Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

Chapter 26

Pumping Station
Design Examples
GARR M. JONES
GARY S. DODSON
THEODORE B. WHITON

CONTRIBUTORS
Roger Cronin
Philip A. Huff
Paul C. Leach
Ralph E. Marquiss
M. Steve Merrill
Earle C. Smith
Patricia A. Trager
William Wheeler

Chapter 12 contains details for selecting pumping pacity: 25.9 L/s (410 gal/min). Improvement of
equipment and installing it in properly designed wet original design.
wells with piping arrangements that allow for easy . Section 26-2. Three dry-pit, V/S pumps for domestic
access in a minimum of space. The principles for the wastewater in a trench-type sump. Capacity: 219 L/s
layout of the basic elements of wastewater and water (5 Mgal/d). Improvement of original design.
pumping stations respectively are given by example in . Section 26-3. Three four-stage, two-speed vertical
Chapters 17 and 18. These principles should be fol- turbines for raw water in a trench-type sump. Ca-
lowed with an overall objective of keeping the instal- pacity: 920 L/s (21 Mgal/d). Designed in 1993, and
lation as simple as possible. The guiding rule should began service in 1995.
be to protect the equipment and installation and, as
Dimensions and values in the plans and text for
much as practicable, protect against the prospect of
each section are, for simplicity, written in either SI
catastrophic failure. Care should be exercised to fol-
units or in U.S. customary units but not usually in
low the requirements of appropriate code documents
both. Readers should have no difficulty in transform-
and industry standards.
ing one set of units into the other.
This chapter contains examples of both actual and
hypothetical designs that reflect improvements in
technology that have occurred since publication of
the first edition of Pumping Station Design in 1989.
26-1. Redesigned Clyde Wastewater
The examples of pumping station design include:
Pumping Station

. Section 26-1. Duplex submersible pumps for do- The Clyde Wastewater Pumping Station in Contra
mestic wastewater in a hopper-bottom sump. Ca- Costa County, California, was rebuilt in 1991 to

26.1
26.2 Chapter 26 Pumping Station Design Examples

feature a self-cleaning sump. It is cleaned by pumping . Location: on shoulder of narrow residential street.
the water level down while vigorously mixing the Considerations include space, visibility, odors,
contents with water from the force main. In the as- noise, and security.
built plans, shown in Figure 17-22, eccentric plug
valves in the valve vault can be regulated to take
water from either the force main or from either of
the two pumps. The water is discharged under con- Station Siting
siderable pressure at the surface of the lowered water
level in the sump while a pump discharges the mixed Station siting is established by the low point in
liquid to the force main. The system works well for the tributary area as well as access, availability of
removing both scum and sludge and leaves the wet property, proximity to residents (i.e., farther is
well remarkably clean. better), and the cost of piping to and from the site.
In this section, the station is described as it might The low point in the tributary area usually dictates
be designed in 2005 with the technology developed the general location. Access is important because
since the original plans were drawn. These changes operation and maintenance staff must be able to
consist of (1) steeper slopes to allow sludge to slide visit the facility at any hour of the day and under
down to the pump intakes so that sludge is removed adverse conditions. Access by public roads (paved, if
with every motor start, and (2) a sloping approach possible) without the need to traverse private prop-
pipe for introducing the inflow without a cascade and erty or move parked automobiles is required. It is
for supplying added storage to reduce the size of the also preferable to provide room for maintaining the
wet well. In other respects, the design approach station without obstructing traffic or endangering
closely follows that of the existing Clyde pumping workers.
station except that fewer valves are used in the valve Property and easement acquisition begins imme-
vault. diately after selecting the preferred site and before
The actual design was carried out in U.S. custom- design on the pump station begins. Many projects
ary units, so those are the units used in this example. have been delayed and/or designs changed because
The original sewer design studies, surveys, and dis- the site acquisition process did not begin soon
cussions with operation and maintenance staff estab- enough. Such delays and changes will result in sig-
lished the following general requirements for this nificant costs to the owner of the facility.
wastewater lift station.

. General: submersible pumps were preferred be-


cause of overall low cost, low maintenance, simpli- Hydraulic Design
city in operation, and minimizing visual impact on
the neighborhood. Hydraulic design includes sizing the force main and
. Flow rates: Present average dry-weather flow: 30 gal/ developing the system curves, which are then used to
min. select the number and size of the pumps. The rest of
Present peak wet-weather flow: 236 gal/min. the facility is designed around the pumps. The force
Future peak wet-weather flow: 410 gal/min main invert elevation at the pumping station should,
(equals the capacity of one pump). if possible, be set to allow for a constantly rising
. Ground elevation: 13.2 ft. Pumping station site is slope. High spots (knees) in a wastewater force
relatively flat. main are to be avoided if at all possible because
. Force main: An existing 8-in. cement-lined ductile knees require air release valves, and it is wise to
iron pipe 2750 ft long was available. avoid them if possible (see Section 5–7). Force main
Invert elevation: 6.6 ft at the pumping station installation costs increase with depth, so it is best to
and 20.6 ft at the discharge. keep the pipe as shallow as possible. The discharge
Slope: constant. end of the force main is susceptible to hydrogen
. Reliability: ability to pump future peak wet-wea- sulfide corrosion and should be protected by using
ther flow with either of the two pumps out of corrosion-resistant piping (PVC, or HDPE) where
service. exposed to air or else be submerged to prevent cor-
Hook-up for portable engine-generator due to rosion. Corrosion-resistant piping, as shown in
lack of space for permanent engine-generator. Figure 26-1, should begin 10 ft before the point
High wet well power-failure and intrusion alarm where the static water level contacts the soffit of the
hooked up to an auto-dialer. force main.
26-1. Redesigned Clyde Wastewater Pumping Station 26.3

