Job Safety Analysis (Jsa) - Water Proofing Work
Job Safety Analysis (Jsa) - Water Proofing Work
Emission,Dust (Skin and eye irritation, cough , Take required work permit(s)
minor breathing problems) Inspection of vehicles /machines
Ensure proper condition / paving of roof surface.
Proper PPE’s shall be provided to deployed works
men. (Hand gloves, nose mask, safety goggles)
1 TO 5
SL. ACTIVITY SUB-ACTIVITY Page 2
POTENTIAL HAZARDS CONTROL MEASURES REMARKS
NO. ( Elimination/ Substitution/Engg control/Administrative/PPE)
Mention briefly the aplicable control measures
3 Painting primer/ painting Fire hazards, explosion, dust hazard, eye Signboard shall be provided indicating full and empty
hazard, respiratory hazard, contaminated air containers.
(Personal Injury )
Precautions shall strictly be taken during painting as
per MSDS.
4 Bitumen Installation of bitumen Caught in-between hazards, Slippage of Use of leather hand gloves.
matetial , Entangling hazards, entrappment,
(Entanglement / Caught in-between may Do not throw material from top. Use ropes or
cause severe injury, disability ) material basket for lowering material.
Use full sleeves & use of leather hand gloves & full
long safety shoes/boots
High Surfaces bitumen; Handle hot mix with shovel or mechanical aid.
Working with hot mix (hand laying when
required i.e. unable to lay with paver); Hot Don’t touch or pick up bitumen with hands
bitumen (Contact with hot object may cause
severe burn injury) One man shall be dedicated to maintain and protect
to over heating of bitumen to control black smoke.
1 TO 5
SL. ACTIVITY SUB-ACTIVITY Page 3
POTENTIAL HAZARDS CONTROL MEASURES REMARKS
NO. ( Elimination/ Substitution/Engg control/Administrative/PPE)
Mention briefly the aplicable control measures
5 Heating Work Heating of bitumen for working temp. Toxic fumes, fire hazard (Personal Injury) Painters shall be fully protected and shall wear body
coveralls with suitable mask.
Application of bitumen Material spillage or falling hazard, burn Work Permit for lifting operations shall be obtained.
hazard (hand, foot) (Contact with hot object
may cause severe burn injury)
6 Material Lifting Lowering and Lifting of materials with Lifting equipment failure( failure of lifting colour coding to be ensure of lifting tools
crane equipment may cause injury/fatality
certified lifting tools shall be used.
Check the physical condition of lifting machines, tools
and tackles.
1 TO 5
SL. ACTIVITY SUB-ACTIVITY Page 4
POTENTIAL HAZARDS CONTROL MEASURES REMARKS
NO. ( Elimination/ Substitution/Engg control/Administrative/PPE)
Mention briefly the aplicable control measures
Ensure hook is having latch to prevent slings or load
from accidentally slipping off the hook. Hooks that
have cracks or have more than 15% in excess of
normal throat opening or more than 10% twist from
the plane of the unbent hook should be replaced .
hit by swing (worker may got injury.) Ground condition shall be checked.
Capacity (SWL) mentioned on lifting permit shall not
be exceeded.
The load shall be moved slowly and carefully.
Crane fall over ( Damage to Sling with adequate capacity and of no damage shall
property/equipment. Major injury/fatality) be selected.
1 TO 5
SL. ACTIVITY SUB-ACTIVITY Page 5
POTENTIAL HAZARDS CONTROL MEASURES REMARKS
NO. ( Elimination/ Substitution/Engg control/Administrative/PPE)
Mention briefly the aplicable control measures
Suspended load falling (Damage to Ensure top rails (950mm-1100mm) are provided on
property/equipment. Major injury/fatality) Roof/platform.
Use full body harness with double lanyards above
1.8m height.
7 work on Roof Work on Roof edge Fall of persons and fall of materials Display safety warning sign.
(unprotected edges)
Opening at height should be barricaded or covered
properly.
Display safety warning sign.
No loose materials near edge shall be allowed.
Openings (Fall of person / material may Ensure no work is conducted directly below the top
cause injury) works.
Person suffering from vertigo Bring the Man basket to the accident site and use it to
reach the suspended worker
Emergency Response Emergency during height work ( cause injury) Ensure that the Man basket has the load capacity for
both the rescuer(s) and the fallen worker. If the fallen
worker is not conscious, two rescuers will probably be
needed to safely handle the weight of the fallen
worker
1 TO 5
SL. ACTIVITY SUB-ACTIVITY Page 6
POTENTIAL HAZARDS CONTROL MEASURES REMARKS
NO. ( Elimination/ Substitution/Engg control/Administrative/PPE)
Mention briefly the aplicable control measures
Signatures:
Permit Issuer:
Supervisor: Permit Holder: VSS Champion:
Note : This format to be used for the non routine activities, which are being carried out occasionally & not listed in department's HIRA document
After the activity completed, the copy of this filled up format is to kept for future reference
1 TO 5