAN SANITARI DALAMAN 0%
974 G7 : ELEKTRIKAL DALAMAN 0%
975 G8 : MENENTANG KEBAKARAN (PASIF) 0%
976 G9 : MENENTANG KEBAKARAN (AKTIF) 0%
977 G10 : PENGUDARAAN MEKANIKAL 0%
978 G11 : PEMASANGAN LIF/ESKALATOR 0%
979 G12 : BANGUNAN 0%
980 G13 : SISTEM BEKALAN AIR LUARAN 0%
981 G14 : RETIKULASI PEMBETUNGAN 0%
982 G15 : LOJI RAWATAN PEMBETUNGAN 0%
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN 0%
984 G17 : JALAN DAN PARIT 0%
985 G18 : LAMPU JALAN 0%
986 G19 : PARIT LUARAN UTAMA 0%
987 G20 : TELEKOMUNIKASI 0%
988 G21 : PANDANGAN DARAT 0%
989 Borang F 0%
990 0%
991 MILESTONE PAYMENT 0%
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 52
ID TaskTask Name Duration Start Finish % Predecessors
Mode Complete

992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20 0%


993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20 0%
994 MS 9 Upon Mechanical Completion of the Facility 0%
995 MS 10 Upon Achieving Commercial Operation Date 0%
996 0%
997 Certificate of Making Good Defects (CMGD) 0%
998 Making good of defects 0%
999 2.5% of the 5% retention sum 0%
1000 0%
1001 FINAL ACCOUNT 0%

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 53
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21 NA NA
2 NA NA
3 POWER ISLAND NA NA
4 Boiler NA NA
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20 NA NA
6 Boiler Pressure Part Fabrication NA NA
7 Drum HT NA NA
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20 NA NA
9 Boiler Steam Drum Fitting Installation NA NA
10 Boiler Main Tubes Installation NA NA
11 Signages NA NA
12 Boiler Non-Pressure Parts NA NA
13 Boiler Structure, platform NA NA
14 Boiler Structure Delivery NA NA
15 Boiler Structure erection Wed 9/30/20 NA NA
16 Boiler House Top Structure Fabrication NA NA
17 Boiler House Top Structure Delivery NA NA
18 Boiler House Top Structure Erection NA NA
19 Boiler House Roofing installation NA NA
20 Blowdown Tank(M) NA NA
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20 NA NA
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20 NA NA
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20 NA NA
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20 NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 54
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20 NA NA
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20 NA NA
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20 NA NA
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20 NA NA
29 Installation NA NA
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20 NA NA
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20 NA NA
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20 NA NA
33 Flash Tank NA NA
34 Flash tank assembly delivery Wed 9/30/20 NA NA
35 Flash tank assembly installation NA NA
36 Flash tank fittings installation NA NA
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20 NA NA
38 Boiler Site Installation Wed 9/30/20 NA NA
39 Structure & Frame NA NA
40 Travelling Grate, Hopper NA NA
41 Travelling Grate/Stoker Installation NA NA
42 Ash Hopper (under Stoker) Installation NA NA
43 Ash Conveyor Plinth NA NA
44 Ash Conveyor Delivery NA NA
45 Ash Conveyor Installation NA NA
46 Refractory Application NA NA
47 Temperory support, Drum Lift, Alignment, Securing NA NA
48 Generating Tube (818 tubes) Mon 9/7/20 NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 55
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

49 Header set up, waterwall, Superheater NA NA


50 1st Superheater Tubes Installation c/w Headers NA NA
51 1st Superheater Fitting Installation NA NA
52 2nd Superheater Tubes Installation c/w Headers NA NA
53 2nd Superheater Fitting Installation NA NA
54 Downcomers Installation NA NA
55 Water Tubes & Membran Wall Installation NA NA
56 Economizer, Steam connection pipes, supports NA NA
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20 NA NA
58 Economizer assembly installation NA NA
59 Economizer fitting installation NA NA
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer NA NA
61 Deaerator fitting installation NA NA
62 CBD assembly Delivery NA NA
63 CBD system installation NA NA
64 CBD fittings installation NA NA
65 Dust Collector Casing & accessories Wed 9/30/20 NA NA
66 Assemble fly ash dust collector frame assembly NA NA
67 Dust Collector Inner pipe Outside Pipe Installation NA NA
68 Dust Collector Guide Vane Damper Installation NA NA
69 Rotary valve , hopper and casing Installation NA NA
70 Steam Piping Installation c/w Insulation NA NA
71 Air Duct Installation c/w Insulation NA NA
72 Gas Duct Installation c/w Insulation NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 56
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

73 Accessories/fitings Installation NA NA
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20 NA NA
75 Insulation and Boiler Outer Casing Application NA NA
76 Boiler Outer Casing Finishing Paint Works NA NA
77 Grating Installation NA NA
78 HandRail Installation NA NA
79 Sootblower Assembly Delivery NA NA
80 Install Sootblower Frames and Hangers NA NA
81 Assemble Long Retractable Sootblowers parts including NA NA
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including NA NA
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and NA NA
drain valves
84 Install sootblower fittings NA NA
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20 NA NA
86 Fuel Feeder Delivery NA NA
87 Fuel Feeder Installation NA NA
88 Service Silo Delivery NA NA
89 Service Silo Installation NA NA
90 Boiler Draft System Wed 9/30/20 NA NA
91 FD/ID Fans,Air Heater,Ducting Site Installation NA NA
92 ID FAN NA NA
93 Centering & Levelling NA NA

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 57
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

94 Anchor Bolt Cementing NA NA


95 Base Grouting NA NA
96 Upper Casing Installation NA NA
97 Suction Cone Installation NA NA
98 Inlet Damper Installation NA NA
99 Primary Force Draft Fan NA NA
100 Centering & Levelling NA NA
101 Anchor Bolt Cementing NA NA
102 Base Grouting NA NA
103 Upper Casing Installation NA NA
104 Suction Cone Installation NA NA
105 Inlet Damper Installation NA NA
106 Silencer Installation NA NA
107 Secondary Force Draft Fan NA NA
108 Centering & Levelling NA NA
109 Anchor Bolt Cementing NA NA
110 Base Grouting NA NA
111 Upper Casing Installation NA NA
112 Suction Cone Installation NA NA
113 Inlet Damper Installation NA NA
114 Silencer Installation NA NA
115 Chimney & CEMS NA NA
116 Chimney Delivery Tue 9/15/20 NA NA
117 Chimney Stack Site Installation NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 58
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

118 Lifting, Centering & Levelling NA NA


119 Anchor Bolt Tightening NA NA
120 Erection NA NA
121 CEMS COMPLETE Tue 9/22/20 NA NA
122 Steam Turbogenerator NA NA
123 STG Site Installation NA NA
124 Gland Sealing Condenser installation NA NA
125 Reducton gear installation NA NA
126 Alignment NA NA
127 Oil unit installation NA NA
128 Prefab pipes & Turbine cover installation NA NA
129 Observation Gantry Fabrication NA NA
130 Observation Gantry Installation NA NA
131 Staircase & railing Fabrication NA NA
132 Staircase & railing Installation NA NA
133 Structure Erection NA NA
134 Roofing Installation NA NA
135 Cladding Installation NA NA
136 Gutter Installation NA NA
137 Floor Finishing NA NA
138 Louvers Installation NA NA
139 Overhead crane Installation NA NA
140 ST-GB-GEN Lifting NA NA
141 ST Centering & Levelling NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 59
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

142 Gearbox Centering & Levelling NA NA


143 Generator Centering & Levelling NA NA
144 STG Anchor Bolt Cementing NA NA
145 STG Base Grouting NA NA
146 ST - GB Alignment NA NA
147 GB - Generator Alignment NA NA
148 ST Piping Installation NA NA
149 ST Insulation NA NA
150 Lube Oil Unit Lifting NA NA
151 Lube Oil Unit Centering & Levelling NA NA
152 Lube Oil Unit Anchor Bolt Cementing NA NA
153 Lube Oil Unit Base Grouting NA NA
154 Steam Air Ejector Delivery NA NA
155 Steam Air Ejector Installation NA NA
156 Turbine Control Panel Installation (TCP) NA NA
157 Cable Installation NA NA
158 BALANCE OF PLANT NA NA
159 Cooling Water System NA NA
160 Vacumn Surface Condenser & Auxiliary NA NA
161 VSC Factory Acceptance Test NA NA
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20 NA NA
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20 NA NA
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20 NA NA
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20 NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 60
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20 NA NA
167 Air Cool Heat Exchanger NA NA
168 Heat Exchanger Delivery Mon 9/7/20 NA NA
169 Heat Exchanger Site Installation NA NA
170 ACHE Lifting & Positioning NA NA
171 Main Cooling Water Pump Plinth NA NA
172 Main Cooling Water Pump Delivery Wed 9/30/20 NA NA
173 Main Cooling Water Pump Installation NA NA
174 Main Cooling Water Pump Anchor Bolt Cementing NA NA
175 Main Cooling Water Pump Base Grouting NA NA
176 Main Cooling Water Piping NA NA
177 Main Cooling Water Valves/Fitting Installation NA NA
178 Cooling Tower NA NA
179 Cooling Tower Delivery Mon 9/28/20 NA NA
180 Cooling Tower Site Installation NA NA
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20 NA NA
182 Auxiliary Cooling Water Pump Installation NA NA
183 ESP 1 day Sat 9/12/20 Sat 9/12/20 NA NA
184 ESP Delivery Sat 9/12/20 NA NA
185 ESP Site Installation NA NA
186 ESP Structure/parts Delivery NA NA
187 ESP Steel Support Structure Erection and Assembly NA NA
188 Install Collecting & Emitting Plates/Electrode NA NA
189 Install Rapping Hammer and Accessories NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 61
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

190 Install Inner and Outer Casing NA NA


191 Install Ash Hopper NA NA
192 Install Rotary Valves NA NA
193 Install Transformer Rectifiers NA NA
194 Install Inlet and Outlet Expansion Joint NA NA
195 Install Inlet and Outlet Dampers NA NA
196 Install gratings and railings NA NA
197 Install all accessories and Fittings NA NA
198 Fuel Handling And Ash Delivery System NA NA
199 Fuel Handling NA NA
200 Conveyor NA NA
201 Fuel Handling Delivery Thu 10/1/20 NA NA
202 Fuel Handling Site Installation NA NA
203 Fuel Conveyor (FC-2&3) Delivery NA NA
204 Fuel Conveyor (FC-2&3) Installation NA NA
205 Silo Diverter Valve Delivery NA NA
206 Silo Diverter Valve Installation NA NA
207 Silo Conveyor Structure Delivery NA NA
208 Silo Conveyor Delivery (SC - 1&2) NA NA
209 Silo Conveyor Structure Erection NA NA
210 Silo Conveyor Installation (SC - 1&2) NA NA
211 Biomass Silos NA NA
212 Biomass Silo Delivery NA NA
213 Biomass Silo Site Installation NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 62
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

214 Fuel Silo#1 Delivery Fri 9/25/20 NA NA


215 Fuel Silo#1 Installation NA NA
216 Fuel Silo#2 Delivery NA NA
217 Fuel Silo#2 Installation NA NA
218 Fuel Silo#1 Rotor Delivery NA NA
219 Fuel Silo#1 Rotor Installation NA NA
220 Fuel Silo#2 Rotor Delivery NA NA
221 Fuel Silo#2 Rotor Installation NA NA
222 Ash System NA NA
223 Ash Tank, Conveyor Design & Engineering NA NA
224 Ash Tank, conveyor Manufacturing NA NA
225 Ash Tank Delivery Thu 10/15/20 NA NA
226 Ash Tank Site Installation NA NA
227 Bottom Ash Tank Design & Engineering NA NA
228 Bottom Ash Tank, conveyor Manufacturing NA NA
229 Bottom Ash Tank Delivery Thu 10/15/20 NA NA
230 Bottom Ash Tank Site Installation NA NA
231 Structure Delivery NA NA
232 Structure erection NA NA
233 Tank Lifting/Installation NA NA
234 Rotary valve installation NA NA
235 Ash Conveyor Delivery NA NA
236 Ash Conveyor Structure Delivery NA NA
237 Ash Conveyor Structure Erection NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 63
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

238 Ash Conveyor Installation NA NA


239 Screw Conveyor Delivery NA NA
240 Screw Conveyor Structure Delivery NA NA
241 Screw Conveyor Structure Erection NA NA
242 Screw Conveyor Installation NA NA
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20 NA NA
244 Pumps Delivery Wed 9/30/20 NA NA
245 Pumps Site Installation NA NA
246 Demin Water System NA NA
247 Demin System NA NA
248 Demin Water System Design & Engineering NA NA
249 Demin Water System Manufacturing NA NA
250 Demin Water System Delivery Tue 9/15/20 NA NA
251 Booster Pump Delivery NA NA
252 Activated Carbon Filter Delivery NA NA
253 Cation Exchange Filter Delivery NA NA
254 Anion Exchange Filter Delivery NA NA
255 HCL Tank Delivery NA NA
256 NaOH Tank Delivery NA NA
257 Boiler Compound Tank Delivery NA NA
258 pH Chemical Tank Delivery NA NA
259 Oxygen Scavenger Tank Delivery NA NA
260 Anti Slime Tank Delivery NA NA
261 Anti Scale Tank Delivery NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 64
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

262 pH Metering Pump Delivery NA NA


263 Make Up Water Pump Delivery NA NA
264 Demin Water Make Up Pump Delivery NA NA
265 HP Boiler Dosing Pump Delivery NA NA
266 LP Boiler Dosing Pump Delivery NA NA
267 Anti Slime Dosing Pump Delivery NA NA
268 Anti Scale Dosing Pump Delivery NA NA
269 Demin Water System Site Installation NA NA
270 Booster Pump Installation NA NA
271 Activated Carbon Filter Installation NA NA
272 Cation Exchange Filter Installation NA NA
273 Anion Exchange Filter Installation NA NA
274 HCL Tank Installation NA NA
275 NaOH Tank Installation NA NA
276 Boiler Compound Tank Installation NA NA
277 pH Chemical Tank Installation NA NA
278 Oxygen Scavenger Tank Installation NA NA
279 Anti Slime Tank Installation NA NA
280 Anti Scale Tank Installation NA NA
281 pH Metering Pump Installation NA NA
282 Make Up Water Pump Installation NA NA
283 Demin Water Make Up Pump Installation NA NA
284 HP Boiler Dosing Pump Installation NA NA
285 LP Boiler Dosing Pump Installation NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 65
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

286 Anti Slime Dosing Pump Installation NA NA


287 Anti Scale Dosing Pump Installation NA NA
288 Demin Tank Design & Engineering NA NA
289 Demin Tank Manufacturing NA NA
290 Demin Tank Delivery Tue 9/15/20 NA NA
291 Demin Tank Site Installation NA NA
292 Neutralization Tank Delivery NA NA
293 Neutralization Tank Installation NA NA
294 Valves/Fitting Installation NA NA
295 Raw Water System NA NA
296 Raw Water Tank Design & Engineering NA NA
297 Raw Water Tank Manufacturing NA NA
298 Raw Water Tank Delivery Tue 9/15/20 NA NA
299 Raw Water Tank Site Installation NA NA
300 Neutralization System NA NA
301 Plant Neutralization System Design & Engineering NA NA
302 Plant Neutralization System Manufacturing NA NA
303 Neutralizing System Delivery Wed 9/30/20 NA NA
304 Site Installation NA NA
305 Diesel Oil Tank NA NA
306 Diesel Oil Tank Design & Engineering NA NA
307 Diesel Oil Tank Manufacturing NA NA
308 Diesel Oil Tank Delivery NA NA
309 Diesel Oil Tank Site Installation NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 66
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

310 Plant Engineering & Interconnection Piping NA NA


311 Plant Interconnecting Pipes Design & Engineering NA NA
312 Instrumentation engineering NA NA
313 Instrumentation Manufacturing NA NA
314 Plant Interconnecting Pipes Manufacturing NA NA
315 Instrumentation Delivery Wed 9/30/20 NA NA
316 Plant Interconnecting Pipes Delivery Sun 9/27/20 NA NA
317 Site Installation Mon 10/5/20 NA NA
318 Power Island Electrical System NA NA
319 Power Island Electrical System Design & Engineering NA NA
320 Panel & Switch gear Manufacturing NA NA
321 Material procurement NA NA
322 Equipment & accessories delivery Sun 10/4/20 NA NA
323 Site Installation NA NA
324 Grid Interconnection System (GIS) NA NA
325 Electrical System Design & Engineering NA NA
326 Transformer, Switch Gear, Equipment Manufacturing NA NA
327 Plant Electrical System Delivery NA NA
328 33kV & 11kV Cable Installation NA NA
329 Sub station & Plant Site installation NA NA
330 DCS NA NA
331 DCS Delivery Wed 9/23/20 NA NA
332 DCS Site Installation NA NA
333 Compressed Air System NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 67
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

