Professional Documents
Culture Documents
Pipeline Welding02776E03
Pipeline Welding02776E03
02776.ENG.MME.STD
Rev.03 - December 2016
GENERAL NOTE This Re-coding does not affect the document content.
TO THE Documents traceability is guaranteed by the unchanged document
DOCUMENT RE-
number.
CODING
Any cross-reference between documents remains unaffected.
/
La presente ricodifica non ha effetto sul contenuto del documento.
NOTA
GENERALE
La rintracciabilità dei documenti è garantita dal numero di documento
ALLA che resta immodificato.
RICODIFICA I riferimenti incrociati fra i vari documenti rimangono validi.
REVISION TRACKING
Rev 00
Date: 06/1986
Rev. 01
Actual revision is of 58 pages.
Date: 04/1991
Rev. 02
Actual revision is of 24 pages.
General revision - Written as Addendum to ISO 13847 –Petroleum and natural gas
industries- Pipeline transportation systems Welding of pipelines- risers & spools.
Change code from MEC to COR. Change code from SPC to SDS
Date: 06/2013
Rev. 03
Actual revision is of 80 pages.
General revision - Reviewed and updated to the latest revision of International Standard
ISO 13847:2013 “Petroleum and natural gas industries – Pipeline transportation
systems – Welding of pipelines”.
Date: 12/2016
INFORMATION REQUEST
Eni personnel can access company standard repository at:
http://wwweandp.eni.it/TSServices/ITEM/Standards-/Normalizat/Documents-/index.asp
External user shall refer to the Project Engineer Manager.
For information about the content of this standard, please refer to responsible and
accountable person as per above RACIE table or to Technical Authority coordinator
(COETA).
HIERARCHY OF REGULATIONS
INDEX
1. SCOPE
This Specification covers the technical requirements for welding and inspection of girth,
branch and fillet welds for onshore pipelines, and is based on International Standard
ISO 13847:2013 Petroleum and natural gas industries – Pipeline transportation systems
– Welding of pipelines.
This specification is applicable for welding of carbon steel line pipes with Specified
Minimum Yield Strength of 485 MPa (grade X70) or less, with diameter of 20 mm and
larger and wall thickness 3 mm or more. It is also applicable to welding into pipelines of
items such as spools, riser, launchers/receivers, fittings (elbows, tees, barred tees,
sweepolets, weldolets, and others), flanges, pup pieces to pipeline and pup pieces to
valve bodies.
The welding processes covered are shielded metal arc welding (SMAW), gas tungsten
arc welding (GTAW), gas metal arc welding (GMAW), gas-shielded flux-cored arc
welding (G-FCAW) and submerged arc welding (SAW). G-FCAW shall not be used for
root pass. The COMPANY shall previously authorize other welding processes.
For sour service, all requirements specified by ISO standard 15156 1-2 (NACE MR 0175)
shall be applied in combination with the additional requirements of this specification.
This specification is applicable for ppH2S ≤ 1MPa.
Additional requirements for sour service with ppH2S > 1MPa, shall be addressed in a
dedicated project specification.
2. GUIDANCE TO USE
Part I gives information about the general data and approach used for development of
the specification.
The clauses in PART II have been marked with the following abbreviations:
- AP: Denotes that an Additional Paragraph has been enclosed in ISO 13847.
- AR: Denotes that Additional Requirements have been addressed in an existing
paragraph of ISO 13847.
- PM: Denotes a Partial Modification to the requirements stated to an existing
paragraph of ISO 13847.
- TR: Denotes a Total Replacement of an existing paragraph of ISO 13847.
3. REFERENCES
The reference documents (i.e. COMPANY specifications, standards and codes) listed in
Part II form an integral part of this specification.
In case of conflict between the requirements stated in this specification and others
specified in the applicable standards, the most stringent requirements shall be applied.
Additional requirements not covered in this specification may be agreed between the
CONTRACTOR and the COMPANY. Should omissions, ambiguity, or incorrect information
exist, they shall be notified as soon as possible by the CONTRACTOR to the COMPANY,
and the COMPANY shall have the right of final decision.
All written responses to the CONTRACTOR from the COMPANY shall be binding.
AR1 SCOPE
BS EN ISO 15653 Fracture Mechanics Toughness Tests Part 2. Method for Determination of
KIc Critical CTOD and Critical J Values of Welds in Metallic Materials.
BS 7910 Guide on Methods for Assessing the Acceptability of Flaws in Fusion welded
metallic structures.
ISO 636 Welding consumables-Rods, wires and deposits for tungsten inert gas
welding of non-alloy and fine grain steels – Classification.
EN 1011-1 Welding - Recommendations for welding of metallic materials. General
guidance for arc welding.
ISO 2400 Non-destructive testing - Ultrasonic testing - Specification for calibration
block No. 1.
ISO 2560 Welding consumables-Covered electrodes for manual metal arc welding of
non-alloy and fine grain steels-Classification.
ISO 3452-1 Non-destructive testing - Penetrant testing - Part 1: General principles.
ISO 3452-3 Non-destructive testing - Penetrant testing - Part 3: Reference test blocks.
ISO 4063 Welding and allied processes - Nomenclature of processes and reference
numbers.
ISO 5580 Non-destructive testing - Industrial radiographic illuminators - Minimum
requirements.
ISO 6848 Arc welding and cutting - Non-consumable tungsten electrodes
classification.
ISO 7963 Non-destructive testing - Ultrasonic testing - Specification for calibration
block No. 2.
ISO 9606 – 1 Qualification testing of welder - Fusion welding - Part 1: steels.
ISO 11699-1 Non-destructive testing - Industrial radiographic film - Part 1: Classification
of film systems for industrial radiography.
ISO 16699-2 Non-destructive testing - Industrial radiographic films - Part 2: Control of
film processing by means of reference values.
ISO 14171 Welding consumables-Solid wire electrodes, tubular cored electrodes and
electrode/flux combinations for submerged arc welding of non-alloy and
fine grain steels. Classification.
ISO 14341 Welding consumables. Wire electrodes and deposits for gas shielded metal
arc welding of non-alloy and fine grain steels. Classification.
ISO 14344 Welding consumables - Procurement of filler materials and fluxes.
ISO 14731 Welding coordination - Tasks and responsibilities.
ISO 15607 Specification and qualification of welding procedures for metallic materials
- General rules.
ISO 15156 Petroleum and natural gas industries - Materials for use in H2S-containing -
environments in oil and gas production – (part 1 and part 2).
ISO 16811-2 Non-destructive testing - Ultrasonic examination - Part 2: Sensitivity and
range setting.
ISO/IEC 17025 General requirements for the competence of testing and calibration
laboratories.
ISO 17065 Conformity assessment — Requirements for bodies certifying products,
processes and services.
ISO 17632 Welding consumables. Tubular cored electrodes for gas shielded and
non-gas shielded metal arc welding of non-alloy and fine grain steels.
Classification.
ISO 17637 Non-destructive testing of welds - Visual testing of fusion-welded joints.
ISO 17638 Non-destructive testing of welds - Magnetic particle testing.
ISO 17639 Destructive test of weld in metallic materials - Macroscopic and
Microscopic examination of welds.
ISO 17640 Non-destructive testing of welds - Ultrasonic testing - Techniques,
testing levels, and assessment.
ASTM G1 Standard Practice for Preparing, Cleaning, and Evaluating Corrosion
Test Specimens.
ASME II Part C Specifications for Welding Rods, Electrodes, and Filler Metals.
MSS SP-44 Steel Pipeline Flanges.
MSS SP-75 High-Test, Wrought, Butt-Welding Fittings.
MSS SP-97 Integrally Reinforced Forged Branch Outlet Fittings – Socket Welding,
Threaded, and Butt Welding Ends.
CEN/TR 14748 Non-destructive testing - Methodology for qualification of non-
destructive tests.
EFC-Publication-n°16 Guidelines on material requirements for carbon and low alloy steels for
H2S containing environments in oil and gas production.
NACE TM-01-77 Laboratory Testing of Metals for Resistance to Sulfide Stress Cracking
and Stress Corrosion Cracking in H2S Environments.
