Quantity Estimate Kanari Park

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 38

QUANTITY ESTIMATE

Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Drilling and Installation 250/200 mm diameter Deep tubewell by Rig Machine
(Using appropriate drilling method)
S.No. Description of Work Unit Quantity Remarks

A Section A : Mobilization/ Demobilization


Mobilization of drilling machine , Equipment,
accessosories & Crew including the hire charge of truck
1 Job 1.00
and crane for lifting heavy loads and demolization on
completion.
2 Rig Setting up and preparation of mud pit . Job 1.00

3 Camp setting up and preparation including site clearance . Job 1.00

Assembling, Centralising & sinking of guide pipe of size


4 m 10.00
22'' dia to a depth of 10 m .

5 Vertical Electric sounding test for conforming aquifer . No 1.00

B Section B : Boring and testing


Drilling of pilot hole by standard bit ranging from 7 5/8'' to
9 7/8'' dia for first 100 m in Hard formation using rotary
1 m 125.00
/ percussion method And Collection of Lithological
samples at every 2 m depth
Electrical logging for full depth of drilled pilot hole
2 Job 1.00
( resestivity test) .
Reaming of the hole in Haed formation (first & second
3 Reaming) by std bit above 9 7/8'' and below 17 1/2'' dia m 125.00
for first initial depth of 100 m .
Reconditioning of bore hole before lowering of pipe
4 m 125.00
assembly 6/12'' dia to a depth upto 100 m and beyond .
Lowering of pipe assembly of 200 to 250mm dia. to a
5 m 125.00
depth of 100 m .
6 Supply and packing of 4-8 mm dia pea gravels . Cu. m. 11.30
Well cementation of top 2.50 m depth P.C.C. of ( 1:2:4)
7 Cu. m. 1.84
dia 1m .
8 50mm Dia MC. G I pipe for gravel packing . Rm 12.00
C Section C Suply of well meterials
Supply and Installation of 250mm ND mild steel ERW
1 housing pipe of thickness 7 mm or above having bevelled m 50.00
ends .
S.No. Description of Work Unit Quantity Remarks

Supply and Installation of 200mm ND mild steel ERW


2 casing pipe of thickness 7 mm or above having bevelled m 51.00
ends .

Supply and Installation of 200mm ND mild steel slotted


pipe of thickness 7 mm with slots of size 1.6mm * 75mm
2 m 24.00
and percentage opening minimum 15% having bevelled
ends .
4 Supply and Installation of MS reducer 250/200 mm dia . No 1.00
Miscellaneous ( MS well cap, , Elbow ,Flange , cross bar,
5 Set 1.00
centralizer, bottom plug , clamps,etc.
D Section D : Well Development
Well development by drilling Rig machine for well size of
1 m 125.00
6'' -12'' dia (back washing and inner wasing) .
Well development by drilling Rig machine for well size of
2 m 125.00
6'' -12'' dia ((water jetting ) .
Well development by compressor machine for well size of
3 Hours 72.00
6'' -12'' dia ( Hiw. 72 hrs) .
4 Well development by pump 6'' - 12'' dia (24 hrs. ) . Hours 24.00
5 Pumping test by suitable pump (100mm dia ) .
a. Drawdwon test (24 hrs. ) . well 1.00
b.step drawdwon test (at least 4 steps to 36 hrs ) . well 1.00
c. Recovery test (for 12 hrs. ) . well 1.00
6 Water quality test ( parameters as per NS DWQ ) . L. S. 1.00
Submission of well completion report with , pumping test
7 Job 1.00
analysis & water quality analysis report .( 3 Copies )
QUANTITY ESTIMATE

Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Suppy and Installation of Pump and Pumping Main (for One Tube Well )
S.No. Description of Works Unit Quantity Remarks

8'' KSB BPHA 384/4D+ HBC 413 submersible pumpset


1 complete with motor cabling and other accessories for set 2 1 for spare
nominal 1800 lpm yield and 84 m total pumping head

Control panel board for above pump with suitable automatic


2 starter and all accessories containing dry run, single phasing set 1
prevention
3 DN 125 mm GI medium class pipe for riser m 54
4 DN 150 mm DI socketed (K9) pipe for pumping main m 60
5 Pipe fittings
DN 150x125 mm DI Double Flanged Reducer pc 1
DN 150 mm 45o Bend Double Flanged pc 1
DN 150 mm Single Flanged Tail Piece pc 1
DN 150 mm DI Mechanical Coupling pc 1
DN 125 mm GI Nipple pc 2
DN 125 mm GI Flanged with rubber gasket set 10
DN 125 mm Non-Return Valve (C.I.D.F) pc 1
DN 125 mm ISOD MS Flanged with Ring Rubber Gasket set 1
DN 125 mm Bulk Water Meter pc 1
Nut Bolt and Washer lot 1
6 Pressure gauge with all accessories no. 1

7 Supply and installation of 4 core 16 mm2 copper armoured m 220 Star/delta


cable
Installation, testing and commissioning of pump, riser pipe
8 and pumping main including all fittings and accessories all job 1
complete
9 lot L.S.
Miscellaneous unforseen items
QUANTITY ESTIMATE

Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Suppy and Installation of Electrical Accessories

S.No. Description of Works Unit Quantity Remarks

Extension of 11 KV electric line from Central Grid to


1 pumping station site including supply and installation of km 0.11
pole, wire etc. and testing and commissioning all complete
2 Supply and installation of Electric Transformer set
2.1 Supply of electrical accessories: m
a) 11/0.4 KV 100 KVA electric transformer complete set set 1
b) Transformer Platform all complete set 1
c) M.C.C.B. no. 1
d) Kwh Meter no. 1
e) 11 KV G.O.A.B. switch set 1
f) 11 KV Dropout fuse set 1
g) 24"x20"x08" Metallic Meter Box for 3 phase meter set 1
h) Lightning arrestor set 1
i) Earthing set with conducter set 1
2.2 Installation of electrical accessories:
a) 11/0.4 KV 50 KVA electric transformer set 1
b) Installation of Earthing set set 1
c) Installation of 11 KV G.O.A.B. switch set 1
d) Energy Meter connection charge set 1
e) 11 KV HT shutdown charge hr 4
f) Installation of lightning arrestor set 1
g) Installation of 11 KV Dropout fuse set set 1
h) Testing charge for 100 KVA Transformer set 1
2.3 Miscellaneous unforseen items lot L.S.
QUANTITY ESTIMATE

Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Borehole Platform
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Breadth

1 Site Clearance 1 4.00 3.10 - 12.40 sqm


2 Earthwork in excavation in ordinary soil
Long wall 2 3.15 0.40 0.475 1.20
Short wall 2 1.45 0.40 0.475 0.55
1.75 cum
3 Flat Brick soling with sand in foundation
Long wall 2 3.15 0.40 - 2.52
Short wall 2 1.45 0.40 - 1.16
3.68 sqm