334 Air Dryer Compressor Delivery Fri 9/25/20 NA NA


335 Air Dryer Compressor Site Installation NA NA
336 Overhead Crane NA NA
337 Overhead Crane Design & Engineering NA NA
338 Overhead Crane Manufacturing NA NA
339 Overhead Crane Delivery Fri 9/25/20 NA NA
340 Overhead Crane Site Installation NA NA
341 CIVIL, STRUCTURAL & BUILDING NA NA
342 Civil and Structural Work NA NA
343 Turbine Hall & Switchboard Room NA NA
344 GROUND FLOOR SLAB AND APRON NA NA
345 FRAME NA NA
346 Frame, column, 2nd Floor NA NA
347 Column NA NA
348 Upper floor beam NA NA
349 Overhead Crane NA NA
350 UPPER FLOOR NA NA
351 STAIRCASES, STEPS AND FINISHES NA NA
352 ROOFS Sun 9/13/20 NA NA
353 Roofing/Cladding,Structure NA NA
354 ROOF TRUSSES NA NA
355 Gutter NA NA
356 Purlin NA NA
357 ROOF COVERING NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 68
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

358 rainwater down pipe NA NA


359 soffit of flat roof NA NA
360 WALL Fri 9/18/20 NA NA
361 brickwall NA NA
362 External wall cladding NA NA
363 External wall louvres cladding NA NA
364 External shera board wall cladding NA NA
365 iron purlin NA NA
366 WINDOWS AND VENTS Fri 9/25/20 NA NA
367 FRAME NA NA
368 Glass NA NA
369 louvres window NA NA
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20 NA NA
371 Door NA NA
372 Hinges NA NA
373 Lockset NA NA
374 door stopper NA NA
375 Sliding Door NA NA
376 FLOOR FINISHES Fri 9/25/20 NA NA
377 cement render NA NA
378 WALL FINISHES NA NA
379 plaster NA NA
380 CEILING FINISHES NA NA
381 skim coat NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 69
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

382 gypsum board ceiling NA NA


383 HANDRAILS AND BALUSTRADINGS NA NA
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20 NA NA
385 MISCELLANEOUS NA NA
386 SURFACE WATER DRAINAGE Wed 9/30/20 NA NA
387 ANTI-TERMITE TREATMENT NA NA
388 ANTI-CLIMBED WALL Sat 10/10/20 NA NA
389 MCC Panel Room NA NA
390 Staircase NA NA
391 Door Installation Fri 9/25/20 NA NA
392 Wall Painting Fri 9/25/20 NA NA
393 Air Conditioner Installation NA NA
394 Lighting Installation NA NA
395 MCC Cabinets Delivery Wed 9/30/20 NA NA
396 MCC Cabinets Installation NA NA
397 Cable Installation NA NA
398 Main Switch Board Room NA NA
399 Wall Painting NA NA
400 Door Installation NA NA
401 Floor Finishing (Power Flout) NA NA
402 Air Conditioner Installation Sat 10/10/20 NA NA
403 Lighting Installation Sat 10/10/20 NA NA
404 Switch Boards Delivery NA NA
405 Switch Boards Installation NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 70
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

406 Cables Installation NA NA


407 Batery Room NA NA
408 Wall Plastering NA NA
409 Wall Painting NA NA
410 Door Installation NA NA
411 Floor Finishing (Power Flout) NA NA
412 Wiring & Lighting Installation Sat 10/10/20 NA NA
413 Battery Delivery Thu 9/17/20 NA NA
414 Battery Installation NA NA
415 Switch Gear Room NA NA
416 Wall Painting NA NA
417 Door Installation NA NA
418 Floor Finishing (Power Flout) NA NA
419 Air Conditioner Installation Sat 10/10/20 NA NA
420 Lighting Installation Sat 10/10/20 NA NA
421 Switch Gear 11kV Delivery Wed 9/30/20 NA NA
422 Switch Gear Installation NA NA
423 Cables Installation NA NA
424 Transformer Yard NA NA
425 Roof column fabrication NA NA
426 Roof Truss Fabrication NA NA
427 Roof column Installation NA NA
428 Roof Truss Installation NA NA
429 Roofing installation NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 71
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

430 Anti-climb Fencing Installation NA NA


431 Transformer Installation NA NA
432 Cables Installation NA NA
433 GIS - Pole Erection (Plant to PPU Naka) NA NA
434 GIS - Cable Installation (Plant to PPU Naka) NA NA
435 Control Room NA NA
436 Brick Works Sat 9/12/20 NA NA
437 Wall Plastering Tue 9/22/20 NA NA
438 Wall Painting NA NA
439 Door Installation NA NA
440 Window Installation NA NA
441 Floor Finishing (Tile) NA NA
442 Ceiling Finishing NA NA
443 Air Conditioner Installation Sat 10/10/20 NA NA
444 Lighting Installation Sat 10/10/20 NA NA
445 DCS System Delivery NA NA
446 DCS System Installation NA NA
447 Vacum Surface Condenser Floor NA NA
448 Toilet NA NA
449 VSC Delivery NA NA
450 VSC Exhaust Duct Installation NA NA
451 VSC Bellow Installation NA NA
452 VSC Lifting to Base NA NA
453 VSC Centering & Levelling NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 72
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

454 VSC Base Grouting NA NA


455 Gland Condenser Delivery NA NA
456 Gland Condenser Lifting to Base NA NA
457 Gland Condenser Centering & Levelling NA NA
458 Gland Condenser Anchor Bolt Cementing NA NA
459 Gland Condenser Base Grouting NA NA
460 Condensate Pump Delivery NA NA
461 Condenser Pump Installation NA NA
462 Condensate Pump Centering & Levelling NA NA
463 Condensate Pump Alignment NA NA
464 Condensate Pump Anchor Bolt Cementing NA NA
465 Condensate Pump Base Grouting NA NA
466 Air Compressor Delivery NA NA
467 Air Filter Delivery NA NA
468 Air Dryer Delivery NA NA
469 Air Receiver Tank Delivery NA NA
470 Air Compressor Installation NA NA
471 Air Filter Installation NA NA
472 Air Dryer Installation NA NA
473 Air Receiver Tank Installation NA NA
474 Accessories/Fitting Installation NA NA
475 Compressed air piping Installation NA NA
476 Demin Water Plant NA NA
477 Foundation c/w apron & ramp NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 73
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

478 ROOFS Sun 9/13/20 NA NA


479 Roofing/Cladding NA NA
480 ROOF TRUSSES NA NA
481 Purlin NA NA
482 ROOF COVERING NA NA
483 Gutter & Downpipe Installation NA NA
484 WALL Fri 9/18/20 NA NA
485 Wall/window/ceilings finishes NA NA
486 External wall cladding NA NA
487 Painting NA NA
488 WINDOWS AND VENTS Fri 9/25/20 NA NA
489 Fixed glass panel window NA NA
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20 NA NA
491 roller shutter NA NA
492 FLOOR FINISHES Fri 9/25/20 NA NA
493 Floor Finishing (Power Flout) NA NA
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20 NA NA
495 Miscellaneous NA NA
496 SURFACE WATER DRAINAGE Wed 9/30/20 NA NA
497 Wiring & Lighting Installation Fri 10/9/20 NA NA
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20 NA NA
499 BOP SPARES DELIVERY Wed 9/30/20 NA NA
500 NA NA
501 NON-POWER ISLAND NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 74
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

502 CIVIL, STRUCTURAL & BUILDING NA NA


503 Earth Work NA NA
504 Slope Boundary (Re-Design & Re-Work) NA NA
505 Retaining Wall-2 NA NA
506 Turfing NA NA
507 Concrete Drains NA NA
508 Civil and Structural Work NA NA
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20 NA NA
510 GROUND FLOOR SLAB AND APRON NA NA
511 Foundation c/w apron & ramp NA NA
512 Conveyor Pit c/w Finishing NA NA
513 Fuel Receiving Hopper Delivery NA NA
514 Fuel Receiving Hopper Installation NA NA
515 Fuel Conveyor (FC - 1A&1B) Delivery NA NA
516 Fuel Conveyor (FC - 1A&1B) Installation NA NA
517 ROOFS Wed 9/16/20 NA NA
518 Gutter NA NA
519 Purlin NA NA
520 ROOF COVERING NA NA
521 Roofing/Cladding NA NA
522 WALL NA NA
523 BRICKWORK NA NA
524 Wall Plastering NA NA
525 External wall cladding NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 75
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

526 Painting NA NA
527 WINDOWS AND VENTS NA NA
528 ALUMINIUM LOUVRES WINDOW NA NA
529 FLOOR FINISHES NA NA
530 WALL FINISHES NA NA
531 MISCELLANEOUS NA NA
532 TRENCHES NA NA
533 SURFACE WATER DRAINAGE NA NA
534 External & Perimeter NA NA
535 Architectural Finishes NA NA
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20 NA NA
537 Water Tank (for Rain Water Harvesting) NA NA
538 Wiring & Lighting Installation NA NA
539 Hose Reel NA NA
540 Sprinkler NA NA
541 Administration Office Mon 9/21/20 NA NA
542 GROUND FLOOR SLAB AND APRON NA NA
543 apron NA NA
544 cable trench NA NA
545 ramp NA NA
546 FRAME NA NA
547 Water tank plinth NA NA
548 STAIRCASES, STEPS, RAMPS AND FINISHES NA NA
549 SKIM COATING NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 76
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

550 ROOFS NA NA
551 Trusses NA NA
552 Purlin NA NA
553 ROOF COVERING NA NA
554 rainwater down pipe NA NA
555 roof slab NA NA
556 WALL NA NA
557 Plaster NA NA
558 Partition/Dry Wall Installation NA NA
559 WINDOWS AND VENTS NA NA
560 FRAME NA NA
561 Glass NA NA
562 DOOR INCLUDING IRONMONGERY NA NA
563 DOOR NA NA
564 door stopper NA NA
565 hinges NA NA
566 lockset NA NA
567 sliding door NA NA
568 FLOOR FINISHES NA NA
569 floor tiles NA NA
570 WALL FINISHES NA NA
571 plaster NA NA
572 wall tiles NA NA
573 Painting NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 77
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

574 CEILING FINISHES NA NA


575 skim coat NA NA
576 gypsum board NA NA
577 ceiling lining NA NA
578 paint NA NA
579 SANITARY APPLIANCES NA NA
580 Pedestal water closet NA NA
581 wash hand basin NA NA
582 handicap basin NA NA
583 Hand spray bidet NA NA
584 tissue holder NA NA
585 shower rose NA NA
586 bib tap NA NA
587 soap dispenser NA NA
588 grab rail NA NA
589 swing-up support rail NA NA
590 Mirror NA NA
591 Floor drainer NA NA
592 trash bin NA NA
593 scupper drain NA NA
594 counter top NA NA
595 toilet cubicle NA NA
596 HANDRAILS AND BALUSTRADINGS NA NA
597 MISCELLANEOUS NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 78
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

598 Mild steel grillwork NA NA


599 SURFACE WATER DRAINAGE NA NA
600 Architectural Finishes NA NA
601 Mechanical & Electrical NA NA
602 External & Perimeter NA NA
603 Wiring NA NA
604 Air Conditioner Installation NA NA
605 Lighting Installation NA NA
606 Plant Storage NA NA
607 Foundation c/w apron & ramp NA NA
608 ROOFS NA NA
609 Roofing/Cladding NA NA
610 ROOF TRUSSES NA NA
611 Purlin NA NA
612 ROOF COVERING NA NA
613 Gutter & Downpipe Installation NA NA
614 WALL NA NA
615 Brickwall NA NA
616 Wall Plastering NA NA
617 Painting NA NA
618 WINDOWS AND VENTS NA NA
619 Lintol NA NA
620 Fixed glass louvres window NA NA
621 DOOR INCLUDING IRONMONGERY NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 79
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

622 Lintol NA NA
623 DOOR NA NA
624 roller shutter NA NA
625 FLOOR FINISHES NA NA
626 Floor Finishing (Power Flout) NA NA
627 WALL FINISHES NA NA
628 Wall/window/ceilings finishes NA NA
629 Plaster NA NA
630 MISCELLANEOUS NA NA
631 Miscellaneous NA NA
632 SURFACE WATER DRAINAGE NA NA
633 Wiring & Lighting Installation NA NA
634 Guardhouse NA NA
635 ROOFS NA NA
636 Roofing/Cladding NA NA
637 ROOF TRUSSES NA NA
638 Purlin NA NA
639 ROOF COVERING NA NA
640 WALL NA NA
641 Wall/window/ceilings finishes NA NA
642 WINDOWS AND VENTS NA NA
643 Frame NA NA
644 Fixed glass louvres window NA NA
645 Fixed glass panel window NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 80
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

646 DOOR INCLUDING IRONMONGERY NA NA


647 Door NA NA
648 hinges NA NA
649 lockset NA NA
650 door stopper NA NA
651 coat hook NA NA
652 FLOOR FINISHES NA NA
653 Apron NA NA
654 Tiles NA NA
655 WALL FINISHES NA NA
656 Plaster NA NA
657 Tiles NA NA
658 CEILING FINISHES NA NA
659 cement board NA NA
660 SANITARY APPLIANCES NA NA
661 water closet NA NA
662 Floor drainer NA NA
663 Mirror NA NA
664 bib tap NA NA
665 shower rose NA NA
666 tissue holder NA NA
667 Hand spray bidet NA NA
668 MISCELLANEOUS NA NA
669 SURFACE WATER DRAINAGE NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 81
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

670 Wiring NA NA
671 Lighting Installation NA NA
672 Compact Sub NA NA
673 Cable Trenches c/w Finishing NA NA
674 Signages NA NA
675 Meter Kiosk NA NA
676 Incoming Cable from TNB NA NA
677 Outgoing Cabble to MSB NA NA
678 Diesel Tank NA NA
679 Bund Wall NA NA
680 Diesel Pump Plinth NA NA
681 Diesel Tank Delivery NA NA
682 Diesel Tank Installation NA NA
683 Diesel Pump Delivery NA NA
684 Diesel Pump Installation NA NA
685 Diesel Genset Delivery NA NA
686 Diesel Genset Installation NA NA
687 Main Junction Modification NA NA
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit NA NA
689 RSA Stage 4 (Part 2) - Work Zone Audit NA NA
690 RSA Stage 4 (Part 3) - Re-Opening NA NA
691 RSA Stage 5 - Operational NA NA
692 New Additional Lane NA NA
693 Kerb NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 82
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

694 Resurface Existing Road NA NA


695 Reconstruct Existing Road NA NA
696 Road Marking & Furniture NA NA
697 External Work NA NA
698 Roadwork NA NA
699 Surface Water Drainage NA NA
700 Water Reticulation NA NA
701 Sewerage System NA NA
702 Fencing & Gate NA NA
703 Flag Poles NA NA
704 Catchment Pond NA NA
705 Meter Room, PPU NAKA NA NA
706 Meter Installation NA NA
707 Misscellanous NA NA
708 Landscape NA NA
709 Fence Base NA NA
710 Chain Link Fence Installation NA NA
711 Sliding Gate Installation NA NA
712 Flag Poles Base Construction NA NA
713 GI Flag Poles Installation NA NA
714 MECHANICAL & ELECTRICAL (M&E) NA NA
715 Non-Plant Mechanical Services NA NA
716 Weighbridge NA NA
717 Weigh Bridge Design & Engineering NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 83
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

718 Weigh Bridge Manufacturing NA NA


719 Weigh Bridge Delivery NA NA
720 Weigh Bridge Site Installation NA NA
721 Fire Fighting System NA NA
722 Hose Reel System NA NA
723 Fire Detection And Alarm System NA NA
724 Clean Agent & Co2 Fire Extinguisher NA NA
725 Portable Fire Extinguisher NA NA
726 Hydrant System NA NA
727 Sign And Notice NA NA
728 ACMV System NA NA
729 SPLIT UNIT AIR CONDITIONING SYSTEM NA NA
730 Indoor/Outdoor Unit NA NA
731 Copper Pipe NA NA
732 Condensate Pipe NA NA
733 ELECTRICAL NA NA
734 GRID INTERCONNECTION NA NA
735 PRELIMINARY WORK NA NA
736 Document to submit for IOD NA NA
737 Test result of interconnection facilities NA NA
738 Power quality report NA NA
739 To do protection setting on site NA NA
740 Reliability Report (RR) NA NA
741 Certificate for competent person for shutdown & testing NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 84
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