Figure 26-1. Piping profile.

Force mains should be sized to provide a min- System curves are developed to define the design
imum fluid velocity of 2.5 ft/s at present flows and a operating point and extreme operating conditions for
maximum fluid velocity of 6 to 8 ft/s at future peak the pumps. Computations for these conditions at the
wet weather flows. The minimum fluid velocity future peak wet weather flowrate are given in
ensures that most solids will be moved through the Table 26-1. Note that K-values are not absolutes.
force main. The maximum fluid velocity is set to min- Different engineers may elect to use different values.
imize headloss and reduce surge pressures in long force Those in Table 26-1 differ somewhat from those in
mains. A 6-in. force main would meet these criteria for Table B-6. Minimum losses are given for a pipe
the stated flow conditions. However, an 8-in. mortar- roughness corresponding to C ¼ 145, and the max-
lined ductile iron pipe was already in place and was imum is for C ¼ 120. The results are shown graphic-
therefore used. The fluid velocity in the force main for ally in Figure 26-2. Point A is the normal flow and
this pumping station with its one duty pump is 2.5 ft/s head condition, and Point B is the extreme flow and
(see Table B-2 for the cross-sectional area). head condition at which the pump may operate.
26.4 Chapter 26 Pumping Station Design Examples

Table 26-1. Total Dynamic Headlosses for Q ¼ 410 gal=min (0:91 ft3 =s)

Headlosses, ft

C ¼ 145 C ¼ 120
Description Minimum Maximum

Station losses (4-in. DIP, v ¼ 10.3 ft/s) K-value


Entrance 0.50 0.82 0.82
908 bends, 2 at 0.25 0.50 0.82 0.82
458 bend 0.20 0.33 0.33
Ball check valve 1.35 2.22 2.22
Eccentric plug valve 0.50 0.82 0.82
Tee, line flow 0.30 — 0.49
908 bend 4- to 8-in. expanding 0.50 0.82 0.82
Tee, branch flow, v ¼ 2.49 ft/s 0.75 0.07 0.07
Force main losses
2750 ft 8–9 in. DIP, lined (v ¼ 2.49) 6.93 9.83
P
Minor losses, valves, discharge. K ¼ 2:5 0.24 0.24
Static lift 8.78a 19.18

Total design head 21.85 (22) 35.64 (36)


a
Wet well is assumed to be filled to ground level.

Not all submersible pump manufacturers include Pump Selection


the entrance and discharge elbow losses in their pump
curves. The specified design point should be clear on Operation and maintenance personnel prefer equip-
what has been included for losses. The minor losses ment with which they are familiar. They do not like
are not very important for pumping stations with ‘‘experimental’’ applications. Pump selection starts
long force mains, but they could be significant for a by soliciting input from the people who operate
lift station with low head requirements. them. Identical pumps are used for multiple pump

Figure 26-2. Pump and system head-capacity curves.


