JOBSITE IBP

ENGINEERING DEPT
PERIOD : September 2021
TANGGAL : 09 September 2021
LOADER : EXCAVATOR HYUNDAI 480
HAULER : DT QWESTER dan DT TATA

NO. DATE TIME LOADER HAULER C/N

1 9-Apr-21 9:00 EXCT HYUNDAI 03 DT-QUESTER 280


2 9-Apr-21 9:00 EXCT HYUNDAI 03 DT-QUESTER 280
3 9-Apr-21 9:00 EXCT HYUNDAI 03 DT-QUESTER 280
Average

JOBSITE IBP
ENGINEERING DEPT
PERIOD : September 2021
TANGGAL : 09 September 2021
LOADER : EXCAVATOR HYUNDAI 480
HAULER : DT QWESTER dan DT TATA

NO. DATE TIME LOADER HAULER C/N

1 8-Sep-21 15:00 EXCT HYUNDAI 03 DT-TATA


2 8-Sep-21 15:00 EXCT HYUNDAI 03 DT-TATA
3 8-Sep-21 15:00 EXCT HYUNDAI 03 DT-TATA
Average

JOBSITE IBP
ENGINEERING DEPT
PERIOD : September 2021
TANGGAL : November 2021
LOADER : EXCAVATOR HYUNDAI 480
HAULER : DT TATA

NO. DATE TIME LOADER HAULER C/N

1 25-Nov-21 10:00 EXCT HYUNDAI 480 DT-TATA


2 25-Nov-21 11:00 EXCT HYUNDAI 480 DT-TATA
3 25-Nov-21 12:00 EXCT HYUNDAI 480 DT-TATA
4 25-Nov-21 13:00 EXCT HYUNDAI 480 DT-TATA
5 25-Nov-21 14:00 EXCT HYUNDAI 480 DT-TATA
Average
DOCUMENT CONTROL SAMPLING DUMP TRUCK OB

Truck
SURVEY Deviation
To LOCATION FROM LOCATION Factor
LCM BCM BCM BCM
OPD PIT 5 PIT 5 12.749 10.199 9.60 0.60
OPD PIT 5 PIT 5 13.252 10.602 9.60 1.00
OPD PIT 5 PIT 5 13.500 10.800 9.60 1.20
ge 13.17 10.534 9.60 0.93

DOCUMENT CONTROL SAMPLING DUMP TRUCK OB

Truck
SURVEY Deviation
To LOCATION FROM LOCATION Factor
LCM BCM BCM BCM
OPD SSDK PIT AMJ 13.939 11.151 9.60 1.55
OPD SSDK PIT AMJ 15.393 12.314 9.60 2.71
OPD SSDK PIT AMJ 13.771 11.017 9.60 1.42
ge 14.37 11.494 9.60 1.89

DOCUMENT CONTROL SAMPLING DUMP TRUCK OB

SURVEY Truck Deviation


To LOCATION FROM LOCATION Factor
LCM BCM BCM BCM
OPD ATS PIT YULI 10.428 8.342 9.60 (1.26)
OPD ATS PIT YULI 12.76 10.208 9.60 0.61
OPD ATS PIT YULI 13.029 10.423 9.60 0.82
OPD ATS PIT YULI 10.651 8.521 9.60 (1.08)
OPD ATS PIT YULI 10.127 8.102 9.60 (1.50)
ge 11.40 9.119 9.60 -0.48
Type of Material Remarks %

Clay UP 6%
Clay UP 10%
Clay UP 13%
10%

Type of Material Remarks %

Clay UP 16%
Clay UP 28%
Clay UP 15%
20%

Type of Material Remarks %

SOIL DOWN -13%


SOIL UP 6%
SOIL UP 9%
SOIL DOWN -11%
SOIL DOWN -16%
-5%
JOBSITE IBP
ENGINEERING DEPT
PERIOD : January 2022
TANGGAL : 21 January 2022
LOADER : EXCAVATOR DOSSAN 520
HAULER : DT MERSI

