Professional Documents
Culture Documents
Chapter-4 Sceduling - Final
Chapter-4 Sceduling - Final
Introduction
Scheduling technique
Bar Charts
Network Scheduling
1. Critical Path method(CPM)
2. Program Evaluation and Review Techniques(PERT)
Construction Project Planning
• Planning: ‐
A trail and error approach is no longer valid for the
construction industry and proper planning is now vital.
The amount of detailing in planning is likely to be the function
of the size of the firm, the complexity of the project and the
expertise of the management.
The programs usually developed are:
– Performance Schedule
– Financial (Cash Flow) Schedule
– Equipment Schedule
– Material delivery Schedule
– Manpower Schedule
– Responsibility Schedule
Construction Project Planning
The construction planning may be said to consist
of the following steps:
Choice of Technology and Construction
Method:
Determination of job activities:
Job Logic /Sequential Relationships/ or
Precedence:
Determination of duration of activities:
The presentation of this planning information in
the form of a schedule or network,
Construction Project Planning
Job Logic /Sequential Act Description Pre
Relationships/ or Precedence: d.
For a project of any A Site clearing __
consequence, there is always B Removal of trees __
more than one general
C General excavation A
approach and no unique order
of procedure exists. It is the D Grading general area A
planner’s responsibility to E Excavation for utility B,C
trenches
examine the workable choices
F Placing formwork & B,C
and select the most suitable reinforcement for concrete
E10 0
Rule 2. Any activity can start immediately when all
preceding activities are completed.
Ej for node j is
given by
E j Max.[ Ei Dij ]
Rule 3. Repeat step2 for the next eligible activity until the
end node is reached.
E10 0
and
E 20 Max.[ E i Di 20 ]
For node 20, node 10 is the only predecessor and hence
i 10
contains only one element. Therefore,
E j Max.[ Ei Dij ]
E 20 E10 D10, 20 0 3 3
,
E 21 E 20 D20, 21 3 2 5
,
E30 E 20 D20,30 3 1 4
E 60 E30 D30, 60 4 1 5
,
Consider node 31, where there are two emerging
activities, i.e.
E 31 Max.[ E i Di ,31 ]
The collection i consists of node 21 and 30 that are preceding
node 31, Therefore,
can be computed
and values of E32 as:
i.e. the latest time for activities is the minimum of the latest
time of all succeeding activities reducing their activity time.
L90 14
. Applying rule 2, it is to determine
L80 L40
L70
L32
L60
L31
L50
L80 Min. j {L j - D80, j } 14 1 13 for j 90
L60 E 60 6 5 1
This float represents the amount by which this particular
activity can be delayed without affecting the total time of the
project.
Also, by definition, free float, if any will exist
only on the activities merge points.
To illustrate the concept of free float, consider
path 10 – 20 – 30 – 50 – 70, total float on activity
50 - 70 is four days and since this is the last
activity prior to merging two activities, this float
is free float also.
Similarly, consider the activity 30-50 which has
a total float of 4 days but has zero free float
because 4 day of free float is due to the activity
50-70.
If activity 30-50 is delayed up to four
days, the early start time of no activity in
the network will be affected.
Therefore, the concept of free float
clearly states that the use of free float
time will not influence any succeeding
activity float time.
Step 4. To Identify Critical Path
t
Optimistic time 0limit of completion time if every thing goes all-righ
Most likely time t l the duration that would occur most often if
the activity was repeated many times
under the same conditions.
The three times were imposed on a normal
distribution to calculate the activity’s
expected time te as,
(t o 4t l t p )
te
6
Normal Probability distribution
Each activity in a PERT network also has a
variance with its completion of time. This
variance measures the dispersion of
possible duration. A large variance means
a wide variation in the outside limits of
estimate and indicates less confidence in
estimating:
2
2 t p to
6
99.7 % within t e 3
95.0 % " t e 2
68.0 % "
t e
Basic PERT Procedure
Compute mean and variance of all jobs
Conduct forward and backward pass on the project
Identify the critical path
Obtain variance of critical path by adding variance of
activities
Obtain the distribution of the project duration
Make probability statements about the project
Chance of meeting the target date
Probability of exceeding a given ceiling date
Probability that the project duration is confined to an interval of
time
A contractor has received order for
constructing a cottage on a sea side
resort. The delivery of materials must be
planned and the complete job finished in
13 weeks. The work involves and the time
required to complete each activities are
given in the table below.
Job Description Time, days
to tl tp
to = optimistic time
tp = pessimistic time
and also the precedence of the activities has to be determined.
Job Description Immediate Time, days (t o 4t l t p )
te
predecesso to tl t 6
p
rs
(1) (2)
A 10 0 0 10 10 0
B 24 0 20 24 44 20
C 14 10 10 24 24 0
D 20 24 24 44 44 0
E 14 24 64 38 78 40
G 8 44 44 52 52 0
H 13 52 63 65 76 11
I 4 42 82 46 86 40
J 12 86 86 98 98 0
K 4 38 78 42 82 40
L 4 52 72 56 76 20
M 24 52 52 76 76 0
N 10 76 76 86 86 0
Difference b/n CPM & PERT
CPM PERT
CPM is an activity oriented PERT is an event oriented
network network
In CPM time estimates are Time estimate are not that
of a fair degree of accuracy accurate & there is uncertainty
CPM follows deterministic attached
PERT follows probabilistic
approach
approach
In CPM, cost is the
In PERT time is the governing
governing factor
factor
Project duration is fixed
Cost is directly proportional to
that the cost is minimum time
The path joins the critical In PERT, critical path is the
activities path which joins the critical
events