DNV-OS-F101 Submarine Pipeline Systems
DNV-RP-F118 Pipe girth weld AUT system qualification and project specific procedure
validation.
API 1104 Welding of Pipelines and Related Facilities.
PM 3.7 company
COMPANY is Eni S.p.A. and its direct and indirect subsidiaries, branch or affiliate in Italy
and abroad
PM 3.8 contractor
CONTRACTOR is the organization and all its subcontractors appointed by COMPANY to
perform welding and inspection activities covered by this specification
AP 3.29 branch
an integrally reinforced fitting welded to a run pipe by a butt-joint with full penetration
or branch connection with full penetration, and connected to a branch pipe by welding,
threaded or flanged joint; includes a branch outlet fitting conforming to MSS SP-97
AP 3.30 by agreement
agreed between the COMPANY and the CONTRACTOR
AP 3.39 subcontractor
SUBCONTRACTOR is the organization appointed by the CONTRACTOR to perform
welding and inspection activities covered by this specification
AR 4.1 Symbols
ppH2S partial pressure of H2S
k thermal efficiency factor
TR 5 COMPLIANCE
CONTRACTOR shall be certified according to the quality requirements of ISO 3834-2 (or
equivalent, if agreed with COMPANY).
The CONTRACTOR is responsible for complying with all of the applicable requirements of
this specification. It is permissible for the COMPANY to make any investigation
necessary in order to ensure the compliance by the CONTRACTOR and to reject any
material that does not comply.
The following table outlines COMPANY’s general requirements and options to be agreed
before the contract’s award as per ISO 13847:2013, sect. 6.
5) permission to transfer WPS between contractors It is not allowed to transfer WPS between
(see 7.6.2) CONTRACTORS. See also par. AR 7.6.2.
6) additional destructive testing of test welds (see In case of sour service, additional hardness testing
8.6.2) is required for welders and welding operators
qualification to be executed in accordance with par.
PM 7.4.3.7.
7) testing of filler material with lot classification and Additional requirements in accordance with clause
extent of testing (see 9.10) AP 7.3.6 and AR 9.10.
8) frequency, extent and method(s) of NDT if To be executed in accordance with par TR 10.1.
different from ISO 13623:2009 (see 10.1)
9) use of mechanized UT equipment (see 10.6.5) Requirements provided in the Annex G.
10) use of ECA (see 11.8) Acceptance criteria shall not be based on ECA (see
TR 11.8).
11) weld repair from inside of the pipe (see 12.2) Not permitted (see TR 12.2).
12) permission for repair-on-repair welding (see Permitted only if approved by COMPANY in non-
12.3) sour service. Not permitted in case of sour service.
13) tests to demonstrate adequate corrosion ISO 13847:2013 Annex A is not applicable.
resistance of the weld in service (see Clause A.2)
14) additional safety measures for in-service ISO 13847:2013 Annex D is not applicable.
welding based on service fluid (see Clause D.1)
15) deletion of transverse notches for detection of See Annex TR G.4.1.
transverse defects (see G.4.1)
16) additional qualification when applying See Annex TR G.4.2.
workmanship criteria (see G.4.2)
17) other NDT method for comparison of AUT See Annex TR G.4.2.
indications (see G.4.2)
18) applicability of Annex E (see Clause E.1) ISO 13847:2013 Annex E is not applicable.
19) supplementary applicable national standards or ISO 13847:2013 Annex E is not applicable.
codes (see Clause E.1)
20) proportion of different NDE techniques (see ISO 13847:2013 Annex E is not applicable.
Table E.1, footnote a)
21) number of welds to be additionally examined ISO 13847:2013 Annex E is not applicable.
when one weld is rejected (see E.3.1)
TR 7.1 General
The WPS shall be specified in accordance with par. TR 7.2, signed and approved by
CONTRACTOR’s Welding Engineer before the issue to COMPANY for approval.
To qualify a WPS the test pieces shall be welded, inspected and tested in accordance
with ISO 15614-1, and with the additional requirement of par. 7.3 and AR 7.4 of this
specification.
The welding and testing for WPS qualification shall be witnessed by an international
recognized Third Party approved by the COMPANY. The same Third Party shall certify all
WPQRs.
All welding procedures shall be qualified using the material designed for the project and
supplied in accordance with the project material specifications.
PWHT shall be applied only with COMPANY approval. In case the PWHT is approved,
base and filler materials shall be provided with material properties guaranteed in the
“simulated“ PWHT condition.
In case of PWHT is required, each welding procedure shall be qualified in the following
simulated PWHT conditions:
Prior to start with welding of test pieces for qualification, at least 30 days before, the
CONTRACTOR shall submit to COMPANY the following documents for approval:
Before starting the welding procedure qualification, CONTRACTOR shall have all pWPSs
approved by COMPANY with the statement “Approved for qualification”.
NDT procedures shall be reviewed and endorsed by a Level III NDT as per ISO 9712.
The Level III qualification certificate shall be included in the documentation submitted.
All activities related to welding and testing for qualification shall be coordinated by the
CONTRACTOR’s welding coordinator or other internal inspector or qualified
representative.
CONTRACTOR shall give to the COMPANY, at least 30 days in advance, notice of all
welding procedure qualification testing, welder qualification testing, and laboratory
testing.
COMPANY, or its representative, shall have the right to witness all of the following:
After satisfactory completion of the WPQT, a final WPS shall be produced. This shall be
based on the pWPS, which shall be modified to reflect any changes that were recorded
during the qualification tests and reported in the WPQR.
Prior to the start of production welding, the reference WPSs and supporting WPQRs shall
be submitted to the COMPANY for approval.
Review and approval of the welding procedures by the COMPANY does not relieve the
CONTRACTOR of the responsibility to produce satisfactory welds.
All relevant COMPANY approved WPSs shall be displayed at each work locations and
shall be readily available to each welder in English and in the welders’ working language
if different from English as considered appropriate.
WPSs for repair welding shall include the following information, in addition to the
requirements applicable for a WPS for production welding:
A procedure for welding parameters recording and heat input calculation shall be issued
for COMPANY approval and shall be applied during both qualification and production.
- Welding Voltage;
- Welding Current;
- Welding speed;
- Heat Input.
During production, such system is required only for mechanized welding and automatic
welding.
The average value per pass of each welding parameter (voltage, current and welding
speed) shall be calculated considering the reference recorded data along the entire
length of the test piece.
In case of pulsed arc, the RMS value shall be the reference value for heat input
calculation. The reference electrical parameter (i.e. peak current, base current, duty
cycle, etc.) shall be recorded in the WPQR and reported in the WPS.
All average values shall be written in the certificate and used to calculate the heat input
per each pass as per the following formula:
V ⋅I
HI = k ⋅ ⋅ 10 −3
6 ⋅ vs
where:
HI is the heat input (KJ/mm);
k is the thermal efficiency factor (according to EN1011-1);
V is the average welding voltage per pass (V);
I is the average welding current per pass (A);
vs is the average welding speed per pass (cm/min).
A different approach for the Heat Input evaluation during WPQT and relevant qualified
range calculation shall be approved by COMPANY.
For mechanized and semi-automatic welding, all equipment, welding machine and tools
used during WPQT shall be of the same manufacturers and model to be applied during
production.
The minimum length of test rings for the WPQT tests of fittings and flanges shall be
agreed with COMPANY.
When an internal line-up clamp will be used in production welding, the length of the test
piece used in the WPQT shall be sufficient to accommodate the full length of the clamp.
Welding procedure for Sweepolets shall be qualified by branch type test piece
representative for the Sweepolet to run pipe joints to be realized in production. An
additional butt-weld test pieces shall be prepared to cover the weld between the
Sweepolet and the run pipe and to cover the weld between the Sweepolet and the
branch pipe.
Welding procedure for Weldolets shall be qualified by branch type test piece
representative for the Weldolet to run pipe joints to be realized in production. An
additional butt-weld test pieces shall be prepared to cover the weld between the
Weldolet and the run pipe and to cover the weld between the Sweepolet and the branch
pipe.
EXAMPLE: A weld between thermal mechanically controlled pipe and a quenched and
tempered forged flange shall be subject to mechanical testing on both sides of the weld.
