11kV switchgears week 17/2022 Schedule

23/04/2022 24/04/2022 25/04/2022 26/04/2022 27/04/2022 28/04/2022


SATURDAY SUNDAY MONDAY TUESDAY WEDNESDAY THURSDAY

Station Mastan Addur PS (220kV) Addur PS (220kV) Rubud


Group"1"

A2 Bus Bar
C.B maintenance

Circuit T611,BSA1A2,BSA2A3 T611,BSA1A2,BSA2A3

SAP Thameem Mahmood/Thameem Mahmood/Thameem Thameem

Remarks

Station Hoora Hoora Hoora


Group"2"

Circuit T311 T312, H.Trafo T313

SAP Mohsen Mohsen Mohsen Mohsen Mohsen


Remarks
Station SHAMAL BUHAIR SANAD SEEF SITRA BSP SITRA VILLAGE

K1,2,3,6,7,9,10,11, K1,5,6,9,10,11,13,14,1
Operation Circuit
13,14,15,22,23
K9,18,19 K3,7,13,23
5,19,20,22,23,24
K5,9,13,19,24

Check
Crew

Time

Station JUFFAIR JUFFAIR JUFFAIR


Protection
Retrofit Circuit A2 BUS BAR

* All Substations mentioned for C.B maintenance or operation check outage Is required for I/Cs , B/Ss and H.Txs.
* H.Tx outage required approval from computer and SCADA sections through operation and system control department.
*All 11kv feeder outages to be confirmed with DCC engineer one hour in advance.