4 Brick soling on edge with sand in base 1 2.50 1.60 - 4 sqm


5 First class brick work in 1:4 cement mortar:
Long wall 2 3.00 0.25 0.30 0.45
Short wall 2 1.60 0.25 0.30 0.24
0.69 cum
6 P.C.C. 1:3:6 (M10) in foundation:
Long wall 2 3.15 0.40 0.075 0.19
Short wall 2 1.45 0.40 0.075 0.09
0.28 cum
7 P.C.C. 1:2:4 (M15) IN
Long Tie Beam 2 3.00 0.25 0.30 0.45
Short Tie Beam 2 1.60 0.25 0.30 0.24
Platform 1 2.50 1.60 0.15 0.6
Thrust block for pipe 2 0.60 0.25 1.00 0.3
Support block for flanged Tee 1 0.40 0.40 0.50 0.08
1.67 cum

8 Reinforcement bar for RCC work @ 135 kg per cum of concrete 225.45 kg
9 Formwork for PCC/RCC work:
PCC in foundation 2 9.20 - 0.075 1.38
Tie beam outer face 2 5.10 - 0.30 3.06
Thrust block for pipe 2 1.70 - 1.00 3.4
Support block for flanged Tee 1 1.60 - 0.50 0.8
8.64 sqm
10 12.5mm thick plaster in 1:4 cement mortar:
Platform 1 2.50 1.60 - 4
Tie beam outer face 2 5.10 - 0.30 3.06
Thrust block for pipe 2 1.70 - 1.00 3.4
Support block for flanged Tee 1 1.60 - 0.50 0.8
11.26 sqm
11 Supply and fixing gantry for chain pulley:
a) Supply of accessories -
100 mm Ø Heavy Class GI Pipe 1 9.60 - - 9.6 m
100 mm Ø GI Socket 4 - - - 4 nos.
100 mm Ø GI Elbow 2 - - - 2 nos.
250x250x12 mm MS Base Plate 4 - - - 4 nos.
12 mm Ø 150 mm long Nut Bolt 8 - - - 8 nos.

b) Transportation of materials up to site 1 - - - 1 job


c) Installation and fixing accessories 1 - - - 1 job
QUANTITY ESTIMATE
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of the Work: R.C.C. Over Head Tank 100 Cum

Length Breadth Height


S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)

RCC Overhead Tank (100cum )Construction


A Provisional sum
a) Insurance premium for the work, Plant and Materials damage
for contract work for all risk including Riot, Strike, Damage,
1 1 1 ps
Malicious damage and Terrorism for contract work for project
Period 18 month
2 b) Lab Test (For Construction work and Materials) 1 1 ps

B Civil works
1 Site cleareance 1 11 11 121 m2
0
2 Earthwork excavation in Hard soil 0
Earthwork excavation upto 1.5 m for raft footing foundation
including 0.5 +0.5 = 1.0 m extra wide for working space width of 0
raft footing = 2.0 m
Excavation in Hard soil 1 21.99 3 2.5 164.93 m3

3 Backfilling work in Hard soil 0


Deduction of sectional area of foundation structure below G/L
from total earthwork excavation = (2.00 * 0.555) + (0.50 * 0.50) -1 21.99 Area = 2.01 -44.1999
+ (0.45 * 1.445) = 2.01 m2
Net backfilling quantity = 164.93 -44.21 = 120.73 m3 1 120.7301 m3

Stone soling (Hard core) without sand (Water Tank area below
4
PCC)
Water Tank area below PCC 1 21.99 2 0.15 6.6 m3
0
5 Sand filling work including watering compaction with Hand 1 21.99 2 0.055 2.42 m3
0
6 Lean concrete PCC (M15) in foundation
Water Tank area below footing 1 21.99 2 0.1 4.4
Sub-total of PCC (M15) 4.4 m3
0
7 PCC for RCC M20 (1:1.5:3)
7.1 PCC up to 4 m height
- Raft slab for foundation 1 21.99 2 0.25 11
0
- Raft beam /Circular girder for foundation 1 21.99 0.5 0.5 5.5
0
- Foundation of staircase 0
0
(0.17+.
- Landing beam for staircase 2 0.9 0.35 0.08
07)/2
0
(1.34+0
- Platform / landing slab for staircase 2 0.9 0.18 0.31
.60)/2
- Steps ( T = 200 mm, R = 200 mm) of staircase 24 0.9 0.27 0.15 0.88
0
- Waist slab 2 3.55 0.9 0.18 1.15
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)
- Columns 6 5.45 0.45 0.45 6.63
0
- Bracing beam 1 21.99 0.35 0.5 3.85
Sub-total 29.4 m3

7.2 PCC from 4 m to 8 m height


(0.17+.
- Landing beam for staircase 2 0.9 0.35 0.08
07)/2
(1.34+0
- Platform / landing slab for staircase 2 0.9 0.18 0.31
.60)/2
- Steps of staircase 24 0.9 0.27 0.15 0.88
- Waist slab 2 3.55 0.9 0.18 1.15
- Columns 6 4 0.45 0.45 4.86
- Bracing beam 1 21.99 0.35 0.5 3.85
Sub-total 11.13 m3

7.3 PCC from 8 m to 12 m height


- Landing beam for staircase 0 0 0 0 0
- Platform / landing slab for staircase 0 0 0 0.18 0
- Steps of staircase 24 0.9 0.27 0.15 0.88
- Waist slab 2 3.55 0.9 0.18 1.15
- Columns 6 4 0.45 0.45 4.86
- Bracing beam 1 21.99 0.35 0.5 3.85
Sub-total 10.74 m3

7.4 PCC from 12 m to 16 m height


- Landing beam for staircase 0 0 0 0 0
- Platform / landing slab for staircase 0 0 0 0.18 0
- Steps of staircase 24 0.9 0.27 0.15 0.88
- Waist slab 2 3.55 0.9 0.18 1.15
- Columns 6 4 0.45 0.45 4.86
- Bracing beam 1 21.99 0.35 0.5 3.85
Sub-total 10.74 m3

7.5 PCC from 16 m to 20 m height


(0.17+.
- Landing beam at balcony lavel 2 0.9 0.35 0.08
(1.34+0 07)/2
Platform / landing slab for staircase 1 0.9 0.18 0.16
.60)/2
- Steps of staircase 24 0.9 0.27 0.15 0.88
- Waist slab 2 3.55 0.9 0.18 1.15
- Columns 6 4 0.45 0.45 4.86
Bottom ring beam 1 21.99 0.4 0.32 2.81
- Tank floor circular slab 1 Area = 40.1515 0.28 11.24
Cantilever slab around the cylindrical tank excluding cutted part
1 21.7898 0.9 0.12 2.35
of slab for staircase
Sub-total 23.53 m3

