Professional Documents
Culture Documents
COEB Construction of Educational Building COEB Construction of Educational Building
COEB Construction of Educational Building COEB Construction of Educational Building
COEB Construction of Educational Building COEB Construction of Educational Building
COEB.V&O Construction Vision and objective 24 06-Nov-18 07-Dec-18 07-Dec-18, COEB.V&O Construction Vision and objective
A1000 Preparation of project Need report 15 06-Nov-18 26-Nov-18 0% Preparation of project Need report
A1010 preparing objective and scope or work 6 27-Nov-18 04-Dec-18 A1000 0% preparing objective and scope or work
A1020 finalizing the scope of work and extent of work 3 05-Dec-18 07-Dec-18 A1010 0% finalizing the scope of work and extent of work
COEB.BP Bidding Process for feasibility 42 27-Nov-18 23-Jan-19 23-Jan-19, COEB.BP Bidding Process for feasibility
A1030 Request for bidding - advertisment 15 27-Nov-18 17-Dec-18 A1000 0% Request for bidding - advertisment
A1040 opening of biddings and quotations 5 18-Dec-18 24-Dec-18 A1030 0% opening of biddings and quotations
A1050 Assessment of Bids 5 25-Dec-18 31-Dec-18 A1040 0% Assessment of Bids
A1060 Awarding the contract 10 01-Jan-19 14-Jan-19 A1050 0% Awarding the contract
A1070 Meetings for detailed feasibility study 7 15-Jan-19 23-Jan-19 A1060 0% Meetings for detailed feasibility study
COEB.FS Feasibility Study 70 06-Nov-18 11-Feb-19 11-Feb-19, COEB.FS Feasibility Study
A1080 Study Planning 20 06-Nov-18 03-Dec-18 0% Study Planning
A1090 Geotechnical invesitgation 30 04-Dec-18 14-Jan-19 A1080 0% Geotechnical invesitgation
A1100 borehole drilling 30 04-Dec-18 14-Jan-19 A1080 0% borehole drilling
A1110 Soil Testing 20 15-Jan-19 11-Feb-19 A1090 0% Soil Testing
A1120 developing detailed stratography 15 15-Jan-19 04-Feb-19 A1100 0% developing detailed stratography
A1130 Environmental ImpactAssessment report 30 04-Dec-18 14-Jan-19 A1080 0% Environmental ImpactAssessment report
A1140 detail of available ground features 5 04-Dec-18 10-Dec-18 A1080 0% detail of available ground features
COEB.DED Detailed Engineering Design 115 11-Dec-18 20-May-19 20-May-19, COEB.DED Detailed Engineering Design
A1150 Design of Foundations for the buildings 30 11-Dec-18 21-Jan-19 A1140 0% Design of Foundations for the buildings
A1160 Water Supply scheme 35 11-Dec-18 28-Jan-19 A1140 0% Water Supply scheme
A1170 Design of Waste Water 25 11-Dec-18 14-Jan-19 A1140 0% Design of Waste Water
A1180 Architectural Design of Buildings 26 11-Dec-18 15-Jan-19 A1140 0% Architectural Design of Buildings
A1190 Detailed Structural Design 30 16-Jan-19 26-Feb-19 A1180 0% Detailed Structural Design
A1200 Inspection of Design 15 27-Feb-19 19-Mar-19 A1190 0% Inspection of Design
A1210 Approval from the Client for the design 10 20-Mar-19 02-Apr-19 A1200 0% Approval from the Client for the design
A1220 Design Changings / ammendments 20 03-Apr-19 30-Apr-19 A1210 0% Design Changings / ammendments
A1230 Finalizing the design 10 01-May-19 14-May-19 A1220 0% Finalizing the design
A1240 Approval of design 4 15-May-19 20-May-19 A1230 0% Approval of design
COEB.E&B Estimating and budgeting 137 21-May-19 27-Nov-19 27-Nov-19, COEB.E&B Estimating and budgeting
A1250 Preparing BoQ items for the Design 15 21-May-19 10-Jun-19 A1240 0% Preparing BoQ items for the Design
A1260 Preparing rates 15 21-May-19 10-Jun-19 A1240 0% Preparing rates
