A Post-Byzantine Mansion in Athens

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

A POST-BYZANTINE MANSION IN ATHENS.

THE RESTORATION
PROJECT OF THE TIMBER STRUCTURAL ELEMENTS

Eleftheria Tsakanika - Theohari1, Harris Mouzakis2

ABSTRACT: This paper presents briefly the structural system, the pathology, the numerical analysis and the
restoration project of a post-Byzantine mansion in Athens, with timber floors and roof that rest on timber frame walls
and timber reinforced rubble masonry walls.

KEYWORDS: restoration, timber masonry reinforcements (ties, lacings), timber frame walls, fiber carbon bar, FCU.

1 INTRODUCTION 123 be reused. New transversal masonry arches were built,


the longitudinal North wall and the quite elaborate North
An important architectural monument of the Ottoman arcade in order to be constructed over them the 1st floor
period in Athens is under restoration since 2008. The of a new mansion which belonged to a prominent family
monument, a two-story mansion, is a rare example of the of Athens (Benizelo’s family) (Figure 3, phase 2).
post-Byzantine architecture in Greece, since it is the only During next centuries, several interventions changed the
building of this kind still standing in the area of Athens original mansion causing important architectural and
(Figure 1b, 2b). A preliminary study of this mansion in structural problems (Figure 3, phase 3). The North
the framework of a diploma thesis, was presented at the façade of the upper floor was closed (Figures 1a, 1b) and
International Timber Engineering Conference in London, new internal timber walls were built at the 1st floor since
in 1991 [1]. the building was divided in 2-4 independent properties.

Figures 1a, 1b. The North facade of the building before Figures 2a, 2b. The South facade of the building before
and after restoration works. and after restoration works.

2 DESCRIPTION OF THE BUILDING The timber projection, the so-called “sahnisi”, that
existed at the center of the South facade was demolished
2.1 GENERAL INDORMATION and the gap was closed with rubble masonry. Almost all
It is a rectangular building, of general dimensions nearly the original openings (windows and upper course
23.0×9.40m. The South longitudinal rubble wall and the windows) were closed and new ones were opened in
three internal transversal walls of the ground floor different positions (Figures 2a, 2b).
belong to an older building or buildings (Figure 3,
phase1). During 17th or 18th century these walls were 2.2 THE LOAD BEARING STRUCTURE OF THE
demolished till the level of the existing floor in order to MANSION
The masonry walls of the ground floor (55-60cm wide),
1
Eleftheria Tsakanika - Theohari, School of Architecture,
and the arcades (35-40cm wide), were made of a three-
National Technical University of Athens, Patision Street 42, leaf rubble masonry with clay mortar.
10682 Athens, Greece. Email: eletsaka@central.ntua.gr. On the contrary, only two walls of the upper floor were
2
Harris Mouzakis, School of Civil Engineering, National made of rubble masonry. They had a lot of openings
Technical University of Athens, Heroon Polytechneiou 9 quite close to each other, reinforced with horizontal
15700, Athens, Greece. Email: harrismo@central.ntua.gr.
N
N
phase 1

phase 2

phase 3

Figure 3. Ground floor plan (before restoration works), Figure 4. Plan of the architectural proposal for the 1st
showing the different phases of the building. (G.Kizis, K. floor, (G.Kizis, K. Aslanidis, Ch. Pinatsi).
Aslanidis, Ch. Pinatsi).