Each heat and lot, or so-called batch herein as per classification according to ISO
14344, shall meet the following:
- Covered electrodes: class C4;
- Bare solid electrodes and rods: class S3;
- Flux cored electrodes and metal cored electrodes and rods: class T3;
- Fluxes for submerged arc welding: class F2.
Covered electrodes and filler wires shall produce weld metal with a tensile test strength
at least equal to the specified minimum tensile strength of the pipe metal. In case of
joints between dissimilar materials, the tensile strength of the weld metal shall not be
less than the highest specified minimum tensile strength of the two base metals.
In case of Sour Service, the Nickel (Ni) content shall not exceed 1.0% in weight for all
consumables.
For sour service, preheating by gas means shall be used only if electrical means
application is not practicable and after COMPANY approval.
Special care shall be apply in order to prevent any damage to the coating.
The specified temperature shall extend around the entire circumference of the pipe or
the part being joined over a length of at least 75 mm on each side of the joint.
The preheating temperature shall be reached before starting the first weld pass (root),
and recorded by contact thermocouples to be fixed at 6 o’clock position of the test piece
(one thermocouple for each side).
Preheating technique applied for the welding test (WPQT) shall be the same utilized in
production.
Each test piece for qualification shall be locally heat treated according to the same
PWHT procedure (insulating systems, heating equipment, temperature registration etc.)
applied on production welds.
Before interruption the weld metal deposit shall be within 1/3 and 2/3 of the parent
metal wall thickness. In any case welding shall not be interrupted before the completion
of the root and hot passes.
Welds of pipe to fitting, fillet, branches and repairs shall not be interrupted; the
preheating temperature shall be maintained until completion of the weld.
For manual welding, in case of sour service, root pass shall be performed by GTAW
process only. Other welding process can be used only if approved by COMPANY.
Permanent and temporary backing (eg. copper shoes, ceramic shoes) are not permitted.
For manual welding, basic coated low hydrogen electrodes shall be used.
Table 1 – Inspection and testing of the test pieces for girth welding
a) Manual UT (in addition to RT) only for mechanized or automatic welding processes.
b) Automatic UT shall be subject to approval, qualification and validation of the inspection
procedure by COMPANY. AUT inspection shall be in accordance with Annex G of this
specification.
c) Test not required for pipe with t ≤ 6 mm.
d) For t < 12 mm, the total number of bends tests shall be split evenly between root and
face bends. For t ≥ 12 mm, side bend tests are required.
e) SSC test requirements as per AP Annex L of this specification only in case of Sour
Service.
Test welds for the approval of a WPS shall be subjected to NDT no sooner than 24 hours
after completion of welding.
The NDT shall be reported in accordance with par. TR 10 of this specification and the
results shall meet the acceptance criteria in par. TR 11.
Test specimens shall be taken from test pieces, which have met the acceptance criteria
for NDT.
Test pieces that fail to meet these criteria shall be disregarded for destructive testing for
WPS approval.
Test specimens may be taken from locations free of acceptable imperfections revealed
by NDT.
To avoid weld imperfections in the test specimen, the location of test specimen may be
rotated by not more than 15 degrees provided the longitudinal seam is avoided (except
in case of specific requirements).
1
6 1
5
3
Figure 1 - Location of test specimens for impact, tensile and bend test
Figure 2 - Location of test specimens for macro, micro and hardness tests
If more than one test piece is required for qualification, each test piece shall be welded
according to the same pWPS to be qualified and using the same base material and the
same welder/s.
For pipes with outside diameter greater than 50 mm, the weld reinforcement shall be
removed on both faces of the specimen. Removal of the reinforcement is not required
for specimens from pipe with an outside diameter of 50 mm or less.
Specimens shall fail in the pipe material, outside the weld metal or FL/HAZ, at the
specified minimum tensile strength of pipe material (base metal) or higher.
When different material grades are joined, the ultimate tensile strength of the joint shall
be at least equal to the specified minimum tensile strength for the lower grade.
Failure of specimens outside the weld or fusion zone at less than 100% of the specified
minimum tensile strength may be an indication of a base material deficiency, and 2
(two) additional specimens shall be cut from the same test joint for tensile testing.
If any of the additional specimens break outside the weld metal or FL/HAZ, below the
tensile strength stated, the pipe shall be considered suspect, and its physical properties
investigated and confirmed to meet specified values before continuing with test welding
for WPS approval.
Failure of specimens at less than 100% of the specified minimum tensile strength shall
be reported to the COMPANY.
Full-size Charpy specimens shall be utilized where pipe wall thickness permits.
For weld metal tests, the specimen notch shall be at the weld centreline.
For HAZ tests the notch shall be placed at a location that results in a test containing 1/3
weld metal and 2/3 base material.
For fusion line +2 mm test, the specimen shall be placed at the same location of the
HAZ test specimen shifted 2 mm to the side of the base material.
Specimen dimensions and test procedure shall be in accordance with ISO 148-1.
The test temperature shall not exceed the test temperature specified for the base
materials.
In case of test piece welded between different base materials, CVN specimens shall be
taken on both sides.
The test temperature shall not be higher than the impact test temperature specified for
pipe material.
For welds in pipe with a wall thickness of 25 mm or less, the average and single Charpy
V-notch toughness at each position shall not be less than that specified for the base
material in the transverse direction (KVT values) and ISO 13847, whichever is more
stringent.
The above impact energy value requirements may be reduced pro rata for sub-size
specimens in accordance with the following formula:
Where:
Charpy-V energy values and test temperatures for wall thicknesses greater than 25 mm
shall be agreed between COMPANY and CONTRACTOR.
Notch location: FL + 2 mm
Notch location: FL + 2 mm
Notch location: FL + 2 mm
The specimens shall be free from cracks and lack of fusion. Any other imperfections
shall be within the limits specified in par. 11.
Photographic documentation showing the entire sample with the hardness survey indent
locations shall be included in the WPQR.
Micro-examination (at 200x and 500x) shall be performed and documented in the root
area of the test piece, and shall include a detailed micro-structural examination of weld
metal, fusion line and heat affected zones (for information only).
Hardness shall be measured and recorded in rows across the weld metal, the HAZ and
the parent metal as indicated:
For the HAZ, the first indentation shall be made as close as possible to the fusion line.
The results from all hardness testing required in the specification shall meet the
requirements specify in the following Table 2:
Non-sour service, all welding 275 N/A 275 325 N/A 325
processes, all thickness
Average hardness value shall be calculated considering only the readings performed on
the same row within the same weld region (WM, HAZ left side and HAZ right side).
Hardness test on parent metal is for information only.
In case of non sour service, if there are single hardness values in the different test
zones (weld metal, HAZ) that do not meet the requirements of Table 2, re-testing shall
be carried out on the reverse side of the tested specimen or after grinding and re-
preparation of the tested surface. None of these additional hardness values shall exceed
the maximum value of Table 2.
The measured yield strength shall be greater than or equal to the SMYS of the parent
pipe metal and shall not exceed the SMYS of the parent pipe metal plus 100 MPa.
The measured ultimate tensile strength shall be recorded for information only.
For thicknesses ≥ 12mm four side bend specimens are required instead of root and face
bend tests.
The diameter of the former shall be 4ts and the bending angle shall be 180° for parent
metal with elongation A ≥ 20%. For parent metal with elongation A < 20% the following
formula shall be applied:
(100 × ts )
d= − ts
A
where:
d is the diameter of the former;
ts is the thickness of the bend test specimen;
A is the minimum tensile elongation required by the material specification.
The bend test shall be considered acceptable if no crack or other imperfection exceeding
3 mm, in any direction, is present in the weld or between the weld and the fusion zone
after bending.
Cracks that originate on the outer radius of the bend along the edges of the specimen
during testing and that are less than 6 mm, measured in any direction, shall not be
considered unless welding imperfections are observed.
Each specimen subjected to the bend test shall meet the above requirements.
Table A.1 - Inspection and testing of the test pieces for branch type test pieces
Table A.2 - Inspection and testing of the test pieces for additional butt-weld
test pieces
a) Test not required for pipe with t < 6 mm. See also para TR 7.4.3.5.
b) For t < 12 mm, the total number of bends shall be split evenly between root and face
bends. For t ≥ 12 mm, side bend tests are required.
c) SSC test requirements as per Annex L of this specification. Specimens to be taken from
weld location corresponding to the minimum heat input. SSC test not required for welding
procedure qualification of fillet welds.