A1270 calculating Man Months 10 21-May-19 03-Jun-19 A1240 0% calculating Man Months
A1280 estimating material and machinery resources 30 21-May-19 01-Jul-19 A1240 0% estimating material and machinery resources
A1290 developing total budgeting 32 02-Jul-19 14-Aug-19 A1280 0% developing total budgeting
A1300 discussion with budgeting 10 15-Aug-19 28-Aug-19 A1290 0% discussion with budgeting
A1310 approval of budget 20 29-Aug-19 25-Sep-19 A1300 0% approval of budget
A1320 adding profits and market rate flucuation 15 26-Sep-19 16-Oct-19 A1310 0% adding profits and market rate flucuation
A1330 totaling the estimate 30 17-Oct-19 27-Nov-19 A1320 0% totaling the estimate
COEB.P&S planning and Scheduling 149 28-Nov-19 23-Jun-20 23-Jun-20, COEB.P&S planning and Scheduling
A1340 developing activity chart 15 28-Nov-19 18-Dec-19 A1330 0% developing activity chart
A1350 allocating teh resources 20 19-Dec-19 15-Jan-20 A1340 0% allocating teh resources
A1360 allocating timelines to the task 32 16-Jan-20 28-Feb-20 A1350 0% allocating timelines to the task
A1370 developing WBS 15 02-Mar-20 20-Mar-20 A1360 0% developing WBS
A1380 development of All activities 20 23-Mar-20 17-Apr-20 A1370 0% development of All activities
A1390 developing baseline for the project 15 20-Apr-20 08-May-20 A1380 0% developing baseline for the project
A1400 scheduling the project as per the deadline 10 11-May-20 22-May-20 A1390 0% scheduling the project as per the deadline
A1410 approval of baseline 8 25-May-20 03-Jun-20 A1400 0% approval of baseline
Actual Level of Effort Remaining Work Milestone Project Completed Date - 27 May 2022
Actual Work Critical Remaining Work summary
Actual Level of Effort Actual Work Remaining Work C...
Activity ID Activity Name Original Start Finish Predecessors Activity % Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration Complete
N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
A1420 finalizing the scheduling 4 04-Jun-20 09-Jun-20 A1410 0% finalizing the scheduling
A1430 finalizing the resources 10 10-Jun-20 23-Jun-20 A1420 0% finalizing the resources
COEB.A&C Approval and Commissioning 104 24-Jun-20 16-Nov-20 16-Nov-20, COEB.A&C Approval and Commissioning
A1440 detailed dicussion with Employer 12 24-Jun-20 09-Jul-20 A1430 0% detailed dicussion with Employer
A1450 breainstorming on detailed design 15 10-Jul-20 30-Jul-20 A1440 0% breainstorming on detailed design
A1460 Environment impact of the design 10 31-Jul-20 13-Aug-20 A1450 0% Environment impact of the design
A1470 development of sustainability plan 12 14-Aug-20 31-Aug-20 A1460 0% development of sustainability plan
A1480 project approval 20 01-Sep-20 28-Sep-20 A1470 0% project approval
A1490 commissioning of the project 10 29-Sep-20 12-Oct-20 A1480 0% commissioning of the project
A1500 allocating funds 25 13-Oct-20 16-Nov-20 A1490 0% allocating funds
COEB.LA Land acquisition Process 60 13-Oct-20 04-Jan-21 04-Jan-21, COEB.LA Land acquisition Process
A1510 demarcating the total land area 15 13-Oct-20 02-Nov-20 A1490 0% demarcating the total land area
A1520 takingover the land from state department 10 03-Nov-20 16-Nov-20 A1510 0% takingover the land from state department
A1530 encroaching the land 5 17-Nov-20 23-Nov-20 A1520 0% encroaching the land
A1540 development allied facilities for construction i.e. road and plane
30 areas
24-Nov-20 04-Jan-21 A1530 0% development allied facilities for construction i.e. road and plane areas