timber elements4, embedded in 5 levels, as it can be


seen at the East wall (the only wall that was saved
intact), giving important information for the architecture
and for the original structural system of the building
(Figures 5a, 5b). At the South wall the original timber
reinforcing system was destroyed after the changes
during the last centuries and it could be located only by
its remnants (Figures 2a).
The 1st level of timber ties exists at the top of all the
walls of the ground floor. The 2nd level exists at the Figures 5a, 5b. The East wall before and during
level of the sill of all windows, the 3d at the middle of restoration works [1].
the stone piers between the windows, the 4th exists at the
level of the lintel and the 5th at the top of the rubble
masonry walls of the upper floor. (Figures 5a, 5b, 6a).
The timber reinforcing system is actually a horizontal
grid embedded in masonry. It is composed of double
longitudinal timbers (16x7cm each), placed at the inner
and outer face of the rubble walls, connected through the
thickness of the wall with smaller transverse timbers
placed over them, every 80-100cm. The connection
between longitudinal and transverse timber elements is
ensured by a vertical nail. (Figure 6b). The transverse Figures 6a, 6b. Typical construction of the horizontal
timbers do not exist at the levels of the floor and the roof timber reinforcing system embedded in the masonry wall.
since in these cases the connection of the longitudinal When the stone piers are in close distances, the timbers
timbers is accomplished with the beams of the floor and at the level of the lintel can be continuous (6a).
the tie-beams of the roof. As the length of timber
elements is smaller than the length of the building, the of plane induced forces, the confining effect (Figure 6a)
connection of the longitudinal timbers along the wall, that is provided at the stone piers between the openings
very important for the continuity of the system, is made [4], are briefly some of the structural beneficiary for the
by a plain scarf joint and one or two nails (Figure 6b). masonry features of this system, especially for seismic
The structural role of the embedded in masonry actions [3, 5, 6].
horizontal timber reinforcements is multiple. The tying The rest of the upper floor was consisted of a timber
of the buildings in several levels as a continuous colonnade at the main façade (Figure 1b) and two types
belt, the tying of the floors and roofs to the walls, the of timber frame walls filled with solid bricks and lime
reinforcement of the connection of the walls at different mortar. Type 1 timber frame had a lot of openings and
levels along their height, the connection of the outer and consequently few diagonal members (Figures 7,8,9a,b),
inner leaf of the masonry walls, the improvement of the while type 2 had few openings and many diagonal
tensile and bending strength of the brittle (by nature) members (Figure 9b, 13c, 23a). In both types, the main
masonry working as reinforcement for in plane and out load bearing system of the frame was composed by
vertical timbers (14x14cm) connected every 70-160cm
4 with two horizontal beams-beddings (14x14cm) at the
Different names of the horizontal timber reinforcing system
of the masonries are : “timber ties, ring beams, or lacings”,
level of the floor and at the level of the roof. The
“hatil”, “cator and cribbage” constructions [2], “ιμάντωσις” connection of the vertical posts to these horizontal
in ancient Greek and “ξυλοδεσιά” in modern Greek [5]. timbers was accomplished by a round tenon of about
6.0cm diameter. The same construction detail was used only on the outer walls, as king post trusses do, but
for the connection of the posts of the timber colonnade mainly on the internal ones (Figures 10,11)5.
of the façade to the beams at the upper and lower part
(Figure 1a). All other vertical and horizontal timbers 3 PATHOLOGY
had smaller sections (7x12, or 6x13cm) and their joint to
each other and to the vertical posts, was in most cases The main structural problems of the building were:
made through shallow grooves and an iron nail. The • The destruction of the continuity of the rubble walls
diagonal timbers were connected just with one iron nail along with the destruction of their horizontal timber
(Figure 22). reinforcing system, due to the interventions of the 19th
The timber frame walls where originally tied to the and 20th century that changed the position of the
masonry stone walls of the upper floor by nails that openings. During the same interventions some parts fof
connected their last timber post with the embedded in the the timber frames were destroyed too (Figures 2a, 7).
stone wall, horizontal timbers (Figure 13c,e). The • The low quality of the rubble walls (three-leaf stone
conscious attempt of the builders to use this timber masonry with small stones and clay mortars).
system in order to reinforce and tie efficiently the • The low quality of the lime mortar used for the brick
“vulnerable” upper floor which is composed of infill of the timber frame walls, the lack of contact of this
differently constructed vertical load bearing systems filling with the surrounding timber elements and the gaps
(timber colonnades, timber frames and stone masonry (loose of contact) at the joints of the timber members
perforated from openings) with various strength and (Figures 9b, 12b, 22).
stiffness properties, is obvious. It must be mentioned
though that the rubble walls and arches of the ground
floor were not connected to each other since they were
built in different phases (Figure 3, phases 1, 2).
All the walls (masonry and timber ones) were covered
with plaster.

Figures 9a, 9b. Timber frame walls before and during


restoration works.

