Professional Documents
Culture Documents
Offshore Wind 2021
Offshore Wind 2021
Intelligence
windeurope.org
windeurope.org March 2022
TEXT AND ANALYSIS:
This report summarises offshore installations from 1 WindEurope Market Intelligence
January 2021 to 31 December 2021. This publication Lizet Ramírez
contains information collected on a regular basis and
then verified with relevant members of the industry. Guy Brindley
Where data is not available assumptions are used.
Rounding of figures is at the discretion of the author. MORE INFORMATION:
policy@windeurope.org
DISCLAIMER +32 2 213 18 38
Neither WindEurope nor its members, nor their
related entities are, by means of this publication,
rendering professional advice or services. Neither
WindEurope nor its members shall be responsible for
any loss whatsoever sustained by any person who
relies on this publication.
•
•
•
•
•
•
Annual
Annual
Annual
CAPACITY NUMBER OF
TYPE OF
COUNTRY WIND FARM CONNECTED IN 2021 TURBINES TURBINE MODEL STATUS*
FOUNDATION
(MW) CONNECTED
71
192
6
12,739
2,308
25 2,986
7,713
2,261
25
5
DEME
38 turbines Asso.Subsea
Subsea 7
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Total investments (€bn) 10.7 2.8 7.2 12.9 12.5 22.1 6.1 9.7 6.6 27.7 16.6
New capacity financed (GW) 3.0 0.5 1.5 2.4 2.5 6.3 2.0 3.9 1.4 7.6 4.8
Annual
NEW CAPACITY
CAPITAL RAISED CAPEX DATE OF FINANCIAL
WIND FARM COUNTRY FINANCED
(€bn) (m€/MW) CLOSE
(MW)
Courseulles-Sur-Mer France 2.1 450 4.8 February
Offshore Transmission
The ongoing Offshore Transmission Network Review (ONTR) proposes four possibilities to seek larger coordination between
interconnectors, offshore wind farms, and their onshore connection. The options apply to the projects’ expected commissioning date.
April’s Energy Bill is expected to give more updates on the multi-purpose interconnector (offshore hybrids), that allow the connection of
wind farms to an interconnector.
Turbines:
89 turbines –
SWT-4.4-130 (SGRE)
Foundations:
Monopiles (EEW)
Cables:
TFK (intra-array)
Vissen & Smit Hanab
(export cable)
Status: open in 2022
Click here to be installed Click here
Commissioning: 2027
average
Germany turbine size**
Status: open in 2023
Commissioning: 2028
Turbines:
38 turbines –
SG 8.0-167 DD (SGRE)
Foundations:
Monopiles (Bladt)
Cables:
TKF(intra-array)
ZTT (export cable)
Status: under evaluation
Click here to be installed Click here
average
Denmark turbine size**
Status: under evaluation
Commissioning: 2030/31
Timetable changes
The Danish Energy Agency put the Hesselø 1 GW tender on hold to carry out additional studies. The preliminary surveys found
soft clay in the seabed of the designated area. The Government is evaluating five possible alternative locations and consulted
with industry to adapt the current timetable. Hesselø was expected to be the next tender in Denmark after Thor.
Turbines:
72 turbines –
SG 8.4-167 DD (SGRE)
Foundations:
Monopiles (EEW)
Cables:
JDR (intra-array)
NKT (export cable)
Click here to be installed Click here Status: open in April 2022
average Commissioning: 2025/26
The Netherlands turbine size**
Status: to be announced
Turbines:
89 turbines –
SWT-4.4-130 (SGRE)
Foundations:
Monopiles (EEW)
Cables:
TFK (intra-array)
Vissen & Smit Hanab
(export cable)
Status: ongoing
Click here to be installed Click here Commissioning: 2028
average
France turbine size**
Status: ongoing
Commissioning: 2028/29
Turbines:
80 Haliade 150-6MW
(GE)
Foundations:
Monopiles (Sif)
Cables:
Prysmian and Louis
Dreyfus TavOcean
(intra-array)
Prysmian (export cable)
Click here to be installed Click here Status: open in 2025
average
Poland turbine size**
Status: open in 2027
Turbines:
1 turbine –
SWT-3.6-120 (SGRE)
Foundations:
Spar (Welcon)
Cables:
Unitech Offshore
(intra-array)
Rest of Click here to be installed Click here Status: under consultation
Europe* average
turbine size**
Status: open in H2 2022