742 TRANSFORMER NA NA
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV NA NA
744 List of Testing NA NA
745 Method of Statement for Testing NA NA
746 Cert for competent person to test NA NA
747 Connection to Grid NA NA
748 Testing and commissioning (SAT) NA NA
749 Earthing NA NA
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV NA NA
751 List of Testing to Submit NA NA
752 Method of Statement for Testing NA NA
753 Cert for competent person to test NA NA
754 Cable Termination NA NA
755 Connection to plant NA NA
756 Testing and commissioning (SAT) NA NA
757 Earthing NA NA
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA) NA NA
759 Cable Termination NA NA
760 Installation/coupling NA NA
761 List of testing to submit NA NA
762 Method of Statement for testing NA NA
763 Testing and commissioning (SAT) NA NA
764 Earthing NA NA
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER) NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 85
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

766 Cable Termination NA NA


767 List of testing to submit NA NA
768 Method of Statement for testing NA NA
769 Testing and commissioning (SAT) NA NA
770 Earthing NA NA
771 REMOTE CONTROL PANEL (RCP) NA NA
772 Cable Termination NA NA
773 Fibre Termination NA NA
774 List of testing to submit NA NA
775 Method of Statement for testing NA NA
776 Testing and commissioning (SAT) NA NA
777 Earthing NA NA
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER) NA NA
779 Supply to the site NA NA
780 Panel Installation NA NA
781 Cable Termination NA NA
782 List of testing to submit NA NA
783 Method of Statement for testing NA NA
784 Testing and commissioning (SAT) NA NA
785 Earthing NA NA
786 REMOTE TERMINAL UNIT (RTU) NA NA
787 Supply & Install NA NA
788 Cable Termination NA NA
789 Fibre Termination NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 86
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

790 List of testing to submit NA NA


791 Method of Statement for testing NA NA
792 Testing and commissioning (SAT) NA NA
793 Earthing NA NA
794 FIBRE FROM PLANT TO PPU NAKA NA NA
795 Fibre Termination NA NA
796 List of testing to submit NA NA
797 Method of Statement for testing NA NA
798 Testing and commissioning (SAT) NA NA
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM) NA NA
800 Supply & Install NA NA
801 List of testing to submit NA NA
802 Method of Statement for testing NA NA
803 Testing and commissioning (SAT) NA NA
804 Earthing NA NA
805 33KV METERING PANEL AT CONSUMER SITE NA NA
806 Supply & Install NA NA
807 Testing and commissioning (SAT) NA NA
808 Earthing NA NA
809 FIBER TERMINATION PATCH FOR GRID NA NA
810 Supply & Install NA NA
811 Testing and commissioning (SAT) NA NA
812 OTDR result NA NA
813 POWER CABLE NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 87
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV) NA NA


815 Installation 3 phase straight joint c/w boding kit NA NA
816 Installation normal single phase straigh joint for cable NA NA
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka NA NA
818 Cert for cable tester NA NA
819 Testing and commissioning (SAT) NA NA
820 VLF test & other tests NA NA
821 1C X 185MM2 XLPE AI CABLE (33KV) NA NA
822 Supply to the site NA NA
823 Intallation cable tray/ladders and other accesorries NA NA
824 Inside Majunaka Substation NA NA
825 Inside PPU Naka NA NA
826 Burried direct ground with sand bending, excavation NA NA
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated NA NA
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund NA NA
829 Along road shoulder & tarcamadam road NA NA
830 lay & terminate to 33kV GIS c/w other accesorries NA NA
831 lay & terminate to 11kV AIS c/w other accesorries NA NA
832 lay & terminate to 11/33kv transformer c/w other accesorries NA NA
833 Cert for cable tester NA NA
834 VLF test & other tests NA NA

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 88
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV) NA NA


836 Supply to the site NA NA
837 Intallation cable tray/ladders and other accesorries NA NA
838 From 11kV panel to 12.5MVA transfomer NA NA
839 lay & terminate to 11kV AIS c/w other accesorries NA NA
840 lay & terminate to 11/33kv transformer c/w other accesorries NA NA
841 Cert for cable tester NA NA
842 VLF test & other tests NA NA
843 Low Voltage NA NA
844 MAIN SWITCH BOARD (MSB) NA NA
845 Supply to the site NA NA
846 Installation in Majunaka Substation NA NA
847 Cable termination incoming and outgoing NA NA
848 Method of statement for testing c/w test form and tester certificate NA NA
849 Site acceptence test for ; NA NA
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB NA NA
851 MSB A c/w breaking capacity 65kA, 1600A ACB NA NA
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole NA NA
Auto Transfer Switch (ATS)
853 MSB C NA NA
854 415V MOTOR CONTROL CENTER (MCC) NA NA
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20 NA NA
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20 NA NA
857 Cable Termination NA NA

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 89
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

858 List of testing to submit NA NA


859 Method of statement for testing c/w test form and tester certificate NA NA
860 Method of Statement for testing NA NA
861 Testing and commissioning (SAT) NA NA
862 Earthing NA NA
863 SUB SWITCHBOARD (SSB) NA NA
864 Supply and deliver to the site NA NA
865 Install SSB c/w overcurrent & earth leakage relay and other NA NA
accessories for;
866 2 SSB at building pentadbiran and tarbin NA NA
867 18 unit Distribution Board (DB) in Majunaka Plant NA NA
868 2 unit isolators at cold water system and DG control system NA NA
869 Street lighting Feeder Pillar NA NA
870 1600A Generator connection box NA NA
871 Meter Kiosk c/w plint and all else accessories as per TNB specification NA NA
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes NA NA
873 Earthing NA NA
874 GENERATOR SET NA NA
875 STANDBY 750KVA GENSET NA NA
876 Supply and deliver to the site NA NA
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable NA NA
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable NA NA
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 90
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

879 Install fuel piping NA NA


880 Earthing system NA NA
881 Install 24 hours fuel tank NA NA
882 24V nickel cadmium NA NA
883 Testing and commsioning NA NA
884 STANDBY 1000KVA GENSET NA NA
885 Supply, lay and terminate cable from Genset to AMF NA NA
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable NA NA
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable NA NA
from Genset to the MAB 1
888 Install fuel piping NA NA
889 Earthing system NA NA
890 Install 10,000 litre fuel tank NA NA
891 24V nickel cadmium NA NA
892 Testing and commsioning NA NA
893 SUBMAIN LV CABLING NA NA
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to NA NA
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C NA NA
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1 NA NA
897 Install floor penetration fire barrier of BOMBA NA NA
898 All outgoing cable from; NA NA

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 91
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

899 MSB A to all Sub-DB NA NA


900 MSB B to all Sub-DB NA NA
901 MSB C to all Sub-DB NA NA
902 SSB Tarbin NA NA
903 SSB Pentadbiran NA NA
904 Testing and commsioning NA NA
905 SUB-CIRCUIT & SMALL POWER WIRING NA NA
906 To wireup all lighting, sso, and other equipment NA NA
907 To supply and install conduit and trunking system NA NA
908 To supply and install underfloor ducting system NA NA
909 ELECTRICAL FITTINGS NA NA
910 Supply all fiting to all buiding NA NA
911 LIGHTNING PROTECTION SINGLE DOME NA NA
912 To install lighting protection NA NA
913 EARTHING NA NA
914 To install Earthing protection NA NA
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM NA NA
916 To supply street lighting / compound lighting system NA NA
917 To install street lighting / compound lighting system NA NA
918 TNC NA NA
919 NA NA
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20 NA NA
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20 NA NA
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20 NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 92
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20 NA NA
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20 NA NA
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20 NA NA
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20 NA NA
927 Plant DOSH Inspection NA NA
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20 NA NA
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20 NA NA
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20 NA NA
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20 NA NA
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20 NA NA
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20 NA NA
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20 NA NA
935 ACW System 4 days Wed 10/7/20Sat 10/10/20 NA NA
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20 NA NA
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20 NA NA
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20 NA NA
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20 NA NA
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20 NA NA
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20 NA NA
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20 NA NA
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20 NA NA
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20 NA NA
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20 NA NA
946 Plant Performance Test NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 93
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

947 Plant Reliability Run (RR) NA NA


948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20 NA NA
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu NA NA
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu NA NA
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20 NA NA
952 Review documents NA NA
953 Line walk at the plant NA NA
954 AT&PA activities at the plant NA NA
955 AT&PA Report preparation and submission NA NA
956 Review and approve AT&PA report NA NA
957 Upload AT&PA report in the e-FiT system NA NA
958 Approval and issuance of FiTCD letter Sat 11/14/20 NA NA
959 NA NA
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP) NA NA
961 Borang F1 NA NA
962 Bomba Inspection NA NA
963 Defect List NA NA
964 Operation and Maintenance Manual with As-Built Dwg NA NA
965 2.5% of the 5% retention sum NA NA
966 NA NA
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21 NA NA

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 94
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

968 G1 : KERJA-KERJA TANAH NA NA


969 G2 : PEMANCANGAN TANDA NA NA
970 G3 : ASAS TAPAK NA NA
971 G4 : STRUKTUR NA NA
972 G5 : PERPAIPAN AIR DALAMAN NA NA
973 G6 : PERPAIPAN SANITARI DALAMAN NA NA
974 G7 : ELEKTRIKAL DALAMAN NA NA
975 G8 : MENENTANG KEBAKARAN (PASIF) NA NA
976 G9 : MENENTANG KEBAKARAN (AKTIF) NA NA
977 G10 : PENGUDARAAN MEKANIKAL NA NA
978 G11 : PEMASANGAN LIF/ESKALATOR NA NA
979 G12 : BANGUNAN NA NA
980 G13 : SISTEM BEKALAN AIR LUARAN NA NA
981 G14 : RETIKULASI PEMBETUNGAN NA NA
982 G15 : LOJI RAWATAN PEMBETUNGAN NA NA
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN NA NA
984 G17 : JALAN DAN PARIT NA NA
985 G18 : LAMPU JALAN NA NA
986 G19 : PARIT LUARAN UTAMA NA NA
987 G20 : TELEKOMUNIKASI NA NA
988 G21 : PANDANGAN DARAT NA NA
989 Borang F NA NA
990 NA NA
991 MILESTONE PAYMENT NA NA
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 95
ID TaskTask Name Duration Start Finish Actual Start Actual Finish
Mode

992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20 NA NA


993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20 NA NA
994 MS 9 Upon Mechanical Completion of the Facility NA NA
995 MS 10 Upon Achieving Commercial Operation Date NA NA
996 NA NA
997 Certificate of Making Good Defects (CMGD) NA NA
998 Making good of defects NA NA
999 2.5% of the 5% retention sum NA NA
1000 NA NA
1001 FINAL ACCOUNT NA NA

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 96
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21 402 days
2 1 day?
3 POWER ISLAND 1 day?
4 Boiler 1 day?
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20 0 days
6 Boiler Pressure Part Fabrication 1 day?
7 Drum HT 1 day?
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20 1 day
9 Boiler Steam Drum Fitting Installation 1 day?
10 Boiler Main Tubes Installation 1 day?
11 Signages 1 day?
12 Boiler Non-Pressure Parts 1 day?
13 Boiler Structure, platform 1 day?
14 Boiler Structure Delivery 1 day?
15 Boiler Structure erection Wed 9/30/20 1 day?
16 Boiler House Top Structure Fabrication 1 day?
17 Boiler House Top Structure Delivery 1 day?
18 Boiler House Top Structure Erection 1 day?
19 Boiler House Roofing installation 1 day?
20 Blowdown Tank(M) 1 day?
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20 1 day
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20 3 days
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20 6 days
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20 1 day
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 97
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20 5 days
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20 2 days
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20 1 day?
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20 1 day
29 Installation 1 day?
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20 6 days
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20 1 day
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20 5 days
33 Flash Tank 1 day?
34 Flash tank assembly delivery Wed 9/30/20 1 day?
35 Flash tank assembly installation 1 day?
36 Flash tank fittings installation 1 day?
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20 1 day?
38 Boiler Site Installation Wed 9/30/20 1 day?
39 Structure & Frame 1 day?
40 Travelling Grate, Hopper 1 day?
41 Travelling Grate/Stoker Installation 1 day?
42 Ash Hopper (under Stoker) Installation 1 day?
43 Ash Conveyor Plinth 1 day?
44 Ash Conveyor Delivery 1 day?
45 Ash Conveyor Installation 1 day?
46 Refractory Application 1 day?
47 Temperory support, Drum Lift, Alignment, Securing 1 day?
48 Generating Tube (818 tubes) Mon 9/7/20 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 98
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
49 Header set up, waterwall, Superheater 1 day?
50 1st Superheater Tubes Installation c/w Headers 1 day?
51 1st Superheater Fitting Installation 1 day?
52 2nd Superheater Tubes Installation c/w Headers 1 day?
53 2nd Superheater Fitting Installation 1 day?
54 Downcomers Installation 1 day?
55 Water Tubes & Membran Wall Installation 1 day?
56 Economizer, Steam connection pipes, supports 1 day?
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20 1 day
58 Economizer assembly installation 1 day?
59 Economizer fitting installation 1 day?
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer 1 day?
61 Deaerator fitting installation 1 day?
62 CBD assembly Delivery 1 day?
63 CBD system installation 1 day?
64 CBD fittings installation 1 day?
65 Dust Collector Casing & accessories Wed 9/30/20 1 day?
66 Assemble fly ash dust collector frame assembly 1 day?
67 Dust Collector Inner pipe Outside Pipe Installation 1 day?
68 Dust Collector Guide Vane Damper Installation 1 day?
69 Rotary valve , hopper and casing Installation 1 day?
70 Steam Piping Installation c/w Insulation 1 day?
71 Air Duct Installation c/w Insulation 1 day?
72 Gas Duct Installation c/w Insulation 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 99
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
73 Accessories/fitings Installation 1 day?
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20 1 day?
75 Insulation and Boiler Outer Casing Application 1 day?
76 Boiler Outer Casing Finishing Paint Works 1 day?
77 Grating Installation 1 day?
78 HandRail Installation 1 day?
79 Sootblower Assembly Delivery 1 day?
80 Install Sootblower Frames and Hangers 1 day?
81 Assemble Long Retractable Sootblowers parts including 1 day?
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including 1 day?
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and 1 day?
drain valves
84 Install sootblower fittings 1 day?
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20 1 day?
86 Fuel Feeder Delivery 1 day?
87 Fuel Feeder Installation 1 day?
88 Service Silo Delivery 1 day?
89 Service Silo Installation 1 day?
90 Boiler Draft System Wed 9/30/20 1 day?
91 FD/ID Fans,Air Heater,Ducting Site Installation 1 day?
92 ID FAN 1 day?
93 Centering & Levelling 1 day?

