Rain S.No Document Pg. No

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Rain

S.NO Document Contents Pg. No.


1. 14.02.2017 The Claimant stated that the rainy Pg. 29, Annexure
Claimant’s letter season was to start soon and therefore, C-10, Vol CD-1
it was important to start construction
work of drains.
2. 16.03.2017 Respondent’s email dated 16.03.2017 Pg. 47, Annexure
Respondent’s This has reference to the work program R-28, Vol RD-1
email submitted by you in February 2017,
showing completion of the work upto
14-10-2018
You will appreciate that the rains
commences in the region by may/June
and last roughly upto sept every year.
Hence in order to achieve completion of
project by 14th October 2018 ( as per
your work program) it is imperative
that ICP Dawki project is substantially
completed before onset of monsoon
season in 2018.
3. 29.05.2017 Respondent’s email Pg. 57, Annexure
Respondent’s As the monsoon season is approaching R-34, Vol RD-1
letter. fast and the good working season is
running out , the project will be thrown
out of gear, if certain works are not
completed in next one month.
4. 06.06.2017 Respondent’s email Pg. 66, Annexure
Respondent’s As the monsoon season is approaching R-41, Vol RD-1
email fast and the good working season is
running out , the project will be thrown
out of gear, if certain works are not
completed in next few days.
5. 10.07.2017 Claimant’s email Pg. 52, Annexure
Claimant’s email It was stated that in all the days of July C-26, Vol CD-1
2017 there has been incessant rain at
the site in which no civil work can be
done.
6. 11.07.2017 Respondent’s email Pg. 96, Annexure
Respondent’s I hope you will appreciate the gravity of R-56, Vol RD-1
email the situation and look into the issues of
inadequate resource deployment for its
intimidate resolution so that the works
which are feasible even in rainy season
does not suffer and some progress can
be made at site.
7. 14.07.2017 Rains have started at site from 2nd half Pg. 55-56,
Claimant’s letter of May when water started rolling Annexure C-27,
down the hill to the site. Contractor’s Vol CD-1
suggestion of engaging dewatering
pump(s) and keep joint records of HP-
Hr. did not find nod from the engineer;
and now the whole site has become a
pool in 1st half of July 2017.
8. 24.07.2017 Respondent’s letter Pg. 106, Annexure
Respondent’s The aforesaid works could have been R-59, Vol RD-1
letter progressed well before start of rainy
season and even during rains some
progress in these works could have
been made.
9. Minutes of MOM: Pg. 58, Annexure
meeting held on Contractor mentioned heavy rains for C-29, Vol CD-1
04.08.2017 past 1½ months have also badly
affected the progress of work, bringing Pg. 128, Annexure
it to virtually a complete standstill. R-67, Vol RD-1
10. 11.08.2017 Claimant’s letter: Pg. 62, Annexure
Claimant’s letter The dry period from Oct, 2016 to May, C-31, Vol CD-1
2017 was lost in land availability. By
the time the land issue was cleared by
the engineer, full rainy season started
from May, 2017 which is continuing till
now (vide copy of DPR attached from
01.06.2017 to 03.08.2017).
11. 15.09.2017 Contractor mentioned heavy rains for Pg. 165, Annexure
Respondent’s past 2½ -3 months have badly affected R-88, Vol RD-1
email the progress of work, bringing it to
virtually a complete standstill. GM/AP
mentioned that contractor’s other site
arrangements like establishment of
laboratory/ casting of paver blocks /
design of pre fabricated sheds etc.
which were independent / unaffected
due to rains are also lacking behind the
schedule. The contractor mentioned
that as the rains have now started
receding they are committed to put in
extra efforts and shall makeup the
shortfall in progress in next two
months.
12. 23.10.2017 The existing ground where foundations Pg. 72, Annexure
Claimant’s letter of various buildings are to come up is C-34, Vol CD-1
still very much surcharged with water
and cannot even withstand the dead
weight of the Excavator itself. Not to
speak of the impact load, when it will
work. The contractor are afraid that,
though the rains have stopped, the
excavator may tend to sink, as it
happened in July 2017, if it is taken on
the existing ground, todo excavation
for foundations.
13. 31.10.2017 Respondent’s email Pg. 182, Annexure
Respondent’s The respondent stated that the R-94, Vol RD-1
letter monsoon has now receded compare to
in July when it was at its peak.
14. 03.01.2018 The respondent stated during monsoon
period, rainfall occurs at dawki only
intermittently.
15. 26.06.2018 The contractor mention that the Pg. 279, Annexure
MOM revised work program could not be R-136, Vol RD-2
achieved due to frequent rain and
water logging/stagnation at site.

You might also like