7.6 PCC from 20 m to 22 m height withoutsilica admixtures


RCC post (100 x 150 mm) for railing at the edge of cantilever
- 16 0.13 0.1 0.9 0.19
slab
Above Top dome 6 0.13 0.1 0.9 0.07

RCC post (100 x 100 mm) for railing at the edge of Staircase 29 0.13 0.1 0.9 0.34

Cylindrical wall (Inner dia. = 6.85 m) 1 21.99 0.15 2 6.6


Sub-total 7.2 m3
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)

7.7 PCC from 22 m to 24.725 m height with 3% Silica admixture


- Cylindrical wall (Inner dia. = 6.85 m) 1 21.9911 0.15 0.8 2.64
- Top dome 1 Area = 48.441 0.125 6.06
- Top ring beam (200 x 200 mm) 1 22.1482 0.2 0.2 0.89
Sub-total 9.59 m3

8 Steel Reinforcement works 14743.83 kg


9 Formwork
9.1 Foundation
- Raft slab for foundation 2 21.9911 0.25 11
- Raft beam /Circular girder for foundation 2 21.9911 0.5 21.99
- Lean concrete PCC (M15) in foundation 0
Water Tank area below footing 2 21.9911 0.1 4.4
Staircase footing 0
Sub-total of formwork 37.39 m2

9.2 Staircase flight including platform


9.2.1 Formwork up to 4 m height
- Landing beam for staircase 2 0.9 0.59 1.06
End of beam for closing 2 0.35 0.07 0.05
(1.34+0
- Platform / landing slab for staircase 2 0.9 1.75
.60)/2
Edge of landing slab 2 1.34 0.18 0.48
- Steps of staircase 24 0.9 0.15 3.24
- Waist slab 2 3.55 0.9 6.39
Edge of waist slab 4 3.55 0.18 2.56
Sub-total of formwork 15.53 m2

9.2.2 Formwork from 4 m to 8 m height


- Landing beam for staircase 2 0.9 0.59 1.06
End of beam for closing 2 0.35 0.07 0.05
(1.34+0
- Platform / landing slab for staircase 2 0.9 1.75
.60)/2
Edge of landing slab 2 1.34 0.18 0.48
- Steps of staircase 24 0.9 0.15 3.24
- Waist slab 2 3.55 0.9 6.39
- Edge of waist slab 4 3.55 0.18 2.56
Sub-total of formwork 15.53 m2

9.2.3 Formwork from 8 m to 12 m height


- Landing beam for staircase 2 0.9 0.59 1.06
End of beam for closing 2 0.35 0.07 0.05
(1.34+0
Platform / landing slab for staircase 1 0.9 0.87
.60)/2
Edge of landing slab 1 1.34 0.18 0.24
- Steps of staircase 24 0.9 0.15 3.24
- Waist slab 2 3.55 0.9 6.39
Edge of waist slab 4 3.55 0.18 2.56
Sub-total of formwork 14.41 m2

9.2.4 Formwork from 12 m to 16 m height


- Landing beam for staircase 2 0.9 0.59 1.06
End of beam for closing 2 0.35 0.07 0.05
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)
(1.34+0
Platform / landing slab for staircase 1 0.9 0.87
.60)/2
Edge of landing slab 1 1.34 0.18 0.24
- Steps of staircase 24 0.9 0.15 3.24
- Waist slab 2 3.55 0.9 6.39
Edge of waist slab 4 3.55 0.18 2.56
Sub-total of formwork 14.41 m2

9.2.5 Formwork from 16 m to 20 m height


- Landing beam for staircase 2 0.9 0.59 1.06
End of beam for closing 2 0.35 0.07 0.05
(1.34+0
Platform / landing slab for staircase 1 0.9 0.87
.60)/2
Edge of landing slab 1 1.34 0.18 0.24
- Steps of staircase 24 0.9 0.15 3.24
- Waist slab 2 3.55 0.9 6.39
Edge of waist slab 4 3.55 0.18 2.56
Sub-total of formwork 14.41 m2

9.3 Column
- Columns at Foundation to Ground 6 1.445 1.8 15.61 m2
Columns Upto 4m 6 4 1.8 43.2 m2
Columns from 4m to 8m 6 4 1.8 43.2 m2
Columns from 8m to 12m 6 4 1.8 43.2 m2
Columns from 12m to 16m 6 4 1.8 43.2 m2
Columns from 16m to 20m 6 4 1.8 43.2 m2
- RCC post for railing at cantilever slab(Above20m) 16 0.46 0.9 6.62
RCC post for railing at Top Dome slab(Above 20m) 6 0.46 0.9 2.48
RCC post for railing at Staircase 29 0.46 0.9 12.01
Sub-total of formwork 252.72
Total formwork 252.72 m2

9.4 Beam
9.4.1 Formwork to 4 m height
- Bracing beam 1 21.9911 1.35 29.69 m2
9.4.2 Formwork from 4 m to 8 m height 0
- Bracing beam 1 21.9911 1.35 29.69 m2
9.4.2 Formwork from 8 m to 12 m height 0
- Bracing beam 1 21.9911 1.35 29.69 m2
9.4.2 Formwork from 12 m to 16 m height 0
- Bracing beam 1 21.9911 1.35 29.69 m2
9.4.3 Formwork from 16 m to 20 m height 0
- Bottom circular ring beam 1 21.9911 1.6 35.19 m2

9.5 Wall & vertical structures


Formwork from 16 m to 20 m & above height
- Cylindrical wall 2 21.99 2.8 123.15
- Tank floor circular slab with cantilever balcony 1 Area = 62.9124 62.92
Cutted part of slab for deduction from balcony where no
- -1 3.5 0.9 -3.15
staircase (straight length = 3.50 m )
- Edge of cantilever balcony slab 1 28.1173 0.08 2.25
Total formwork 185.17 m2
9.6 Dome portion
- Top ring beam 1 22.7765 0.2 4.56
Inner side face of ring beam 1 21.5199 0.2 4.31
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)

spherica
l
- Top dome 1 48.45
surface
area =

Sub-total of formwork 57.32


Total formwork 57.32 m2

12.5 mm thick cement plaster on wall (1:4) without silica


10
Admixture

10.1 Cement plaster up to 4 m height


- Landing beam for staircase 2 0.9 0.59 1.06
End of beam for closing 2 0.35 0.07 0.05
0
(1.34+0
- Landing of staircase at top & botom 4 0.9 3.49
.60)/2
Edge of landing slab 2 1.34 0.18 0.48
2 0.9 0.18 0.32
- Steps of staircase 24 0.9 0.27 5.83
25 0.9 0.15 3.38
0
- Waist slab 2 3.55 0.9 6.39
Both edge of waist slab 4 3.55 0.18 2.56
0
- Columns (450 x 450 mm) 6 4 1.8 43.2
0
- Bracing beam(350 x 500 mm) 1 21.9911 1.7 37.38
Sub-total 104.14 m2

