HIN Classification: Safety Main Element: Scaffolding Sub-Element: Misk City HSE
Standards
Despite issuance of Stop Work Notice (ARC-SWN-002, date: 08-02-2022) it is observed that Al Babtian allowed
the works (Use of scaffold) to be undertaken which is unacceptable as the transgressions noted on referred SWN
had not yet been completed and offered for approval. Also despite HINs (ARC-HIN-002 date: 02-12-2021, ARC-
HIN-016, date: 20-12-2021, ARC-HIN-033, date: 06-01-2022) and client HSE Manager instructions (email by Mr.
Roger Anderson dated: 04-01-2022), Al Babtain did not arrange necessary measures to ensure that all of the work
at heights and working platforms are safe for their manpower. Violating of MiSK City HSE Standards. Major Non-
Compliances and failures are following:
Page 1 of 3 MiSK HIN Template Rev 1. COPYRIGHT © JONES LANG LASALLE IP, INC. 2022. All Rights Reserved
HSE Improvement Notice (HIN / NCR)
Unsecured ladder and on ly one rung above the platform. No Unused scaffold stair access with tag on it. Should be red
sole board provided for the scaffold. tagged and must dismantle.
Al Babtain Project Manager instructed to comply the requirements of Stop Work Notice (ARC-SWN-002, date: 08-
02-2022) and HINs (ARC-HIN-002 date: 02-12-2021, ARC-HIN-016, date: 20-12-2021, ARC-HIN-033, date: 06-01-
2022).
- All scaffold erections and inspections by the competent personnel only. Submit 3 rd party certificates for the
scaffold erectors and inspectors.
- Provide approved RAMS for scaffolding works.
- Permits to be issued with approved RAMS, approved drawings and othere relevant approved documents
in place.
- Ladders must be secured with proper angle and 5 steps above the platform.
- Scaffold over soft ground must have sole board underneath.
- Scaffolds must be inspected by the scaffold inspector within the inspection time frame.
Relevant Project HSE Standards or Statutory HIN Assigned to:
Requirements which were not being followed:
Section 2 – Corrective Actions Proposed (to be filled out by Assignee and Agreed by PMCM)
Proposed Actions to correct deficiencies:
Are works temporarily suspended pending completion of the corrective actions? No ☒ Yes ☐