COEB.BP2 Bidding process for Contractor 30 24-Nov-20 04-Jan-21 04-Jan-21, COEB.BP2 Bidding process for Contractor
A1550 advertisment for the contractor 15 24-Nov-20 14-Dec-20 A1530 0% advertisment for the contractor
A1560 assessment of bids 10 15-Dec-20 28-Dec-20 A1550 0% assessment of bids
A1570 awarding of contract 5 29-Dec-20 04-Jan-21 A1560 0% awarding of contract
COEB.BoP Begining of Project Construction 52 05-Jan-21 17-Mar-21 17-Mar-21, COEB.BoP Begining of Project Construction
A1580 start of the project 2 05-Jan-21 06-Jan-21 A1570 0% start of the project
A1590 submitting security deposits 15 07-Jan-21 27-Jan-21 A1580 0% submitting security deposits
A1600 releasing mobilization advance 15 28-Jan-21 17-Feb-21 A1590 0% releasing mobilization advance
A1620 Mobilization of Contractor 20 18-Feb-21 17-Mar-21 A1600 0% Mobilization of Contractor
COEB.C&G Clearing and Grabbing 5 18-Mar-21 24-Mar-21 24-Mar-21, COEB.C&G Clearing and Grabbing
A1610 Site Clearing and Grabing 5 18-Mar-21 24-Mar-21 A1620 0% Site Clearing and Grabing
A1640 Making layout of the area 4 18-Mar-21 23-Mar-21 A1620 0% Making layout of the area
COEB.LP Layout Plan demarkcation 25 24-Mar-21 27-Apr-21 27-Apr-21, COEB.LP Layout Plan demarkcation
A1650 demarcaition of layout plan of Admn Block 10 24-Mar-21 06-Apr-21 A1640 0% demarcaition of layout plan of Admn Block
A1660 demarcation of open spaces 10 07-Apr-21 20-Apr-21 A1650 0% demarcation of open spaces
A1670 construction of temporary facility for contractor 5 21-Apr-21 27-Apr-21 A1660 0% construction of temporary facility for contractor
COEB.CoAdmnB Construction of Admn Block 143 28-Apr-21 12-Nov-21 12-Nov-21, COEB.CoAdmnB Construction of Admn
A1680 Layout of Admn Block 3 28-Apr-21 30-Apr-21 A1670 0% Layout of Admn Block
A1690 Excavation for Foundations 20 03-May-21 28-May-21 A1680 0% Excavation for Foundations
A1700 Lean concrete 2 31-May-21 01-Jun-21 A1690 0% Lean concrete
A1710 Reinforcement for beams and Columns 30 02-Jun-21 13-Jul-21 A1700 0% Reinforcement for beams and Columns
A1720 Concreting for Columns and Beams 10 14-Jul-21 27-Jul-21 A1710 0% Concreting for Columns and Beams
A1730 Formwork for Slab 10 28-Jul-21 10-Aug-21 A1720 0% Formwork for Slab
A1740 Concreting of Slab 10 11-Aug-21 24-Aug-21 A1730 0% Concreting of Slab
A1750 Columns for First Floor 10 25-Aug-21 07-Sep-21 A1740 0% Columns for First Floor
A1760 Concrete slab word for first floor 15 08-Sep-21 28-Sep-21 A1750 0% Concrete slab word for first floor
A1770 Flooring Works 10 29-Sep-21 12-Oct-21 A1760 0% Flooring Works
A1780 Electrical and plumbing works 10 13-Oct-21 26-Oct-21 A1770 0% Electrical and plumbing works
A1790 finihsing works 13 27-Oct-21 12-Nov-21 A1780 0% finihsing works
COEB.CoAB Construction of Academic Blocks 229 28-Apr-21 14-Mar-22 14-Mar-22, COEB.CoAB Construct
A1820 Layout of Academic Block 10 28-Apr-21 11-May-21 A1670 0% Layout of Academic Block
A1830 Excavation for Foundations 4 12-May-21 17-May-21 A1820 0% Excavation for Foundations
A1840 Lean concrete 13 18-May-21 03-Jun-21 A1830 0% Lean concrete
A1850 Reinforcement for beams and Columns 16 04-Jun-21 25-Jun-21 A1840 0% Reinforcement for beams and Columns
Actual Level of Effort Remaining Work Milestone Project Completed Date - 27 May 2022
Actual Work Critical Remaining Work summary
Actual Level of Effort Actual Work Remaining Work C...