10.2 Cement plaster from 4 m to 8 m height


- Landing beam for staircase 2 0.9 0.59 1.06
End of beam for closing 2 0.35 0.07 0.05
0
(1.34+0
- Landing of staircase at top & botom 4 0.9 3.49
.60)/2
Edge of landing slab 2 1.34 0.18 0.48
2 0.9 0.18 0.32
- Steps of staircase 24 0.9 0.27 5.83
25 0.9 0.15 3.38
0
- Waist slab 2 3.55 0.9 6.39
Both edge of waist slab 4 3.55 0.18 2.56
0
- Columns (450 x 450 mm) 6 4 1.8 43.2
0
- Bracing beam(350 x 500 mm) 1 21.9911 1.7 37.38

Sub-total 104.14

10.3 Cement plaster from 8 m to 12 m height


- Landing beam for staircase 2 0.9 0.59 1.06
End of beam for closing 2 0.35 0.07 0.05
0
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)
(1.34+0
- Landing of staircase at top & botom 4 0.9 3.49
.60)/2
Edge of landing slab 2 1.34 0.18 0.48
2 0.9 0.18 0.32
Steps of staircase 24 0.9 0.27 5.83
- 25 0.9 0.15 3.38
0
Waist slab 2 3.55 0.9 6.39
- Both edge of waist slab 4 3.55 0.18 2.56
0
Columns (450 x 450 mm) 6 4 1.8 43.2
0
- Bracing beam(350 x 500 mm) 1 21.9911 1.7 37.38
0
Sub-total 104.14

10.4 Cement plaster from 12 m to 16 m height


Landing beam for staircase
- End of beam for closing 2 0.9 0.59 1.06
2 0.35 0.07 0.05
Landing of staircase at top & botom 0
(1.34+0
- Edge of landing slab 4 0.9 3.49
.60)/2
2 1.34 0.18 0.48
Steps of staircase 2 0.9 0.18 0.32
24 0.9 0.27 5.83
- 25 0.9 0.15 3.38
Waist slab 0
Both edge of waist slab 2 3.55 0.9 6.39
- 4 3.55 0.18 2.56
Columns (450 x 450 mm) 0
6 4 1.8 43.2
Bracing beam(350 x 500 mm) 0
- 1 21.9911 1.7 37.38

Sub-total 104.14

10.4 Cement plaster from 16 m & above height

surface
- Top dome (top & bottom surfaces) 2 48.45 96.9
area =

- Top ring beam 1 22.78 0.2 4.56


- RCC post for railing at cantilever slab 16 0.46 0.9 6.62
RCC post for railing at Top dome slab 6 0.46 0.9 2.48
RCC post for railing at Staircase 29 0.46 0.9 12.01
top of RCC post 51 0.13 0.1 0.66
Sub-total 123.23
Total quantity of cement plaster 682.19 m2

12.5 mm thick cement plaster on wall (1:3) with 3% Silica


11
Admixture
Inner side of beam face 1 21.5199 0.2 4.3
Tank floor circular slab (top & bottom surfaces) 2 Area = 36.85 73.7
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)
Cylindrical wall inner & outer surface 2 21.9911 2.8 123.15
Total 201.15 m2

12 Cement punning Floor work (1:1)


Cylindrical watar tank wall (inner surface) 1 21.5199 3 64.56
Tank floor circular slab (inner surface) 1 Area = 36.8528 36.85
Sub-total of cement punning 101.41 m2

40-50 mm thick cement concrete (gravel 6 mm down) mix M20


13
laid over concrete floor base
Volume
Tank floor circular slab (inner surface) 1 1.65838 1.66 m3
=

Two coats of Weather coat paint with primer (Qty as Plaster -


14 1 780.615 m2
Plaster inside of tank wall)

15 Scaffolding Work 1 1 Job

16 32 mm dia GI railing
- Railing on cantilever balcony 2 24.7 49.4
Railing on Top of Dome 2 5.5 11
Railing on staircase (longitudinal both sides) from base up to
- 0
top , Nos. = 2*2
2 53.6 107.2
Sub-total of 32 mm dia. GI railing 167.6 Rm

Supply and installation of inspection ladders from balcony to the


17 top of dome and inner ladder from top of dome to bottom of 2 300 kg
dome
Supply and fixing of 750 mm *750mm Rectangular Iron angle
18 framed manhole cover including all fittings in spherical dome of 1 1 set
tank
19 Fixing Mosquito proof net with Wooden beads 4 0.45 0.45 0.81 m2
Two coat readymade enamel paint over one coat of primer all
20 2 0.75 3.5 5.25
around the railing pipe and inspec. Iron Ladder
Railing pipe 1 167.6 0.1005 16.84
Total of Emamel painting on railing 22.09 m2
Supply & Installation of electric bulb on the top of tankd dom
21 1 job
including electrification work all complete
22 Supply & Installation ofwater level indicator all complete 1 1 no
23 Floor finishing & Surface drainage work
a E/W excavation in foundation hard soil
For floor finishing 1 4.57 4.57 0.35 22.95
For Surface Drainage 1 30.772 0.66 0.65 13.2
For Chamber 1 1.15 1.15 1 1.32
Near Entrance gate area out of Drain 1 3.1 2.4 0.25 1.86
Total Quantity 39.33 m3

b Stone soling work without sand


For floor finishing 1 4.57 4.57 0.2 13.12
For Surface Drainage 1 30.772 0.66 0.15 3.05
For Chamber 1 1.15 1.15 0.15 0.2
Near Entrance gate area out of Drain 1 3.1 2.4 0.15 1.12
Total Quantity 17.49 m3
c PCC (1:2:4) works
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)
For floor finishing 1 4.57 4.57 0.15 9.84
For Surface Drainage 1 30.772 0.66 0.1 2.03
For Chamber 1 1.15 1.15 0.1 0.13
Near Entrance gate area out of Drain 1 3.1 2.4 0.1 0.74
Total Quantity 12.74 m3
d 1st Class brick work in 1:4 c/s morter
For Surface Drainage 2 30.772 0.225 0.4 5.54
For Chamber 1 3.68 0.23 0.75 0.63
Total Quantity 6.17 m3
e 20mm thick Cement Plaster in 1:4 C/S morter
For floor finishing 1 4.57 4.57 65.58
For Surface Drainage 0
inside of wall 2 30.772 0.4 24.62
Top of wall 2 30.772 0.225 13.85
Bottom of drain 1 30.772 0.2 6.15
For Chamber 0
Inner side wall 1 2.76 0.75 2.07
Floor 1 0.69 0.69 0.48
Top of wall 1 3.68 0.23 0.85
Near Entrance gate area out of Drain 1 3.1 2.4 7.44
Total Quantity 121.04 m2

f 3 mm thick cement punning in (1:1 ) c/m


For Surface Drainage
inside of wall 2 30.772 0.4 24.62
Top of wall 2 30.772 0.225 13.85
Bottom of drain 1 30.772 0.2 6.15
For Chamber 0
Inner side wall 1 2.76 0.75 2.07
Floor 1 0.69 0.69 0.48
Top of wall 1 3.68 0.23 0.85
Inner side wall 1 3.1 2.4 7.44
Total Quantity 55.46 m2