26-1. Redesigned Clyde Wastewater Pumping Station 26.5

applications whenever possible to simplify mainten- tained within the walls. If a disposable form is used,
ance and provide interchangeability of parts. It is the concrete should be covered with a protective liner
advantageous to have service and parts available such as PVC. The vertical walls above the ‘‘cone’’
from a nearby source. should also be protected with a PVC liner.
The selected pump curve and impeller diameter
should meet the design point near the best efficiency
point (BEP). The selected pump should also operate Active Volume
at the low head and high head extremes without
cavitating or vibrating. Pump curves with steep slopes The active or working volume of wet well and ap-
are better than those with flat slopes because there is proach pipe must be adequate to limit the frequency
less variation in capacity with varying head condi- of pump starts to a safe value. Conical bottoms reduce
tions. (Flat spots or dips in the pump curve are there- the volume available in the wet well, but the addition
fore undesirable.) Wherever possible, choose impellers of an approach pipe laid on a 2% gradient, as de-
of intermediate size so that a larger impeller can be scribed in Example 12-2, supplies additional volume.
substituted for larger future flows. The motor is sized The normal LWL is set above the invert of the
for the worst possible operating point (which is often approach (inlet) pipe by 60% of its diameter and the
the low head extreme with one pump operating). For invert is set at or somewhat above the top of the pump
multiple pumps, the best pump efficiency should be at volute. Except during cleaning, (1) the motor is always
normal operating conditions and not at the ultimate at least half-submerged, and (2) there is no free fall into
peak flows. However, the emphasis should be on the wet well. Consult the manufacturer about the min-
finding pumps that can operate within the POR at imum submergence for the motor and the maximum
the most frequent pumping condition, within the frequency of pump starts. Starting frequency for small
AOR for all pumping conditions, and without vibra- to medium-sized submersible pumps may be expected
tion or cavitation at all anticipated service condi- to vary between 10 and 20 starts/hour depending on the
tions. resting time between starts. Using an alternator in
stations with multiple pumps to switch lead pumps
after each pump cycle reduces the starting frequency
Wet Well and prolongs the life of the motor. However, one pump
may be out of service, so duplex stations must be
The wet well is designed to (1) have adequate space for operable without alternation. Nevertheless, when
the pumps, (2) facilitate cleaning, (3) contain sufficient both pumps are serviceable, alternation could be used
storage volume, (4) limit pump starts, and (5) minimize to extend the life of the starters and motors.
installation costs. For a small duplex submersible Inlet pipes are traditionally oriented in a plane nor-
pumping station, the most economical wet well is mal to the plane of the pumps, as shown by the dashed
often a reinforced concrete pipe 1.8 or 2.4 m (6 or lines in Figure 12-31. Such a configuration tends to
8 ft) in diameter standing on a cast concrete bottom. promote rotation that could increase to swirling in
To improve solids removal, the pumps are con- pump intakes. A better configuration is to orient them
fined by close-fitting, nearly conical, smooth walls in the plane of the pumps so that the pump motor acts as
sloping at 60 degrees or more. Sludge and grit slide a baffle for the incoming current as shown in Figure
down the walls to the pump suction. If the walls clear 26-3a and b by the solid lines in Figure 12-31. Baffles are
the pump volutes by no more than 100 mm (4 in.), desirable to break up incoming currents and reduce
the flat floor area is small and within the influence of turbulence. Furthermore, as the current is split by the
the suction currents of both pumps. Consequently, pump motor, there is no tendency for rotation to occur.
the sludge is so confined that it cannot accumulate Calculate the required active volume from Equa-
under the inactive pump for longer than one pump tion 12-8. If the allowable starting frequency for one
cycle if the pumps are alternated. The sloping walls pump is 10 cycles/hour, each cycle takes 6 min and
may be constructed by placing a custom form in the the required volume is
wet well and injecting concrete behind the form.
Fiberglass-reinforced plastic or stainless steel (or TQ
any smooth, durable material) can be used as the V¼
4
form and can then remain in place as a liner to
(6 min)(410 gal=min)
provide a smooth, corrosion-resistant surface to fa- ¼ ¼ 615 gal ¼ 61:8 ft3
cilitate cleaning. Holes are required in the form for 4
the pump discharge elbows, which are largely con- where T ¼ time in minutes and Q ¼ flow in gpm.
26.6 Chapter 26 Pumping Station Design Examples

Figure 26-3. Layout of redesigned Clyde pumping station. (a) Plan view; (b) Section A-A.

The wet well and approach pipe are laid out so pipe and not in the wet well. The HWL is set at
that the working volume is 615 gal. The existing wet 4.80 ft. At the upstream manhole, the invert elevation
well has limited volume, but an approach pipe 100 ft of the approach pipe is 4.30 ft. On a rising grade of
long by 12 in. in diameter, laid on a 2% slope, in- 2%, the invert on the upstream side of a 48-in. man-
creases the working volume to 870 gal. The invert hole would be 0.08 ft higher, but there is some form
elevation at the wet well is 2.30 ft. The LWL is set and friction loss in the transition from half-filled
at 2.80 ft to force the hydraulic jump to occur in the sewer to quarter-filled approach pipe, so an increase
26-1. Redesigned Clyde Wastewater Pumping Station 26.7

of 0.05 ft brings the sewer invert to an elevation of mechanical device on the pump, and a single manu-
4.43, as shown in Figure 26-1. facturer.