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 100
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
94 Anchor Bolt Cementing 1 day?
95 Base Grouting 1 day?
96 Upper Casing Installation 1 day?
97 Suction Cone Installation 1 day?
98 Inlet Damper Installation 1 day?
99 Primary Force Draft Fan 1 day?
100 Centering & Levelling 1 day?
101 Anchor Bolt Cementing 1 day?
102 Base Grouting 1 day?
103 Upper Casing Installation 1 day?
104 Suction Cone Installation 1 day?
105 Inlet Damper Installation 1 day?
106 Silencer Installation 1 day?
107 Secondary Force Draft Fan 1 day?
108 Centering & Levelling 1 day?
109 Anchor Bolt Cementing 1 day?
110 Base Grouting 1 day?
111 Upper Casing Installation 1 day?
112 Suction Cone Installation 1 day?
113 Inlet Damper Installation 1 day?
114 Silencer Installation 1 day?
115 Chimney & CEMS 1 day?
116 Chimney Delivery Tue 9/15/20 1 day?
117 Chimney Stack Site Installation 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 101
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
118 Lifting, Centering & Levelling 1 day?
119 Anchor Bolt Tightening 1 day?
120 Erection 1 day?
121 CEMS COMPLETE Tue 9/22/20 1 day?
122 Steam Turbogenerator 1 day?
123 STG Site Installation 1 day?
124 Gland Sealing Condenser installation 1 day?
125 Reducton gear installation 1 day?
126 Alignment 1 day?
127 Oil unit installation 1 day?
128 Prefab pipes & Turbine cover installation 1 day?
129 Observation Gantry Fabrication 1 day?
130 Observation Gantry Installation 1 day?
131 Staircase & railing Fabrication 1 day?
132 Staircase & railing Installation 1 day?
133 Structure Erection 1 day?
134 Roofing Installation 1 day?
135 Cladding Installation 1 day?
136 Gutter Installation 1 day?
137 Floor Finishing 1 day?
138 Louvers Installation 1 day?
139 Overhead crane Installation 1 day?
140 ST-GB-GEN Lifting 1 day?
141 ST Centering & Levelling 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 102
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
142 Gearbox Centering & Levelling 1 day?
143 Generator Centering & Levelling 1 day?
144 STG Anchor Bolt Cementing 1 day?
145 STG Base Grouting 1 day?
146 ST - GB Alignment 1 day?
147 GB - Generator Alignment 1 day?
148 ST Piping Installation 1 day?
149 ST Insulation 1 day?
150 Lube Oil Unit Lifting 1 day?
151 Lube Oil Unit Centering & Levelling 1 day?
152 Lube Oil Unit Anchor Bolt Cementing 1 day?
153 Lube Oil Unit Base Grouting 1 day?
154 Steam Air Ejector Delivery 1 day?
155 Steam Air Ejector Installation 1 day?
156 Turbine Control Panel Installation (TCP) 1 day?
157 Cable Installation 1 day?
158 BALANCE OF PLANT 1 day?
159 Cooling Water System 1 day?
160 Vacumn Surface Condenser & Auxiliary 1 day?
161 VSC Factory Acceptance Test 1 day?
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20 1 day?
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20 3 days
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20 3 days
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20 5 days
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 103
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20 7 days
167 Air Cool Heat Exchanger 1 day?
168 Heat Exchanger Delivery Mon 9/7/20 1 day?
169 Heat Exchanger Site Installation 1 day?
170 ACHE Lifting & Positioning 1 day?
171 Main Cooling Water Pump Plinth 1 day?
172 Main Cooling Water Pump Delivery Wed 9/30/20 1 day?
173 Main Cooling Water Pump Installation 1 day?
174 Main Cooling Water Pump Anchor Bolt Cementing 1 day?
175 Main Cooling Water Pump Base Grouting 1 day?
176 Main Cooling Water Piping 1 day?
177 Main Cooling Water Valves/Fitting Installation 1 day?
178 Cooling Tower 1 day?
179 Cooling Tower Delivery Mon 9/28/20 1 day?
180 Cooling Tower Site Installation 1 day?
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20 1 day?
182 Auxiliary Cooling Water Pump Installation 1 day?
183 ESP 1 day Sat 9/12/20 Sat 9/12/20 1 day
184 ESP Delivery Sat 9/12/20 1 day?
185 ESP Site Installation 1 day?
186 ESP Structure/parts Delivery 1 day?
187 ESP Steel Support Structure Erection and Assembly 1 day?
188 Install Collecting & Emitting Plates/Electrode 1 day?
189 Install Rapping Hammer and Accessories 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 104
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
190 Install Inner and Outer Casing 1 day?
191 Install Ash Hopper 1 day?
192 Install Rotary Valves 1 day?
193 Install Transformer Rectifiers 1 day?
194 Install Inlet and Outlet Expansion Joint 1 day?
195 Install Inlet and Outlet Dampers 1 day?
196 Install gratings and railings 1 day?
197 Install all accessories and Fittings 1 day?
198 Fuel Handling And Ash Delivery System 1 day?
199 Fuel Handling 1 day?
200 Conveyor 1 day?
201 Fuel Handling Delivery Thu 10/1/20 1 day?
202 Fuel Handling Site Installation 1 day?
203 Fuel Conveyor (FC-2&3) Delivery 1 day?
204 Fuel Conveyor (FC-2&3) Installation 1 day?
205 Silo Diverter Valve Delivery 1 day?
206 Silo Diverter Valve Installation 1 day?
207 Silo Conveyor Structure Delivery 1 day?
208 Silo Conveyor Delivery (SC - 1&2) 1 day?
209 Silo Conveyor Structure Erection 1 day?
210 Silo Conveyor Installation (SC - 1&2) 1 day?
211 Biomass Silos 1 day?
212 Biomass Silo Delivery 1 day?
213 Biomass Silo Site Installation 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 105
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
214 Fuel Silo#1 Delivery Fri 9/25/20 1 day?
215 Fuel Silo#1 Installation 1 day?
216 Fuel Silo#2 Delivery 1 day?
217 Fuel Silo#2 Installation 1 day?
218 Fuel Silo#1 Rotor Delivery 1 day?
219 Fuel Silo#1 Rotor Installation 1 day?
220 Fuel Silo#2 Rotor Delivery 1 day?
221 Fuel Silo#2 Rotor Installation 1 day?
222 Ash System 1 day?
223 Ash Tank, Conveyor Design & Engineering 1 day?
224 Ash Tank, conveyor Manufacturing 1 day?
225 Ash Tank Delivery Thu 10/15/20 1 day?
226 Ash Tank Site Installation 1 day?
227 Bottom Ash Tank Design & Engineering 1 day?
228 Bottom Ash Tank, conveyor Manufacturing 1 day?
229 Bottom Ash Tank Delivery Thu 10/15/20 1 day?
230 Bottom Ash Tank Site Installation 1 day?
231 Structure Delivery 1 day?
232 Structure erection 1 day?
233 Tank Lifting/Installation 1 day?
234 Rotary valve installation 1 day?
235 Ash Conveyor Delivery 1 day?
236 Ash Conveyor Structure Delivery 1 day?
237 Ash Conveyor Structure Erection 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 106
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
238 Ash Conveyor Installation 1 day?
239 Screw Conveyor Delivery 1 day?
240 Screw Conveyor Structure Delivery 1 day?
241 Screw Conveyor Structure Erection 1 day?
242 Screw Conveyor Installation 1 day?
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20 1 day
244 Pumps Delivery Wed 9/30/20 1 day?
245 Pumps Site Installation 1 day?
246 Demin Water System 1 day?
247 Demin System 1 day?
248 Demin Water System Design & Engineering 1 day?
249 Demin Water System Manufacturing 1 day?
250 Demin Water System Delivery Tue 9/15/20 1 day?
251 Booster Pump Delivery 1 day?
252 Activated Carbon Filter Delivery 1 day?
253 Cation Exchange Filter Delivery 1 day?
254 Anion Exchange Filter Delivery 1 day?
255 HCL Tank Delivery 1 day?
256 NaOH Tank Delivery 1 day?
257 Boiler Compound Tank Delivery 1 day?
258 pH Chemical Tank Delivery 1 day?
259 Oxygen Scavenger Tank Delivery 1 day?
260 Anti Slime Tank Delivery 1 day?
261 Anti Scale Tank Delivery 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 107
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
262 pH Metering Pump Delivery 1 day?
263 Make Up Water Pump Delivery 1 day?
264 Demin Water Make Up Pump Delivery 1 day?
265 HP Boiler Dosing Pump Delivery 1 day?
266 LP Boiler Dosing Pump Delivery 1 day?
267 Anti Slime Dosing Pump Delivery 1 day?
268 Anti Scale Dosing Pump Delivery 1 day?
269 Demin Water System Site Installation 1 day?
270 Booster Pump Installation 1 day?
271 Activated Carbon Filter Installation 1 day?
272 Cation Exchange Filter Installation 1 day?
273 Anion Exchange Filter Installation 1 day?
274 HCL Tank Installation 1 day?
275 NaOH Tank Installation 1 day?
276 Boiler Compound Tank Installation 1 day?
277 pH Chemical Tank Installation 1 day?
278 Oxygen Scavenger Tank Installation 1 day?
279 Anti Slime Tank Installation 1 day?
280 Anti Scale Tank Installation 1 day?
281 pH Metering Pump Installation 1 day?
282 Make Up Water Pump Installation 1 day?
283 Demin Water Make Up Pump Installation 1 day?
284 HP Boiler Dosing Pump Installation 1 day?
285 LP Boiler Dosing Pump Installation 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 108
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
286 Anti Slime Dosing Pump Installation 1 day?
287 Anti Scale Dosing Pump Installation 1 day?
288 Demin Tank Design & Engineering 1 day?
289 Demin Tank Manufacturing 1 day?
290 Demin Tank Delivery Tue 9/15/20 1 day?
291 Demin Tank Site Installation 1 day?
292 Neutralization Tank Delivery 1 day?
293 Neutralization Tank Installation 1 day?
294 Valves/Fitting Installation 1 day?
295 Raw Water System 1 day?
296 Raw Water Tank Design & Engineering 1 day?
297 Raw Water Tank Manufacturing 1 day?
298 Raw Water Tank Delivery Tue 9/15/20 1 day?
299 Raw Water Tank Site Installation 1 day?
300 Neutralization System 1 day?
301 Plant Neutralization System Design & Engineering 1 day?
302 Plant Neutralization System Manufacturing 1 day?
303 Neutralizing System Delivery Wed 9/30/20 1 day?
304 Site Installation 1 day?
305 Diesel Oil Tank 1 day?
306 Diesel Oil Tank Design & Engineering 1 day?
307 Diesel Oil Tank Manufacturing 1 day?
308 Diesel Oil Tank Delivery 1 day?
309 Diesel Oil Tank Site Installation 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 109
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
310 Plant Engineering & Interconnection Piping 1 day?
311 Plant Interconnecting Pipes Design & Engineering 1 day?
312 Instrumentation engineering 1 day?
313 Instrumentation Manufacturing 1 day?
314 Plant Interconnecting Pipes Manufacturing 1 day?
315 Instrumentation Delivery Wed 9/30/20 1 day?
316 Plant Interconnecting Pipes Delivery Sun 9/27/20 1 day?
317 Site Installation Mon 10/5/20 1 day?
318 Power Island Electrical System 1 day?
319 Power Island Electrical System Design & Engineering 1 day?
320 Panel & Switch gear Manufacturing 1 day?
321 Material procurement 1 day?
322 Equipment & accessories delivery Sun 10/4/20 1 day?
323 Site Installation 1 day?
324 Grid Interconnection System (GIS) 1 day?
325 Electrical System Design & Engineering 1 day?
326 Transformer, Switch Gear, Equipment Manufacturing 1 day?
327 Plant Electrical System Delivery 1 day?
328 33kV & 11kV Cable Installation 1 day?
329 Sub station & Plant Site installation 1 day?
330 DCS 1 day?
331 DCS Delivery Wed 9/23/20 1 day?
332 DCS Site Installation 1 day?
333 Compressed Air System 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 110
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
334 Air Dryer Compressor Delivery Fri 9/25/20 1 day?
335 Air Dryer Compressor Site Installation 1 day?
336 Overhead Crane 1 day?
337 Overhead Crane Design & Engineering 1 day?
338 Overhead Crane Manufacturing 1 day?
339 Overhead Crane Delivery Fri 9/25/20 1 day?
340 Overhead Crane Site Installation 1 day?
341 CIVIL, STRUCTURAL & BUILDING 1 day?
342 Civil and Structural Work 1 day?
343 Turbine Hall & Switchboard Room 1 day?
344 GROUND FLOOR SLAB AND APRON 1 day?
345 FRAME 1 day?
346 Frame, column, 2nd Floor 1 day?
347 Column 1 day?
348 Upper floor beam 1 day?
349 Overhead Crane 1 day?
350 UPPER FLOOR 1 day?
351 STAIRCASES, STEPS AND FINISHES 1 day?
352 ROOFS Sun 9/13/20 1 day?
353 Roofing/Cladding,Structure 1 day?
354 ROOF TRUSSES 1 day?
355 Gutter 1 day?
356 Purlin 1 day?
357 ROOF COVERING 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 111
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
358 rainwater down pipe 1 day?
359 soffit of flat roof 1 day?
360 WALL Fri 9/18/20 1 day?
361 brickwall 1 day?
362 External wall cladding 1 day?
363 External wall louvres cladding 1 day?
364 External shera board wall cladding 1 day?
365 iron purlin 1 day?
366 WINDOWS AND VENTS Fri 9/25/20 1 day?
367 FRAME 1 day?
368 Glass 1 day?
369 louvres window 1 day?
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20 1 day?
371 Door 1 day?
372 Hinges 1 day?
373 Lockset 1 day?
374 door stopper 1 day?
375 Sliding Door 1 day?
376 FLOOR FINISHES Fri 9/25/20 1 day?
377 cement render 1 day?
378 WALL FINISHES 1 day?
379 plaster 1 day?
380 CEILING FINISHES 1 day?
381 skim coat 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 112
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
382 gypsum board ceiling 1 day?
383 HANDRAILS AND BALUSTRADINGS 1 day?
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20 7 days
385 MISCELLANEOUS 1 day?
386 SURFACE WATER DRAINAGE Wed 9/30/20 1 day?
387 ANTI-TERMITE TREATMENT 1 day?
388 ANTI-CLIMBED WALL Sat 10/10/20 1 day?
389 MCC Panel Room 1 day?
390 Staircase 1 day?
391 Door Installation Fri 9/25/20 1 day?
392 Wall Painting Fri 9/25/20 1 day?
393 Air Conditioner Installation 1 day?
394 Lighting Installation 1 day?
395 MCC Cabinets Delivery Wed 9/30/20 1 day?
396 MCC Cabinets Installation 1 day?
397 Cable Installation 1 day?
398 Main Switch Board Room 1 day?
399 Wall Painting 1 day?
400 Door Installation 1 day?
401 Floor Finishing (Power Flout) 1 day?
402 Air Conditioner Installation Sat 10/10/20 1 day?
403 Lighting Installation Sat 10/10/20 1 day?
404 Switch Boards Delivery 1 day?
405 Switch Boards Installation 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 113
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
406 Cables Installation 1 day?
407 Batery Room 1 day?
408 Wall Plastering 1 day?
409 Wall Painting 1 day?
410 Door Installation 1 day?
411 Floor Finishing (Power Flout) 1 day?
412 Wiring & Lighting Installation Sat 10/10/20 1 day?
413 Battery Delivery Thu 9/17/20 1 day?
414 Battery Installation 1 day?
415 Switch Gear Room 1 day?
416 Wall Painting 1 day?
417 Door Installation 1 day?
418 Floor Finishing (Power Flout) 1 day?
419 Air Conditioner Installation Sat 10/10/20 1 day?
420 Lighting Installation Sat 10/10/20 1 day?
421 Switch Gear 11kV Delivery Wed 9/30/20 1 day?
422 Switch Gear Installation 1 day?
423 Cables Installation 1 day?
424 Transformer Yard 1 day?
425 Roof column fabrication 1 day?
426 Roof Truss Fabrication 1 day?
427 Roof column Installation 1 day?
428 Roof Truss Installation 1 day?
429 Roofing installation 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 114
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
430 Anti-climb Fencing Installation 1 day?
431 Transformer Installation 1 day?
432 Cables Installation 1 day?
433 GIS - Pole Erection (Plant to PPU Naka) 1 day?
434 GIS - Cable Installation (Plant to PPU Naka) 1 day?
435 Control Room 1 day?