The extent of inspection and testing of test pieces for the approval of a WPS for fillet
welding shall be in accordance with the following Table B.1 for fillet weld test pieces and
with the previous Table A.2 for the additional butt-weld test pieces.
Table B.1 - Inspection and testing of the test pieces for fillet weld
If impact tests cannot be taken from the additional butt-weld test piece, fracture tests
are required from the actual fillet weld.
For pipe with a diameter of 168.3 mm or less, two fracture test specimens shall be
taken from the test piece. Four specimens shall be taken for pipe with a diameter above
168.3 mm.
The specimens shall be taken from diametrically opposed positions around the
circumference.
Fracture tests shall be performed by breaking specimens with the root of the weld in
tension, using one of the following methods:
- supporting both ends and striking the center of the specimen; or
- gripping one end and striking the other.
The exposed surface of each broken specimen shall be free from cracks, lack of fusion
and lack of penetration. The presence of other imperfections in the weld metal shall be
within the following limits.
a) Gas pores: The greatest dimension of any single pore shall not exceed 20% of the
wall thickness or 3 mm, whichever is smaller. The combined area of all pores shall not
exceed 5% of the affected area.
TR 7.5 Re-testing
PM 7.5.1 General
A new preliminary WPS shall be prepared for approval testing in case a test piece
fails to comply with the requirements of this specification.
The reason for the failure shall be investigated and reported by the CONTRACTOR
before any re-testing is performed.
If the investigation reveals that the test results are influenced by improper sampling,
machining, preparation, treatment or testing, the test sample and specimen (as
relevant) shall be replaced by two further test specimens correctly prepared
(obtained for each test specimen that failed) and retested.
A destructive test failing to meet the specified requirements shall be rejected if the
reason for failure cannot be related to improper sampling, machining, preparation,
and treatment or testing of specimens.
Re-testing of a test failing to meet the specified requirements shall only be performed
subject to agreement.
Re-testing for tensile and Charpy V-notch tests shall be in accordance with ISO
15614-1 requirements.
Hardness re-testing shall be as per par. TR 7.4.3.7. In sour service hardness re-
testing is not permitted.
A change in one or more of the essential variables beyond the specified range requires
the approval of another WPS in accordance with this specification.
TR 7.6.3.4 thickness
For girth welding, the approved pipe thickness range shall be as follow:
For branch and fillet welding, the approved thickness range shall be as specified in ISO
15614-1.
Only the welding test diameters are qualified for mechanized or automatic girth welds.
For branch and fillet welds, the diameter range shall be as specified in ISO 15614-1.
For girth, branch and fillet welding, an approved WPS shall be used for the welding
positions as specified in Table 4.
A variation in the pipe angle up to ± 15° is admitted for each welding position.
In addition, in case of sour service, batch is an essential variable for all filler metals.
Any change in batch of filler metals shall require Batch Testing or WPS re-qualification.
Batch Testing shall be performed in accordance with Annex N of this specification.
For sour service, the arc energy average value for each pass shall range within 10%
below the average value qualified, and 10% above the average value qualified in the
corresponding pass in the supporting WPQR.
Any weld produced with arc energy exceeding the above listed restriction shall be
rejected and completely removed from the pipeline.
If multiple test pieces are necessary for qualifying a pWPS (i.e. where the size of the
test piece will not allow extraction of test specimens in the correct locations), based on
recorded parameters for all test pieces, the lowest and highest average arc energy
values shall be defined for each pass.
The maximum arc energy variation between the lowest and highest for the different test
pieces shall not exceed 20% for each pass.
The tolerance above specified, for non-sour (i.e. ±15%) and sour service (i.e. ±10%),
shall be applied on the lowest and highest arc energy values provided that:
- Hardness test specimens are taken from the test piece welded with the lowest
arc energy;
- Impact test specimens are taken from the test piece welded with the highest arc
energy.
Any change in electrode diameter respect to the approved WPS is not be permitted.
The last cap pass shall not be deposited on the base material side.
Maximum weald bead width shall not exceed 3 times the electrode core diameter.
The approved flux shall be limited to the flux of the same type, classification and brand
qualified during welding of the test piece.
For mechanized welding, no changes are permitted in the number and sequence of
passes that shall be exactly as per the qualified welding test.
AR 7.6.5.3 Gas metal arc welding (GMAW) and gas-shielded flux-cored arc
welding (GSFCAW)
For mechanized and automatic welding of girth welds, the following additional essential
variables shall apply:
- any change of control software;
- any change of pre-set parameters (parameters that cannot be adjusted by the
welder) for automatic welding;
- any change in programmed parameters and their variation, except that
necessary variation in oscillation width for welding of thinner/ heavier wall than
used during qualification shall be allowed for mechanized GMAW;
- any change in limits for parameters that can be adjusted by the welder (“hot-key
limits”).
Any change in diameter and codification of tungsten electrode respect to the approved
WPS is not admitted.
Each WPS used for the original weld shall have a separated repair approval test.
Only manual welding processes (GTAW and/or SMAW) are admitted for repair welding.
Inspection and testing of the test piece shall be as per TR 7.4 of this specification.
Each repair procedure shall have “ad hoc” test pieces for qualification, separated from
the test pieces used for the qualification of the original weld.
Each repair procedure qualification test shall include at least the follows:
- Full thickness repair centered on the initial weld axis (through thickness repair);
- Mid-thickness or partial penetration repair with groove centered on the initial
weld fusion line. Max excavation depth shall be qualified and shall be deeper
than 50% of base material wall thickness, but shall not involve removal of hot
and root pass weld metal;
- Single pass cap repair.
Back weld repairs are not permitted.
Re-repairs (repeated repairs) are permitted only after COMPANY approval. Any re-repair
procedure shall be qualified and approved by COMPANY.
If PWHT is required for the original weld, all repair welds shall be submitted to PWHT
after completion. Each repair procedure qualification test (full thickness repair, mid-
thickness repair and single pass cap repair) shall be representative of the repairs to be
performed in production including the relevant number and sequence of PWHTs.
Table A.3- Inspection and testing of the test pieces for repair girth welds and
additional butt-weld test pieces for repair branch and fillet welds
a) Manual UT (in addition to RT) only for mechanized or automatic welding processes
b) Automatic UT shall be subject to approval, qualification and validation of the inspection
procedure. Indications to be confirmed by MUT.
c) Test not required for pipe with t < 6 mm.
d) For t < 12 mm, the total number of bends shall be split evenly between root and face bends. For t
≥ 12 mm, side bend tests are required.
e) SSC test requirements as per Annex L of this specification only in case of Sour Service.
Table B.3- Inspection and testing of the test pieces for branch and fillet type
test pieces
In case of test piece made of two different base materials (having different supply
condition and different manufacturer for sour service), repairs shall be qualified on both
sides.
Location of mechanical test specimens in the repair test piece shall be in the lower part
of the pipe as per Figure 5 (between 4 and 6 o’clock position).
The number of sets for Charpy-V impact test shall be 5 (five) for base material
thickness ≤ 20 mm and 10 (ten) for base material thickness > 20 mm.
Partial Penetration Repairs
The method for testing partial penetration repair shall be in accordance with par. TR
7.4.3.5 taking into account the following additional requirements for Charpy-V impact
test.
- Repair weld centerline;
- Repair fusion line on the pipe/base material side;
- Repair fusion line on original weld side;
- Repair fusion line +2 mm on the pipe/base material side;
- Repair fusion line +2 mm on original weld side.
For base material thickness ≤ 20 mm the location of the Charpy-V impact test
specimens shall be as per Figure 5.A.a) Charpy-V impact test shall be 5 (five).
For base material thickness > 20 mm, the Charpy-V impact test specimens specified in
Figure 5.A.b) shall be tested in addition to the Charpy-V impact test specimens specified
above for base material thickness ≤ 20. The total number of sets for Charpy-V impact
test shall be 10 (ten).