Standby Power Controls and Alarms

The site cannot accommodate the installation of a The pumps are set up in a lead/lag arrangement with
permanent engine-generator for standby power. The automatic alternation after each pump cycle to bal-
operator has chosen to store a portable engine-gener- ance run times and minimize starts per hour. HAND/
ator at a site about a mile from this facility. A power OFF/AUTO operator selector switches are provided
failure and high-water alarm indicate potential for each pump at the control panel located with a
overflow at the station. During dry-weather flow, view of the wet well. Pumps are operated by the wet
more than one hour is available to transport and well water level indicated by a pressure transducer/
connect the portable engine-generator. However, transmitter hanging in a PVC pipe in the wet well.
during wet weather periods, there may be less than Keypad controllers are generally preferred because
10 min available for that task. Wastewater pumping they are easy to operate, do not have pins (easy to
stations should normally be provided with perma- lose), and can be programmed with a security code.
nent, on-site standby power to reduce the exposure The high-water-level alarm consists of a float switch
to wastewater overflows. connected to an auto-dialer that pages the on-call
operator. A stainless-steel chain supported by the
hatch frame is connected to the float switch so the
Station Piping operator can periodically test the switch. A nylon
cord would serve the same purpose at less cost.
Station piping within the wet well is limited to the two
pump discharge lines and a force main drain line.
Piping within the wet well is as simple as possible Operation and Maintenance
with few fittings and no valves. Flange bolts within
the wet well are 316 stainless steel, as are the pipe Double-leaf, spring-loaded aluminum hatches rated
supports and hardware. The piping design within the for an H-20 loading are installed over the wet well for
wet well minimizes items that corrode, that require access to the pumps. Similar hatches are installed
regular maintenance, or that may catch floating de- over the valve vault. Safety chains are provided to
bris. Valves and fittings are contained in a separate create a barrier when the hatch is open. Hatches are
valve pit next to the wet well. equipped with padlocks for protection against van-
The valve pit contains the pump isolation and check dalism.
valves on the two pump discharge lines and their con- Telescoping stainless-steel tubes are used for guide
nection to the force main. A valved force main drain rails for installing the pumps. Except during times
line that discharges back into the wet well is also in- needed, they are lifted out of the water and hence
cluded. It can be used to agitate the contents of the wet do not collect debris. Lifting chains to the pumps are
well vigorously so that scum, mixed into the contents, omitted because it is easier to lift the pump by its
is ejected with the wastewater. Such mixing eliminates lifting bail. Lifting by a chain requires a high boom.
the need to pump the water level down to the pump The owner uses a truck-mounted boom and winch for
volute to develop vortices for engulfing the scum—an lifting pumps but, alternatively, a fixed crane or hoist
operation that subjects the pump to vibration, stress, could be installed on site. Winches are equipped with
and wear of the mechanical seals. Valve stems and nuts ratchets for use in both directions.
are extended nearly to grade to permit operation with- The site is equipped with overhead lights with
out the need to enter the vault. electric power supplied from a nearby power service
An alternative is the use of a pump that ejects part pole. Lights are also provided within the outer door
of its discharge into the wet well during the first of the control panel. A weather guard extending
minute or two after the pump is switched on. The 18 in. in front of the panel is installed at the top
water ejected through a flush valve mixes the solids so front of the control panel. A hook-up with a manual
that some are discharged to the force main during transfer switch makes it easy to use the owner’s
each pump cycle. The advantage is that the wet well trailer-mounted engine-generator.
is kept continuously clean automatically. The disad- Wash-down water is obtained on-site from the
vantages are a small loss of efficiency, the added potable water supply. The equipment consists of an
26.8 Chapter 26 Pumping Station Design Examples

air-gap tank, water pump, and hose bibb contained Figures 17-13 and 17-14, so the same units are used
in a locked steel cabinet. The wash-water pump, in this section. The station has been in continuous
equipped with a preset timer for automatic shutoff, operation since 1967. The following example is a
also has an automatic recirculation line with a pres- revised version of the existing station, modified to
sure regulating valve. Steel traffic bollards are placed reflect: (1) wet well design developments that facili-
around the water and electrical control cabinets. tate the self-cleaning features described in Chapter
There is no fencing around the site. 12; (2) the best in current technology; and (3) more
recent and stringent reliability standards. The station
consists of three 2.5 Mgal/d pumps operating against
Final Check a total dynamic head of 189 feet.
The top of the influent sewer is no more than 6 ft
After completing the pump selection and piping lay- below finished grade. For such a shallow site, hori-
outs, the system hydraulics are checked again to see zontal pumps were selected for both the 1965 and the
that the pump selected is the best fit, and that the current designs. Because they are less prone to vibra-
motor and electrical gear are sized adequately. The tion, horizontal pumps are preferred when they can
drawings and specifications are reviewed by the be justified by little increase in structure cost. Instead
owner, and the operators are walked through the of the eddy-current couplings used in the original
design system-by-system. Final revisions are made station, the revised design has 125-hp adjustable-fre-
before bidding the project. quency drives. A 300-kW standby generator protects
against power outages.
The force main terminates at an interceptor sewer
Critique 3150 ft from the pumping station site at an elevation
123 ft above the soffit of the influent sewer. Calcula-
Compare Figures 26-3, 17-21, and 17-22. The choice tions were performed by using PUMPGRAF ß [1], a
of pumping station configuration for each site should computer spreadsheet program configured specific-
be based on sound judgment in which first cost is ally for pumping station design work.
balanced against cleanliness and desired control of
odors and the ease and cost of maintenance.
Some operators prefer that the pump discharge Individual Hydraulic Losses
lines be cross-connected with each other upstream
from the check valves (with a valve on each branch) Calculations for individual hydraulic losses from the
and connected to the force main drain line, as in pump inlet to the connection with the discharge
Figure 17-22. Although such piping increases the manifold were performed first and are shown in
number of valves, the size of the valve vault, and Table 26-2. The pump inlet bell diameter in the wet
the project cost, it allows the operator to agitate the well was selected on the basis of a conservative limit-
wet well contents with one pump before pumping to ing fluid velocity of 4.5 ft/s even though ANSI/HI
the force main with the other. It also allows the 9.8-2000 allows 5.5 ft/s. Maximum velocities in
operator to backflow one pump with the other to pump connecting piping were considered acceptable
remove clogs without removing the pump. for a variable-speed station, where higher losses are
The plans in Figure 26-3 indicate a cone-shaped only realized when the equipment operates at full
hopper bottom. To keep the water surface area as small speed. Upon completion of these calculations, they
as possible so that scum will be readily drawn into the were automatically loaded into the program for the
pump intakes at pump-down, the sides of the sump calculation of station system losses.
should hug the pump volutes with no more than 4 in.
of clearance. These pumps are too far apart. A clearance
of 4 in. is enough. Interference is no consideration. The Station System Losses
pumps are not operated simultaneously.
Station system headlosses in the force main (includ-
ing static lift) were calculated from the manifold to
26-2. Redesigned Kirkland Wastewater the point of discharge and are shown in Table 26-3.
Pumping Station Instead of the asbestos cement pipe used in the ori-
ginal project, HDPE was the material selected for the
Designed originally in 1965, the Kirkland Pumping force main. Losses were initially calculated for a
Station is shown in U.S. customary units in Hazen-Williams C of 140 and then recalculated for
26-2. Redesigned Kirkland Wastewater Pumping Station 26.9