436 Brick Works Sat 9/12/20 1 day?
437 Wall Plastering Tue 9/22/20 1 day?
438 Wall Painting 1 day?
439 Door Installation 1 day?
440 Window Installation 1 day?
441 Floor Finishing (Tile) 1 day?
442 Ceiling Finishing 1 day?
443 Air Conditioner Installation Sat 10/10/20 1 day?
444 Lighting Installation Sat 10/10/20 1 day?
445 DCS System Delivery 1 day?
446 DCS System Installation 1 day?
447 Vacum Surface Condenser Floor 1 day?
448 Toilet 1 day?
449 VSC Delivery 1 day?
450 VSC Exhaust Duct Installation 1 day?
451 VSC Bellow Installation 1 day?
452 VSC Lifting to Base 1 day?
453 VSC Centering & Levelling 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 115
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
454 VSC Base Grouting 1 day?
455 Gland Condenser Delivery 1 day?
456 Gland Condenser Lifting to Base 1 day?
457 Gland Condenser Centering & Levelling 1 day?
458 Gland Condenser Anchor Bolt Cementing 1 day?
459 Gland Condenser Base Grouting 1 day?
460 Condensate Pump Delivery 1 day?
461 Condenser Pump Installation 1 day?
462 Condensate Pump Centering & Levelling 1 day?
463 Condensate Pump Alignment 1 day?
464 Condensate Pump Anchor Bolt Cementing 1 day?
465 Condensate Pump Base Grouting 1 day?
466 Air Compressor Delivery 1 day?
467 Air Filter Delivery 1 day?
468 Air Dryer Delivery 1 day?
469 Air Receiver Tank Delivery 1 day?
470 Air Compressor Installation 1 day?
471 Air Filter Installation 1 day?
472 Air Dryer Installation 1 day?
473 Air Receiver Tank Installation 1 day?
474 Accessories/Fitting Installation 1 day?
475 Compressed air piping Installation 1 day?
476 Demin Water Plant 1 day?
477 Foundation c/w apron & ramp 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 116
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
478 ROOFS Sun 9/13/20 1 day?
479 Roofing/Cladding 1 day?
480 ROOF TRUSSES 1 day?
481 Purlin 1 day?
482 ROOF COVERING 1 day?
483 Gutter & Downpipe Installation 1 day?
484 WALL Fri 9/18/20 1 day?
485 Wall/window/ceilings finishes 1 day?
486 External wall cladding 1 day?
487 Painting 1 day?
488 WINDOWS AND VENTS Fri 9/25/20 1 day?
489 Fixed glass panel window 1 day?
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20 1 day?
491 roller shutter 1 day?
492 FLOOR FINISHES Fri 9/25/20 1 day?
493 Floor Finishing (Power Flout) 1 day?
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20 10.13 days?
495 Miscellaneous 1 day?
496 SURFACE WATER DRAINAGE Wed 9/30/20 1 day?
497 Wiring & Lighting Installation Fri 10/9/20 1 day?
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20 1 day?
499 BOP SPARES DELIVERY Wed 9/30/20 1 day?
500 1 day?
501 NON-POWER ISLAND 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 117
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
502 CIVIL, STRUCTURAL & BUILDING 1 day?
503 Earth Work 1 day?
504 Slope Boundary (Re-Design & Re-Work) 1 day?
505 Retaining Wall-2 1 day?
506 Turfing 1 day?
507 Concrete Drains 1 day?
508 Civil and Structural Work 1 day?
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20 1 day?
510 GROUND FLOOR SLAB AND APRON 1 day?
511 Foundation c/w apron & ramp 1 day?
512 Conveyor Pit c/w Finishing 1 day?
513 Fuel Receiving Hopper Delivery 1 day?
514 Fuel Receiving Hopper Installation 1 day?
515 Fuel Conveyor (FC - 1A&1B) Delivery 1 day?
516 Fuel Conveyor (FC - 1A&1B) Installation 1 day?
517 ROOFS Wed 9/16/20 1 day?
518 Gutter 1 day?
519 Purlin 1 day?
520 ROOF COVERING 1 day?
521 Roofing/Cladding 1 day?
522 WALL 1 day?
523 BRICKWORK 1 day?
524 Wall Plastering 1 day?
525 External wall cladding 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 118
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
526 Painting 1 day?
527 WINDOWS AND VENTS 1 day?
528 ALUMINIUM LOUVRES WINDOW 1 day?
529 FLOOR FINISHES 1 day?
530 WALL FINISHES 1 day?
531 MISCELLANEOUS 1 day?
532 TRENCHES 1 day?
533 SURFACE WATER DRAINAGE 1 day?
534 External & Perimeter 1 day?
535 Architectural Finishes 1 day?
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20 1 day?
537 Water Tank (for Rain Water Harvesting) 1 day?
538 Wiring & Lighting Installation 1 day?
539 Hose Reel 1 day?
540 Sprinkler 1 day?
541 Administration Office Mon 9/21/20 1 day?
542 GROUND FLOOR SLAB AND APRON 1 day?
543 apron 1 day?
544 cable trench 1 day?
545 ramp 1 day?
546 FRAME 1 day?
547 Water tank plinth 1 day?
548 STAIRCASES, STEPS, RAMPS AND FINISHES 1 day?
549 SKIM COATING 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 119
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
550 ROOFS 1 day?
551 Trusses 1 day?
552 Purlin 1 day?
553 ROOF COVERING 1 day?
554 rainwater down pipe 1 day?
555 roof slab 1 day?
556 WALL 1 day?
557 Plaster 1 day?
558 Partition/Dry Wall Installation 1 day?
559 WINDOWS AND VENTS 1 day?
560 FRAME 1 day?
561 Glass 1 day?
562 DOOR INCLUDING IRONMONGERY 1 day?
563 DOOR 1 day?
564 door stopper 1 day?
565 hinges 1 day?
566 lockset 1 day?
567 sliding door 1 day?
568 FLOOR FINISHES 1 day?
569 floor tiles 1 day?
570 WALL FINISHES 1 day?
571 plaster 1 day?
572 wall tiles 1 day?
573 Painting 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 120
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
574 CEILING FINISHES 1 day?
575 skim coat 1 day?
576 gypsum board 1 day?
577 ceiling lining 1 day?
578 paint 1 day?
579 SANITARY APPLIANCES 1 day?
580 Pedestal water closet 1 day?
581 wash hand basin 1 day?
582 handicap basin 1 day?
583 Hand spray bidet 1 day?
584 tissue holder 1 day?
585 shower rose 1 day?
586 bib tap 1 day?
587 soap dispenser 1 day?
588 grab rail 1 day?
589 swing-up support rail 1 day?
590 Mirror 1 day?
591 Floor drainer 1 day?
592 trash bin 1 day?
593 scupper drain 1 day?
594 counter top 1 day?
595 toilet cubicle 1 day?
596 HANDRAILS AND BALUSTRADINGS 1 day?
597 MISCELLANEOUS 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 121
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
598 Mild steel grillwork 1 day?
599 SURFACE WATER DRAINAGE 1 day?
600 Architectural Finishes 1 day?
601 Mechanical & Electrical 1 day?
602 External & Perimeter 1 day?
603 Wiring 1 day?
604 Air Conditioner Installation 1 day?
605 Lighting Installation 1 day?
606 Plant Storage 1 day?
607 Foundation c/w apron & ramp 1 day?
608 ROOFS 1 day?
609 Roofing/Cladding 1 day?
610 ROOF TRUSSES 1 day?
611 Purlin 1 day?
612 ROOF COVERING 1 day?
613 Gutter & Downpipe Installation 1 day?
614 WALL 1 day?
615 Brickwall 1 day?
616 Wall Plastering 1 day?
617 Painting 1 day?
618 WINDOWS AND VENTS 1 day?
619 Lintol 1 day?
620 Fixed glass louvres window 1 day?
621 DOOR INCLUDING IRONMONGERY 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 122
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
622 Lintol 1 day?
623 DOOR 1 day?
624 roller shutter 1 day?
625 FLOOR FINISHES 1 day?
626 Floor Finishing (Power Flout) 1 day?
627 WALL FINISHES 1 day?
628 Wall/window/ceilings finishes 1 day?
629 Plaster 1 day?
630 MISCELLANEOUS 1 day?
631 Miscellaneous 1 day?
632 SURFACE WATER DRAINAGE 1 day?
633 Wiring & Lighting Installation 1 day?
634 Guardhouse 1 day?
635 ROOFS 1 day?
636 Roofing/Cladding 1 day?
637 ROOF TRUSSES 1 day?
638 Purlin 1 day?
639 ROOF COVERING 1 day?
640 WALL 1 day?
641 Wall/window/ceilings finishes 1 day?
642 WINDOWS AND VENTS 1 day?
643 Frame 1 day?
644 Fixed glass louvres window 1 day?
645 Fixed glass panel window 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 123
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
646 DOOR INCLUDING IRONMONGERY 1 day?
647 Door 1 day?
648 hinges 1 day?
649 lockset 1 day?
650 door stopper 1 day?
651 coat hook 1 day?
652 FLOOR FINISHES 1 day?
653 Apron 1 day?
654 Tiles 1 day?
655 WALL FINISHES 1 day?
656 Plaster 1 day?
657 Tiles 1 day?
658 CEILING FINISHES 1 day?
659 cement board 1 day?
660 SANITARY APPLIANCES 1 day?
661 water closet 1 day?
662 Floor drainer 1 day?
663 Mirror 1 day?
664 bib tap 1 day?
665 shower rose 1 day?
666 tissue holder 1 day?
667 Hand spray bidet 1 day?
668 MISCELLANEOUS 1 day?
669 SURFACE WATER DRAINAGE 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 124
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
670 Wiring 1 day?
671 Lighting Installation 1 day?
672 Compact Sub 1 day?
673 Cable Trenches c/w Finishing 1 day?
674 Signages 1 day?
675 Meter Kiosk 1 day?
676 Incoming Cable from TNB 1 day?
677 Outgoing Cabble to MSB 1 day?
678 Diesel Tank 1 day?
679 Bund Wall 1 day?
680 Diesel Pump Plinth 1 day?
681 Diesel Tank Delivery 1 day?
682 Diesel Tank Installation 1 day?
683 Diesel Pump Delivery 1 day?
684 Diesel Pump Installation 1 day?
685 Diesel Genset Delivery 1 day?
686 Diesel Genset Installation 1 day?
687 Main Junction Modification 1 day?
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit 1 day?
689 RSA Stage 4 (Part 2) - Work Zone Audit 1 day?
690 RSA Stage 4 (Part 3) - Re-Opening 1 day?
691 RSA Stage 5 - Operational 1 day?
692 New Additional Lane 1 day?
693 Kerb 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 125
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
694 Resurface Existing Road 1 day?
695 Reconstruct Existing Road 1 day?
696 Road Marking & Furniture 1 day?
697 External Work 1 day?
698 Roadwork 1 day?
699 Surface Water Drainage 1 day?
700 Water Reticulation 1 day?
701 Sewerage System 1 day?
702 Fencing & Gate 1 day?
703 Flag Poles 1 day?
704 Catchment Pond 1 day?
705 Meter Room, PPU NAKA 1 day?
706 Meter Installation 1 day?
707 Misscellanous 1 day?
708 Landscape 1 day?
709 Fence Base 1 day?
710 Chain Link Fence Installation 1 day?
711 Sliding Gate Installation 1 day?
712 Flag Poles Base Construction 1 day?
713 GI Flag Poles Installation 1 day?
714 MECHANICAL & ELECTRICAL (M&E) 1 day?
715 Non-Plant Mechanical Services 1 day?
716 Weighbridge 1 day?
717 Weigh Bridge Design & Engineering 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 126
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
718 Weigh Bridge Manufacturing 1 day?
719 Weigh Bridge Delivery 1 day?
720 Weigh Bridge Site Installation 1 day?
721 Fire Fighting System 1 day?
722 Hose Reel System 1 day?
723 Fire Detection And Alarm System 1 day?
724 Clean Agent & Co2 Fire Extinguisher 1 day?
725 Portable Fire Extinguisher 1 day?
726 Hydrant System 1 day?
727 Sign And Notice 1 day?
728 ACMV System 1 day?
729 SPLIT UNIT AIR CONDITIONING SYSTEM 1 day?
730 Indoor/Outdoor Unit 1 day?
731 Copper Pipe 1 day?
732 Condensate Pipe 1 day?
733 ELECTRICAL 1 day
734 GRID INTERCONNECTION 1 day
735 PRELIMINARY WORK 1 day
736 Document to submit for IOD 1 day?
737 Test result of interconnection facilities 1 day?
738 Power quality report 1 day?
739 To do protection setting on site 1 day?
740 Reliability Report (RR) 1 day?
741 Certificate for competent person for shutdown & testing 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 127
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
742 TRANSFORMER 1 day?
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV 1 day?
744 List of Testing 1 day?
745 Method of Statement for Testing 1 day?
746 Cert for competent person to test 1 day?
747 Connection to Grid 1 day?
748 Testing and commissioning (SAT) 1 day?
749 Earthing 1 day?
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV 1 day?
751 List of Testing to Submit 1 day?
752 Method of Statement for Testing 1 day?
753 Cert for competent person to test 1 day?
754 Cable Termination 1 day?
755 Connection to plant 1 day?
756 Testing and commissioning (SAT) 1 day?
757 Earthing 1 day?
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA) 1 day?
759 Cable Termination 1 day?
760 Installation/coupling 1 day?
761 List of testing to submit 1 day?
762 Method of Statement for testing 1 day?
763 Testing and commissioning (SAT) 1 day?
764 Earthing 1 day?
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER) 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 128
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
766 Cable Termination 1 day?
767 List of testing to submit 1 day?
768 Method of Statement for testing 1 day?
769 Testing and commissioning (SAT) 1 day?
770 Earthing 1 day?
771 REMOTE CONTROL PANEL (RCP) 1 day?
772 Cable Termination 1 day?
773 Fibre Termination 1 day?
774 List of testing to submit 1 day?
775 Method of Statement for testing 1 day?
776 Testing and commissioning (SAT) 1 day?
777 Earthing 1 day?
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER) 1 day?
779 Supply to the site 1 day?
780 Panel Installation 1 day?
781 Cable Termination 1 day?
782 List of testing to submit 1 day?
783 Method of Statement for testing 1 day?
784 Testing and commissioning (SAT) 1 day?
785 Earthing 1 day?
786 REMOTE TERMINAL UNIT (RTU) 1 day?
787 Supply & Install 1 day?
788 Cable Termination 1 day?
789 Fibre Termination 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 129
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
790 List of testing to submit 1 day?
791 Method of Statement for testing 1 day?
792 Testing and commissioning (SAT) 1 day?
793 Earthing 1 day?
794 FIBRE FROM PLANT TO PPU NAKA 1 day?
795 Fibre Termination 1 day?
796 List of testing to submit 1 day?
797 Method of Statement for testing 1 day?
798 Testing and commissioning (SAT) 1 day?
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM) 1 day?
800 Supply & Install 1 day?
801 List of testing to submit 1 day?
802 Method of Statement for testing 1 day?
803 Testing and commissioning (SAT) 1 day?
804 Earthing 1 day?
805 33KV METERING PANEL AT CONSUMER SITE 1 day?
806 Supply & Install 1 day?
807 Testing and commissioning (SAT) 1 day?
808 Earthing 1 day?
809 FIBER TERMINATION PATCH FOR GRID 1 day?
810 Supply & Install 1 day?
811 Testing and commissioning (SAT) 1 day?
812 OTDR result 1 day?
813 POWER CABLE 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 130
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV) 1 day?
815 Installation 3 phase straight joint c/w boding kit 1 day?
816 Installation normal single phase straigh joint for cable 1 day?
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka 1 day?
818 Cert for cable tester 1 day?
819 Testing and commissioning (SAT) 1 day?
820 VLF test & other tests 1 day?
821 1C X 185MM2 XLPE AI CABLE (33KV) 1 day?
822 Supply to the site 1 day?
823 Intallation cable tray/ladders and other accesorries 1 day?
824 Inside Majunaka Substation 1 day?
825 Inside PPU Naka 1 day?
826 Burried direct ground with sand bending, excavation 1 day?
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated 1 day?
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund 1 day?
829 Along road shoulder & tarcamadam road 1 day?
830 lay & terminate to 33kV GIS c/w other accesorries 1 day?
831 lay & terminate to 11kV AIS c/w other accesorries 1 day?
832 lay & terminate to 11/33kv transformer c/w other accesorries 1 day?
833 Cert for cable tester 1 day?
834 VLF test & other tests 1 day?