Activity ID Activity Name Original Start Finish Predecessors Activity % Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration Complete
N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
A1860 Concreting for Columns and Beams 20 28-Jun-21 23-Jul-21 A1850 0% Concreting for Columns and Beams
A1870 Formwork for Slab 21 26-Jul-21 23-Aug-21 A1860 0% Formwork for Slab
A1880 Concreting of Slab 20 24-Aug-21 20-Sep-21 A1870 0% Concreting of Slab
A1890 Columns for First Floor 21 21-Sep-21 19-Oct-21 A1880 0% Columns for First Floor
A1900 Concrete slab word for first floor 34 20-Oct-21 06-Dec-21 A1890 0% Concrete slab word for first floor
A1910 Flooring Works 24 07-Dec-21 07-Jan-22 A1900 0% Flooring Works
A1920 Electrical and plumbing works 26 10-Jan-22 14-Feb-22 A1910 0% Electrical and plumbing works
A1930 finihsing works 20 15-Feb-22 14-Mar-22 A1920 0% finihsing works
COEB.CoL Construction of Library 251 28-Apr-21 13-Apr-22 13-Apr-22, COEB.CoL Constru
A1940 demarcation of library area 20 28-Apr-21 25-May-21 A1670 0% demarcation of library area
A1950 Excavation for Foundations 35 26-May-21 13-Jul-21 A1940 0% Excavation for Foundations
A1960 Lean concrete 36 14-Jul-21 01-Sep-21 A1950 0% Lean concrete
A1970 Reinforcement for beams and Columns 23 02-Sep-21 04-Oct-21 A1960 0% Reinforcement for beams and Columns
A1980 Concreting for Columns and Beams 20 05-Oct-21 01-Nov-21 A1970 0% Concreting for Columns and Beams
A1990 Formwork for Slab 20 02-Nov-21 29-Nov-21 A1980 0% Formwork for Slab
A2000 Concreting of Slab 25 30-Nov-21 03-Jan-22 A1990 0% Concreting of Slab
A2030 Flooring Works 25 04-Jan-22 07-Feb-22 A2000 0% Flooring Works
A2040 Electrical and plumbing works 24 08-Feb-22 11-Mar-22 A2030 0% Electrical and plumbing works
A2050 finihsing works 23 14-Mar-22 13-Apr-22 A2040 0% finihsing works
COEB.COH Construction of Hostel Buildings 283 28-Apr-21 27-May-22
A2060 Layout Plan 29 28-Apr-21 07-Jun-21 A1670 0% Layout Plan
A2070 Excavation for Foundations 28 08-Jun-21 15-Jul-21 A2060 0% Excavation for Foundations
A2080 Lean concrete 27 16-Jul-21 23-Aug-21 A2070 0% Lean concrete
A2090 Reinforcement for beams and Columns 26 24-Aug-21 28-Sep-21 A2080 0% Reinforcement for beams and Columns
A2100 Concreting for Columns and Beams 26 29-Sep-21 03-Nov-21 A2090 0% Concreting for Columns and Beams
A2110 Formwork for Slab 24 04-Nov-21 07-Dec-21 A2100 0% Formwork for Slab
A2120 Concreting of Slab 25 08-Dec-21 11-Jan-22 A2110 0% Concreting of Slab
A2130 Flooring Works 23 12-Jan-22 11-Feb-22 A2120 0% Flooring Works
A2140 Electrical and plumbing works 54 14-Feb-22 28-Apr-22 A2130 0% Electrical and plumbing work
A2150 finihsing works 21 29-Apr-22 27-May-22 A2140 0%
COEB.COH.CoD Construction of Dormatries 148 28-Apr-21 19-Nov-21 19-Nov-21, COEB.COH.CoD Construction of Dorma
A2160Layout Plan 23 28-Apr-21 28-May-21 A1670 0% Layout Plan
A2170Excavation for Foundations 12 31-May-21 15-Jun-21 A2160 0% Excavation for Foundations
A2180Lean concrete 5 16-Jun-21 22-Jun-21 A2170 0% Lean concrete
A2190Reinforcement for beams and Columns 13 23-Jun-21 09-Jul-21 A2180 0% Reinforcement for beams and Columns
A2200Concreting for Columns and Beams 15 12-Jul-21 30-Jul-21 A2190 0% Concreting for Columns and Beams
A2210Formwork for Slab 14 02-Aug-21 19-Aug-21 A2200 0% Formwork for Slab
A2220Concreting of Slab 5 20-Aug-21 26-Aug-21 A2210 0% Concreting of Slab
A2230Flooring Works 18 27-Aug-21 21-Sep-21 A2220 0% Flooring Works
A2240Electrical and plumbing works 19 22-Sep-21 18-Oct-21 A2230 0% Electrical and plumbing works
A2250finihsing works 24 19-Oct-21 19-Nov-21 A2240 0% finihsing works
COEB.COH.CoA Construction of Annexies 132 28-Apr-21 28-Oct-21 28-Oct-21, COEB.COH.CoA Construction of Annexies
A2260Layout Plan 10 28-Apr-21 11-May-21 A1670 0% Layout Plan
A2270Excavation for Foundations 10 12-May-21 25-May-21 A2260 0% Excavation for Foundations
A2280Lean concrete 5 26-May-21 01-Jun-21 A2270 0% Lean concrete
A2290Reinforcement for beams and Columns 15 02-Jun-21 22-Jun-21 A2280 0% Reinforcement for beams and Columns
A2300Concreting for Columns and Beams 10 23-Jun-21 06-Jul-21 A2290 0% Concreting for Columns and Beams
A2310Formwork for Slab 20 07-Jul-21 03-Aug-21 A2300 0% Formwork for Slab
A2320Concreting of Slab 2 04-Aug-21 05-Aug-21 A2310 0% Concreting of Slab
A2330Flooring Works 30 06-Aug-21 16-Sep-21 A2320 0% Flooring Works
Actual Level of Effort Remaining Work Milestone Project Completed Date - 27 May 2022
Actual Work Critical Remaining Work summary
Actual Level of Effort Actual Work Remaining Work C...