Table 26-2. Pump Intake and Discharge Headlosses

2.5 ¼ Starting Flow  mgd Title: Revised Kirkland Pumping Station


119.98 ¼ Elev @ Start  Feet Brown and Caldwell
140 ¼ Default C-Value >25 New C: 140 HiGrf LoGrf PmpCorr

14 ¼ Default Diam Inch New D: 14 53.34 ¼ Target Headloss


304.8 ¼ Default Pipe Length Feet 9.185 ¼ Total Headloss – Feet
Date: 06-July 96 ParaEq ¼ 3169.6 ¼ EqivLnth (Std¼def) – Feet
Flow, Item Description of Diameter, K or Fixed Length, Loss, Hyd Grad, ft Vel, V-Hd,
mgd Friction Loss in. Cval Loss ft Item No. ft Pmp ! Dch fps ft

2.5 Bell Mouth Entrance 14 0.05 1 0.01 119.97 3.6 0.2


2.5 908 Elbow 10 0.3 2 0.23 119.74 7.1 0.78
2.5 Plug Valve 10 0.6 3 0.47 119.27 7.1 0.78
2.5 Reducer 10 0.01 4 0.01 119.26 7.1 0.78
2.5 PUMP 14 0.01 5 0.00 119.26 3.6 0.2
2.5 Increaser 6 1 6 6.03 113.23 19 6.03
2.5 908 Elbow 10 0.6 7 0.47 112.76 7.1 0.78
2.5 Check Valve 14 3.5 8 0.71 112.05 3.6 0.2
2.5 Plug Valve 10 0.6 9 0.47 111.58 7.1 0.78
2.5 Branch Flow Tee 10 1 10 0.78 110.80 7.1 0.78
2.5 11

Table 26-3. Force Main Headlosses for C ¼ 140

5 ¼ Starting Flow – mgd Revised Kirkland Pumping Station


119.98 ¼ Elev @ Start – Feet Title: Brown and Caldwell
120 ¼ Default C-Value > 25 New C: 120 HiGrf PmpCorr
14 ¼ Default Diam – Inch New D: 14 ¼ Target Headloss
1000 ¼ Default Pipe Length – Feet 169.49 ¼ Total Headloss  Feet

Date: 06-July-96 ParaEq ¼ 3341.6 ¼ EqivLnth (Std¼def)  Feet


Flow, Item Description of Diam, K or Length, Item Loss, Hyd Grad, ft Vel, V-Hd,
mgd Friction Loss in. Cval Fixed Loss ft No. ft Pmp ! Dch fps ft