Supply of DI pipes, fittings and accessories as per drawing and


24
specification
a Inlet Fittings
i) DN 150 DI Tail Piece 1 1 No
ii) DN 150 DI Pipe(Class k-9) 24 24 Rm
iii) DN 150 DI Bell mouth 1 1 No
iv) DN 150 DI Duck Foot bend 90 degree Double Flanged 1 1 No
v) DN 150 DI Mechanical coupling with Rubber ring 1 1 No
vi) DN 150 DI bend with Double Flanged 1 1 No

b Washout Fittings
i) DN 150 DI Tail Piece 1 1 No
ii) DN 150 DI Pipe(Class k-9) 20 20 No
iii) DN 150 DI Bell mouth 1 1 Rm
iv) DN 150 DI Duck Foot bend 90 degree Double Flanged 1 1 No
v) DN 150 DI Sluice Valve 1 1 No
vi) DN 150 DI Mechanical coupling with Rubber ring 1 1 No
vii) DN 150 DI bend with Double Flanged 1 1 No

c Overflow Fittings
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)
i) DN 150 DI Tail Piece 1 1 No
ii) DN 150 DI Pipe(Class k-9) 24 24 No
iii) DN 150 DI Bell mouth 1 1 No
iv) DN 150 DI Duck Foot bend 90 degree Double Flanged 1 1 Rm
v) DN 150 DI Mechanical coupling with Rubber ring 1 1 No
vi) DN 150 DI bend with Double Flanged 1 1 No

d Outlet Fittings
i) DN 200 DI Tail Piece 1 1 No
ii) DN 150 DI Pipe(Class k-9) 20 20 No
iii) DN 150 DI Bell mouth 1 1 No
iv) DN 150 DI Duck Foot bend 90 degree Double Flanged 1 1 No
v) DN 150 DI Sluice Valve 1 1 Rm
vi) DN 150 DI Mechanical coupling with Rubber ring 1 1 No
vii) DN 150 DI Bulk Water Meter 1 1 No
viii) DN 150 DI bend with Double Flanged 1 1 No

Jointing and fitting of inlet, outlet,washout and overflow


25 1 1 No
pipe ,bell mouth,duck foots etc.
Supply and Installation of Electric balb on the top of Tank dom
26 1 1 No
including Electrification work all complete
27 Supply and Installation of water level indicator all complete 1 1 No
Supply and installation of Iron angle framed Grill Gate at
28 1 1 No
staircase on 3rd bracing (Size 0.90*1.80 m)
Provide safety equipment for the engineer & mason & labours at
29 each of the site office of the types and number specified for the 1 1 No
period of the contract as per specification
Leak proof test and disinfection of reservoir all complete
30 1 1 No
QUANTITY ESTIMATE

Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Valve Box

Height or
S.No. Description of Works No. Length Breadth Quantity Unit
Breadth

1 EARTH WORK

Layout & setting out of the building


including site clearance of grass, shrubs
excavation of loose/soft soil to maximum
1.1 1 1.76625 1.76625
depth of 15mm. Including dressing,
levelling and disposal the excavated
materials within the premises.

TOTAL 1.76625 m2

Earthwork in excavation in all kinds of soil


and diposing lead up to 30m including
dressing of sides, ramming of bottom,
1.2 watering, ramming, consolidation and 1 1.069625 1.5 1.604438
dressing, with all necessary shoring and
dewatering as well as backfilling the trench
and compact

TOTAL 1.604438 m3

1.3 Back filling 1 40% of Excavation 0.641775 m3

2 CONCRETE WORK

Supplying, mixing, placing, compacting &


curing different mixes of plain cement
concrete for foundation bases & floors
2.1
excluding the cost of formwork &
reinforcement bars, as per drawing,
specification & instruction all complete

M-20 grade PCC(1:1.5:3)


1 0.070686 0.05 0.003534
1 0.017671 0.05 0.000884
1 1.069625 0.15 0.160444
TOTAL 0.164862 m3
Deductions
1 0.2355 0.075 0.15 0.002649
TOTAL 0.162212 m3
Providing, placing, fixing centering and
2.2 shuttering of plywood or steel form
work .)
1 0.942478 0.05 0.047124
1 0.471239 0.05 0.023562
1 3.666239 0.15 0.549936
TOTAL 0.620622 m2
3 STONEWORK

Dry Stone soling in foundation and floors


in true line & level including watering,
3.1
compacting etc. all complete as per
drawing, specification & instruction.