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 131
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV) 1 day?
836 Supply to the site 1 day?
837 Intallation cable tray/ladders and other accesorries 1 day?
838 From 11kV panel to 12.5MVA transfomer 1 day?
839 lay & terminate to 11kV AIS c/w other accesorries 1 day?
840 lay & terminate to 11/33kv transformer c/w other accesorries 1 day?
841 Cert for cable tester 1 day?
842 VLF test & other tests 1 day?
843 Low Voltage 1 day?
844 MAIN SWITCH BOARD (MSB) 1 day?
845 Supply to the site 1 day?
846 Installation in Majunaka Substation 1 day?
847 Cable termination incoming and outgoing 1 day?
848 Method of statement for testing c/w test form and tester certificate 1 day?
849 Site acceptence test for ; 1 day?
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB 1 day?
851 MSB A c/w breaking capacity 65kA, 1600A ACB 1 day?
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole 1 day?
Auto Transfer Switch (ATS)
853 MSB C 1 day?
854 415V MOTOR CONTROL CENTER (MCC) 1 day?
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20 1 day
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20 3 days
857 Cable Termination 1 day?

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 132
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
858 List of testing to submit 1 day?
859 Method of statement for testing c/w test form and tester certificate 1 day?
860 Method of Statement for testing 1 day?
861 Testing and commissioning (SAT) 1 day?
862 Earthing 1 day?
863 SUB SWITCHBOARD (SSB) 1 day?
864 Supply and deliver to the site 1 day?
865 Install SSB c/w overcurrent & earth leakage relay and other 1 day?
accessories for;
866 2 SSB at building pentadbiran and tarbin 1 day?
867 18 unit Distribution Board (DB) in Majunaka Plant 1 day?
868 2 unit isolators at cold water system and DG control system 1 day?
869 Street lighting Feeder Pillar 1 day?
870 1600A Generator connection box 1 day?
871 Meter Kiosk c/w plint and all else accessories as per TNB specification 1 day?
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes 1 day?
873 Earthing 1 day?
874 GENERATOR SET 1 day?
875 STANDBY 750KVA GENSET 1 day?
876 Supply and deliver to the site 1 day?
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable 1 day?
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable 1 day?
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 133
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
879 Install fuel piping 1 day?
880 Earthing system 1 day?
881 Install 24 hours fuel tank 1 day?
882 24V nickel cadmium 1 day?
883 Testing and commsioning 1 day?
884 STANDBY 1000KVA GENSET 1 day?
885 Supply, lay and terminate cable from Genset to AMF 1 day?
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable 1 day?
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable 1 day?
from Genset to the MAB 1
888 Install fuel piping 1 day?
889 Earthing system 1 day?
890 Install 10,000 litre fuel tank 1 day?
891 24V nickel cadmium 1 day?
892 Testing and commsioning 1 day?
893 SUBMAIN LV CABLING 1 day?
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to 1 day?
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C 1 day?
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1 1 day?
897 Install floor penetration fire barrier of BOMBA 1 day?
898 All outgoing cable from; 1 day?

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 134
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
899 MSB A to all Sub-DB 1 day?
900 MSB B to all Sub-DB 1 day?
901 MSB C to all Sub-DB 1 day?
902 SSB Tarbin 1 day?
903 SSB Pentadbiran 1 day?
904 Testing and commsioning 1 day?
905 SUB-CIRCUIT & SMALL POWER WIRING 1 day?
906 To wireup all lighting, sso, and other equipment 1 day?
907 To supply and install conduit and trunking system 1 day?
908 To supply and install underfloor ducting system 1 day?
909 ELECTRICAL FITTINGS 1 day?
910 Supply all fiting to all buiding 1 day?
911 LIGHTNING PROTECTION SINGLE DOME 1 day?
912 To install lighting protection 1 day?
913 EARTHING 1 day?
914 To install Earthing protection 1 day?
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM 1 day?
916 To supply street lighting / compound lighting system 1 day?
917 To install street lighting / compound lighting system 1 day?
918 TNC 1 day?
919 1 day?
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20 36 days
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20 28.13 days
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20 14 days
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 135
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20 3 days
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20 3 days
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20 1 day
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20 1 day
927 Plant DOSH Inspection 1 day?
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20 38.63 days
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20 4 days
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20 4 days
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20 4 days
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20 4 days
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20 4 days
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20 4 days
935 ACW System 4 days Wed 10/7/20Sat 10/10/20 4 days
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20 3 days
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20 3 days
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20 1 day
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20 1 day
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20 2 days
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20 3 days
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20 3 days
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20 5 days
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20 2 days
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20 0 days
946 Plant Performance Test 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 136
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
947 Plant Reliability Run (RR) 1 day?
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20 17.25 days?
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu 1 day
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu 1 day
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20 1 day
952 Review documents 1 day?
953 Line walk at the plant 1 day?
954 AT&PA activities at the plant 1 day?
955 AT&PA Report preparation and submission 1 day?
956 Review and approve AT&PA report 1 day?
957 Upload AT&PA report in the e-FiT system 1 day?
958 Approval and issuance of FiTCD letter Sat 11/14/20 1 day?
959 1 day?
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP) 1 day?
961 Borang F1 1 day?
962 Bomba Inspection 1 day?
963 Defect List 1 day?
964 Operation and Maintenance Manual with As-Built Dwg 1 day?
965 2.5% of the 5% retention sum 1 day?
966 1 day?
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21 92 days

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 137
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
968 G1 : KERJA-KERJA TANAH 1 day?
969 G2 : PEMANCANGAN TANDA 1 day?
970 G3 : ASAS TAPAK 1 day?
971 G4 : STRUKTUR 1 day?
972 G5 : PERPAIPAN AIR DALAMAN 1 day?
973 G6 : PERPAIPAN SANITARI DALAMAN 1 day?
974 G7 : ELEKTRIKAL DALAMAN 1 day?
975 G8 : MENENTANG KEBAKARAN (PASIF) 1 day?
976 G9 : MENENTANG KEBAKARAN (AKTIF) 1 day?
977 G10 : PENGUDARAAN MEKANIKAL 1 day?
978 G11 : PEMASANGAN LIF/ESKALATOR 1 day?
979 G12 : BANGUNAN 1 day?
980 G13 : SISTEM BEKALAN AIR LUARAN 1 day?
981 G14 : RETIKULASI PEMBETUNGAN 1 day?
982 G15 : LOJI RAWATAN PEMBETUNGAN 1 day?
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN 1 day?
984 G17 : JALAN DAN PARIT 1 day?
985 G18 : LAMPU JALAN 1 day?
986 G19 : PARIT LUARAN UTAMA 1 day?
987 G20 : TELEKOMUNIKASI 1 day?
988 G21 : PANDANGAN DARAT 1 day?
989 Borang F 1 day?
990 1 day?
991 MILESTONE PAYMENT 1 day?
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 138
ID TaskTask Name Duration Start Finish Remaining
Mode Duration November 1 Dec
11/5 11/19 1
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20 1 day?
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20 1 day
994 MS 9 Upon Mechanical Completion of the Facility 1 day?
995 MS 10 Upon Achieving Commercial Operation Date 1 day?
996 1 day?
997 Certificate of Making Good Defects (CMGD) 1 day?
998 Making good of defects 1 day?
999 2.5% of the 5% retention sum 1 day?
1000 1 day?
1001 FINAL ACCOUNT 1 day?

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 139
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1
12/3 12/17 12/31 1/14
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 Marc
1/14 1/28 2/11 2/25
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/25 3/11 3/25 4/8
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/8 4/22 5/6 5/20
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/20 6/3 6/17 7/1
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1
7/1 7/15 7/29 8/12
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 O
8/12 8/26 9/9 9/23
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novembe
9/23 10/7 10/21 11/4
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1
11/4 11/18 12/2 12/16
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 Febr
12/16 12/30 1/13 1/27
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 March 1
1/27 2/10 2/24 3/10
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 M
3/10 3/24 4/7 4/21
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode April 1 May 1 June 1
4/21 5/5 5/19 6/2
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode June 1 July 1
6/2 6/16 6/30 7/14
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 Se
7/14 7/28 8/11 8/25
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode August 1 September 1 October 1
8/25 9/8 9/22 10/6
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode October 1 November 1
10/6 10/20 11/3 11/17
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 Janua
11/17 12/1 12/15 12/29
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode December 1 January 1 February 1
12/29 1/12 1/26 2/9
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 140
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 141
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 142
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 A
2/9 2/23 3/8 3/22
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 143
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 144
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 145
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 146
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 147
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 147
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode March 1 April 1 May 1
3/22 4/5 4/19 5/3
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 148
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 149
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 150
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 151
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 152
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 152
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode May 1 June 1
5/3 5/17 5/31 6/14
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 153
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 154
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 155
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 156
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 Aug
6/14 6/28 7/12 7/26
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20 9/1
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 157
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 158
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 159
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 160
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 160
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 161
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 162
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 163
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 164
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 165
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 166
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 167
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 168
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 169
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 170
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 171
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 172
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 173
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 174
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 175
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 176
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 177
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 178
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 179
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 179
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 179
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 180
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 181
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 182
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 183
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 184
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 185
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 186
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 187
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 188
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 189
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 190
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 191
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 192
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 193
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 194
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 195
ID TaskTask Name Duration Start Finish
Mode July 1 August 1 September
7/26 8/9 8/23 9/6
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 195
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20 9/1
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 196
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 197
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 198
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 199
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 200
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 201
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 201
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 202
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 203
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 204
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 205
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 206
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 206
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 207
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 208
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 209
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 210
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 211
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 212
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 213
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 214
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 215
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 216
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 217
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 218
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 219
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 219
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 219
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 219
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 219
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 219
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 220
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 220
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 220
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 220
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 220
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 221
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 221
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 221
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20 1
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 222
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 223
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 224
ID TaskTask Name Duration Start Finish
Mode September 1 October 1
9/6 9/20 10/4 10/18
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 225
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 226
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 227
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20 10/25
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 228
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 229
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 230
ID TaskTask Name Duration Start Finish
Mode October 1 November 1 Decem
10/18 11/1 11/15 11/29
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 230
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 230
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days 10/25
Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 231
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 232
ID TaskTask Name Duration Start Finish
Mode November 1 December 1 January 1
11/29 12/13 12/27 1/10
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 232
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 232
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 233
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 234
ID TaskTask Name Duration Start Finish
Mode January 1 February 1 M
1/10 1/24 2/7 2/21
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 234
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 234
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 235
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 236
ID TaskTask Name Duration Start Finish
Mode February 1 March 1 April 1
2/21 3/7 3/21 4/4
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 236
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 236
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode April 1 May 1
4/4 4/18 5/2 5/16
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 237
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode May 1 June 1 July 1
5/16 5/30 6/13 6/27
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 238
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode June 1 July 1 August 1
6/27 7/11 7/25 8/8
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 239
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode August 1 September 1
8/8 8/22 9/5 9/19
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
1 Majunaka Rice Husk Power Plant Project 402 days Tue 9/1/20 Thu 9/30/21
2
3 POWER ISLAND
4 Boiler
5 Boiler Design Approval (DOSH) 0 days Tue 9/1/20 Tue 9/1/20
6 Boiler Pressure Part Fabrication
7 Drum HT
8 Boiler Pressure Part Delivery (2nd Shipment) 1 day Tue 4/14/20 Tue 4/14/20
9 Boiler Steam Drum Fitting Installation
10 Boiler Main Tubes Installation
11 Signages
12 Boiler Non-Pressure Parts
13 Boiler Structure, platform
14 Boiler Structure Delivery
15 Boiler Structure erection Wed 9/30/20
16 Boiler House Top Structure Fabrication
17 Boiler House Top Structure Delivery
18 Boiler House Top Structure Erection
19 Boiler House Roofing installation
20 Blowdown Tank(M)
21 Delivery 1 day Fri 9/18/20 Fri 9/18/20
22 Install, Anchor Bolt, Grouting 3 days Sat 9/19/20 Mon 9/21/20
23 Steam Connecting pipes,bracket,stopper & accessories(M) 6 days Fri 9/18/20 Wed 9/23/20
24 Delivery 1 day Fri 9/18/20 Fri 9/18/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 240
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
25 Installation of Spool, Valves & accessories 5 days Sat 9/19/20 Wed 9/23/20
26 Welding & RT(TA) 2 days Mon 9/21/20Wed 9/23/20
27 Air Duct, Gas Duct Assembly(B) 1 day? Sun 9/20/20 Sun 9/20/20
28 Delivery 1 day Sun 9/20/20 Sun 9/20/20
29 Installation
30 Air Preheater(M) 6 days Fri 9/18/20 Wed 9/23/20
31 APH Delivery 1 day Fri 9/18/20 Fri 9/18/20
32 APH Installation 5 days Sat 9/19/20 Wed 9/23/20
33 Flash Tank
34 Flash tank assembly delivery Wed 9/30/20
35 Flash tank assembly installation
36 Flash tank fittings installation
37 Refactories, Brick, Anchor, Insulation Sat 10/10/20
38 Boiler Site Installation Wed 9/30/20
39 Structure & Frame
40 Travelling Grate, Hopper
41 Travelling Grate/Stoker Installation
42 Ash Hopper (under Stoker) Installation
43 Ash Conveyor Plinth
44 Ash Conveyor Delivery
45 Ash Conveyor Installation
46 Refractory Application
47 Temperory support, Drum Lift, Alignment, Securing
48 Generating Tube (818 tubes) Mon 9/7/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
49 Header set up, waterwall, Superheater
50 1st Superheater Tubes Installation c/w Headers
51 1st Superheater Fitting Installation
52 2nd Superheater Tubes Installation c/w Headers
53 2nd Superheater Fitting Installation
54 Downcomers Installation
55 Water Tubes & Membran Wall Installation
56 Economizer, Steam connection pipes, supports
57 Economizer Delivery 1 day Mon 2/24/20Mon 2/24/20
58 Economizer assembly installation
59 Economizer fitting installation
60 Deaerator, Flash Tank, CBDE, Blowdown, Silencer
61 Deaerator fitting installation
62 CBD assembly Delivery
63 CBD system installation
64 CBD fittings installation
65 Dust Collector Casing & accessories Wed 9/30/20
66 Assemble fly ash dust collector frame assembly
67 Dust Collector Inner pipe Outside Pipe Installation
68 Dust Collector Guide Vane Damper Installation
69 Rotary valve , hopper and casing Installation
70 Steam Piping Installation c/w Insulation
71 Air Duct Installation c/w Insulation
72 Gas Duct Installation c/w Insulation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
73 Accessories/fitings Installation
74 Inner & Outer casing, soot blower, insulation acc. Wed 9/30/20
75 Insulation and Boiler Outer Casing Application
76 Boiler Outer Casing Finishing Paint Works
77 Grating Installation
78 HandRail Installation
79 Sootblower Assembly Delivery
80 Install Sootblower Frames and Hangers
81 Assemble Long Retractable Sootblowers parts including
Poppet Valves and Motor
82 Assemble Rotary Retractable Sootblowers parts including
Poppet Valves and Motor
83 Connect and weld sootblower pipings, main stop valve, and
drain valves
84 Install sootblower fittings
85 Service Silo, Screw conveyor, RV, duct connection Wed 9/30/20
86 Fuel Feeder Delivery
87 Fuel Feeder Installation
88 Service Silo Delivery
89 Service Silo Installation
90 Boiler Draft System Wed 9/30/20
91 FD/ID Fans,Air Heater,Ducting Site Installation
92 ID FAN
93 Centering & Levelling