TR 8.1 General
All welders and welding operators employed by the CONTRACTOR for the project shall
be qualified before starting of production welding as per requirements of:
All welder qualifications shall be carried out in the presence of the Third Party Inspector
and COMPANY representative.
For girth welds, full size test welds shall be done for welders and welder operators
qualification.
All welders shall be qualified either by the satisfactory qualification of Welding Procedure
Qualification Testing (WPQT) in which he was involved with welding, or the separate
qualification testing by both destructive and non-destructive methods
Production welds shall not be used for the purposes of qualifying welders.
Any welder found responsible for a high level of defects/repairs in production and/or for
arbitrary deviation from the applicable WPS shall be removed from production. At the
discretion of Inspector, the welder in question may be retested after an agreed period of
retraining.
Welders who have completed the test piece for the successful approval of the WPS in
accordance with the requirements of par. 7.4 can be approved for production welding.
In case of sour service the pipe for test welds shall be of those to be used during
construction of the pipeline.
The welder shall make a test weld under simulated field conditions.
When testing manual or semi-automatic welders for execution of a weld without back
pass, the test pipe ends shall be closed so that internal check of the weld root cannot be
made by welders during performance of welding.
The CONTRACTOR shall use same welding consumables and the same or equivalent
welding equipment to those to be used during construction of the pipeline.
The pipe for test welds shall be of those to be used during construction of the pipeline.
The welder shall make a test weld under simulated field conditions.
TR 8.7 Re-testing
A welder or welding operator may produce additional test pieces if it is agreed that
failure of the test piece weld is due to metallurgical or other extraneous causes outside
the control of the welder.
In case of failure resulting from lack of skill, a welder or welding operator shall receive
further training before further test welding for approval is permitted. Further re-testing
after a second failure is not permitted.
9 PRODUCTION WELDING
AR 9.2 Equipment
All welding equipment shall be validated on site before using in construction; equipment
that does not meet these requirements shall be either repaired or replaced.
Weld habitat shall be dry, free of moisture and isolated from atmospheric agents.
Bevels prepared by thermal cutting shall be dressed to obtain the final configuration by
grinding or machining removing at least 2 mm of material from the surface in the as
thermal cut condition.
The beveling operator shall check the bevel configuration for compliance with suitable
tools or gauges at regular intervals. The bevel surfaces, before welding, shall be smooth
and uniform.
All traces of grease, oil, paint, cutting fluids, marking crayons, inks, process sing
chemicals, machine lubricants and temperature indicating crayons shall be removed
from the welding groove and an area extending back 50 mm from the bevel. The
cleaned area shall include the edges of the joint, as well as the interior of the pipe and
any area that shall be subject to heating by preheat, welding or post weld heat
treatment.
After cutting and beveling, the new end preparation shall be subjected to the following
testing:
- Visual Testing (VT);
- Ultrasonic Testing (UT) for de-lamination;
- Magnetoscopic (MT) or Liquid Penetrant Testing (LPT).
De-lamination check may be avoided if pipe cut-back leaves at least 50 mm of the end
zone length already ultrasonically inspected in the pipe mill. Otherwise, a lamination
check of the new pipe end shall be performed up to a minimum length of 50 mm from
the same new pipe end.
VT, UT for de-lamination and MT/LPT shall be performed for all bevelled pipe ends,
including bevels for branch connections.
TR 9.6 Support
Components to be welded shall not be moved during welding until both the root and hot
passes have been completed.
PM 9.7 Line-up
Modify second paragraph:
Internal misalignment shall be checked on all joints after coupling in at least 4 (four)
positions, before root pass start. Internal misalignment shall be uniformly distributed
around the pipe and shall not exceed 2 mm. Larger misalignments shall be corrected by
tapering the pipe ends by grinding or machining, with a slope not exceeding 1:4,
provided the specified minimum wall thickness of the pipe is maintained.
The line-up clamp shall be designed to prevent damage to the pipe and coatings.
Only temporary tack welds using bullets or bridging are admitted. Temporary tack weld
shall be completely included inside the weld bevel without any involvement of root and
outside surfaces.
Temporary tack welds using bridging or bullets (round solid pieces manufactured
through project pipe base material) shall only be performed according to the qualified
applicable WPS.
All temporary tack welds shall be completely removed by grinding before to proceed
with welding of the joint.
Where temporary tack welds are removed, the bevel configuration and root gaps
specified in the WPS shall be maintained for the subsequent pass and the groove
visually inspected prior to resuming welding of the root pass.
A detailed storage, baking and handling procedure for all consumables shall be prepared
by the CONTRACTOR for COMPANY approval (see AP Annex M.7).
Only vacuum packaging is allowed for covered electrodes; after the pack is open the
electrodes shall be used only according to the manufacturer recommendation. At the
opening date, each “vacuum” pack shall be signed by the CONTRACTOR inspector with
registration of date and opening time.
Baking and re-use of electrodes shall be in accordance with the recommendations of the
manufacturer of the electrode.
Each tin or packet of electrodes or reel of filler wire shall be clearly marked with the
respective batch number. In the event of consumables being unmarked or showing
signs of deterioration or other damage, they shall be discarded. Different grades,
different brands and different batches (when requested as essential variable, see TR
7.6.4.5) of electrodes and filler materials than those qualified and approved shall not be
used and completely segregated.
Fluxes re-baking and recycling are admitted within the restriction specified by
manufacturer and in any case the ratio of recycled to new flux shall be proper qualified
during WPQT (see TR 7.6.4.5).
Welding consumables (including covered electrodes with “vacuum” pack) shall be stored
at a temperature and humidity recommended by the Manufacturer.
TR 9.12 Preheating
All the requirements defined in par. AP 7.3.7 of this specification shall be met.
The preheating temperature shall be reached before starting with the first (root) weld
pass and maintained until the entire weld has been completed unless demonstrating the
soundness of the process through the qualification of partially completed weld according
to par. AP 7.3.9.
In any case, a temperature drop below the preheating temperature before the end of
the hot pass is not admitted.
The temperature of the joint shall be determined and measured by thermometer based
on contact thermocouples.
Crayons or paints which indicate temperature by color change shall not be used.
The temperature shall be measured on the face opposite of that to which the heat is
applied. If this is not practicable, the heat source may be removed and the temperature
determined on the heated face once the temperature has equalized. The time between
removal of the heat source and measurement of temperature shall be approximately 2
min for thicknesses up to and including 25 mm, plus 1 min for each 12 mm thickness
above 25 mm.
Repair by welding of pipe material affected by accidental arc strikes is not permitted.
For GMAW process, specific “tip” electrical connector shall be ceramic coated for the
root and hot passes deposition in order to avoid any arc strikes inside the narrow bevel.
Arc strikes shall be removed in accordance with a documented procedure (see AP Annex
AP M.11) that shall define the methods for the following:
TR 9.14 Backing
Permanent and temporary backing (eg. copper shoes, ceramic shoes) are not be
permitted.
The completed weld shall have a uniform width around the entire circumference with a
smooth transition to the base material. Internal and external reinforcements shall not
exceed the values as specified in par. TR 11.3.1.
Production welds (pipe to pipe) can be interrupted only if simulated during the
procedure qualification (according to AP 7.3.9) and only if the weld metal deposit is
within 1/3 and 2/3 of the parent metal wall thickness. In any case, the weld shall not be
interrupted before the completion of the root and hot passes.
Upon discontinuation of welding, the joint shall be wrapped in dry insulating and heat
resisting material with a waterproof backing for cooling in a slow and uniform manner.
Partially completed weld (discontinued) shall be restarted after reheating within the
interpass temperature range specified in the WPS.
Partially completed weld shall be traced, welding starting date shall be recorded and the
welds shall be completed within 24 hours.
For repairs, pipe to fittings (bends, tees, branches, etc.), fillet and golden welds,
partially completed welding is not admitted.
PWHT procedures shall be submitted to the COMPANY for approval (see AP Annex
M.14).
- heating method (the number and the layout of electrical pads shall be defined);
- PWHT holding temperature range;
- PWHT holding time;
- heating and cooling rates;
- soak band (SB) width;
- heated band (HB) width;
- insulation band (IB) width;
- axial temperature gradients;
- type and thickness of insulation;
- number, location and type of thermocouples for each band (soak, heated and
insulation bands);
- method for removal of thermocouples.