5 Fixed Static head 122 1 123.00 289.48


5 908 Elbow 14 0.6 2 0.49 288.99 7.2 0.8
5 Straight Pipe 14 120 25 3 0.35 288.64 7.2 0.8
5 908 Elbow 14 0.3 4 0.24 288.40 7.2 0.8
5 Straight Pipe 14 120 140 5 1.95 286.45 7.2 0.8
5 458 Elbow 14 0.25 6 0.20 286.25 7.2 0.8
5 Straight Pipe 14 120 1040 7 14.47 271.77 7.2 0.8
5 908 Elbow 14 0.3 8 0.24 271.53 7.2 0.8
5 228 Elbow 14 0.1 9 0.08 271.45 7.2 0.8
5 Straight Pipe 14 120 975 10 13.57 257.88 7.2 0.8
5 908 Elbow 14 0.3 11 0.24 257.64 7.2 0.8
5 Straight Pipe 14 120 995 12 13.85 243.79 7.2 0.8
5 Outlet Loss 14 1 13 0.81 242.98 7.2 0.8
5 14
26.10 Chapter 26 Pumping Station Design Examples

a C of 120. Individual losses for the pump inlet and rating for the pump. In this example, the pumps are
discharge piping in Table 26-2 were not included in to be rated at 2.5 Mgal/d at a total head of 180 ft.
these calculations. The pump selection is considered acceptable because
the intersection between the pump performance
curve and the expected range of operating conditions
Pump Selection lies well within the AOR. Note that the intersection
between the manufacturer’s curve and the station
Station system losses were then transferred through system curves lies to the right of the pump’s best
the program to the pump selection program (see efficiency point. As speed is reduced in variable-
Table 26-4), and a pump was selected from a previ- speed operation, the point of intersection of the
ously entered library of pump manufacturers’ catalog curves passes through the pump’s zone of best effi-
information. Plots of the selected performance ciency.
curves against station system curves are shown in After an acceptable pump selection was found, the
Figures 26-4 and 26-5. The pump performance program was used to evaluate pump performance at
curves plotted on the figure have been adjusted for variable speed, and these data are shown in Table 26-5
individual pump inlet and discharge piping losses of and in Figure 26-5. As indicated, the minimum oper-
9.2 ft at 2.5 Mgal/d. These values must be added to ating speed is approximately 1300 rev/min, which
the information on the plot to arrive at the correct corresponds to a flow rate of 0.6 Mgal/d.
26-2. Redesigned Kirkland Wastewater Pumping Station 26.11

280 280
1785 rev/min
260

17
85
%
240 240
64

62
Tw
op 220
70 um 16 70
200 72 ps 200 0 72
O

73 re 73

Head, ft
ne
Head, ft

v/
0 m
72
pu

2 180 in 72
=1 0
m

C 14 12
71 C=
p

160 0 160 50 71
14
67 C= 67 14
0
64
140 13
64 C=
0 0
120 120

100

80 80
0 1 2 3 4 5 6 0 1 2 3 4 5 6
Discharge, Mgal/d Flow rate, Mgal/d

Figure 26-4. Pump and system curves. Figure 26-5. Single pump at variable speed operation.
26.12 Chapter 26 Pumping Station Design Examples

Hydraulic Profile velocity above the trench to 1 ft/s for any inflow. At
the maximum inflow of 5.0 Mgal/d, a cross-sectional
Next, a plot (Figure 26-6) of the force main and hy- area of 7:75 ft2 is required, and at half the flow with
draulic profiles was constructed for a visual portrayal the inlet pipe half full, the required cross-sectional
of hydraulic conditions in the system at both minimum area above the trench must be no less than 3:88 ft2 .
and maximum system capacity. From an inspection of In this design, the second criterion is the more critical
the plot, it was found that the hydraulic profile remains and results in locating the top of the trench 4.0 in.
well above the force main profile from the pumping below the invert of the influent pipe. If the sides are
station to the point of discharge under all operating allowed to slope at 45 degrees, the wet well above the
conditions. In addition, there appeared to be no high inlet pipe can be made 5 ft wide. Note that installing
points or knees that would be the location of column the sluice gate requires a flat surface at least 12 in.
separation in a hydraulic transient condition. Finally, wider than the diameter of the inlet pipe.
the pipeline profile does not touch the mirror image
line, so column separation does not appear to be a Pump Intakes
problem (see Section 7-1). For a 21-in. force main
constructed of HDPE, the wave propagation velocity The dimensions of a ductile iron bend and flare were
is about one-third of that for ductile iron or asbestos judged to be unfavorable, so a special fitting consist-
cement (refer to Chapter 7). Based on inspection of the ing of a short-radius steel 90-degree bend welded
force main/hydraulic profile plots and the low wave between a 14  10 reducer (with an OD of 14 in. or
propagation velocity, a formal transient analysis might 1.17 ft) and a steel flange was selected. The trench
not be necessary. However, under the rules given in was made 2.33 ft wide—equivalent to two bell
Section 6-8, a transient analysis would be required diameters.
because (1) the TDH exceeds 50 ft and the flow rate The maximum intake fluid velocity for a single
exceeds 500 gal/min, and (2) the pipeline has a long, pump at a flow rate of 2.9 Mgal/d (see Figures 26-4
steep gradient followed by a long, shallow gradient. and 26-5) is 4.2 ft/s. The minimum center-to-center
spacing of pump intakes should be at least 2.5 D or
Geometry 2.92 ft.