NO. DATE TIME LOADER HAULER C/N

1 21-Jan-22 9:00 EXCT DOSSAN 520 DT-MERSI


2 21-Jan-22 10:30 EXCT DOSSAN 520 DT-MERSI
3 21-Jan-22 11:10 EXCT DOSSAN 520 DT-MERSI
4 21-Jan-22 12:00 EXCT DOSSAN 520 DT-MERSI
5 21-Jan-22 12:15 EXCT DOSSAN 520 DT-MERSI
Average
DOCUMENT CONTROL SAMPLING DUMP TRUCK OB

Truck Deviation
SURVEY
To LOCATION FROM LOCATION Factor
LCM BCM BCM BCM
OPD EEM PIT EEM 13.978 11.182 9.60 1.58
OPD EEM PIT EEM 14.413 11.530 9.60 1.93
OPD EEM PIT EEM 13.218 10.574 9.60 0.97
OPD EEM PIT EEM 11.439 9.151 9.60 (0.45)
OPD EEM PIT EEM 15.011 12.009 9.60 2.41
ge 13.61 10.889 9.60 1.29
Type of Material Remarks %

CLAY UP 16%
CLAY UP 20%
CLAY UP 10%
CLAY DOWN -5%
CLAY UP 25%
13%
JOBSITE IBP
ENGINEERING DEPT
PERIOD : February 2022
TANGGAL : February 2022
LOADER : EXCAVATOR DOSSAN 520
HAULER : DT MERSI

NO. DATE TIME LOADER HAULER C/N

1 25-Feb-22 9:00 EXCT DOSSAN 520 DT-MERSI


2 25-Feb-22 10:30 EXCT DOSSAN 520 DT-MERSI
3 25-Feb-22 11:10 EXCT DOSSAN 520 DT-MERSI
4 25-Feb-22 12:00 EXCT DOSSAN 520 DT-MERSI
5 25-Feb-22 12:15 EXCT DOSSAN 520 DT-MERSI
6 25-Feb-22 12:25 EXCT DOSSAN 520 DT-MERSI
Average

JOBSITE IBP
ENGINEERING DEPT
PERIOD : February 2022
TANGGAL : February 2022
LOADER : EXCAVATOR DOSSAN 520
HAULER : DT MERSI

NO. DATE TIME LOADER HAULER C/N

1 26-Feb-22 14:00 AM EXCT DOSSAN 520 DT-MERSI


2 26-Feb-22 14:30AM EXCT DOSSAN 520 DT-MERSI
3 26-Feb-22 15:10: AM EXCT DOSSAN 520 DT-MERSI
4 26-Feb-22 15:30 PM EXCT DOSSAN 520 DT-MERSI
5 26-Feb-22 16:10 PM EXCT DOSSAN 520 DT-MERSI
Average
DOCUMENT CONTROL SAMPLING DUMP TRUCK OB

Truck Deviation
SURVEY
To LOCATION FROM LOCATION Factor
LCM BCM BCM BCM
OPD EEM PIT EEM 9.18 7.341 9.60 (2.26)
OPD EEM PIT EEM 9.18 7.341 9.60 (2.26)
OPD EEM PIT EEM 10.534 8.427 9.60 (1.17)
OPD EEM PIT EEM 10.29 8.232 9.60 (1.37)
OPD EEM PIT EEM 9.301 7.441 9.60 (2.16)
OPD EEM PIT EEM 8.916 7.133 9.60 (2.47)
ge 57.39 7.65 9.60 -1.84

DOCUMENT CONTROL SAMPLING DUMP TRUCK OB

Truck
SURVEY Deviation
To LOCATION FROM LOCATION Factor
LCM BCM BCM BCM
OPD EEM PIT EEM 12.23 9.787 9.60 0.19
OPD EEM PIT EEM 12.25 9.798 9.60 0.20
OPD EEM PIT EEM 9.666 7.733 9.60 (1.87)
OPD EEM PIT EEM 11.794 9.435 9.60 (0.16)
OPD EEM PIT EEM 13.113 10.490 9.60 0.89
ge 59.06 9.45 9.60 -0.15
Type of Material Remarks %

top soil DOWN -24%


top soil DOWN -24%
top soil DOWN -12%
top soil DOWN -14%
top soil DOWN -22%
top soil DOWN -26%
-19%

Type of Material Remarks %

clay DOWN 2%
clay DOWN 2%
clay DOWN -19%
clay DOWN -2%
clay UP 9%
-2%