Gujarat Urja Vikas Nigam LTD

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Gujarat Urja Vikas Nigam Ltd. v. Essar Power Ltd.

Factual Background:
The appellant company was engaged in the business of electricity generation. It entered into a
Power purchase Agreement (PPA) with the Gujarat Electricity Board. The Parties inter alia
agreed that out of the total generating capacity of 515 MW the appellant company would allocate
300 MW to the Board and 215 MW to the Essar Group of Companies. As per Clause 11 of the
agreement, the parties agreed that in the event of any dispute, resolution will take place by
mutual agreement. And in the event to resolve the dispute by amicable settlement, the parties
will submit the dispute to arbitration. Certain dispute arose between the parties which was
attempted to be resolved by amicably but was of no avail. Hence, the respondent company called
upon the appellant Nigam to refer the dispute to the arbitrator. Since, Nigam did not send it
approval, the respondent company approached the Gujarat HC under Section 11(5) and (6) of the
1996 Act. The Court appointed Retired Judge Ahmedi as the sole arbitration after which the
appeal was filed. 
Argument of the Counsels and Important Provisions:
The learned senior counsel for the appellant Mr. KK Venugopal relied on Section 174 and 173 of
the Electricity Act. Section 174 states that:
“Save as otherwise provided in section 173, the provisions of this Act shall have effect
notwithstanding anything inconsistent therewith contained in any other law for the time being in
force or in any instrument having effect by virtue of any law other than this Act.”
Section 173 of the Act states that:
“Nothing contained in this Act or any rule or regulation made thereunder or any instrument
having effect by virtue of this Act, rule or regulation shall have effect in so far as it is
inconsistent with any other provisions of the Consumer Protection Act, 1986 (68 of 1986) or the
Atomic Energy Act, 1962 (33 of 1962) or the Railways Act, 1989 (24 of 1989).”
It was argued that a conjoint reading of these provisions indicates that ordinarily the Act of 2003
will prevail over all other laws or instruments. He also relied on Section 86 of the 2003 Act and
referred to clause (f) which states that one of the functions of the state commission is to
adjudicate upon the disputes between the licensees and generating companies and to refer any
dispute for arbitration. He submitted that Section 86(1)(f) clearly indicates that the disputes
between the licensees and generating companies can only be adjudicated upon by the State
Commission, either itself or by an arbitrator to whom the Commission refers the dispute. Hence
the High Court cannot refer disputes since such power of adjudication or reference to an
arbitrator has been specifically given to the State Commission. 
He thus concluded that since the Electricity Act is a special law dealing with arbitrations of
disputes between licensees and the generating companies, the general provision of Section 11 of
the 1996 Act will not apply for appointing an arbitrator for such disputes in view of the maxim
Generalia specialibus non derogant. 
On the other hand Shri F.S. Nariman, learned senior counsel for the respondent referred to
Section 175 of the 2003 Act. Section 175 provides:
“Provisions of this Act to be in addition to and not in derogation of other laws  The provisions
of this Act are in addition to and not in derogation of any other law for the time being in force.”
He submitted that the Act of 2003 does not prohibit the application of the provisions of the Act
of 1996 including Section 11 thereof. Hence he submitted that a reference can be made by the
Court under Section 11(5) and (6) of the said Act of disputes between licensees and generating
companies. Accordingly, the High Court order was valid.
Ratio decidendi:
The Court noted that Section 86(1)(f) of the Act of 2003 is a special provision for adjudication of
disputes between the licensee and the generating companies. Such disputes can be adjudicated
upon either by the State Commission or the person or persons to whom it is referred for
arbitration. The Court noted that Section 174 provides that the Electricity Act, 2003 will prevail
over anything inconsistent in any other law. It held that the inconsistency may be express or
implied. Since Section 86(1)(f) is a special provision for adjudicating disputes between licensees
and generating companies, in our opinion by implication Section 11 of the Arbitration and
Conciliation Act, 1996 will not apply to such disputes i.e. disputes between licensees and
generating companies. Hence, Section 11 will not apply to such disputes. 
Critical Analysis 
At the first glance, it may seem that Section 174 and Section 175 of the 2003 Act have apparent
inconsistency. While Section 174 says that the said Act will prevail over other laws, Section 175
says that the said Act is in addition and not in derogation of any other law. However, a
harmonious construction of the provisions of the Electricity Act, 2003 and the Arbitration and
Conciliation Act, 1996 can be looked into.
Whenever there is a dispute between a licensee and the generating companies only the State
Commission or Central Commission (as the case may be) or arbitrator (or arbitrators) nominated
by it can resolve such a dispute, whereas all other disputes would be decided in accordance with
Section 11 of the Arbitration and Conciliation Act, 1996. The Court finally held:
“Section 86(1)(f) is only restricted to the authority which is to adjudicate or arbitrate between
licensees and generating companies. Procedural and other matters relating to such proceedings
will of course be governed by Arbitration and Conciliation Act, 1996, unless there is a
conflicting provision in the Act of 2003.”
Similarly, in the case of Hindustan Zinc Limited v. Ajmer Vidyut Vitram Nigam Limited the
award was challenged before the Commercial Court in Section 34 petition under the 1996 Act
after which a Section 37 appeal was filed. The High Court held that the hat worn by the
appellant-company, was that of an open access consumer and not that of a generating company.
As a result of which, Section 86 (1)(f) of the Electricity Act would not be attracted. The Supreme
Court referred to the Gujarat Urja case and held that the adjudication upon disputes can only be
between licensees and generating companies and not between licensees and consumers, which is
provided for in an open access situation by Section 42. Hence, the High Court was right in
stating that the Arbitrator could not, in law, have been appointed by the State Commission under
Section 86 of the Electricity Act.

You might also like