Project name Actual work done % Completion Remedial Actions
Adsorption tanks On hold. 65% To commence after commissioning of leach tanks. Commissioned 98% Bundwall construction starting when contractor issue has been finalised. Leach tanks CV 8 Extension On hold. 12% on Hold. Generator Farm On hold. 60% on Hold.