• The excessive deformation of the roof located at the


central south part, due to the small section of the
longitudinal beams that supported the rafters at the
middle of their span. (Figures 10, 11, 19a).
Figure 7. Longitudinal section showing the type 1 timber
frame of the 1st floor before restoration works. The • The bending failure of the main horizontal beam on
original openings were closed and a part of it was which the central part of the roof was resting on (Figures
destroyed due to the changes of the last centuries [1]. 11, 20a, 20b). As mentioned before, the loads from the
roof are transferred at the outer walls of the building, but
mainly at the internal longitudinal timber frame and the
beam (19x23cm) which spans the opening that exists at
the centre of the building. (Figures 8, 10, 14). It is
interesting to be noted, the intelligent solution which the
constructors of the roof invented in order to reduce the
vertical loads transferred on this beam. The longitudinal
timber at the ridge of the roof is supported by posts,
every ~1.80m (see Figure 10, Φ1), except in the area
over the beam (Φ2), where the posts are replaced by two
Figure 8. Longitudinal section showing the proposal for diagonal timbers. These timbers transfer the loads at the
the restoration of the timber skeleton. (based on drawing supports of the beam under which the corner posts of the
of G.Kizis, K. Aslanidis, Ch. Pinatsi). timber frame walls exist, reducing the bending stresses
on the beam. It seems that this was not enough since
The load-bearing structure of the floor was made of finally a bending failure occurred.
simple supported timber beams, placed every 40cm, • The out of plain deformation of the longitudinal
connected to the rubble masonry under them through the South stone masonry of the 1st floor (about 30cm!),
horizontal timber ties on which they were nailed on. mainly due to seismic action. The wall was kept in that
The roof is a typical example of the “post and beam” deformed position due to an old retaining scaffolding
system, a quite common type of roof in Byzantine and (Figure 2a, 13a,b) which stopped working some months
post Byzantine buildings in Greece and other countries
around Eastern Mediterranean. It’s main structural 5
For more details concerning the description, the pathology
characteristic is that the vertical loads are transferred and the structural behavior of the “post and beam” system and
from the closely set rafters (every 40-50cm), through a of this specific roof, see [7].
three-dimensional system of beams, posts and struts, not
before the restoration project starts. As a result, the
central part of the wall collapsed (Figure 13b).
Thankfully, most of this part would be demolished
anyway since it was built in the place of the original
timber projection “sahnisi” (Figures 2b, 14). It is worth
to be noted, that the rigidity of the transverse timber
frame walls of the upper floor which were nailed at the
a b
timber ties of the South stone wall, was tested on site,
since the seismic event/s that caused the detachment of
the South masonry left no damages or deformations on c d
30cm
the timber frames. The detached nails from the deformed
masonry wall could be seen clearly (Figure 13e). Transverse timber frame
wall (type 2)
e

Figure 10. Transverse and longitudinal section of the Figures 13a,b,c,d,e. The South masonry wall before
roof [1]. restoration works (deformed out of plain and collapsed).

4 METHODS OF ANALYSIS AND


NUMERICAL MODEL
A detailed finite element model was developed for the
numerical investigation of the seismic response of the
monument, using linear analysis. The numerical analysis
was performed using the ABAQUS software and shell
finite elements.

Figure 11. Three-dimensional finite element model of the


roof. The numerical analysis verified the local structural
problems.

• The building remained exposed to the weather for


Timber projection (“sahnisi”)
several years and all the plaster from the walls was
removed due to an unfinished restoration project
(Figures 1a, 2a, 9a,9b, 12a,b,c, 18a). As a consequence,
many of the timber elements of the roof, the floor and
the external timber columns of the main facade suffered
a lot from decay, but not from insect attack since the
infestation that had occurred in the past was not any
more in progress.

Figure 14. Geometry of the numerical model of the whole


building as it would be restored (phase 2).