The station capacity is 5 Mgal/d or 7:75 ft3 =s. From Intake Submergence
the principles presented in Chapter 12, the cross-
sectional area of the wet well above the trench should Submergence, governed by Equation 12-1, was calcu-
be sufficient to limit the average forward (plug flow) lated to be 3.0 ft at runout conditions for a single

200
Maximum hy
180 draulic profile

160

140
e
Mirror imag
Elevation, ft

120

100

80
Pipe line profile
60

40

20

0
0 500 1000 1500 2000 2500 3000 3500
Distance from pumping station, ft.
Figure 26-6. Plot of hydraulic and force main profiles.
26-2. Redesigned Kirkland Wastewater Pumping Station 26.13

pump. (Details of a somewhat similar calculation are the last pump. For this short trench, a dropped floor
given in Example 12-1, Part C.) The LWL would be set is unnecessary as proven by model studies.
somewhat above the invert of the influent pipe. For
example, minimum flow would be expected to be about
one-tenth of maximum flow or 0.5 Mgal/d. By using Plans
Figure B-4 or Table B-8, minimum flow depth in the
influent sewer can be determined and the LWL set at The plans, shown in Figures 26-7 through 26-9, illus-
that same elevation. For practicality, however, if the 4 trate the conceptual design for the revised station.
ma signal from a 4 to 20 ma range is set at the invert of Because the station must be located on a very small
the influent pipe, the LWL should be about right. The site, the pump inlets were located at the minimum
trench depth was based on submergence with respect to permissible separation so as not to encroach on the
(1) wet well level even with normal flow depth in the space needed for the engine-generator. The pump
influent sewer, (2) LWL at runout for a single pump, inlet piping for Pumps 2 and 3 were skewed to permit
and (3) a floor clearance of D/2 for upstream pumps. the pumps to be located with a clear separation of
The trench must be at least 2.5 D deep, but it might have 3.5 ft between bases.
to be deeper to satisfy submergence requirements. The wet well has been revised to include an ogee
The last pump (farthest from the influent sewer) ramp and a motor-operated sluice gate to protect the
has its inlet located D/4 above the floor. Find the wet well in emergencies. Instead of locating a grated
sequent depth during pump-down, however, and walkway over the pump inlet channel as in the ori-
make sure the inlet is about D/2 below the water ginal design, a walkway alongside the channel makes
surface to avoid losing prime too quickly. For other access far more convenient for housekeeping chores
wet wells, it might be necessary to drop the floor at (such as hosing grease off the walls).

UP
AF Converter

Walkway
B B
Wet well

Standby gen-set

Motor control center


UP

Motors

Pump 3 Pump 2 Pump 1

Shelf
Roll-up door

A
0 5 10 ft
Scale
Figure 26-7. Ground floor plan. Revised Kirkland Pumping Station.
26.14 Chapter 26 Pumping Station Design Examples

Hand rail

Walkway

Figure 26-8. Section A-A. Revised Kirkland Pumping Station.

Figure 26-9. Section B-B. Revised Kirkland Pumping Station.