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
94 Anchor Bolt Cementing
95 Base Grouting
96 Upper Casing Installation
97 Suction Cone Installation
98 Inlet Damper Installation
99 Primary Force Draft Fan
100 Centering & Levelling
101 Anchor Bolt Cementing
102 Base Grouting
103 Upper Casing Installation
104 Suction Cone Installation
105 Inlet Damper Installation
106 Silencer Installation
107 Secondary Force Draft Fan
108 Centering & Levelling
109 Anchor Bolt Cementing
110 Base Grouting
111 Upper Casing Installation
112 Suction Cone Installation
113 Inlet Damper Installation
114 Silencer Installation
115 Chimney & CEMS
116 Chimney Delivery Tue 9/15/20
117 Chimney Stack Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
118 Lifting, Centering & Levelling
119 Anchor Bolt Tightening
120 Erection
121 CEMS COMPLETE Tue 9/22/20
122 Steam Turbogenerator
123 STG Site Installation
124 Gland Sealing Condenser installation
125 Reducton gear installation
126 Alignment
127 Oil unit installation
128 Prefab pipes & Turbine cover installation
129 Observation Gantry Fabrication
130 Observation Gantry Installation
131 Staircase & railing Fabrication
132 Staircase & railing Installation
133 Structure Erection
134 Roofing Installation
135 Cladding Installation
136 Gutter Installation
137 Floor Finishing
138 Louvers Installation
139 Overhead crane Installation
140 ST-GB-GEN Lifting
141 ST Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
142 Gearbox Centering & Levelling
143 Generator Centering & Levelling
144 STG Anchor Bolt Cementing
145 STG Base Grouting
146 ST - GB Alignment
147 GB - Generator Alignment
148 ST Piping Installation
149 ST Insulation
150 Lube Oil Unit Lifting
151 Lube Oil Unit Centering & Levelling
152 Lube Oil Unit Anchor Bolt Cementing
153 Lube Oil Unit Base Grouting
154 Steam Air Ejector Delivery
155 Steam Air Ejector Installation
156 Turbine Control Panel Installation (TCP)
157 Cable Installation
158 BALANCE OF PLANT
159 Cooling Water System
160 Vacumn Surface Condenser & Auxiliary
161 VSC Factory Acceptance Test
162 VSC Delivery 1 day? Wed 9/30/20Wed 9/30/20
163 VSC & Duct Site Installation 3 days Thu 10/1/20 Sat 10/3/20
164 Steam Air Ejector,flash box, Relief Valve Installation 3 days Thu 10/1/20 Sat 10/3/20
165 Condensate Pumps Installation 5 days Thu 10/1/20 Mon 10/5/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
166 Pre-fab pipes & accessories Site Installation 7 days Sun 10/4/20 Sat 10/10/20
167 Air Cool Heat Exchanger
168 Heat Exchanger Delivery Mon 9/7/20
169 Heat Exchanger Site Installation
170 ACHE Lifting & Positioning
171 Main Cooling Water Pump Plinth
172 Main Cooling Water Pump Delivery Wed 9/30/20
173 Main Cooling Water Pump Installation
174 Main Cooling Water Pump Anchor Bolt Cementing
175 Main Cooling Water Pump Base Grouting
176 Main Cooling Water Piping
177 Main Cooling Water Valves/Fitting Installation
178 Cooling Tower
179 Cooling Tower Delivery Mon 9/28/20
180 Cooling Tower Site Installation
181 Auxiliary Cooling Water Pump Delivery Mon 9/28/20
182 Auxiliary Cooling Water Pump Installation
183 ESP 1 day Sat 9/12/20 Sat 9/12/20
184 ESP Delivery Sat 9/12/20
185 ESP Site Installation
186 ESP Structure/parts Delivery
187 ESP Steel Support Structure Erection and Assembly
188 Install Collecting & Emitting Plates/Electrode
189 Install Rapping Hammer and Accessories
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
190 Install Inner and Outer Casing
191 Install Ash Hopper
192 Install Rotary Valves
193 Install Transformer Rectifiers
194 Install Inlet and Outlet Expansion Joint
195 Install Inlet and Outlet Dampers
196 Install gratings and railings
197 Install all accessories and Fittings
198 Fuel Handling And Ash Delivery System
199 Fuel Handling
200 Conveyor
201 Fuel Handling Delivery Thu 10/1/20
202 Fuel Handling Site Installation
203 Fuel Conveyor (FC-2&3) Delivery
204 Fuel Conveyor (FC-2&3) Installation
205 Silo Diverter Valve Delivery
206 Silo Diverter Valve Installation
207 Silo Conveyor Structure Delivery
208 Silo Conveyor Delivery (SC - 1&2)
209 Silo Conveyor Structure Erection
210 Silo Conveyor Installation (SC - 1&2)
211 Biomass Silos
212 Biomass Silo Delivery
213 Biomass Silo Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
214 Fuel Silo#1 Delivery Fri 9/25/20
215 Fuel Silo#1 Installation
216 Fuel Silo#2 Delivery
217 Fuel Silo#2 Installation
218 Fuel Silo#1 Rotor Delivery
219 Fuel Silo#1 Rotor Installation
220 Fuel Silo#2 Rotor Delivery
221 Fuel Silo#2 Rotor Installation
222 Ash System
223 Ash Tank, Conveyor Design & Engineering
224 Ash Tank, conveyor Manufacturing
225 Ash Tank Delivery Thu 10/15/20
226 Ash Tank Site Installation
227 Bottom Ash Tank Design & Engineering
228 Bottom Ash Tank, conveyor Manufacturing
229 Bottom Ash Tank Delivery Thu 10/15/20
230 Bottom Ash Tank Site Installation
231 Structure Delivery
232 Structure erection
233 Tank Lifting/Installation
234 Rotary valve installation
235 Ash Conveyor Delivery
236 Ash Conveyor Structure Delivery
237 Ash Conveyor Structure Erection
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
238 Ash Conveyor Installation
239 Screw Conveyor Delivery
240 Screw Conveyor Structure Delivery
241 Screw Conveyor Structure Erection
242 Screw Conveyor Installation
243 Boiler Feed Water Pumps 1 day Wed 9/30/20Wed 9/30/20
244 Pumps Delivery Wed 9/30/20
245 Pumps Site Installation
246 Demin Water System
247 Demin System
248 Demin Water System Design & Engineering
249 Demin Water System Manufacturing
250 Demin Water System Delivery Tue 9/15/20
251 Booster Pump Delivery
252 Activated Carbon Filter Delivery
253 Cation Exchange Filter Delivery
254 Anion Exchange Filter Delivery
255 HCL Tank Delivery
256 NaOH Tank Delivery
257 Boiler Compound Tank Delivery
258 pH Chemical Tank Delivery
259 Oxygen Scavenger Tank Delivery
260 Anti Slime Tank Delivery
261 Anti Scale Tank Delivery
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
262 pH Metering Pump Delivery
263 Make Up Water Pump Delivery
264 Demin Water Make Up Pump Delivery
265 HP Boiler Dosing Pump Delivery
266 LP Boiler Dosing Pump Delivery
267 Anti Slime Dosing Pump Delivery
268 Anti Scale Dosing Pump Delivery
269 Demin Water System Site Installation
270 Booster Pump Installation
271 Activated Carbon Filter Installation
272 Cation Exchange Filter Installation
273 Anion Exchange Filter Installation
274 HCL Tank Installation
275 NaOH Tank Installation
276 Boiler Compound Tank Installation
277 pH Chemical Tank Installation
278 Oxygen Scavenger Tank Installation
279 Anti Slime Tank Installation
280 Anti Scale Tank Installation
281 pH Metering Pump Installation
282 Make Up Water Pump Installation
283 Demin Water Make Up Pump Installation
284 HP Boiler Dosing Pump Installation
285 LP Boiler Dosing Pump Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
286 Anti Slime Dosing Pump Installation
287 Anti Scale Dosing Pump Installation
288 Demin Tank Design & Engineering
289 Demin Tank Manufacturing
290 Demin Tank Delivery Tue 9/15/20
291 Demin Tank Site Installation
292 Neutralization Tank Delivery
293 Neutralization Tank Installation
294 Valves/Fitting Installation
295 Raw Water System
296 Raw Water Tank Design & Engineering
297 Raw Water Tank Manufacturing
298 Raw Water Tank Delivery Tue 9/15/20
299 Raw Water Tank Site Installation
300 Neutralization System
301 Plant Neutralization System Design & Engineering
302 Plant Neutralization System Manufacturing
303 Neutralizing System Delivery Wed 9/30/20
304 Site Installation
305 Diesel Oil Tank
306 Diesel Oil Tank Design & Engineering
307 Diesel Oil Tank Manufacturing
308 Diesel Oil Tank Delivery
309 Diesel Oil Tank Site Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
310 Plant Engineering & Interconnection Piping
311 Plant Interconnecting Pipes Design & Engineering
312 Instrumentation engineering
313 Instrumentation Manufacturing
314 Plant Interconnecting Pipes Manufacturing
315 Instrumentation Delivery Wed 9/30/20
316 Plant Interconnecting Pipes Delivery Sun 9/27/20
317 Site Installation Mon 10/5/20
318 Power Island Electrical System
319 Power Island Electrical System Design & Engineering
320 Panel & Switch gear Manufacturing
321 Material procurement
322 Equipment & accessories delivery Sun 10/4/20
323 Site Installation
324 Grid Interconnection System (GIS)
325 Electrical System Design & Engineering
326 Transformer, Switch Gear, Equipment Manufacturing
327 Plant Electrical System Delivery
328 33kV & 11kV Cable Installation
329 Sub station & Plant Site installation
330 DCS
331 DCS Delivery Wed 9/23/20
332 DCS Site Installation
333 Compressed Air System
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
334 Air Dryer Compressor Delivery Fri 9/25/20
335 Air Dryer Compressor Site Installation
336 Overhead Crane
337 Overhead Crane Design & Engineering
338 Overhead Crane Manufacturing
339 Overhead Crane Delivery Fri 9/25/20
340 Overhead Crane Site Installation
341 CIVIL, STRUCTURAL & BUILDING
342 Civil and Structural Work
343 Turbine Hall & Switchboard Room
344 GROUND FLOOR SLAB AND APRON
345 FRAME
346 Frame, column, 2nd Floor
347 Column
348 Upper floor beam
349 Overhead Crane
350 UPPER FLOOR
351 STAIRCASES, STEPS AND FINISHES
352 ROOFS Sun 9/13/20
353 Roofing/Cladding,Structure
354 ROOF TRUSSES
355 Gutter
356 Purlin
357 ROOF COVERING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
358 rainwater down pipe
359 soffit of flat roof
360 WALL Fri 9/18/20
361 brickwall
362 External wall cladding
363 External wall louvres cladding
364 External shera board wall cladding
365 iron purlin
366 WINDOWS AND VENTS Fri 9/25/20
367 FRAME
368 Glass
369 louvres window
370 DOOR INCLUDING IRONMONGERY Fri 9/25/20
371 Door
372 Hinges
373 Lockset
374 door stopper
375 Sliding Door
376 FLOOR FINISHES Fri 9/25/20
377 cement render
378 WALL FINISHES
379 plaster
380 CEILING FINISHES
381 skim coat
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
382 gypsum board ceiling
383 HANDRAILS AND BALUSTRADINGS
384 Handrail and balustrading 7 days Wed 5/6/20 Tue 5/12/20
385 MISCELLANEOUS
386 SURFACE WATER DRAINAGE Wed 9/30/20
387 ANTI-TERMITE TREATMENT
388 ANTI-CLIMBED WALL Sat 10/10/20
389 MCC Panel Room
390 Staircase
391 Door Installation Fri 9/25/20
392 Wall Painting Fri 9/25/20
393 Air Conditioner Installation
394 Lighting Installation
395 MCC Cabinets Delivery Wed 9/30/20
396 MCC Cabinets Installation
397 Cable Installation
398 Main Switch Board Room
399 Wall Painting
400 Door Installation
401 Floor Finishing (Power Flout)
402 Air Conditioner Installation Sat 10/10/20
403 Lighting Installation Sat 10/10/20
404 Switch Boards Delivery
405 Switch Boards Installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
406 Cables Installation
407 Batery Room
408 Wall Plastering
409 Wall Painting
410 Door Installation
411 Floor Finishing (Power Flout)
412 Wiring & Lighting Installation Sat 10/10/20
413 Battery Delivery Thu 9/17/20
414 Battery Installation
415 Switch Gear Room
416 Wall Painting
417 Door Installation
418 Floor Finishing (Power Flout)
419 Air Conditioner Installation Sat 10/10/20
420 Lighting Installation Sat 10/10/20
421 Switch Gear 11kV Delivery Wed 9/30/20
422 Switch Gear Installation
423 Cables Installation
424 Transformer Yard
425 Roof column fabrication
426 Roof Truss Fabrication
427 Roof column Installation
428 Roof Truss Installation
429 Roofing installation
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
430 Anti-climb Fencing Installation
431 Transformer Installation
432 Cables Installation
433 GIS - Pole Erection (Plant to PPU Naka)
434 GIS - Cable Installation (Plant to PPU Naka)
435 Control Room
436 Brick Works Sat 9/12/20
437 Wall Plastering Tue 9/22/20
438 Wall Painting
439 Door Installation
440 Window Installation
441 Floor Finishing (Tile)
442 Ceiling Finishing
443 Air Conditioner Installation Sat 10/10/20
444 Lighting Installation Sat 10/10/20
445 DCS System Delivery
446 DCS System Installation
447 Vacum Surface Condenser Floor
448 Toilet
449 VSC Delivery
450 VSC Exhaust Duct Installation
451 VSC Bellow Installation
452 VSC Lifting to Base
453 VSC Centering & Levelling
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
454 VSC Base Grouting
455 Gland Condenser Delivery
456 Gland Condenser Lifting to Base
457 Gland Condenser Centering & Levelling
458 Gland Condenser Anchor Bolt Cementing
459 Gland Condenser Base Grouting
460 Condensate Pump Delivery
461 Condenser Pump Installation
462 Condensate Pump Centering & Levelling
463 Condensate Pump Alignment
464 Condensate Pump Anchor Bolt Cementing
465 Condensate Pump Base Grouting
466 Air Compressor Delivery
467 Air Filter Delivery
468 Air Dryer Delivery
469 Air Receiver Tank Delivery
470 Air Compressor Installation
471 Air Filter Installation
472 Air Dryer Installation
473 Air Receiver Tank Installation
474 Accessories/Fitting Installation
475 Compressed air piping Installation
476 Demin Water Plant
477 Foundation c/w apron & ramp
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
478 ROOFS Sun 9/13/20
479 Roofing/Cladding
480 ROOF TRUSSES
481 Purlin
482 ROOF COVERING
483 Gutter & Downpipe Installation
484 WALL Fri 9/18/20
485 Wall/window/ceilings finishes
486 External wall cladding
487 Painting
488 WINDOWS AND VENTS Fri 9/25/20
489 Fixed glass panel window
490 DOOR INCLUDING IRONMONGERY Fri 9/25/20
491 roller shutter
492 FLOOR FINISHES Fri 9/25/20
493 Floor Finishing (Power Flout)
494 MISCELLANEOUS 10.13 days?Wed 9/30/20Fri 10/9/20
495 Miscellaneous
496 SURFACE WATER DRAINAGE Wed 9/30/20
497 Wiring & Lighting Installation Fri 10/9/20
498 CRITICAL SPARES DELIVERY 1 day? Wed 9/30/20Wed 9/30/20
499 BOP SPARES DELIVERY Wed 9/30/20
500
501 NON-POWER ISLAND
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
502 CIVIL, STRUCTURAL & BUILDING
503 Earth Work
504 Slope Boundary (Re-Design & Re-Work)
505 Retaining Wall-2
506 Turfing
507 Concrete Drains
508 Civil and Structural Work
509 Biomass Storage 1 day? Wed 9/16/20Wed 9/16/20
510 GROUND FLOOR SLAB AND APRON
511 Foundation c/w apron & ramp
512 Conveyor Pit c/w Finishing
513 Fuel Receiving Hopper Delivery
514 Fuel Receiving Hopper Installation
515 Fuel Conveyor (FC - 1A&1B) Delivery
516 Fuel Conveyor (FC - 1A&1B) Installation
517 ROOFS Wed 9/16/20
518 Gutter
519 Purlin
520 ROOF COVERING
521 Roofing/Cladding
522 WALL
523 BRICKWORK
524 Wall Plastering
525 External wall cladding
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
526 Painting
527 WINDOWS AND VENTS
528 ALUMINIUM LOUVRES WINDOW
529 FLOOR FINISHES
530 WALL FINISHES
531 MISCELLANEOUS
532 TRENCHES
533 SURFACE WATER DRAINAGE
534 External & Perimeter
535 Architectural Finishes
536 Mechanical & Electrical 1 day? Wed 9/16/20Wed 9/16/20
537 Water Tank (for Rain Water Harvesting)
538 Wiring & Lighting Installation
539 Hose Reel
540 Sprinkler
541 Administration Office Mon 9/21/20
542 GROUND FLOOR SLAB AND APRON
543 apron
544 cable trench
545 ramp
546 FRAME
547 Water tank plinth
548 STAIRCASES, STEPS, RAMPS AND FINISHES
549 SKIM COATING
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
550 ROOFS
551 Trusses
552 Purlin
553 ROOF COVERING
554 rainwater down pipe
555 roof slab
556 WALL
557 Plaster
558 Partition/Dry Wall Installation
559 WINDOWS AND VENTS
560 FRAME
561 Glass
562 DOOR INCLUDING IRONMONGERY
563 DOOR
564 door stopper
565 hinges
566 lockset
567 sliding door
568 FLOOR FINISHES
569 floor tiles
570 WALL FINISHES
571 plaster
572 wall tiles
573 Painting
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
574 CEILING FINISHES
575 skim coat
576 gypsum board
577 ceiling lining
578 paint
579 SANITARY APPLIANCES
580 Pedestal water closet
581 wash hand basin
582 handicap basin
583 Hand spray bidet
584 tissue holder
585 shower rose
586 bib tap
587 soap dispenser
588 grab rail
589 swing-up support rail
590 Mirror
591 Floor drainer
592 trash bin
593 scupper drain
594 counter top
595 toilet cubicle
596 HANDRAILS AND BALUSTRADINGS
597 MISCELLANEOUS
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
598 Mild steel grillwork
599 SURFACE WATER DRAINAGE
600 Architectural Finishes
601 Mechanical & Electrical
602 External & Perimeter
603 Wiring
604 Air Conditioner Installation
605 Lighting Installation
606 Plant Storage
607 Foundation c/w apron & ramp
608 ROOFS
609 Roofing/Cladding
610 ROOF TRUSSES
611 Purlin
612 ROOF COVERING
613 Gutter & Downpipe Installation
614 WALL
615 Brickwall
616 Wall Plastering
617 Painting
618 WINDOWS AND VENTS
619 Lintol
620 Fixed glass louvres window
621 DOOR INCLUDING IRONMONGERY
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
622 Lintol
623 DOOR
624 roller shutter
625 FLOOR FINISHES
626 Floor Finishing (Power Flout)
627 WALL FINISHES
628 Wall/window/ceilings finishes
629 Plaster
630 MISCELLANEOUS
631 Miscellaneous
632 SURFACE WATER DRAINAGE
633 Wiring & Lighting Installation
634 Guardhouse
635 ROOFS
636 Roofing/Cladding
637 ROOF TRUSSES
638 Purlin
639 ROOF COVERING
640 WALL
641 Wall/window/ceilings finishes
642 WINDOWS AND VENTS
643 Frame
644 Fixed glass louvres window
645 Fixed glass panel window
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
646 DOOR INCLUDING IRONMONGERY
647 Door
648 hinges
649 lockset
650 door stopper
651 coat hook
652 FLOOR FINISHES
653 Apron
654 Tiles
655 WALL FINISHES
656 Plaster
657 Tiles
658 CEILING FINISHES
659 cement board
660 SANITARY APPLIANCES
661 water closet
662 Floor drainer
663 Mirror
664 bib tap
665 shower rose
666 tissue holder
667 Hand spray bidet
668 MISCELLANEOUS
669 SURFACE WATER DRAINAGE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
670 Wiring
671 Lighting Installation
672 Compact Sub
673 Cable Trenches c/w Finishing
674 Signages
675 Meter Kiosk
676 Incoming Cable from TNB
677 Outgoing Cabble to MSB
678 Diesel Tank
679 Bund Wall
680 Diesel Pump Plinth
681 Diesel Tank Delivery
682 Diesel Tank Installation
683 Diesel Pump Delivery
684 Diesel Pump Installation
685 Diesel Genset Delivery
686 Diesel Genset Installation
687 Main Junction Modification
688 RSA Stage 4 (Part 1) - Verification & Traffice Management Audit
689 RSA Stage 4 (Part 2) - Work Zone Audit
690 RSA Stage 4 (Part 3) - Re-Opening
691 RSA Stage 5 - Operational
692 New Additional Lane
693 Kerb
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
694 Resurface Existing Road
695 Reconstruct Existing Road
696 Road Marking & Furniture
697 External Work
698 Roadwork
699 Surface Water Drainage
700 Water Reticulation
701 Sewerage System
702 Fencing & Gate
703 Flag Poles
704 Catchment Pond
705 Meter Room, PPU NAKA
706 Meter Installation
707 Misscellanous
708 Landscape
709 Fence Base
710 Chain Link Fence Installation
711 Sliding Gate Installation
712 Flag Poles Base Construction
713 GI Flag Poles Installation
714 MECHANICAL & ELECTRICAL (M&E)
715 Non-Plant Mechanical Services
716 Weighbridge
717 Weigh Bridge Design & Engineering
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
718 Weigh Bridge Manufacturing
719 Weigh Bridge Delivery
720 Weigh Bridge Site Installation
721 Fire Fighting System
722 Hose Reel System
723 Fire Detection And Alarm System
724 Clean Agent & Co2 Fire Extinguisher
725 Portable Fire Extinguisher
726 Hydrant System
727 Sign And Notice
728 ACMV System
729 SPLIT UNIT AIR CONDITIONING SYSTEM
730 Indoor/Outdoor Unit
731 Copper Pipe
732 Condensate Pipe
733 ELECTRICAL
734 GRID INTERCONNECTION
735 PRELIMINARY WORK
736 Document to submit for IOD
737 Test result of interconnection facilities
738 Power quality report
739 To do protection setting on site
740 Reliability Report (RR)
741 Certificate for competent person for shutdown & testing
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
742 TRANSFORMER
743 STEP-UP TRANSFORMER 12.5MVA 11/33 KV
744 List of Testing
745 Method of Statement for Testing
746 Cert for competent person to test
747 Connection to Grid
748 Testing and commissioning (SAT)
749 Earthing
750 STEP-DOWN TRANSFORMER 2500 KVA 11/415 KV
751 List of Testing to Submit
752 Method of Statement for Testing
753 Cert for competent person to test
754 Cable Termination
755 Connection to plant
756 Testing and commissioning (SAT)
757 Earthing
758 33KV GAS INSULATED SWITCHGEAR PANELS (TNB PPU NAKA)
759 Cable Termination
760 Installation/coupling
761 List of testing to submit
762 Method of Statement for testing
763 Testing and commissioning (SAT)
764 Earthing
765 33KV AIR INSULATED SWITCHGEAR (CONSUMER)
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
766 Cable Termination
767 List of testing to submit
768 Method of Statement for testing
769 Testing and commissioning (SAT)
770 Earthing
771 REMOTE CONTROL PANEL (RCP)
772 Cable Termination
773 Fibre Termination
774 List of testing to submit
775 Method of Statement for testing
776 Testing and commissioning (SAT)
777 Earthing
778 11KV AIR INSULATED SWITCHGEAR (CONSUMER)
779 Supply to the site
780 Panel Installation
781 Cable Termination
782 List of testing to submit
783 Method of Statement for testing
784 Testing and commissioning (SAT)
785 Earthing
786 REMOTE TERMINAL UNIT (RTU)
787 Supply & Install
788 Cable Termination
789 Fibre Termination
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
790 List of testing to submit
791 Method of Statement for testing
792 Testing and commissioning (SAT)
793 Earthing
794 FIBRE FROM PLANT TO PPU NAKA
795 Fibre Termination
796 List of testing to submit
797 Method of Statement for testing
798 Testing and commissioning (SAT)
799 RELAY PROTECTION 110VDC (GIS SWITCHGEAR ROOM)
800 Supply & Install
801 List of testing to submit
802 Method of Statement for testing
803 Testing and commissioning (SAT)
804 Earthing
805 33KV METERING PANEL AT CONSUMER SITE
806 Supply & Install
807 Testing and commissioning (SAT)
808 Earthing
809 FIBER TERMINATION PATCH FOR GRID
810 Supply & Install
811 Testing and commissioning (SAT)
812 OTDR result
813 POWER CABLE
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
814 3C X 150MM2 XLPE AI. ARIEL BUNDLE CABLE (33KV)
815 Installation 3 phase straight joint c/w boding kit
816 Installation normal single phase straigh joint for cable
150mm2 AI ABC and 185mm2 XLPE AI
817 Termination to plant and PPU Naka
818 Cert for cable tester
819 Testing and commissioning (SAT)
820 VLF test & other tests
821 1C X 185MM2 XLPE AI CABLE (33KV)
822 Supply to the site
823 Intallation cable tray/ladders and other accesorries
824 Inside Majunaka Substation
825 Inside PPU Naka
826 Burried direct ground with sand bending, excavation
along clay soil for cable (fibre optic lay in pipe)
827 Burried direct ground 150mm2 & 100mm2 corrugated
HDPE pipe for 185mm2 XLPE AI cable
828 Along substation compund
829 Along road shoulder & tarcamadam road
830 lay & terminate to 33kV GIS c/w other accesorries
831 lay & terminate to 11kV AIS c/w other accesorries
832 lay & terminate to 11/33kv transformer c/w other accesorries
833 Cert for cable tester
834 VLF test & other tests

