Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

NAME OF PROJECT:-125 KL OVER HEAD TANK 15m STAGING

TYPE OF WORK :- BAR BENDING SCHEDULE WITH CONCRETE QUANTITY


OVER ALL SUMMARY
Sr.No. DESCRIPTION Dia. 8mm 10mm 12mm 16mm 20mm TOTAL (Kg.)
1 TOP DOME 176.15 0 0 0 0 176.15
2 CYLINDRICAL WALL 916.16 0 0 0 916.16
3 BALCONY 74.1 0 0 0 0 74.1
4 BOTTOM DOME 176.88 68.54 78.71 0 0 324.13
COLUMN MAIN BARS &
5 381.7 0 598.08 0 0 979.78
STIRRUPS
6 BRACES 283.05 0 580.2 0 0 863.25
7 RING BEAM TOP 81.9 0 0 130.69 209.55 422.14
8 FOUNDATION 0 264.26 0 0 0 264.26
9 STAIRS 46.51 191.66 0 0 0 238.17
10 LANDING BEAM 44.8 0 46.28 25.28 0 116.36
TOTAL STEEL (Kg.) 2181.3 524.46 1303.27 155.97 209.55 4374.5
TOTAL STEEL (Kg.) (INCLUDING 3% OF WASTAGE) 4506
ESTIMATE OF CONCRETE VOLUME
S.NO DETAILS OF WORK Volume UNIT
1 Top Dome 6.09 CUM
A QUANTITY OF CEMENT 48.72 NOS.
B QUANTITY OF SAND 2.39 CUM 84.33725 CUFT
C QUANTITY OF AGGREGATE 4.78 CUM 168.6745 CUFT
2 Container's Dome 14.72 CUM
A QUANTITY OF CEMENT 117.76 NOS.
B QUANTITY OF SAND 5.77 CUM 203.6092 CUFT
C QUANTITY OF AGGREGATE 11.54 CUM 407.2184 CUFT
3 Bottom Dome 9.97 CUM
A QUANTITY OF CEMENT 79.76 NOS.
B QUANTITY OF SAND 3.91 CUM 137.9743 CUFT
C QUANTITY OF AGGREGATE 7.82 CUM 275.9487 CUFT
4 Balcony 2.56 CUM
A QUANTITY OF CEMENT 20.48 NOS.
B QUANTITY OF SAND 1 CUM 1.152 CUFT
C QUANTITY OF AGGREGATE 2 CUM 2.304 CUFT
5 Ring beam (TOP) 4.91 CUM
A QUANTITY OF CEMENT 39.28 NOS.
B QUANTITY OF SAND 1.92 CUM 67.7521 CUFT
C QUANTITY OF AGGREGATE 3.84 CUM 135.5042 CUFT
6 Braces 5.38 CUM
A QUANTITY OF CEMENT 43.04 NOS.
B QUANTITY OF SAND 2.11 CUM 74.45673 CUFT
C QUANTITY OF AGGREGATE 4.22 CUM 148.9135 CUFT
7 Columns 13.12 CUM
A QUANTITY OF CEMENT 91.84 NOS.
B QUANTITY OF SAND 4.5 CUM 158.794 CUFT
C QUANTITY OF AGGREGATE 9 CUM 317.588 CUFT
8 Footing (RCC) 10.584 CUM
A QUANTITY OF CEMENT 84.672 NOS.
B QUANTITY OF SAND 4.15 CUM 146.4433 CUFT
C QUANTITY OF AGGREGATE 8.3 CUM 292.8867 CUFT
9 Footing (PCC) 1.764 CUM
A QUANTITY OF CEMENT 7.056 NOS.
B QUANTITY OF SAND 0.35 CUM 12.35064 CUFT
C QUANTITY OF AGGREGATE 0.7 CUM 24.70129 CUFT
10 Staircase with landing 5.53 CUM
A QUANTITY OF CEMENT 44.24 NOS.
B QUANTITY OF SAND 2.17 CUM 76.57399 CUFT
C QUANTITY OF AGGREGATE 4.34 CUM 153.148 CUFT
OVER ALL SUMMARY
TOTAL 74.628 CUM
1 QUANTITY OF CEMENT 597.024 NOS.
2 QUANTITY OF SAND 29.25 CUM 1032.161 CUFT
3 QUANTITY OF AGGREGATE 58.5 CUM 2064.322 CUFT
4 QUANTITY OF REINFORCEMENT 4506 KG
NOTE:- QUANTITY SHOULD BE VERIFY BEFORE EXECUTION OF THE WORK