Prelim Exam - Summer 2022 Marks - 70
Subject - IEQ
Year - TYME
Marks

1)Attempt any FIVE of the following: 10


a) Enlist various QC tools.
b) State the types and location of display
c) Define method study & state its objective.
d) Define TQM.
e) What is quality of conformance.
f) State the merits of acceptance sampling.
g) What do you mean by process planning? State its significance.

2)Attempt any THREE of the following: 12


a) Differentiate between Inspection and Quality Control.
b) Define the process chart & draw the symbols used for process chart.
c) Apply ergonomics aspect for designing Lever for Hand Press machine.
d) Describe ‘Part Print Analysis’ with suitable example.

3)Attempt any THREE of the following: 12


a) List down eight important steps for planning a process for a product from raw
material to finished product in an industry.
b) Explain in brief different “Recording Techniques” used in method study.
c) Prepare a Two handed process chart for a task of sharpening the pencil
with appropriate process chart symbol.
d) What is Six Sigma - Definition and Meaning? State Significance of six
sigma.

P.T.O
22657 [2]

Marks

4. Attempt any THREE of the following: 12


a) State the meaning of “Quality of design” & “Quality of Conformance”.
b) Explain the ‘cost of quality’ & ‘value of quality’.
c) Why allowances are considered while calculating standard time.
d) State the advantages & dis-advantages of combined operations.
e) Write different steps to be followed for ergonomics considerations
in machine design.

5. Attempt any TWO of the following: 12


a)

Calculate the standard time for the activity which consists of three
elements. The various allowances are given as percentage of the
normal time.
b) Draw and explain Histogram, Pareto chart and Scatter diagram.
c) Outline appropriate process chart for the activity “replace old battery
of car”.

6. Attempt any TWO of the following: 12


a) The following table gives the no. of defects in alignment observed at
the final inspection of a certain model of an car, prepare C-chart and
comment on it.
Car Number 1 2 3 4 5 6 7 8 9 10 11 12 13

No.of defect 7 6 6 7 4 7 8 12 9 9 8 5 5

b) Draw the X-R control chart and explain the following terms on it.
i)Extreme variations
ii)Shift
iii)Indication of trend.
c) Draw a neat labeled sketch of O.C. curve. State the procedural
steps of construction of O.C. curve.