Professional Documents
Culture Documents
"Lit Board") and PCO Signage (Flange Double Sided) - Non-Lit Boards
"Lit Board") and PCO Signage (Flange Double Sided) - Non-Lit Boards
(hereinafter referred to as the “Act”) against the Judgment and Order dated
20.01.2022 passed by the Ld. Single Judge of this Hon'ble Court rejecting a
petition preferred by the Appellant herein u/s 34 of the Act. The Appellant had
22.09.2021 passed by the Ld. Sole Arbitrator. By the aforesaid award the Ld.
That the Petitioner and Respondent into Agreement dated 17.09.2009, pursuant
way of which the Petitioner was awarded the work of brand visibility of BSNL
based agreement solely for Empanelment and the work carried out by the
Petitioner was governed by the Release Order. That the Petitioner proceeded to
complete the work as per the contractual requirements. As per the provisions of
the Release Order, the invoices of the Respondent had to be paid within 15
the invoices raised by the Appellant within the stipulated period of 15 days. At
the time of submission of the invoices, the Respondent never raised an issue that
the invoices submitted by the Appellant were defective or they lacked proper
of 15 days from the submission of the invoices. Even after repeated requests by
the Appellant the invoices remained unpaid. The Respondent finally carried out
the verification after considerable delay. In certain cases, such verification was
carried out after a period of one year from the submission of invoices. On the
delay, the Respondent denied payment to the Appellant on the ground that the
installations done by the Appellant were not found. The Respondent further
significant to point out that as per the terms of the contract there was no
installed.
the Award dated 22.09.2021, the Ld. Arbitrator rejected the claims raised by the
demonstrate that the work was actually done by the Claimant. The Ld.
days from the date of submission of invoices. However, the Arbitrator rejected
the claims raised on the ground that as per the verification done by the
Respondent, months after the installation, the boards were not found at the site.
The Arbitrator failed to appreciate the provisions of the contract whereby the
invoices had to be paid by the Respondent within 15 days. The Arbitrator noted
that the Appellant had placed material on record to demonstrate that the work
had been done by it as per contractual provisions, but choose not to consider
was upheld merely on the ground that the Appellant was aware of such
imposition.
By the impugned order, the Ld. Single Judge failed to set aside the aforesaid
Award of the Ld. Arbitrator. The impugned order is challenged inter-alia on the
following grounds:
a. The Ld. Single Judge failed to appreciate that the Ld. Arbitrator had rewritten
the terms of the contract. The invoices of the Appellant had to be paid within
these 15 days. Further, the payment of the invoices were not contingent on
the verification by the Respondent. There was no provision in the contract
which entitled the Respondent to conduct verification even after delay of more
than a year. The award was therefore patently illegal and contrary to the terms
b. Further, the Appellant was not responsible for the maintenance and security of
the installed boards. The payment to the Appellant was dependent upon the
work of installation done by it. Such installation work was evident from the
the invoices, the Respondent never disputed these documents. The payment
to the Appellant was not dependent on the availability of the installations at the
location after a period of almost a year. The award has imposed a liability on
the Appellant which was not contemplated by the Contract. The award was
c. The Appellant led evidence to prove that the work of installation was done by
it as per the contractual requirements. The Ld. Award as well as the Ld. Single
Judge failed to consider the evidence in view of the verification reports of the
Respondent which were done after considerable delay. The Ld. Arbitrator
holds, that “There is no denying that the Claimant has filed plethora of
The Ld. Arbitrator failed to consider the documents placed on record by the
Claimant to signify the work done and ii. The Ld. Arbitrator had made the
after one year. The Ld. Single Judge also notes that “In order to succeed,
CCL had to simply prove that the installations had been successfully carried
out. The only way it could have been done this, was by cogent evidence.”
However, the Ld. Single Judge upheld the non-consideration of the cogent
evidence by the Ld. Arbitrator. It is therefore submitted that the award is based
d. Further, the Ld. Arbitrator had upheld the imposition of Liquidated Damages
on the ground that the Appellant was aware of such imposition. The Ld. Single
Judge upheld the imposition of Liquidated Damages even when there was no
It is submitted that the award and the impugned order is therefore contrary to
e. Further, the award was based on perverse reasoning. The Award was based
on reasoning which no reasonable person would have adopted. The payment
the boards installed. The payment could not be made contingent on the
availability of such boards after one year by which time the boards could have
been removed by the act of third parties. The PCO owners could have shut
unfathomable for any agency to ensure that the 1000s of boards installed by it
remained at site even after more than one year. Verification done after months
could not have been relied upon as proof of the actual work done by the
In light of the aforesaid, it is submitted that the Impugned order has upheld
an award which has been passed without any consideration of the terms of
the contract, suffered from patent illegality, and was based on the non-