The geometry of the numerical model (Figure 14),


included all the architectural details of the 2nd and main
Figures 12a, 12b, 12c. Decayed timbers at the timber phase of monument, as it would be restored. In this
façades and the roof. Figure, the rubble masonry walls are shown with green
color, the timber frame walls and timber columns are acceleration is 0.16g for seismic events with a return
shown with blue color. period of 475 years and 0.21g for a return period of
The seismic vulnerability derived from the absence of around 1000 years (corresponds to an importance factor
connections between walls built at different periods or of 1.3). The response spectrum method was used for the
walls built with different structural systems (masonry seismic excitation of the structure for damping ζ=5% and
and timber frame walls) was taken into account in the soil category B (TΒ=0.18sec and TC=0.60sec).
model using spring elements (Figure 14, red color). The The natural modes of the structure were calculated and
soil under the footings was taken into account in the the corresponding eigenperiods were compared to the
model with the depth of 5m in order to describe the soil- results from ambient vibration measurements of the real
structure interaction effects. The soil was modeled as structure.
elastic material with Young’s modulus E=12.25MPa and In Figures 15 and 16 the minimum and the maximum
Poisson’s ratio v=0.25 according to the results of the principle stresses that were developed on the masonry
geotechnical investigation and it was considered walls are presented respectively, while in Figure 17 the
massless in order to prevent stationary waves. relative displacements of the structure along X direction
The walls were assumed elastic with properties are depicted for triaxial earthquake.
depending on the different construction types. For the
determination of the mechanical properties of the
masonry, the method of homogenization was applied.
The stiffness of each composite timber frame wall with
infill of mud bricks was determined from the analysis of
a standalone finite element model. Afterwards these
composite walls were incorporated into the model of the
monument with the use of equivalent shell elements. The
timber posts of the main façade were taken into account
as hinged beam elements constrained in plane by the
compact baluster which was also taken into account in
the model even though it is a non load bearing element. Figure 15. Minimum principle stresses – General view
The roof was analysed by a separate 3D linear finite (combination g + q ± E).
element model (Figure 11). The reaction forces of the
roof and the floor were applied on the finite element
model of the whole structure and their deformable
diaphragmatic action was taken into account using shell
elements.
Linear elastic analysis was applied for the investigation
of the seismic response of the structure and for the
assessment of the effectiveness of the strengthening
measures. This approach is qualitative since linear elastic
analysis is not realistic when the developed stresses
exceed the tensile strength of the masonry.
Elastic analysis cannot predict directly the real forces
that will be developed to the horizontal timber Figure 16. Maximum principle stresses – General view
reinforcement and the stone part of the masonry, since (combination g + q ± E).
initiation of cracking leads to the redistribution of the
stresses. Nevertheless, the positive effect of timber ties
on the seismic behavior of masonry structures was taken
into account for the proposed interventions, and
consequently for the evaluation of the results of the
numerical analysis too, estimating the forces of the
embedded timber reinforcements assuming that the
tensile strength of the masonry is zero6.
According to the Greek Seismic Code, Athens belongs to
the seismic zone I, in which the effective peak

6
[4], Vintzileou 2008, 970. “The experimental work presented
in this paper has proven that timber ties act as confining
reinforcement for masonry in compression, thus, enhancing its Figure 17. Relative displacements of the structure along
compressive strength and, much more important, enhancing its X direction for triaxial earthquake.
deformation at failure. Furthermore, it was demonstrated that
timber reinforced masonry may sustain substantially higher Taking into account the beneficial effect of the timber
shear load than plain masonry; it can also undergo large shear reinforcements, and that the maximum tensile strength of
cracks without disintegration. These results seem to be in
the masonry walls several months after the application of
accordance with the observations made on historic buildings”.
the pozzolan-lime injections, will reach 300kPa (see
6.5), it is evident that the value of the tensile principle elements (materials and systems in most cases reversible
stresses are over the above limit at few and small areas and compatible with the existing ones), avoiding cement
and consequently there is no danger for the integrity of or reinforced concrete.
the structure. The minimum compression principle stress • Preservation as much as possible of the authentic
(500kPa) is lower than the compression strength of the material (e.g. minimization of replacements of timbers)
masonry wall after the injections. using simple techniques in combination with more
The forces that were developed on the springs (Figure sophisticated ones [8]. In all cases, the new timber pieces
14), were used for the designing of the steel elements can be easily distinguished from the old ones.
that were used for the connection of the different wall A brief description of the most important structural
systems along their height (see 6.6.1). interventions is following :
The maximum developed acceleration at the level of the
roof was 1g, considering the roof as an appendix. This 6.1 ROOF
value was used for the design of the steel rods that were Concerning the reinforcement of the connections which
used to connect the roof through the timber ties to all most of them work in compression instead of tension, the
load bearing walls of the building (see 6.6.2) use of screws, bolts and timber wedges, can secure the
joints while the loads can be transferred through the
5 DIAGNOSTIC METHODS simple contact of the members without the need of
special cuttings. One of the most problematic joint of the
The diagnostic survey was made by a multi-disciplinary roofs is the connection of the rafters to the tie beams,
team (architects, engineers, conservators, technicians), in because of the decay problems that occur usually in that
order to be determined the condition of all the timber area. In “post and beam” roofs, the axial forces of the
elements, load and non load bearing ones [7]. Various closely set rafters (every 45cm), are quite small and their
methods were used : ultra-sound, resistograph, along joints to the tie-beams at the external walls, carry less
with the visual examination by the engineers and mainly loads compared to the loads that usually have the king-
the craftsmen and the conservators that had the post trusses at the same joint [7]. In some cases, as
opportunity to work on the material. All the above numerical analysis verified, these forces can be
diagnostic procedure provided the necessary transferred by 2 screws (6-10mm in diameter) without
documentation for saving timber elements that otherwise taking into account the contribution of the cuttings. In
could have been replaced with new ones. the cases though that new timbers have to substitute the
The examination of timber samples taken from different decayed parts, the formation of the connections can be
structural elements, proved that the wood species of the made using simple methods and not necessarily
existing timbers was pine7. specialized personnel (Figures 18a,b,c,d).
The systematic measurements of the moisture content of
the existing timbers, was about 9-11%. The knowledge
of wood moisture content was important because it is a
limiting factor for the development of fungi and wood
boring insects. Besides that, the new members and parts
of members that were going to be used should be of the
same species of wood and have almost the same
moisture content with the existing ones in order to have a b
similar structural and hygroscopic behavior. This was
extremely important for new timbers that substituted c d
decayed parts (wooden prosthesis) especially in areas, as
the timber colonnade at the main façade, where the
moisture content of the environment and consequently of
the timbers has many and often fluctuations.