If this is not practicable, girth welds shall be heat-treated locally by heating a band
around the entire circumference, centered on the girth weld, using an electrical
resistance mat, gas-fired muffles or other methods by agreement.
The width of the soak band (SB), centered on the girth weld, shall not be less than 6 x
t, where t is the thickness of the thicker component.
The width of the heated band (HB) shall not be less than , where r is the internal
radius of the larger component, and t is the thickness of the thicker component.
Sufficient insulation shall be fitted to ensure that the temperature of the weld and its
heat-affected zone is not less than specified in the WPS, and that the temperature at
the edge of the heated band is not less than half the peak temperature. In addition, the
adjacent portion of the assembly outside the heating zone shall be thermally insulated
so that the temperature gradient is not harmful. To meet this requirement, the total
insulated band (IB) width shall be at least .
Assemblies of different wall thicknesses may be placed in the same furnace charge for
PWHT and treated in accordance with the requirements for PWHT of the thickest
assembly in the charge, provided that the minimum thickness of the charge is not less
than 50% of the thickness of the thickest assembly.
PWHT on production weld shall be performed according to the PWHT procedure applied
for WPS qualification.
The temperature and time shall be as indicated in the qualified WPS; in any case, post-
weld heating shall be applied immediately after completion of the weld, before the weld
area cools to a temperature below the minimum interpass temperature.
For all the welds realized by mechanized welding, the average values of the following
welding parameters shall be recorded per each pass:
- Welding Voltage;
- Welding Current;
- Welding Speed (or arc duration).
For at least 25% of the entire production of welds realized by manual welding
procedure, the average values of the following welding parameters shall be recorded per
each pass:
- Welding Voltage;
- Welding Current;
- Welding Speed;
- Preheating and Interpass Temperatures.
For all the welds, preheating, interpass temperatures and heat input shall be
continuously monitored by CONTRACTOR inspector and shall not exceed the acceptance
range as per approved WPS and the requirements of this specification.
AP 9.23 Tapering
In case of pipe wall thickness transition pup pieces shall be preferably used.
Transition technique between pipes of different steel grade shall be agreed with the
COMPANY.
Wall thickness transition shall be smooth and gradually reached with a slope not
exceeding 1:4; it shall be realized at proper distance from the bevel edge to ensure that
any NDT on the girth weld is applicable as per the reference procedure.
The tapering area shall be NDT inspected and the wall thickness shall be recorded in at
least n°4 positions equally distributed around the pipe. The tapering area shall be free
of any indication during both manual UT lamination and MT checks.
This operational demonstration shall consist, as a minimum, of two full girth welds
made consecutively, each weld being required to meet the production acceptance
criteria without the need for any repair.
Each of these pre-production welds shall be uniquely identified and reserved for possible
mechanical evaluation by COMPANY.
This operational demonstration shall not be applied for welding procedures qualified
specifically for tie-in welds, flange welds, Tee-piece welds, etc.
COMPANY reserve the right to ask a production test whereas possible in relation with
the actual operational condition.
The following tests can be required by the COMPANY in case of production test:
- Macro and hardness;
- All weld tensile;
- Charpy V-notch fracture toughness.
Residual magnetism shall be measured with a calibrated Hall effect gauss meter or
equivalent equipment.
Four readings shall be taken 90° apart around the circumference of each end of pipe.
The residual magnetism shall not exceed an average value (out of 4 measurements) of
2.0 mT (20 Gauss), with a maximum single value of 2.5 mT (25 Gauss).
An application specific procedure shall be issued for COMPANY approval (AP Annex
M.15).
10 NON-DESTRUCTIVE TESTING
TR 10.1 General
All completed girth welds, after PWHT (if required), shall be inspected according to
Table A.4.
b) Manual UT, MT and LPT equipment shall be always available on site to supplement the
primary NDT method on any doubtful area nominated by the CONTRACTOR’s Inspector
and/or when required by COMPANY representative.
c) In lieu of Radiographic Testing, only after COMPANY approval, AUT inspection can be
used. AUT inspection shall be in accordance with Annex G of this specification.
All completed branch and fillet welds, after PWHT (if required), shall be inspected
according to Table A.5.
Table A.5- Inspection of production branch and fillet welds (after PWHT
if required)
The COMPANY requires full written procedures for each NDT method for review and
approval for all test welds at least 30 days before starting of test welding. These
procedures shall have been reviewed and endorsed by a Level III NDT as per ISO 9712.
The qualification certificate of the Level III shall be included in the documentation
submission Results of NDT shall meet the acceptance criteria specified in par. 11 for
each NDT method employed.
All slag, spatter, and all type of foreign material shall be removed prior to weld
examination; any bonding media, inks or dyes used for crack detection, shall be
removed also. In case of RT reshoot for doubts on films interpretation, light grinding of
the external cap passes of inspected welds is allowed. Flush grinding is not permitted,
unless after written COMPANY approval.
The roles and responsibilities of NDT personnel shall be as defined in ISO 9712.
All NDT operators shall have at least two years’ experience on pipeline working in the
NDT method qualified.
Personnel for manual UT and AUT examination shall be qualified by practical test
provided by COMPANY before the start of welding activities.
Practical demonstrations shall be conducted under anticipated field conditions and with
weld temperatures as foreseen during the testing of production welds.
The make and type of NDT equipment for testing of production welds shall be the same
as used for the approval of NDT procedures.
NDT procedures shall be qualified before starting with any inspection activities.
All the NDT procedure qualification records shall be always available on site for
COMPANY inspection.
For all tie-ins and golden welds, VT examination shall be performed also after deposition
of root pass.
The (internal) root surface shall be examined through one or more “inspection window”
to be positioned in the upper part of line pipe. Method of visual inspection to be used in
the field shall be demonstrated during manual welding qualifications (i.e. no access from
pipe ends, inspection window from 10 to 2 o’clock).
Technique of inspection shall be agreed upon and demonstrated feasible during welding
qualifications. Opening of window shall be as per qualification during WPQT. Technique
may not permit 100% internal inspection, but shall inspect approximately from 2 to 10
o’clock (¾ of the internal surface). Details shall be defined in the VT procedure.
TR 10.5.1 Technique
Inspection shall be carried out by X-Ray (Gamma ray are not permitted). Only extra
fine-grain radiographic films (class C4 according to ISO 11699-1) shall be used.
TR 10.5.2 Procedure
Radiographic procedures shall define the following:
- pipe diameter and wall thickness;
- radiation source;
- technique (equipment rating, in voltage, external or internal equipment);
- geometric relationships (source focal-spot size, film focus distance, object-film
distance, radiation angle with respect to weld and film);
- penumbra or geometric un-sharpness;
- film type (trade name, designation and dimensions);
- intensifying screens (front and/or back, material thickness, filters);
- exposure conditions;
- processing (developing time/temperature, stop-bath, fixation, washing, drying,
automatic processing, thio testing frequency);
- IQI sensitivities, in per cent of wall thickness, based on source- and film-side
indicators, respectively, essential IQ wire shall be reported;
- density;
- film overlap;
- weld joint geometries;
- temperature of welds during inspection;
- archival life;
- initial source strength.
During radiographic procedure approval testing, wire-type IQIs shall be placed both on
the source side and on the film side. Only one IQI is required for each radiograph for
short film lengths where the distance between IQIs would be less than 100 mm.
IQIs shall be wire type. IQIs wires shall be made of ferrous materials according to ISO
19232-1.
Sensitivities for source-side IQIs shall, for both single wall and double wall techniques,
be in accordance with ISO 17636-1, Class Band Table 6 of this specification.
There shall be an intermediate and final weld approval testing. The approval testing
reliability shall have a minimum of 2 sets of radiographs.
All relevant data on the procedure approval testing, including results, shall be
documented.
Radiographs from the procedure approval testing shall be kept available on site for
reference throughout the period of production welding.
IQI sensitivity on film side shall be qualified during the procedure qualification by the
corresponding sensitivity required for IQI on the source side.
IQI sensitivity on film side shall be qualified during the procedure approval by the
corresponding sensitivity required for IQI on the source side.
Film width shall be enough to guarantee the complete examination of the weld and at
least 30 mm of parent metal for each side.
