WBS - Master Project Schedule
WBS - Master Project Schedule
WBS - Master Project Schedule
QUDOS Project
Level 2 Level 3 Duration 2015 2016 2017
Date Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Key Project Milestones 660
4 Procurement 150
Procurement Strategy Complete 15
Procurement of MEP Long Lead Items Start
5 Construction 450
1 Preliminary: Site & sale office, facilities, mockup villa, apartment 45
Mock-up villa, apartment 120
Villas Complete 300
Apartments Complete 360
Hotel/Retail Complete 405
Landscape, Site facilities Completion 240
2 Sub-structure of Hotel and Apartment
3 Super-structure of Hotel and Apartment
4 Finishing and Fitout Hotel
5 Finishing and Fitout Apartment
6 Loose furniture and Equipment for Hotel
7 Loose furniture and Equipment for Apartment
8 Structure of Villa
9 Finishing and fitout of villa
10 Loose furniture and Equipment for Villa
11 MEP for Hotel and Apartment
12 MEP for Villa
13 C&S for Infrastructure
14 MEP for Infrastructure
15 Landscaping
16 Swimming pool
17 Public and Facilities
Date Date
Preparation Approve