26-3. Jameson Canyon Raw Water Pumping Station 26.15

Instead of a spiral stair (permissible under then- River system and delivers it to the City of Vallejo,
prevailing codes), a conventional stairway for access California, Fleming Hill Water Treatment Plant. In
from grade level to the pump room is used in the addition to the new pumping station, the project in-
revised design. All station auxiliaries (water pumps, cluded construction of a parallel pipeline from the res-
hydropneumatic tank, air compressors) are located ervoir to the treatment plant on an alignment through
on an L-shaped bench along the south and east Gordon Valley. The original station, which has been
walls. To conserve space at grade level, cabinets for retained and modified to function as a reserve facility,
electrical equipment (instead of being located in a was found to be troublesome because of capacity-limit-
separate room with a controlled climate) are to be ing inlet conditions and other defects. In addition to
furnished with an internal cooling system. other problems, the station was sometimes troubled by
accumulations of silt in the reservoir.
Vertical turbine pumps were selected for the new
Critique station because it could be constructed without the
cost of a pump room below ground level. Three
The suction bells, spaced at 2.5 D on centers, could pumps were installed initially, with a position for a
perhaps be spaced at 2.0 D on centers (as shown for fourth. Each pump has a nominal capacity of 416 L/s
unconfined wet wells in an older edition of the Hy- (9.5 Mgal/d).
draulic Institute’s Standards [2]) and thereby save The new pumping station can receive water from
14 in. of wet well length. But the greater spacing is three sources, all with differing energy gradients. To
more conservative and still keeps the wet well very limit costs and provide acceptable sump levels for
short. Whether to keep this spacing and splay or bend operation with any source, a modulating butterfly
the suction pipes, or to use rectilinear piping (as in the valve (installed upstream from the station but down-
original shown in Figure 17-13) and a much longer stream from the connection to the three sources)
wet well, is a matter of engineering judgment. One operates to maintain a fixed level in the pump
disadvantage of the plans shown here is that if the sump. The siltation problem noted in the operation
suction piping for Pump No. 3 ever clogs, it would be of the existing station dictated a sump configuration
more difficult to rod out debris than it would be for a that could avoid accumulations of the silt that ham-
straight pipe. The need for rodding, however, is rare pered the operation of the existing station. The plan
because of the protection afforded by setting the and cross-sectional views of the finished design are
pump intakes at relatively small floor clearances. shown in Figures 26-10 and 26-11.
The pump intake piping will be fitted with flush-out An evaluation of operational considerations
connections to permit clearing the pipe with high- showed that two-speed pumps afforded considerable
pressure water. Mitered bends of a radius long savings in operation and maintenance costs over vari-
enough to pass rodding equipment could be used as able-speed drives, which would have no significant
an alternative. Another disadvantage is that because advantages for this facility. The sump was designed
of the elbow connection, the distance from the back with sufficient volume to accept a two- to three-minute
wall to the center of the pump intake is 1.0 D instead fluctuation in water delivery rate without upsetting
of the preferred 0.75 D. The latter disadvantage can the pump control system. Power-actuated 400-mm
be overcome by adding vertical fillets at the corners (16-in.) ball valves on the pump discharges were
of the back wall to inhibit vortex formation in the specified to control surges in the station sump on
stagnant water downstream of the intake. pump start-up and shut-down.
A trench width of 2.33 ft is too narrow for install- An overflow consisting of a weir, trough, and three
ing flow splitters, cones, or fillets. Omit them, as they 600-mm (24-in.) pipes (Figures 26-10 and 26-11)
were omitted in the original pumping station. Al- from the sump to the reservoir is for relieving surges
though side wall and floor vortices are known to and backflow to the sump on power failure.
exist, they have caused no problems. After a thorough economic analysis of the needs
and options for service during a power failure, an on-
site emergency generator was eliminated in favor of
26-3. Jameson Canyon Raw Water reconditioning a 597-kW (800-hp) pump with a com-
Pumping Station bination motor and engine drive installed in the exist-
ing station. Piping from the new station to the
The Jameson Canyon Pumping Station was constructed existing station a short distance away included
to replace an existing installation at the Cache Slough power-actuated valves that can be operated from a
Reservoir, which receives water from the Sacramento remote control center.
Figure 26-10. Plan of Jameson Canyon Pumping Station. Courtesy of Brown and Caldwell.

Figure 26-11. Cross-section of Jameson Canyon Pumping Station. Courtesy of Brown and Caldwell.
26-3. Jameson Canyon Raw Water Pumping Station 26.17

Using the Stoner Associates (now Advantica, Inc.) close. The pumps had to be specified to accept this
LIQT-PC [3] program, a transient analysis of pump- reverse flow and spin backward without damage.
ing operations revealed that a high point in the trans- Time delays are provided to prevent restart until the
mission main approximately 5500 m (3.4 miles) from pump stops turning. A large number of air-vacuum
the pumping station effectively limited station dis- valves were installed in the transmission main.
charge head at lower flows. Depending upon the
operational mode at the water treatment plant (throt-
tling or free discharge), the hydraulic profile was
dominated by the high point for flows less than Critique
657 L/s (15 Mgal/d) for throttling or 920 L/s
(21 Mgal/d) for free discharge (see Figure 26-12). The decision to omit the ogee spillway for removing
The high point in the transmission main also sediment is a matter of balancing the extra cost of a
would be the site of a vapor cavity of damaging longer wet well against the possible deterioration of
proportions on power failure at maximum flowrates. water quality caused by possible organics deposited
The transient analysis showed that the stop-and- with the solids. The likelihood of problem sediments
check ball valves at each pump must be controlled was judged to be remote for Jameson Canyon, but for
to close in 8 min on power failure to keep the pres- other raw water pumping stations, the inclusion of an
sures in the transmission main under control (see ogee spillway should be considered. If the water is
Figure 26-12). During power failure, water will clean, some cost could be saved by substituting a flat
bleed back through the pumps as the ball valves bench for the sloping side walls.

Figure 26-12. Minimum and maximum hydraulic grade lines and pipeline profile. From a Stoner Associates (now
Advantica, Inc.) LIQT-PC transient analysis.
26.18 Chapter 26 Pumping Station Design Examples

26-4. References 2. Hydraulic Institute Standards for Centrifugal, Rotary &


Reciprocating Pumps, 14th ed., The Hydraulic Institute,
1. Wheeler, W., PUMPGRAFß. Contact William Wheeler at Parsippany, NJ (1983).
683 Limekiln Road, Doylestown, PA 18906-2335 for this 3. Stoner Associates. Now Advantica, Inc., 5177 Richmond
program. Ave., Ste 900, Houston, TX 77056. www/advantica.biz.

You might also like