PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN

VENDOR : SOPAN P.O. NO. : 6300002455 Dated 15.11.2019


CLIENT : NAYARA ENERGY LIMITED REPORT NO. :
PMC : PEMS DATE :
JOB TITAL : CHECK LIST FOR -LV BUS DUCT
Ref Dwg No.: SOP-NAYA-PS-ELE-LBT-210

BASE FRAME AND SEC. No.


Sr. No. PANEL TAG NO. NO. OF INTERCONNETION CONTROL EARTHING OF ANCHORING TO TOP FINAL LEVELING TAGGING, DRESSING. REMARKS
SECTION OF SECTION WIRING STATUS BUSDUCT & ALINGMENT
HEADER
SEC. No. L W D
SECTION SECTION SECTION SECTION SECTION SECTION SECTION SECTION SECTION

CONNECT TO PMCC
-A1

1 A1 230 800 450


INCOMER -01
-A2

2 A2 1250 800 450 INTERCONNECTED


-A3

3 A3 1960 800 450 INTERCONNECTED


-A4

4 A4 1535 800 450 INTERCONNECTED

CHECK AS PER GAD


OK
THE EARTHING
LV BUS DUCT OK CHECKED OK AS CONNECTION IS DONE
-A5

5 CHECKED BY G.A PER SCHEM CHECKED OK CHECKED OK CHECKED OK A5 2542 800 450 INTERCONNECTED
415V, 3200A ON THE LEFT SIDE OF
DRAWING DRAWING
THE PANEL AND THE
BOTTOM OF THE RIGHT
SIDE.
-A6

6 A6 3000 800 450 INTERCONNECTED


-A7

7 A7 2542 800 450 INTERCONNECTED


-A8

8 A8 1595 800 450 INTERCONNECTED

CONNECT TO 1600KVA
-A9

9 A9 1315 800 450 111KV/0.433V


TRAFSFORMER

COMMENTS:-

SOPAN PEMS NAYARA (P)

Page 1 of 7
PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN
VENDOR : SOPAN P.O. NO. : 6300002455 Dated 15.11.2019
CLIENT : NAYARA ENERGY LIMITED REPORT NO. :
PMC : PEMS DATE :-
QUALITY INSPECTION RECORD/ ACTIVITY COMPLETION RECORD FOR HT PANEL/LT PANEL/BUS DUCT-LV BUS DUCT
Location : MCC
Ref Dwg No.: SOP-NAYA-PS-ELE-LBT-210
Sr. CHECKED
DESCRIPTION / ACTIVITY REMARKS
No. STATUS SOPAN PEMS NAYARA
A Material receiving inspection OK
B check installation of HT Panel/LT Panel / Bus Duct according to GAD drawings. OK
C Check Every panel board with supports for adequacy, workmanship, spacing, leveling, alignment & painting OK
D Ensure proper Coupling, fixing of sectionalized switch boards. OK
E Ensure all the connection of cable as per cable schedule and capacity of switch gear and equipment. OK
F Ensure earthing connection to each switch board body. OK
G Check the bus bar and cable termination tightness as required. OK
H Ensure connection of control wiring as per drawing. OK
I Check metering and function of all indicating lamps and other accessories. OK
J Check IR value & continuity of cables. OK
K Activity completion.

COMMENTS: 1. HT PANEL/LT PANEL/BUS DUCT ERECTION/INSTALLATION WORK IS COMPLETED AS PER REFER DRAWING
2. ATTACHED MEGGER REPORT NO: ___________________________________________________________________

SOPAN PEMS NAYARA (P)


PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN
VENDOR : SOPAN P.O. NO. : 6300002455 Dated 15.11.2019
CLIENT : NAYARA ENERGY LIMITED REPORT NO. :
PMC : PEMS DATE :- 29.11.2021
TEST REPORT FOR LT/ HT PANEL/ BUS DUCT
Ref Dwg No.:
1 Location: MCC ROOM
Specified Location: LV BUS DUCT- 415V, 3200A
2 Name plate details:
Make : GLOBE ELECTRRICAL INDUSTRIES Type :
S.No of charger : Fault level :
Rated Voltage : 415 V

3 Section or I/C fed from : 400A ACB INCOMER


Section or I/C fed from : N/A
Section or I/C fed from : N/A
Section or I/C fed from : N/A
Section or I/C fed from : N/A

4 No. of Incomming feeders : 1


No. of outgoing feeders
: 1
excluding spare feeders
No. of spare feeder :
Items/Equipment a/c to BOM :

5 General Checks Yes/ No Yes/ No

Earthing of the panels &


General cleaning of panels & assembly YES YES
assembly

Glands, termination &


Bus bar alignment & connection YES
spacing of cables

Vermin proofing & cable


Tagging & ferruling of cables YES YES
entry sealing

Tightness of cable connections YES Meterts & metering circuit

Indicating lamps & control


Taping of exposed portion of cables
switches keys

Bus trunking & tightness of bolt/ nu Nomenclatures of various


YES YES
connections feeders

Switch unit & door interlock Danger board YES

Contractor closing & tripping Fuses, Switches ranges


YES
mechanism matching with load

6 Circuits checking

PT circuits
Space heater & current circuits CHECKED OK
Contactor closing &
tripping mechanism
Control circuits OK