TR 10.5.6 Intensifying screens
Front and back intensifying lead screens in the range 0.02 ÷ 0.15 mm shall be used.
All exposed radiographic films shall be processed suitable for storage for a minimum of
10 years under controlled conditions.
The film processing shall be daily controlled in accordance with ISO 11699-2; frequency
for Thio testing shall be detailed in the radiographic procedure.
Ultrasonic testing for transversal indication check requires partially or fully cap removal;
in any case, a flat surface for the probe coupling is requested.
TR 10.6.2 Equipment
UT equipment shall meet the requirements in ASME, Section V.
The name of the manufacturer, the identification number, the transducer frequency, the
refraction angle and the output point shall be clearly marked on each probe.
Tandem techniques shall be used for girth welds with a bevel angle between 0° and
10°.
When using straight-beam probes for weld testing, the DAC curve shall be drawn
similarly to that for angle probes.
The length of indications shall be defined as the circumferential distance over which the
echo height exceeds the reporting level.
At least two different angle shear wave transducers shall be used. Use of 45° shear
wave probe is mandatory for manual UT on girth welds.
Length, position, and DAC percentage together with echo characteristic shall be
documented for each indication.
- Calibration block;
- Probe angles and frequency and scan plan;
- Sensitivity level;
- Equipment and model;
- Surface correction factor (“transfer” correction);
- Conclusion (accept or reject);
- Sketch including defect locations and recordable indication locations;
- Operator’s name, signature and method certification level.
MT shall not be performed when surface temperatures exceed 300°C. Only dry MT shall
be used for tests with surface temperatures between 60°C and 300°C.
A detailed Liquid Penetrant Testing procedure shall be submitted for COMPANY approval
and shall define the following:
- quality and dimension of material to be examined;
- welding process;
- type of equipment;
- compatibility of testing materials with the parts to be tested;
- preparation, pre-cleaning and testing;
- inspection;
- acceptance criteria;
- post cleaning and protection;
- retesting;
- reporting.
In order to verify the LPT procedure, a reference object with known defects such as a
testing panel described in ISO 3452-3 or equivalent shall be used.
The reference object and the penetrant products shall achieve, before testing, the same
temperature as relevant for the actual testing to be performed.
The minimum defect size to be detected shall comply with the maximum acceptable
defect zone.
Liquid Penetrant Testing shall be carried out instead MT, only when this last method is
not applicable.
- contract number;
- applicable procedure specification;
- weld identification;
- test reports presenting the results of testing;
- description and location (with sketch where appropriate) of all reportable
indications;
- for shop welds, reference to the fabrication drawings;
- actions taken;
- date of testing;
- name and qualification level of inspector;
- approval signature of responsible inspector.
TR 11.1 General
The acceptance criteria specified in this paragraph shall apply to imperfections detected
by radiographic, ultrasonic, magnetic particle, liquid penetrant and visual testing.
Imperfections shall be classified in accordance with ISO 6520-1.
Acceptance shall not be based on ECA.
In sour service, any imperfections exposed to the internal surface, such us root
undercut, lack of penetration, lake of fusion at the root single side, burn through, start
and stop irregularity, shrinkage groove, hollow bead is not acceptable.
In case of execution of different NDT on the same area, the most stringent acceptance
criteria shall be adopted.
The field joint coating operation shall not start until final approval of the weld has been
given.
Weld reinforcement on external profile shall be not less than 1.0 mm nor more than
3.0 mm in height and it shall not exceed 3 mm beyond the original weld preparation.
Root penetration height on the internal profile shall not exceed 3.0 mm.
AP 11.3.4 Spatter
Spatter is not acceptable.
AP 11.3.6 Overlap
Overlap is not acceptable.
Root concavities with film densities exceeding the density of the thinnest base metal
adjacent to the weld shall be not acceptable, regardless their single and total length.
TR 11.4.4 Burn-through
Burn-through (defined as a portion of the root bead where excessive penetration has
caused weld puddle to be blown into the pipe) is not acceptable.
TR 11.4.7 Cracks
Any type of cracks shall be unacceptable, regardless their length. COMPANY shall be
immediately advised every time it occurs.
A defect (axial) is considered isolated if the distance between the first and the second
defect is greater than the separation of the two.
A flaw (embedded) is considered isolated if the first flaw respect to the second flaw is
located at a distance that is at least 1½ more than the height separation between the
two.
A defect is considered surface breaking when it is far from the inner or outer surface by
a distance less than its height.
Spherical porosity may be classified as a planar indication with the area containing the
porosity being evaluated as a single planar imperfection in accordance with TR 11.5.3.
For any type of services, all indications, characterized as planar by ISO 23279,
referred to cracks, are unacceptable regardless of length.
For sour service, all indications, characterized as planar by ISO 23279, referred to
lack of fusion open to the surfaces, both internal and external, and incomplete
penetration are unacceptable regardless of length.
In any case, the sum of defect lengths in each individual section of 300 mm of
continuous welding shall not exceed 25 mm if located on inner surface and 50 mm in
the volume or on outer surface.
TR 12.1 General
WPS for repair welding shall be approved in accordance with paragraph TR 7 of this
specification.
If PWHT is required for the original weld, all repair welds shall be submitted to PWHT
after completion.
MT or LPT check shall be done in the excavation area after defect removal to assure that
the exposed defect has been completely removed.
Maximum excavation depth shall be measured by dedicated gauges and recorded in the
welding inspection report.
Weld excavations shall be sufficiently deep and long to remove the defect. NDT of the
excavated area, to confirm the complete removal of the defect shall be performed
before commencement of repair welding.
Repaired areas shall be examined using the same testing method which detected the
defect. Should the testing reveal further imperfections, they shall be evaluated as new
imperfections, i.e. remnants of the original defect may remain if within the acceptance
criteria of this specification.
It is not necessary to perform NDT on the complete weld again. A minimum length of
50 mm beyond the ends of the repair shall be examined.
In case of PWHT, the entire weld subject to repair shall be NDT examined.
TR 13 DOCUMENTATION
The retention period and location of the records shall be decided by agreement.
Full details of the joining technique and associated equipment shall be submitted to the
COMPANY for approval prior to use. The procedure shall conform to the manufacturer’s
recommendations.
TR C.2.1 General
Prior to starting, the contractor shall submit a procedure specification to the COMPANY
for approval.
The procedure and operators shall be approved by making three consecutive test joints,
in the presence of the COMPANY, on material to be used in production. The test material
shall be selected by the COMPANY to represent the upper quartile of the carbon
equivalent range.
The electrical resistance of each weld shall be measured and shall not exceed 0,1 Ω.
The mechanical strength of the weld shall be tested by means of a sharp blow from a 1
kg hammer.
All three of the test welds shall be sectioned and prepared for metallographic testing.
The tests described in TR C.2.2 and TR C.2.3 shall be performed on the sections.
The depth of copper penetration below the surface of the pipe material shall be
measured metallographically. The fusion line of the weld or braze shall not be more
than 1 mm below the pipe surface. Intergranular copper penetration of pipe material
shall not exceed 0,5 mm beyond the fusion
line when a specimen is examined at a magnification not exceeding ×50.
Each test section shall be tested using a 98,07 N load. A traverse shall be made across
the weld zone.
The traverse shall consist of at least six impressions; two in the heat-affected zone each
side of the
weld/braze and one in the parent metal each side of the weld/braze.
The hardness values shall not exceed 250 HV10 for sour service and pipe thickness less
than 9 mm, 275 HV10 for sour service and pipe thickness above 9 mm and 325 HV for
non-sour service.
G.1 General
This Annex provides requirements for the automatic ultrasonic testing (AUT) of girth
welds in pipelines with a nominal wall thickness of 8 mm or over.
The system shall be capable of locating and measuring the position of welding
anomalies if applied in conjunction with workmanship acceptance criteria.
The AUT system used shall provide an adequate number of inspection channels for the
complete volumetric inspection of the weld and heat affected zone in one
circumferential scan.
This requirement may be deviated from only in cases where full coverage in one scan
cannot be obtained.
The weld shall be divided into vertical testing zones taking into account the weld bevel
configuration and welding passes. Where practicable, the height of the testing zone
should not exceed the height of the welding pass.