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
835 1C X 500MM2 XLPE/AI/CWS/LA/HDPE CABLE (11KV)
836 Supply to the site
837 Intallation cable tray/ladders and other accesorries
838 From 11kV panel to 12.5MVA transfomer
839 lay & terminate to 11kV AIS c/w other accesorries
840 lay & terminate to 11/33kv transformer c/w other accesorries
841 Cert for cable tester
842 VLF test & other tests
843 Low Voltage
844 MAIN SWITCH BOARD (MSB)
845 Supply to the site
846 Installation in Majunaka Substation
847 Cable termination incoming and outgoing
848 Method of statement for testing c/w test form and tester certificate
849 Site acceptence test for ;
850 MSB 1 c/w breaking capacity 65kA, 3000A ACB
851 MSB A c/w breaking capacity 65kA, 1600A ACB
852 MSB B c/w breaking capacity 65kA, 1600A ACB, 4 pole
Auto Transfer Switch (ATS)
853 MSB C
854 415V MOTOR CONTROL CENTER (MCC)
855 Supply to the site 1 day Thu 10/1/20 Thu 10/1/20
856 Panel Installation 3 days Wed 9/2/20 Fri 9/4/20
857 Cable Termination

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
858 List of testing to submit
859 Method of statement for testing c/w test form and tester certificate
860 Method of Statement for testing
861 Testing and commissioning (SAT)
862 Earthing
863 SUB SWITCHBOARD (SSB)
864 Supply and deliver to the site
865 Install SSB c/w overcurrent & earth leakage relay and other
accessories for;
866 2 SSB at building pentadbiran and tarbin
867 18 unit Distribution Board (DB) in Majunaka Plant
868 2 unit isolators at cold water system and DG control system
869 Street lighting Feeder Pillar
870 1600A Generator connection box
871 Meter Kiosk c/w plint and all else accessories as per TNB specification
872 UPS Battery for DCS panel requires 15kW and supply 30 minutes
873 Earthing
874 GENERATOR SET
875 STANDBY 750KVA GENSET
876 Supply and deliver to the site
877 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to AMF board laid underground
878 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to essential and emergency board

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
879 Install fuel piping
880 Earthing system
881 Install 24 hours fuel tank
882 24V nickel cadmium
883 Testing and commsioning
884 STANDBY 1000KVA GENSET
885 Supply, lay and terminate cable from Genset to AMF
generator connection box
886 Supply, lay and terminate 8x630mm2 XLPE PVC cable
from Genset to AMF board laid underground
887 Supply, lay and terminate 8x500mm2 XLPE PVC cable
from Genset to the MAB 1
888 Install fuel piping
889 Earthing system
890 Install 10,000 litre fuel tank
891 24V nickel cadmium
892 Testing and commsioning
893 SUBMAIN LV CABLING
894 Lay 150mm² dia UPVC Class B pipe for incoming cable to
MSB room cable entry trench
895 Lay cable 4C 150mmsq Cable from TNB LV Board to MSB C
896 Lay cable 11 x 800mm² Cable from 11/0415 kV Transformer to MSB1
897 Install floor penetration fire barrier of BOMBA
898 All outgoing cable from;

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
899 MSB A to all Sub-DB
900 MSB B to all Sub-DB
901 MSB C to all Sub-DB
902 SSB Tarbin
903 SSB Pentadbiran
904 Testing and commsioning
905 SUB-CIRCUIT & SMALL POWER WIRING
906 To wireup all lighting, sso, and other equipment
907 To supply and install conduit and trunking system
908 To supply and install underfloor ducting system
909 ELECTRICAL FITTINGS
910 Supply all fiting to all buiding
911 LIGHTNING PROTECTION SINGLE DOME
912 To install lighting protection
913 EARTHING
914 To install Earthing protection
915 STREET LIGHTING / COMPOUND LIGHTING SYSTEM
916 To supply street lighting / compound lighting system
917 To install street lighting / compound lighting system
918 TNC
919
920 TESTING AND COMMISSIONING 36 days Sat 10/10/20Sat 11/14/20
921 Boiler Hydrostatic Test 28.13 days Thu 9/17/20 Wed 10/14/20
922 Notication to DOSH 14 days Thu 9/17/20 Wed 9/30/20
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
923 Temperoray Equipment & Piping connection 3 days Fri 9/25/20 Sun 9/27/20
924 Water filling & leakage test, pre-HT 3 days Thu 10/1/20 Sat 10/3/20
925 Hydrostatic Test (HT)-Attended by DOSH 1 day Sun 10/4/20 Sun 10/4/20
926 Drainage 1 day Sun 10/4/20 Mon 10/5/20
927 Plant DOSH Inspection
928 Plant Process Piping Leak Test 38.63 days Mon 10/5/20Wed 11/11/20
929 Steam Extraction piping 4 days Wed 10/7/20Sat 10/10/20
930 Main steam, PRDS piping 4 days Wed 10/7/20Sat 10/10/20
931 Condensate Extraction Piping 4 days Wed 10/7/20Sat 10/10/20
932 Feed Water Piping 4 days Wed 10/7/20Sat 10/10/20
933 Steam Turbine Generator System 4 days Wed 10/7/20Sat 10/10/20
934 MCW Piping 4 days Wed 10/7/20Sat 10/10/20
935 ACW System 4 days Wed 10/7/20Sat 10/10/20
936 Compressed Air System 3 days Thu 10/8/20 Sat 10/10/20
937 Equipment Dry Run Test 3 days Thu 10/8/20 Sat 10/10/20
938 Plant Final Inspection 1 day Fri 9/4/20 Fri 9/4/20
939 Plant Mechanical Completion 1 day Sat 10/10/20 Sat 10/10/20
940 Calibration Fuel Feeding 2 days Sun 10/11/20Mon 10/12/20
941 Chemical Boiling Out 3 days Mon 10/12/20Thu 10/15/20
942 Steam Test 3 days Thu 10/15/20Sun 10/18/20
943 Plant Commissioning 5 days Sun 10/18/20Fri 10/23/20
944 Grid Interconnection Test 2 days Fri 10/23/20 Sun 10/25/20
945 Initial Operation Date (IOD) 0 days Sun 10/25/20Sun 10/25/20
946 Plant Performance Test
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
947 Plant Reliability Run (RR)
948 Commercial Operation Date (COD) 17.25 days?Thu 10/29/20Sat 11/14/20
949 Notification to conduct the Acceptance Test & Performance 1 day Thu Thu
Assessment (AT&PA) to SEDA 10/29/20 10/29/20
950 Requisite documents submission: a) Checklist of AT&PA 1 day Thu Thu
documentation (Form 1); b) Information about the Project (Form 10/29/20 10/29/20
2); c) Information about the Plant (Form 3);
951 AT&PA fees payment 1 day Thu 10/29/20Thu 10/29/20
952 Review documents
953 Line walk at the plant
954 AT&PA activities at the plant
955 AT&PA Report preparation and submission
956 Review and approve AT&PA report
957 Upload AT&PA report in the e-FiT system
958 Approval and issuance of FiTCD letter Sat 11/14/20
959
960 Certificate of Practical Completion (CPC) & Defect Liability Period (DLP)
961 Borang F1
962 Bomba Inspection
963 Defect List
964 Operation and Maintenance Manual with As-Built Dwg
965 2.5% of the 5% retention sum
966
967 Certificate of Completion and Compliance (CCC) 92 days Thu 12/31/20Wed 3/31/21

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
968 G1 : KERJA-KERJA TANAH
969 G2 : PEMANCANGAN TANDA
970 G3 : ASAS TAPAK
971 G4 : STRUKTUR
972 G5 : PERPAIPAN AIR DALAMAN
973 G6 : PERPAIPAN SANITARI DALAMAN
974 G7 : ELEKTRIKAL DALAMAN
975 G8 : MENENTANG KEBAKARAN (PASIF)
976 G9 : MENENTANG KEBAKARAN (AKTIF)
977 G10 : PENGUDARAAN MEKANIKAL
978 G11 : PEMASANGAN LIF/ESKALATOR
979 G12 : BANGUNAN
980 G13 : SISTEM BEKALAN AIR LUARAN
981 G14 : RETIKULASI PEMBETUNGAN
982 G15 : LOJI RAWATAN PEMBETUNGAN
983 G16 : SISTEM BEKALAN ELEKTRIK LUARAN
984 G17 : JALAN DAN PARIT
985 G18 : LAMPU JALAN
986 G19 : PARIT LUARAN UTAMA
987 G20 : TELEKOMUNIKASI
988 G21 : PANDANGAN DARAT
989 Borang F
990
991 MILESTONE PAYMENT
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 241
ID TaskTask Name Duration Start Finish
Mode September 1 October 1 Novem
9/19 10/3 10/17 10/31
992 EPCC MILESTONE 1 day? Wed 9/30/20Wed 9/30/20
993 MS 8 Upon Completion of Boiler Hydrostatic Test 1 day Wed 9/30/20Wed 9/30/20
994 MS 9 Upon Mechanical Completion of the Facility
995 MS 10 Upon Achieving Commercial Operation Date
996
997 Certificate of Making Good Defects (CMGD)
998 Making good of defects
999 2.5% of the 5% retention sum
1000
1001 FINAL ACCOUNT

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: EOT1 titan schedule
Date: Mon 9/21/20 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary