This estimate has been framed in the office of the Assistant Engineer, DWS Sub-
Division, Ampi for an amounting to Rs.3,90,082.00(Rupees Threelakhs Ninety
Thousand And Eighty Two) Only in/c. 3% Contingency for the above mentioned work.
Report
This priliminary estimate has been framed by the Assistant Engineer, DWS Sub-
Division, Ampi for an amounting to Rs. 3,90,082.00(Rupees Three lakhs Ninety
Thousand And Eighty Two) Only in/c. 3% contingency to meet up the probable
expenditure to be incurred for the above mentioned work. The people of this villagers is
facing acute water crises for which this innovative scheme has been proposed. At present
this villagers are dinking water from the river side open well.
Hence, this estimate requires necessary technical sanction from the competent
authority of the department concern.
Cost :-Rs.3,90,082.00
Method :-By Contract.
Time :- 12 (Twelve) Months.
Rate :-Based on DWS SOR-2020, PWD (R&B) & approved rate.
T&P :-Will be arranged by the Agency.