1 0.070686 0.15 0.010603


1 1.069625 0.05 0.053481
TOTAL 0.064084
Deductions
1 0.2355 0.075 0.05 0.000883
TOTAL 0.063201 m3
4 Surface Box 1 1 No.
5 G.I pipe 80 Dia 1 3 3m
6 Extension CI/DI pipe 150 Dia 1 1 1m
Remarks
QUANTITY ESTIMATE
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Operator's Building
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
A OFFICE BUILDING
1 Site clearance 1 14.80 7.80 115.44 Sqm
2 Earthwork in Excavation (Centre Line Length)
a)Main Foundation 1 42.00 0.90 0.90 34.02
b)Apron 1 31.70 0.60 0.30 5.71
c)Steps 1 4.50 0.60 0.30 0.81
Total 40.54 Cum
3 Flat Brick Soiling
a)In Foundation 1 42.00 0.90 37.80
b)In Floors of Central Room 1 3.00 3.60 10.80
c)In Floors of Other Room 2 4.30 3.60 30.96
d)In Verandas 2 3.60 1.30 9.36
e)Apron 1 31.70 0.60 19.02
f)Steps Foundation 1 4.50 0.60 2.70
Total 110.64 Sqm
4 Lean Concrete (1:3:6)
a)In Foundation (50mm Thick) 1 42.00 0.90 0.05 1.89
b)Base of Apron (50mm Thick) 1 31.70 0.60 0.05 0.95
c)Base of Steps (50mm Thick) 2 4.50 0.60 0.05 0.27
Total 3.11 Cum
5 Brick Masonry Works in 1:6 C/S Ratio
a)In Foundation (750mm Thick) 1 42.45 0.75 0.30 9.55
b)In Foundation (450mm Thick) 1 43.35 0.45 0.30 5.85
c)In Foundation (350mm Thick) 1 43.65 0.35 0.78 11.84
d)In Super Structure (upto 2.75m Ht.) 1 44.01 0.23 2.75 27.84
e)Apron 1 31.70 0.60 0.35 6.66
f)Steps 1 4.50 0.60 0.45 1.22
1 4.50 0.30 0.23 0.31
Total 63.26
Deduction
Window
W1 6 1.50 0.23 1.50 3.11
W2 2 1.20 0.23 1.50 0.83
Ventillation 6 0.60 0.23 0.45 0.37
Door
D1 2 1.05 0.23 2.10 1.01
D2 1 0.90 0.23 2.10 0.43
Veranda Opening 1 3.60 0.23 2.10 1.74
Total deduction 7.49
Net Quantity 55.77 Cum
DPC Course of 50mm Th. of PCC (1:2:4)
6 1 43.65 0.35 0.05 0.86 Cum
with WPC
7 Backfilling of Earth in Foundation 50% of Total Excavation 20.27
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
Earth filling and compaction for room 10.13
Total 30.40 Cum
8 PCC 1:2:4 for RCC Works
a)Slab 1 12.47 5.51 0.10 6.87
b)Periphery Beam 1 39.01 0.23 0.23 2.06
c)In Lintel Above Opening 1 5.00 0.23 0.23 0.26
Lintel above Window
W1 6 2.00 0.23 0.23 0.63
W2 2 1.50 0.23 0.23 0.16
Lintel above Door
D1 2 1.25 0.23 0.23 0.13
D2 1 1.00 0.23 0.23 0.05
Total 10.18 Cum
9 Reinforcement Bar for RCC Works
a)Periphery Beam
12 mm Diameter Bar 4 39.01 Unit Wt. 0.89 138.88
6 mm Diameter Bar for Stirrup 234 1.04 Unit Wt. 0.223 54.27
b)In Lintel above Door and Window
W1
10mm Dia Bar 24 2.00 Unit Wt. 0.62 29.76
6 mm Diameter Bar for Stirrup 72 0.50 Unit Wt. 0.223 8.03
W2
10mm Dia Bar 8 1.50 Unit Wt. 0.62 7.44
6 mm Diameter Bar for Stirrup 24 0.50 Unit Wt. 0.223 2.68
Door
D1
10mm Dia Bar 8 1.25 Unit Wt. 0.62 6.20
6 mm Diameter Bar for Stirrup 24 0.50 Unit Wt. 0.223 2.68
D2
10mm Dia Bar 4 1.25 Unit Wt. 0.62 3.10
6 mm Diameter Bar for Stirrup 12 0.50 Unit Wt. 0.223 1.34
Sub Total254.36
Lap & Hooks 10 % of above 25.44
Total 279.80 Kg
C. Slab of Building 130 g/Cu.m. 6.87 893.23
Grand Total= 1173.03 Kg
10 Form Work
a)For DPC 2 43.65 0.05 4.37
b)Lintel for Opening
i) Side of Lintel 2 5.00 0.23 2.30
ii) Bottom of Lintel 1 3.60 0.23 0.83
c)Slab
d)Central Room 1 3.00 3.60 10.80
e)Other Room 2 4.30 3.60 30.96
f)In Verandas 1 3.60 1.30 4.68
i) Chajja Beat 1 35.96 0.10 3.60
ii) Side of Tie Beam 1 39.01 0.23 8.97
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
g)In Lintel Door and Window
Window
W1 12 2.00 0.23 5.52
W2 4 1.50 0.23 1.38
Door 0.00
D1 4 1.25 0.23 1.15
D2 2 1.00 0.23 0.46
Grand Total= 75.01 Sqm
11 Earth Filling & Compaction up to 500mm
a)In Floors of Central Room 1 3.00 3.60 0.35 3.78
b)In Floors of Other Room 2 4.30 3.60 0.35 10.84
c)In Verandas 1 3.60 1.30 0.35 1.64
Total 16.25 Cum
12 Sand of 75 mm Thick Filling in Floor
a)In Floors of Central Room 1 3.00 3.60 0.075 0.81
b)In Floors of Other Room 2 4.30 3.60 0.075 2.32
c)In Verandas 1 3.60 1.30 0.075 0.35
3.48 Cum
13 PCC 1:2:4 Work of 50mm Thick in Floor
a)In Floors of Central Room 1 3.00 3.60 0.05 0.54
b)In Floors of Other Room 2 4.30 3.60 0.05 1.55
c)In Verandas 1 3.60 1.30 0.05 0.23
d)Steps 1 3.00 0.30 0.05 0.05
1 3.00 0.30 0.05 0.05
Total 2.41 Cum
14 Cement Sand Plaster of 12.5mm Thick of 1:4 C/S ratio
a)In Floors and Cilling of Central Room 2 3.00 3.60 21.60
b)In Floors and cilling of Other Room 2 4.30 3.60 30.96
c)In Verandas 2 3.60 1.30 9.36
d)Chajja 1 33.56 0.60 20.14
e)Steps 1 3.00 0.45 1.35
1 3.00 0.45 1.35
f)Apron 1 31.70 0.70 22.19
g)Inner Walls
In wall of Central Room 2 3.00 3.00 18.00
2 3.60 3.00 21.60
In wall of Other Room 2 4.30 3.00 25.80
2 3.60 3.00 21.60
In wall of Verandas 2 3.60 3.00 21.60
2 1.30 3.00 7.80
h)Outer Walls
Below DPC 1 Perimeter= 43.65 0.60 26.19
Top Face of DPC 1 Perimeter= 43.65 0.12 5.24
Above Plinth to Slab Level (ht=3m) 1 Perimeter= 44.01 3.00 132.03
Floor of Roof Top 1 12.47 5.51 68.71
Total 455.51
Deduction
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
Window
W1 6 1.50 1.50 13.50
W2 2 1.20 1.50 3.60
Ventilation 6 0.60 0.45 1.62
Door
D1 2 1.05 2.10 4.41
D2 1 0.90 2.10 1.89
Veranda Opening 1 3.60 2.10 7.56
Total Deduction 32.58
Net Quantity 422.93 Sqm
15 Neat Cement Punning of 3 to 3.5mm Thick
a)In Floors and Cilling of Central Room 1 3.00 3.60 10.80
