Retained 

Logic / Out of Sequence Progress 

Original Plan 

Retained Schedule Logic (Acceptable) 
 

 
 
Progress Over‐Ride Logic (Unacceptable) 
 

 
 

When using progress over‐ride the logic will be ignored hence the term progress over‐ride. As you can see from the 

BEFORE the studs are complete. THIS IS 
example above using progress‐overide will permit the drywall to finish 
IMPOSSIBLE.  

 

Project CPM Scheduling | 1
©2010 M.C. Dean, Inc 
Retained Logic / Out of Sequence Progress – (continued) 
 
The CPM network is updated as of the Data Date. In the example below the Data Date is work day 151.    
 
Activity A has started, but as of the Data Date the activity is estimated by the superintendent to require an 
additional 5 work days (WD) to complete.  
 
Activity B has started out‐of‐sequence relative to its planned Finish‐to‐Start relationship with Activity A.  It is 
also estimated by the superintendent to require an additional 5 WD to complete after activity A has finished.  
 
Note that historical information (actual dates) are not included in the forward or backward pass calculations.  
 
 
When using the retained logic setting the relationships remain in effect  
 
 
 
  Data Date = 151
 
  EF= 155
 
Activity A  RD = 5wd
  151 + 5 ‐1 =155 
 
Dashed line is 
 
implied not 
 
FS Relationship  graphically shown 
 
 
 
EF= 160 
 
  Activity B  RD = 5wd 156 + 5 ‐1 =160
 
 
 
 

 

Project CPM Scheduling | 2
©2010 M.C. Dean, Inc 