7 Insulation resistance test (in mega ohms):


Date of Testing: 31-08-2021 Temperature: Calibration Center No.: IS 1248 PART-9
P.TEJ CALIBRATION
Meggar Used: YES 1KV Calibration Validity: 30-08-2022 Calibration Agency:
CENTRE
Description RY YB BR RN YN BN RE YE BE NE
Bus Bar >812MΩ >816M>79M8Ω >612MΩ >618MΩ >594MΩ >512MΩ >584MΩ >533MΩ >551MΩ

6 Remarks: Fit/Unfit for commissioning

Tested by Witnessed by
Vendor SOPAN PEMS NAYARA
Sign

Name
Date
SOPAN O&M CO. PVT. LTD.
CLIENT : Nayara Energy Limited CONSULTANT: PEMS
Electrical works at Proposed Petroleum Storage Terminal at Pali, Rajasthan
Doc.No.: SOP-NAYA-PS-ELE-LTP-204 Rev. No. : 0 FORMAT F-01
TESTING REPORT - LV BUS DUCT 415V, 3200A
REPORT NO.:- DATE:-
Sr. Instrument Calibrating
Instrument Details Make Model Calibration Validity Calibration Cert. No. Remark
No. S.No. Agency
5KVA INSULATION
1 MECO MECO DIT-954 547249 8/30/2022 PTCC PTCC/SEP/SOM-09 OK
TESTER
Sr. BUSBAR / SIZE / CHECK IR IN GΩ
PANEL TAG NO. LENGTH (M) REMARKS
No. RATING DATE R-Y Y-B B-R R-N Y-N B-N R-E Y-E B-E N-E
3200A, 2X200X10
1 LV BUS DUCT 415V, 3200A mm AL./PH. & 15969mm 29.11.2021 >812MΩ >816MΩ >79M8Ω >612MΩ >618MΩ >594MΩ >512MΩ >584MΩ >533MΩ >551MΩ
2X200X10 mm AL./N

REMARKS:-

SOPAN O&M CO. PVT. LTD. PEMS Nayara Energy Ltd.


Sign : Sign : Sign :

Name : Name : Name :

Date : Date : Date :


PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN
VENDOR : SOPAN P.O. NO. : 6300002455 Dated 15.11.2019
CLIENT : NAYARA ENERGY LIMITED REPORT NO. :
PMC : PEMS DATE : 15 FEB 2022
COMMISIONING REPORT FOR LT - PANEL
Ref Dwg No.:
Location: MCC ROOM
Specified Location:
Name plate details: LV BUS DUCT- 415V, 3200A
Make : ELECMECH SWITCHGEARS & INSTRUMENTATION Type :
S.No of charger : Fault level : 50KV for 1 sec.
Rated Voltage : 415 V
Area: FIRE PUMP HOUSE Tag No: LV BUS DUCT- 415V, 3200A Report No :

S.No Description Checked Remarks


G GENERAL
Has ground continuity been verified? (Ground/bond straps installed & verifiedwhere
G1 applicable)
CHECKED OK

G2 Is electrical wiring/ equipment protected from probable liquid leak sources? CHECKED OK
Is a Ground Fault Circuit Interrupt (GFCI) system installed & operating per design,where
G3 applicable?
CHECKED OK

G4 Maximo Tag, Nameplate, and Serial Number are attached to equipment. CHECKED OK

G5 Equipment and components are labeled according to labeling standard. CHECKED OK


Project was installed according to the construction
G6 drawings provided by System Owner.
CHECKED OK

D DOCUMENTATION:
Submittal of equipment operation manuals and
D1 specifications to System Owner.
SUMITTED

As-built documentation such as red line drawings are


D2 submitted to System Owner.
SUMITTED

E ELECTRICAL:

E1 Check equipment and nameplate details with datasheet. CHECKED OK

E2 Verify protection of live parts is correct. CHECKED OK

E3 Check for mechanical damage. CHECKED OK

E4 Confirm equipment is mounted/anchored according to drawings and Manufacturer’s instructions. CHECKED OK

E5 Confirm bus duct is properly supported. CHECKED OK

E6 Confirm bus bars and connecting links are tightened to specified torque. CHECKED OK

E7 Verify phase identification is correct. CHECKED OK

Verify unit is internally and externally clean, and covers are securely fastened with all
E8 screws in place.
CHECKED OK

E9 Confirm equipment is grounded according to drawings and Manufacturer’s instructions. CHECKED OK

E10 Perform Ductor test across all bolted connections. CHECKED OK

E11 Verify silica gel breather in busduct are installed. CHECKED OK

E12 Verify heaters are correctly installed. CHECKED OK

E13 Verify Vendor Service Representative participation, if required.

E14 Verify all testing complete and documented including. CHECKED Report are attached

Note :-

Description SOPAN PEMS NAYARA

Signature

Name Sidharth Sahoo


Date 15-Feb-22