6 STRUCTURAL INTERVENTIONS
The main principles concerning the restoration of the load
bearing elements of the building were the following :
• Preservation of the original and authentic structural
system, even if it is not visible after the restoration
works. Figures 18a,b,c,d. Intervention proposal (18a) and
• Reinforcement of the original structural system due different ways that the decayed part of the rafters and the
to the fact that the building is located in a seismic area tie-beams was substituted.
and its use will change (an old mansion will become a
museum, which means high level of safety for the As mentioned in pathology, the numerical analysis of the
building and visitors), using mainly timber and steel 3d model of the roof showed that the section of the
longitudinal beam at the middle span of the rafters was
7
Anastasia Pournou, Department of Conservation of
inadequate. The proposed solution was the addition of
Antiquities and Works of Art, Technological Educational new struts (more dense supporting) (Figures 19a, 19b), an
Institute of Athens, Greece.
easy to apply and reversible intervention in order to
maintain the original beam at its position.

Figures 19a, 19b. View of the deformed beam at the


middle span of the rafters (19a) and its reinforcement by
adding new timber struts (19b).

The main timber beam at the central part of the roof was
reinforced with carbon fibres tissues (FCU500/200) due
to bending failure (see also pathology), (Figures 20a,b). a c

e d

Figures 21a,b,c,d,e. Different ways of substituting the


Figures 20a, 20b. Bending failure of the main timber decayed parts of posts of the main façade and of a post
beam at the central part of the roof (20a). Reinforcement belonging to a timber frame (21d).
of the beam with carbon fibres tissues (20b).
diameter of the carbon fiber bars gave the opportunity to
6.2 FLOOR have the needed strength and the minimum distances
The existing timber floors were replaced because of their from the edges of timbers with small section, (15x15cm)
bad condition ,with new timber ones (beams and planks (Figures 21b, 21c) .
3cm thick). As mentioned before, simple techniques (Figures 18)
were used in combination with more sophisticated ones
6.3 TIMBER COLLONADE OF THE MAIN depending on the importance of the architectural and
FACADE structural role of each member, its pathology, its
The posts of the main façade of square section position, and the economy. For example, the connection
(15x15cm) were severely decayed especially at their of the post in Figure 21d was made just with a timber
lower part (Figures 1a, 12a). In order to save as much as tenon and epoxy resin, while the connection of the posts
possible of the original material, the method of wooden that belong to timber frame walls (Figure 21d), was
prosthesis was used. The decayed parts, were removed accomplished by the suitable formation of the ends of
and they were replaced with new timber pieces of the the two pieces, the use of stainless bolts and some times,
same wood species (pine) and of the same moisture not always, the use of epoxy resin at their contact area.
content with the old ones (Figures 21a-d). The geometry
of the ends of the connected timbers was decided not to 6.4 TIMBER FRAME WALLS
be the same for every post since their decayed parts were • Reinforcement of all timber connections using at
different. As a consequence, the final connection for least 2 stainless steel screws of 6mm diameter9 and
each post was decided after the decayed part was timber wedges in order to reestablish the contact of the
removed and the anaglyph of the sound part was timber members, where ever was needed. Two types of
revealed. For the most difficult cases the connection screws were used : type 1 with only a part of the shank
between the old and the new timbers was accomplished threaded and type 2 with a shank fully threaded
with carbon fiber bars (8mm in diameter) fixed 50cm at (Figure 22). Type 1 screws were used in the cases that a
each piece with a bi-components epoxy resin8. The small better contact of the timbers had to be assured, since
8
The accuracy of the work, and the specialized knowledge
needed for using sensitive epoxy resins dictated after several
9
tests with carpenters, the use of specialized in wood Screws with diameter more than 6mm were causing splitting
conservators with knowledge of carpentry under the at the existing (old) timber elements, as the tests on site
supervision of the engineers. showed.
type 2 screws though they work better for tensile forces, For the same reason over the straps, a stainless mesh
they keep the distance of the connected members steady. attached by nails was used too (Figures 28b, 28c).