The AUT techniques shall use Pulse echo (using either fixed angle or phased array
probes), ToFD (time-of-flight diffraction) and mapping channels.
ToFD provides additional information for the evaluation of the overall AUT inspection
result and enhancing the ability to determine the through-thickness dimension and the
depth position of imperfections within the weld volume.
The AUT system functionality shall be in accordance with ASTM E1961:2011, Clause 6,
and the following:
a) ToFD shall meet the requirements of ISO 10863. A single ToFD configuration
shall be used for wall thickness ≤ 25mm, whereas a dual ToFD configuration
shall be used for wall thickness > 25mm;
c) the AUT system shall incorporate inspection techniques for the detection of
transverse imperfections.
G.3 Procedure
The procedure for AUT shall be documented in accordance with ASTM E1961.
The procedure for AUT shall be approved by the COMPANY after the qualification of AUT
system.
Two transverse notches shall be added for the detection of transverse defects. The
notches shall be 10 mm long and 2 mm deep, and one notch shall be positioned on the
internal pipe surface and one notch on the outside surface.
Holes shall normally be protected from degradation by covering the hole with a suitable
sealant. Filling of surface notches and other near surface reflectors may influence the
reflecting ability of the reference reflector and shall be avoided.
The calibration block shall be from pipe material with similar diameter, thickness, heat
treatment and acoustic properties (attenuation value of not more than ± 3dB from the
actual project material).
Acceptable amplitude response limit and length indication are the principal parameters
for acceptance. Accurate determination of flaw height is not normally a requirement.
Qualification of the system and procedure shall be by demonstration that the response
obtained for all reflectors meets the requirements of ASTM E1961.
AUT indications obtained from the “blind” testing shall be compared with the results of
radiography, manual ultrasonic testing and any other NDT method previously applied for
the characterization of the artificial flaws in the validation block. The characterization of
the artificial flaws in the validation block shall be certified by a Third Party charged by
the COMPANY.
G.4.3 Specific requirements for use with acceptance criteria determined by ECA
G.5 Validity
- reference reflectors;
- working temperature range;
- system equipment data acquisition and data processing;
- system software;
- temperate ranges;
- material for calibration block.
G.7.1.1 General
The reference level shall be based on 3 mm flat bottomed hole and 1 mm deep surface
notches.
All AUT indications with a response over 40% of the reference level shall be evaluated in
accordance with this paragraph.
G.7.1.2 Cracks
Indications which by their location and orientation may suggest the presence of a crack
shall be investigated. Indications confirmed to be a crack shall be considered defects.
Linear surface (LS) imperfections (other than cracks) interpreted to be open to the inner
or outer pipe
surface shall be considered defects should any of the following conditions exist:
Linear buried (LB) indications (other than cracks) interpreted to be subsurface within
the weld and not surface-connected shall be considered defects should any of the
following conditions exist:
All transverse indications exceeding 40 % FSH shall be further inspected with manual
UT or other appropriate inspection techniques.
Transverse (T) indications (other than cracks) shall be considered volumetric and
evaluated using the criteria for volumetric indications below. The letter T shall be used
to designate all reported transverse indications.
Volumetric cluster (VC) indications shall be considered defects when the maximum
dimension of VC indications exceeds 12.5 mm.
Any accumulation of relevant indications (AR) shall be considered a defect when either
of the following conditions exist:
AP L.1 General
This Annex specify the requirements for the testing of line pipe girth welds by means of
sulphide stress cracking (SSC) tests as part of the procedure qualification testing
requirements.
A detailed test procedure based upon this specification shall be prepared by
CONTRACTOR and approved by COMPANY.
Detailed cut Plan shall be defined before testing start and shall be approved by
COMPANY.
Both full and reduced thickness transverse specimens shall be with root surface
machined flush removing the minimum amount material.
Full thickness (FT) specimen with a width of minimum 15 mm shall be used for
specimen transverse to the girth weld. CONTRACTOR could propose other width values
to COMPANY, for approval. Reduced specimen (size 115×15×5 mm) can be used, with
COMPANY approval, taken at mid thickness and at internal surface.
The weld shall always be in the center of the specimen. Test specimens shall be marked
using a stamped or vibratory stencilled in a region within 13 mm of either end on the
compression side. An evidence of test specimen identification shall be provided.
After specimen preparation NDT shall be executed on all specimens prior to test (e.g.
dye penetrant or magnetic particles). Specimens showing superficial weld imperfections
shall be scrapped.
Test specimens shall be degreased with solvent and rinsed with acetone before testing.
The stressed section of the test specimen shall not be contaminated after cleaning.
In case of other test configurations they shall be proposed and approved by COMPANY.
The strain gage readings shall be used to determine the displacement, to achieve the
strain corresponding of a stress applied equal to 90% of AYS.
AP L. 4 Test arrangement
The SSC test shall be carried out with Solution A as defined in the standard NACE
TM0177 or if required by COMPANY at project specific conditions.
Any deviation from the test solution shall be agreed between COMPANY and
CONTRACTOR before starting the test.
If corrosion products are present, a cleaning procedure for corrosion product removal
shall be performed in accordance to ASTM G1.
The samples showing evident cracking after testing, shall be examined in the fracture
surfaces in order to check that cracking did not occur starting (or caused by) an original
weld imperfection.
Evidence of original weld imperfection, shall be reported to the COMPANY for final
decision.
The hardness values shall comply with the limit specified in the par. AR 7.4.3.7 of this
specification.
Any specimen failure shall be immediately reported to the COMPANY for review and
confirmation.
Any tendency for blistering shall be reported after visual examination, with photographic
documentation.
The report shall be finalised and submitted to COMPANY after discussion of the results.
AP M.1 General
CONTRACTOR shall submit for COMPANY approval the CVs of the following key
personnel of the QA/QC department:
Project Quality Manager shall be responsible of the QA/QC department and shall be
clearly identified in the project organization chart.
PQM shall be responsible of the QA/QC team organisation to assure that all this
Specification requirements are fulfilled.
PQM shall be available on site on full time basis during the pipeline construction and
shall be responsible of the preparation of the quality control plan.
Welding engineer (IWE) shall be the focal point in leading all the welding procedure
qualification, NDT and laboratory tests.
CONTRACTOR’s welding inspectors (IWI) shall be available and shall be responsible for
supervision and monitoring in site activities to assure that all this Specification
requirements are fulfilled.
Welding inspector shall supervise each areas where welding activities are ongoing
including all the actions that could affect the final welding qualities (e.g. pipe cutting,
bevel preparation acceptance, etc.).
AP M.11 Arc strike and surface defect removal without welding operation
A procedure shall define and detail at least the following:
- Localization of the defect;
- Defect removal;
- Thickness monitoring;
- NDT;
- Minimum admissible thickness;
- Records and inspection forms;
- Personnel responsibilities and duties.
AP N.1 General
Batch testing shall be conducted to verify that consumables not tested during
qualification of the welding procedure will give a deposited weld metal nominally
equivalent to those batches used for welding procedure qualification, with respect to
chemistry and mechanical properties.
The batch testing shall be performed for all welding consumables, including possible
wire/flux combinations. Consumable batches and combinations used during WPQR are
considered tested.
Each individual product (brand name and dimensions) shall be tested once per
batch/lot, except for solid wire originating from the same heat, where one diameter may
represent all. SAW fluxes do not require individual testing but SAW wires shall be tested
in combination with a selected, nominal batch of flux of the same classification as used
for welding.
The testing shall be performed on samples taken from test pieces welded according to
the welding procedure to be used in production. Samples shall be removed from the 12
and 6 o'clock positions and from the 3 or 9 o'clock positions.
The testing at each position shall include:
Test temperature shall be the same as for qualification of the relevant welding
procedure.
For solid wire, the analysis shall represent the product itself. For coated electrodes and
cored wires, the analysis shall represent the weld metal, deposited according to EN
26847 (ISO 6847). The analysis, made by manufacturer or contractor, shall include:
- all elements specified in the relevant classification standard and the relevant
data sheet;
- Ni content.
The chemical analysis shall be in accordance with the composition ranges stated in the
Manufacturer's data sheets.