Activity ID Activity Name Original Start Finish Predecessors Activity % Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration Complete
N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M
A2340Electrical and plumbing works 10 17-Sep-21 30-Sep-21 A2330 0% Electrical and plumbing works
A2350finihsing works 20 01-Oct-21 28-Oct-21 A2340 0% finihsing works
COEB.LS Landscapping of the open spaces 96 22-Nov-21 04-Apr-22 04-Apr-22, COEB.LS Landscap
A2360 Creating Area of Spaces 10 22-Nov-21 03-Dec-21 A2250 0% Creating Area of Spaces
A2370 development Open Spaces 6 06-Dec-21 13-Dec-21 A2360 0% development Open Spaces
A2380 Development of Patios 10 14-Dec-21 27-Dec-21 A2370 0% Development of Patios
A2390 Development of Internal GArdening 20 28-Dec-21 24-Jan-22 A2380 0% Development of Internal GArdening
A2400 Development of Open Sitting Spaces 10 25-Jan-22 07-Feb-22 A2390 0% Development of Open Sitting Spaces
A2410 Open Area Theater 10 08-Feb-22 21-Feb-22 A2400 0% Open Area Theater
A2420 Finishing Works of Open Theater 10 22-Feb-22 07-Mar-22 A2410 0% Finishing Works of Open Theater
A2430 floor work of Landscape 20 08-Mar-22 04-Apr-22 A2420 0% floor work of Landscape
COEB.CoPA Construction of Playing Area and 55 28-Apr-21
gounds 13-Jul-21 13-Jul-21, COEB.CoPA Construction of Playing Area and gounds
A2440 Layout Plan 10 28-Apr-21 11-May-21 A1670 0% Layout Plan
A2450 Demarcation of Lines 10 12-May-21 25-May-21 A2440 0% Demarcation of Lines
A2460 Flooring Works 10 26-May-21 08-Jun-21 A2450 0% Flooring Works
A2470 Allied Works related to Sport 25 09-Jun-21 13-Jul-21 A2460 0% Allied Works related to Sport
COEB.CoP&AF Construction of Parking 78 28-Apr-21
and Allied Facilities 13-Aug-21 13-Aug-21, COEB.CoP&AF Construction of Parking and Allied Fa
A2480 Floowing of Parking Area 10 28-Apr-21 11-May-21 A1670 0% Floowing of Parking Area
A2490 Flooring of Bus Terminal 15 12-May-21 01-Jun-21 A2480 0% Flooring of Bus Terminal
A2500 Demarcation of Lines 10 02-Jun-21 15-Jun-21 A2490 0% Demarcation of Lines
A2510 Bycyle Area 15 16-Jun-21 06-Jul-21 A2500 0% Bycyle Area
A2520 Open Space 13 07-Jul-21 23-Jul-21 A2510 0% Open Space
A2530 RestArea 15 26-Jul-21 13-Aug-21 A2520 0% RestArea
COEB.FW Finishing Works 50 09-Jun-21 17-Aug-21 17-Aug-21, COEB.FW Finishing Works
A2540 Outdoor facade Works 20 09-Jun-21 06-Jul-21 A2460 0% Outdoor facade Works
A2550 outdoor Paintjob 10 07-Jul-21 20-Jul-21 A2540 0% outdoor Paintjob
A2560 Development of Green Walls 20 21-Jul-21 17-Aug-21 A2550 0% Development of Green Walls
COEB.IW Final Inspection 21 18-Aug-21 15-Sep-21 15-Sep-21, COEB.IW Final Inspection
A2570 Final Inspection by Employer 5 18-Aug-21 24-Aug-21 A2560 0% Final Inspection by Employer
A2580 Approval by State department 10 25-Aug-21 07-Sep-21 A2570 0% Approval by State department
A2590 Approval by Educational Secratery 6 08-Sep-21 15-Sep-21 A2580 0% Approval by Educational Secratery
COEB.EoP End of Project 3 16-Sep-21 20-Sep-21 20-Sep-21, COEB.EoP End of Project
A2600 Inaguaration 3 16-Sep-21 20-Sep-21 A2590 0% Inaguaration
A2610 Closing of Project 0 20-Sep-21 0% Closing of Project,
Actual Level of Effort Remaining Work Milestone Project Completed Date - 27 May 2022
Actual Work Critical Remaining Work summary