6.5 RUBBLE MASONRY WALLS REINFORCED


WITH HORIZONTAL TIMBER ELEMENTS
• Consolidation and reinforcement of the rubble walls
using premixed, cement free, pozzolan-lime grout for the
injections, for the mortars and for the rejointing.
• Preservation of the existing timber reinforcing
system of the rubble walls of the 1st floor at the areas that
the decay was superficial (Figure 5b, East wall).
• Reconstruction of the timber reinforcing system of
the South wall in places that the masonry had to be built
Figure 22. Reinforcement of all the timber / timber again in order to be restored the original façade of the
connections of the timber frame walls using timber South wall12 (Figures 2b, 6a, 6b, 24a). The
wedges and two types of steel screws. reconstruction of the timber reinforcing system was
necessary too in some places at the level of the roof and
• Reestablishment of the contact (wedging) between the floor due to decay problems (Figures 30a, 30b).
the brick infill and the surrounding timber elements, • Reinforcement of the original connection of the
using premixed, cement free, pozzolan-lime mortar. The longitudinal timbers along the wall, using additional
same mortar was used for the reconstruction of the brick stainless steel metal plates and screws (Figure 24b).
filling in the areas that the timber frame or the infill was
destroyed from previous interventions (Figures 23a,b).

Figures 23a, 23b. Timber frame walls during restoration


works.
a
• Reinforcement of the overall behavior of the timber
frame walls with an embedded in the plaster mesh of
stainless10 steel, nailed every 20-30cm on the timber
elements of the frame and occasionally at the mortar of
the brick wall. The use of the steel grid was necessary b c d
for avoiding cracks at the plaster of a composite wall,
made of materials (timber and bricks) with different
physical and mechanical properties. Furthermore, its use Figures 24a,b,c,d. View of the South wall (24a).
can improve the in-plane and out-of plane seismic Reinforcement of the longitudinal connection of the
timber ties by steel plates and screws (24b). The window
behavior of the timber walls without changing their
frames were nailed to the timber reinforcing system of the
stiffness properties 11. wall using timber wedges (filling the gaps) (24c) and
• The timber skeleton of the projection “sahnisi” that screws (24d).
existed at the central part of the South wall (Figure 1b),
was reconstructed according to the architectural study, • Reinforcement of the rubble masonry around the
without filling, covered with plywood in both sides perimeter of the openings increasing the section of the
(Figure 28a). In order the cohesion of the plaster to be timber frames of the windows and the shutters, placed in
increased, straps of plywood (20mm wide and 9mm outer and inner face of the walls, from 8x8cm to 8x13cm
thick) were nailed every 20mm on the plywood sheets. (Figure 24c). Their connection (their “sewing”) with
10 several screws to the timber reinforcing system of the
The steel mesh had to be stainless because the mortar and the
wall at the level of the lintel, the level of the sill and at
breathable ready-mixed plaster used for the timber frame walls
was free of cement, consisted mainly of hydraulic asbestos. the middle height of the piers (Figure 24d), provide
11
The brick infill plays a significant role on the overall load
12
bearing capacity of the timber frames. This role is not easy to According to the architectural proposal, all the external stone
be estimated through numerical analysis without experimental masonries and all the internal ones at ground floor should be
data which till now are unfortunately few, taking also in left without plaster and the wood species of their timber
account the variety of the structural systems. (e.g. Santos 1999, reinforcements should be oak (a more durable species) instead
Cóias e Silva, Vítor 2002, Ceccotti et al. 2006 [9]). of pine.
additional confinement to the surrounding stone piers
and consequently increase the strength of the
surrounding masonry wall. The connection and
interaction of secondary or non structural members (e.g.
window frames) with the main load bearing system, has
to be evaluated too even if it is hasn’t been taken into
account in the numerical models. Their contribution to
the overall behavior of the building may be important,
especially as a second line of defence against a strong
seismic event [6].
Figures 26a, 26b. Plywood sheets were used between
6.6 INTREVENTIONS CONCERNING THE the horizontal tie-beams of the roof and the boards of the
OVERALL BEHAVIOR OF THE BUILDING ceiling.
In order to improve the seismic behavior of the building
the following measures were taken:

6.6.1 Reinforcement of the connection of the walls in


vertical plane
The built in different phases
longitudinal and transversal walls of
the ground floor were connected
with stainless steel rods (d=20cm)
every 80-100cm, fixed in masonry
with non shrinkage cement mortar.
At the level of the floor the arches
were connected to the South wall
using steel bars anchored in steel
angles screwed at the timber ties.
The longitudinal and transversal timber frame walls Figures 27a, 27b. Connection of last timber post of the
were connected to each other using stainless bolts or timber frame walls with the longitudinal timbers
screws (d=12cm) every 80cm along their height. embedded in rubble wall (red dotted lines), using carbon
The rubble masonry walls of the 1st floor were connected steel screws (system WT).
with the timber frame walls using :
- carbon steel screws (system WT, d=8cm) driven from
the last timber post to the horizontal ties of the masonry
(as the original connection was) (Figures 27a, 27b).
- stainless steel plates and steel fasteners (bolts and
screws) connecting the last timber post, the transverse
elements of the timber ties of the masonry and the last
post of the new timber skeleton of the timber projection
(Figure 28b). As mentioned before, the steel rods were
designed in order to withstand the forces that were
developed on the springs used at the numerical model for Figures 28a, 28b, 28c. The connection of the timber
the connection of the different wall systems. frame walls with the South masonry wall was improved
by the use of the steel plates and the steel mesh that was
6.6.2 Connections of the walls with the floor and the applied on both new and old timber frame walls.
roof (horizontal plane)
The reinforcement of the diaphragmatic action of the (almost every 40-50cm) horizontal beams of the roof and
timber floor was not proved by the numerical analysis to the floor were screwed on (Figures 30a,b). The
be necessary, since at the ground floor there are several horizontal beams of the roof were connected with the
transversal walls (massive or arched) in close distances same way on the upper beams of the timber colonnade
2.70-4.70m improving the out of plane behavior of the and of the longitudinal timber frame wall of the upper
longitudinal walls. On the contrary, at the upper floor floor. These beams were connected with the transversal
where less transversal walls exist, the addition of timber frame walls too (external and internal ones), with
plywood sheets between the horizontal tie-beams of the additional timbers and bolts.
roof and the boards of the ceiling (Figures 26a, b) was Special care was taken for the connection of the timber
considered necessary in order to improve further the ties to the walls under them in order the seismic forces to
diaphragmatic action at that level even though the be transferred from the horizontal to the vertical load
existing roof was quite stiff in space because of its bearing systems. At the level of the floor, the connection
structural system and its geometry [7]. The connection of the timber ties was accomplished using stainless steel
of the floor and the roof with the rubble walls of the rods of 12mm diameter every 80-100cm, fixed slightly
building was accomplished using the existing inclined in the masonry with non shrinkage cement
horizontal timber system of ties on which the closely set mortar. (Figure 30b).
authenticity of the “invisible” in many cases load bearing
system.