b)In Floors and cilling of Other Room 1 4.30 3.60 15.48
c)In Verandas 1 3.60 1.30 4.68
d)Steps 1 3.00 0.45 1.35
1 3.00 0.45 1.35
e)Apron 1 31.70 0.70 22.19
Total 55.85 Sqm
16 Doors & Windows Frame of Sal Wood
Door-D1
Long Wood 4 0.10 0.07 2.10 0.06
Short Wood 2 1.05 0.07 0.10 0.01
Door-D2
Long Wood 2 0.10 0.07 2.10 0.03
Short Wood 1 0.90 0.07 0.10 0.01
Window-W1
Long Wood 24 0.10 0.07 1.50 0.25
Short Wood 18 1.50 0.07 0.10 0.19
Window-W2
Long Wood 6 0.10 0.075 1.50 0.07
Short Wood 6 1.20 0.075 0.10 0.05
Ventilation
Long Wood 12 0.10 0.075 0.60 0.05
Short Wood 12 0.45 0.075 0.10 0.04
Total 0.77 Cum
17 38mm panelled Shutter Sal Wood For Door 2 0.90 2.10 3.78
1 0.75 2.10 1.58
5.36 Sqm
18 Glazed Shutter in Window
Window-W1 6 1.20 1.05 7.56
Window-W2 2 0.75 1.05 1.58
Total 9.14 Sqm
19 Cement Wash on Inner & Outer Walls 422.93 Sqm
20 Enamel Paint Works in Doors & Windows(Double the Area of Flush Door) 14.49 Sqm
21 MS Grill Work for Window 1 13.50 Sq.m. 9.14 123.32 Kg
B DOUBLE COMPARTMENT LATRINE
1 Site clearance 1 4.00 2.00 8.00 Sqm
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
2 Earthwork in Excavation (Centre Line Length)
a)Main Foundation 1 11.36 0.80 0.60 5.45
b)Apron 1 13.00 0.45 0.30 1.76
c)Steps 1 3.00 0.60 0.30 0.54
Total 7.75 Cum
3 Flat brick soiling
a)In Foundation 1 11.36 0.75 8.52
b)In Floors of Large Compartment 1 2.00 1.50 3.00
c)In Floors of Small Compartment 1 1.00 1.50 1.50
d)Apron 1 13.00 0.45 5.85
e)Steps Foundation 1 3.00 0.60 1.80
Total 20.67 Sqm
4 Lean Concrete (1:3:6)
a)In Foundation (50mm Thick) 1 11.36 0.75 0.05 0.43
b)Base of Apron (50mm Thick) 1 13.00 0.45 0.05 0.29
c)Base of Steps (50mm Thick) 2 3.00 0.60 0.05 0.18
Total 0.90 Cum
5 Brick Masonry Works in 1:6 C/S Ratio
a)In Foundation (600mm Thick) 1 11.51 0.60 0.23 1.59
b)In Foundation (450mm Thick) 1 11.66 0.45 0.15 0.79
c)In Foundation (350mm Thick) 1 11.76 0.35 0.45 1.85
d)In Super Structure (upto 2.5m Ht.) 1 11.88 0.23 2.50 6.83
e)Apron 1 13.00 0.45 0.23 1.35
f)Steps 1 3.00 0.60 0.45 0.81
1 3.00 0.30 0.23 0.21
Total 13.42
Deduction
Ventillation 2 0.60 0.23 0.45 0.12
Door D1 2 0.75 0.23 1.95 0.67
Total deduction 0.80
Net Quantity 12.62 Cum
DPC Course of 50mm Th. of PCC (1:2:4)
6 1 11.76 0.35 0.05 0.21 Cum
with WPC
7 Backfilling of Earth in Foundation 50% of Total Excavation 3.87
Earth filling and compaction for room 1.94
Total 5.81 Cum
8 PCC 1:2:4 for RCC Works
a)Slab 1 4.60 2.90 0.10 1.33
b)Periphery Beam 1 11.90 0.23 0.15 0.41
c)In Lintel Above Door 1 1.00 0.23 0.10 0.02
Total 1.77 Cum
9 Reinforcement Bar for RCC Works
a)Periphery Beam
10 mm Diameter Bar 4 11.90 Unit Wt. 0.62 29.51
6 mm Diameter Bar for Stirrup 80 1.04 Unit Wt. 0.22 18.55
b)In Lintel above Door and Window
D1
10mm Dia Bar 4 1.00 Unit Wt. 0.62 2.48
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
c)Slab of Building 130 g/Cu.m. 1.33 173.42
Grand Total= 223.97 Kg
10 Form Work
a)For DPC 2 11.76 0.05 1.18
b)Lintel for Opening
c)Slab
d)Large Compartment 1 2.00 1.50 3.00
e)Small Compartment 1 1.00 1.50 1.50
i) Chajja Beat 1 15.00 0.10 1.50
ii) Side of Tie Beam 1 11.90 0.15 1.79
f)In Lintel Door and Window
Door 0.00
D1 2 1.00 0.10 0.20
Grand Total= 9.16 Sqm
11 Earth Filling & Compaction up to 500mm
a)Large Compartment 1 2.00 1.50 0.35 1.05
b)Small Compartment 2 1.00 1.50 0.35 1.05
Total 2.10 Cum
12 Sand of 75 mm Thick Filling in Floor
a)Large Compartment 1 2.00 1.50 0.08 0.23
b)Small Compartment 2 1.00 1.50 0.08 0.23
Total 0.45 Cum
13 PCC 1:2:4 Work of 50mm Thick in Floor
a)Large Compartment 1 2.00 1.50 0.05 0.15
b)Small Compartment 2 1.00 1.50 0.05 0.15
c)Steps 1 2.00 0.30 0.05 0.03
1 2.00 0.30 0.05 0.03
Total 0.36 Cum
14 Cement Sand Plaster of 12.5mm Thick of 1:4 C/S ratio
a)In Floors and Cilling of Large Compartment 2 2.00 1.50 6.00
b)In Floors and cilling of Small Compartment 2 1.00 1.50 3.00
c)Chajja 1 15.00 0.45 6.75
d)Steps 1 2.00 0.45 0.90
1 2.00 0.45 0.90
e)Apron 1 13.00 0.70 9.10
f)Inner Walls
In wall of Large Compartment 2 2.00 2.50 10.00
2 1.50 2.50 7.50
In wall of Small Compartment 2 1.00 2.50 5.00
2 1.00 2.50 5.00
g)Outer Walls
Below DPC 1 Perimeter= 11.76 0.45 5.29
Top Face of DPC 1 Perimeter= 11.76 0.12 1.41
Above Plinth to Slab Level (ht=2.5m) 1 Perimeter= 11.88 2.50 29.70
Floor of Roof Top 1 4.60 2.90 13.34
Total 103.89
Deduction
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
Ventilation 2 0.60 0.45 0.54
Door
D1 2 0.75 1.95 2.93
Total Deduction 3.47
Net Quantity 100.43 Sqm
15 Neat Cement Punning of 3 to 3.5mm Thick
a)In Floors and Cilling of Large
1 2.00 1.50 3.00
Compartment
b)In Floors and cilling of Small
1 1.00 1.50 1.50
Compartment
c)Steps 1 2.00 0.45 0.90
1 2.00 0.45 0.90
d)Apron 1 13.00 0.70 9.10
Total 15.40 Sqm
16 Doors & Windows Frame of Sal Wood
Door-D1
Long Wood 4 0.10 0.07 1.95 0.05
Short Wood 2 0.75 0.07 0.10 0.01
Ventilation
Long Wood 4 0.10 0.08 0.60 0.02
Short Wood 4 0.45 0.08 0.10 0.01
Total 0.10 Cum
17 38mm panelled Shutter Sal Wood For Door 2 0.60 1.85 2.22
2.22 Sqm
18 Glazed Shutter in Ventilation
2 0.50 0.40 0.40
Total 0.40 Sqm
19 Cement Wash on Inner & Outer Walls 85.93 Sqm
20 Enamel Paint Works in Doors & Windows(Double the Area of Flush Door) 2.62 Sqm

