1. Gastek provided a progress report on a nitrogen plant project for Afcons as of June 26, 2015. Revisions were made to P&IDs, instrument data sheets, and the PLC system based on client comments.
2. Drawings for the equipment layout, electrical panels, fabricated vessels, and foundations were submitted or under development. Purchase orders were placed for long-lead components.
3. Fabrication of the air receiver and surge vessel was underway, with seams being welded. Approval was received for nitrogen storage tank drawings from the Controller of Explosives.
1. Gastek provided a progress report on a nitrogen plant project for Afcons as of June 26, 2015. Revisions were made to P&IDs, instrument data sheets, and the PLC system based on client comments.
2. Drawings for the equipment layout, electrical panels, fabricated vessels, and foundations were submitted or under development. Purchase orders were placed for long-lead components.
3. Fabrication of the air receiver and surge vessel was underway, with seams being welded. Approval was received for nitrogen storage tank drawings from the Controller of Explosives.
1. Gastek provided a progress report on a nitrogen plant project for Afcons as of June 26, 2015. Revisions were made to P&IDs, instrument data sheets, and the PLC system based on client comments.
2. Drawings for the equipment layout, electrical panels, fabricated vessels, and foundations were submitted or under development. Purchase orders were placed for long-lead components.
3. Fabrication of the air receiver and surge vessel was underway, with seams being welded. Approval was received for nitrogen storage tank drawings from the Controller of Explosives.
1. Gastek provided a progress report on a nitrogen plant project for Afcons as of June 26, 2015. Revisions were made to P&IDs, instrument data sheets, and the PLC system based on client comments.
2. Drawings for the equipment layout, electrical panels, fabricated vessels, and foundations were submitted or under development. Purchase orders were placed for long-lead components.
3. Fabrication of the air receiver and surge vessel was underway, with seams being welded. Approval was received for nitrogen storage tank drawings from the Controller of Explosives.
1 P&I D – Rev-0 of the system submitted on 26 -03-2015. Comments received on 24-04 -2015. P&ID – Rev-01 submitted on 15th May- 2015. No comments have been received so far, hence considered approved. 2 Instrument Data Sheets –Part-1– Rev-0 submitted on 26 -03-2015. Comments received on 21-04 -2015. Clarifications to comments sent on 24-04-15 and accepted by M/s Afcons. 3 Instrument Data Sheets –Part-2– Rev-0 covering PLC system submitted on 08-05-2015 on receipt of comments on P&ID- Rev-0. Comments received on 19th May – 2015 on Rev-0 drawings and documents regarding PLC system. Clarifications sent on 28th May – 2015 with revision of PLC model to ET-200 SP. Most of the clarifications accepted by M/s Afcons vide their response dated 8 th June – 2015. Certain comments given by M/s Afcons vide their mail dated 8 th June – 2015 are under Gastek’s review and shall be clarified by 11th June - 2015. Pending points / comments on PLC System clarified over phone and Afcon’s remarks / acceptance received vide mail dated 24th June – 2015. 3 Revised PLC System drawings and documents (PLC wiring Diagram / IO details / PLC Configuration and Program Logic), based on the comments and clarifications, underway and shall be submitted by 3 rd June - 2015.3 QAP, FAT & SAT of PLC Panel submitted on 10 th June – 2015. Comments received on 25 th June. Revised document submitted on 26th June – 2015.3 Detailed PLC Panel GA (External & Internal) shall be submitted within 10 days on acceptance of PLC wiring diagram along with above details. 4 Equipment Layout- Rev-0 submitted on 08-04-2015. Comments received on 17-04-15, followed by mail dated 29 th April for a scheduled meeting on 7 th May-15 at Kandla Site. Revised Equipment Layout drawing sent on 14th May – 2015, as per the discussions at Kandla Site. Comments/ Remarks on Equipment Layout Drawing received on 22nd June - 2015. Revised drawings with clarifications submitted on 26th June – 2015.3 5 Electrical Panel GA & Wiring Drawings submitted on 10-04-15 and comments regarding rating of Incomer received on 17th April-15. Clarifications sent on 18th April – 2015 regarding incomer ACB rating and being accepted by M/s Afcons. Fresh set of comments to replace FSU’s with MCCB’s received on 24 th April- 2015. Comments incorporated, and Rev-01 Drawings sent on 15th May-2015. Further comments received on 20th May and 26th May – 2015. Clarifications sent on 6th June – 2015. Pending points / comments on Electrical System clarified over phone and Afcon’s remarks / acceptance received vide mail dated 24th June – 2015. 3 Revised drawings shall be submitted by 3rd June - 2015.3 Comments on Electrical Panel QAP submitted by Gastek on 10 th May-2015 received on 24th June – 2015 with Category -1 Stamping. Rev-01submitted on 26th June - 2015. 3 6 Vendors Drawing List – Rev-01 submitted on 4th May. 7 Drawings of Air receiver and Surge Vessel for PSA Nitrogen Plant submitted on 4 th May – 2015. 8 Drawing of storage tanks submitted on 8th May – 2015. 9 Detailed Design Calculations of Air Receiver, Surge Vessel and N2 Storage Tanks sent on 9 th June – 2015. JOB PROGRESS OF GASTEK AS ON 26TH JUNE - 2015 2000 Nm3/Hr – 96.00 % PURITY PSA NITROGEN PACKAGE AFCON’S P.O # : 2282/VTKN/PUR/ PACKAGES/007 VTKN CAPEX UPGRADATION PROJECT GASTEK” JOB # 2120 PROJECT # 2282 Sheet 2 of 4
JOB PROGRESS REPORT – 03 continued…
10 Comments on Drawings and design calculations of Air Receiver, Surge vessel and N2 Storage Tanks received on 12th June – 2015.3 11 Confirmations to comments on fabricated vessels sent by Gastek on 19 th June – 2015.3 12 Drawing of Air Receiver has been revised as per comments and submitted on 26 th June – 2015. Drawings of Surge Vessel and N2 storage Tanks under internal review and shall be submitted by 30 th June - 2015.3 13 Electrical and Instrumentation Cable Schedule are on Hold on account of finalization of equipment layout. Revised equipment layout already submitted on 26th June – 2015. 14 Purchase orders of Major Bought out Components with longer delivery period, already placed. Un-priced scanned copies sent vide Job Progress Schedule dated 5 th May – 2015. Placement of Purchase Orders for Panels (Electrical & PLC) on hold on account of acceptance from M/s Afcons. 15 Soil investigation report received on 1st June – 2015. Foundation drawing development for air receiver, surge vessel and N2 Storage Tanks underway. Foundation drawing development of PSA Skid ON HOLD, on account of non finalization of Layout. 16 3 No’s Nitrogen Storage Tanks Fabrication drawing and Design calculations of 3 No’s Nitrogen Storage Tanks have been submitted to Third Party Inspection Agency (M/s Bax Counsel Inspection Bureau P Ltd) of Controller of Explosives (CCE). Approval of drawings and documents expected by 18th June. Drawings and documents pertaining to N2 Storage Tanks approved by Controller of Explosives (CCE).3 Procurement of materials for shell and dish ends and flanges with nozzle materials underway. 3 JOB PROGRESS OF GASTEK AS ON 26TH JUNE - 2015 2000 Nm3/Hr – 96.00 % PURITY PSA NITROGEN PACKAGE AFCON’S P.O # : 2282/VTKN/PUR/ PACKAGES/007 VTKN CAPEX UPGRADATION PROJECT GASTEK” JOB # 2120 PROJECT # 2282 Sheet 3 of 4
JOB PROGRESS REPORT – 03 continued…
17 Air Receiver 3 Long seams of Air Receiver complete. Circumferential seam of air receiver complete First Dish end fitment with shell complete. Root run of 2nd dish end complete. Nozzle opening for Manhole and other nozzles pending. Final weld of 2nd dish end shall commence after opening for manhole is made. JOB PROGRESS OF GASTEK AS ON 26TH JUNE - 2015 2000 Nm3/Hr – 96.00 % PURITY PSA NITROGEN PACKAGE AFCON’S P.O # : 2282/VTKN/PUR/ PACKAGES/007 VTKN CAPEX UPGRADATION PROJECT GASTEK” JOB # 2120 PROJECT # 2282 Sheet 4 of 4
JOB PROGRESS REPORT – 03 continued…
18 Surge Vessel 3 Root run of long seams completed Root run of 2 No’s Circumferential seams for three number shell complete. Set up of 1st dish end underway.
19 PSA Towers & Carbon Bed:-3
Since changes in equipment layout as submitted on 26 th June – 2015, which may require changes in nozzle orientation are not foreseen, detailed drawings and design calculations for PSA Towers and Carbon Bed are underway. However, plates for shell and dish ends as per design requirement are available.