ACKNOWLEDGEMENTS
Figure 29. Authors wish to thank the Archdiosece of Athens for
The connection of the supporting the study and the restoration project, the
original timber tie with Hellenic Ministry of Culture, the construction company,
the wall at the level of and mainly the conservators and the craftsmen that made
the roof was not this restoration work possible.
adequate. Architectural design: G. Kizis, K. Aslanidis, Chr.
Pinatsi. Structural design: E. Tsakanika, H. Mouzakis,
E. Zarogianni. Supervision of restoration works: E.
Tsakanika, V. Tsouras.

REFERENCES
[1] S. Lazouras, E. Tsakanika. A Traditionally Built
House of the 16th Century in Athens. In
International Timber Engineering Conference,
pages 3.550-3.556, London 1991.
[2] R. Hugues. Hatil Construction in Turkey. In
International Conference “Earthquake Safe”
Lessons to be learned from traditional
Figures 30a, 30b. Connection of the new timber ties at
construction”, Istanbul 2000.
the corner of the roof with half-lap joint secured with
screws. The transverse timber pieces under the
[3] P. Touliatos. The box framed entity and function of
longitudinal timber ties can be seen too (30a). the structures. The importance of wood’s role, in
Connection of the timber ties at the level of the floor with Conservation of Historic Wooden Structures. In
the masonry wall by stainless steel rods (30b). International Conference «Conservation of
Historic Wooden Structures”, vol.1, pages 52-64.
For the design of the steel rods (see chapter 4). At the Florence 2005.
level of the roof except the above steel rods, an [4] E.Vintzileou. Effect of Timber Ties on the Behavior
additional measure was taken. Transverse timber of Historic Masonry. Journal of Structural
elements were embedded in masonry under the Engineering, Volume: 134, Issue 6, 961-972, 2008.
longitudinal beams, connected to each other by a screw [5] National Technical University of Athens / Earth-
of 8mm diameter (Figure 30a). This system of anchorage quake Protection and Planning Organization EPPO.
could be used in cases were no metal rods are available. “Investigation of timber reinforced masonry.”
The use the transverse timbers improves the connection Research Rep., E. Vintzileou, P. Touliatos, and E.
of the two faces of the three-leaf masonry and the Tsakanika, eds. in Greek, 2005.
collaboration and cohesion of the timber grid with the [6] E. Tsakanika, Methodology concerning the
surrounding masonry (a kind of mechanical anchorage in restoration of Historical Buildings. Case studies :
the wall). The Turkish Mansion and the Hagi Mehmet Aga
Mosque in Rhodes. In International Conference
7 CONCLUSIONS «Conservation of Historic Wooden Structures”,
vol.2, pages 194-203, Florence 2005.
The positive effect of the timber reinforced or the timber [7] E. Tsakanika. Byzantine and Post-Byzantine
based load bearing systems (horizontal and vertical ones) Historical Timber Roofs in Greece. Typical
on the seismic behavior of historical structures, is proven failures, misunderstanding of their structural
in several cases all over the world for thousands of years. behaviour, restoration proposals. In ICOMOS 16th
Quite a lot of work has been done concerning their International Conference «From Material to
typological and architectural features but less work, Structure», Florence 2007.
mainly in a qualitative way, has been done on their [8] C. Bertolini, P. Touliatos, N. Miltiadou, N.
constructional and structural features. Delinikolas, A. Crivellaro, T. Marzi, E. Tsakanika,
A better understanding of this kind of structures based O. Pignatelli, G. Biglione. The timber roof of Hagia
also on experimental and analytical investigations Paraskevi Basilica in Halkida, Greece: Multi-
(qualitative way) is very important too, since relative disciplinary methodological approach for the
research works are very few especcially if one takes into understanding of the structural behaviour. Analysis
account the variety of the structural systems. and diagnosis. In International Conference «From
The multi-disciplinary team that should work on a Material to Structure», Florence 2007.
restoration project, must have the necessary tools to [9] A. Ceccotti, P. Faccio, M. Nart, C. Sandhaas, P.
evaluate the existing condition of a historical building Simeone P. Seismic Behaviour of historic timber
and moreover to select the proper interventions using frame buildings in the Italian dolomites. In
innovative and/or simple techniques that will save the ICOMOS, 15th International Symposium, Istanbul,
authenticity of our architectural heritage, including the 2006.

You might also like