C SEPTIC TANK & SANITARY FITTINGS


1 Site clearance
Toilet 1 3.00 2.00 6.00
Soak Pit 1 1.77 1.77
Total 7.77 Sqm
2 Earthwork in Excavation
Foundation 1 3.00 2.00 2.20 13.20
Soak Pit 1 1.77 2.00 3.53
Total 16.73 Cum
3 Brick soiling On Edge
Foundation 1 3.00 2.00 6.00
Soak Pit 1 1.77 1.77
Total 7.77 Sqm
4 Lean Concrete (1:2:4)
In Foundation 1 3.00 2.00 0.10 0.60
Soak Pit 1 1.77 0.05 0.09
Total 0.69 Cum
5 Brick Masonry Works in 1:6 C/S Ratio
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
Partion wall 1 10.00 0.23 2.00 4.60
Baffle wall 1 1.50 0.10 1.75 0.26
Soak Pit 1 0.90 2.00 1.80
Total 6.66 Cum
6 Backfilling of Earth in Foundation 50% of Total Excavation 8.37
Total 8.37 Cum
7 PCC 1:2:4 for RCC Works
Slab 1 3.00 2.00 0.10 0.60
Soak Pit 1 4.71 0.10 0.47
Total 1.07 Cum
8 Reinforcement Bar for RCC Works
Slab 130 g/Cu.m. 0.60 78.00
Soak Pit 17.55
Grand Total= 95.55 Kg
9 Form Work
Foundation PCC Side 1 10.00 0.10 1.00
Slab 1 3.00 2.00 6.00
Side of Slab 1 10.00 0.10 1.00
Grand Total= 8.00 Sqm
10 Cement Sand Plaster of 12.5mm Thick of 1:4 C/S ratio
In Floors 1 2.40 1.50 3.60
In Partion wall 2 1.50 2.00 3.00
In baffle wall 2 1.50 1.75 2.63
In Partion wall 4 1.20 2.00 2.40
Outer Wall Above GL 1 10.00 0.30 3.00
Total 14.63 Sqm
11 Neat Cement Punning of 3 to 3.5mm Thick Same As Item No 11.63 Sqm
12 Pan With All Necessary Fittings & Transportation
Commode Pan 1 1.00 Set
Ceramic Pan (Normal) 1 1.00 Set
13 Low levelled Cistern (Plastic) 2 1.00 Set
14 Wash Basin (16"X22") 1 1.00 Set
15 Supply & fixing for plastic Tank ( 500 Ltr.) 1 1.00 No.
Supply and Installation of Brass Tap, Shower,
16 All type Pipe with all Necessary Fitting (8 1 1.00 Job
point connection)
D ELECTRIFICATION
Electricity Wiring for POWER SOCKET 3 Point
1 (Concealed-all set with 3/20 copper wire)
Electricity Wiring (Concealed-all set with 20 Point
2 3/22 copper wire)
Ceiling Fan (42") (NS/ISI)With Regulator of 3 Set
3 5 Steps
4 CFL light set with holder 12 Set
5 Power Socket 3 Set
Power Socket 5/16 Ampere 5 Pin with light 3 Set
6 indicator & Box.
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
7 HDD Pipe of 15 to 20mm in Diameter 35 m
8 MCB 3 No.
9 MCB Box 1 No.
10 Main Switch-60 Ampere 1 No.
11 Service Wire 50 m
12 Plastic Meter Box 1 No.
13 Meter 1 No.
QUANTITY ESTIMATE

Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Valve Chamber(0.9*0.9*1)

Height or
S.No. Description of Works No. Length Breadth Quantity Unit
Breadth

1 EARTH WORK

Layout & setting out of the building


including site clearance of grass, shrubs
excavation of loose/soft soil to
1.1
maximum depth of 15mm. Including
dressing, levelling and disposal the
excavated materials within the premises.
1 2.00 2.00 4.00
Total 4.00 m2

Earthwork in excavation in all kinds of


soil and diposing lead up to 30m
including dressing of sides, ramming of
1.2 bottom, watering, ramming,
consolidation and dressing, with all
necessary shoring and dewatering as
well as backfilling the trench and
compact 1 1.60 1.60 1.23 3.14
Total 3.14 m3

1.3 Back filling 1 40% of Excavation 1.25 m3

2 CONCRETE WORK

Supplying, mixing, placing, compacting


2.1 & curing different mixes of plain cement
concrete for foundation bases & floors
excluding the cost of formwork &
reinforcement bars, as per drawing,
specification & instruction all complete
a) M15(PCC) 1 4.60 0.55 0.10 0.25
b) M15(RCC) 1 1.40 1.40 0.15 0.29
c) Beneath valve 1 0.13 0.10 0.24 0.00
Total 0.55 m3
Supplying, fixing, cutting, bending,
2.2 binding and placing in position steel
reinforcement bar including the cost of
14 gauge galvanized iron binding wire
all complete as per drawing,
specification and approval of engineer.
a) Tor Steel 31.12
Total 31.12 kg

2.3 Providing, placing, fixing centering and s 4 2.30 0.10 0.92


Providing & laying Brick masonary 4 1.40 0.15 0.84
using with 1:6 cement sand mortar 1.40 1.40 1.96
including scaffolding, curing, cleaning,
Total 1.76 m2
and racking out mortar joints & making
3 BRICKWORK
ducts, recesses where required as per
3.1 drawing, specification & approval of
engineer. 1 4.60 0.25 1.00 1.15
Total 1.15 m3

Dry flat brick soling in foundation and


3.2 floors in true line & level including
watering, compacting etc. all complete
as per drawing, specification &
instruction.
a) On flat 1 1.60 1.60 2.56 m2
Total 2.56 m2
4
PLASTER AND FINISHING WORK

Providing and laying 12.5mm thick


plaster on wall with 1:6 cement sand
4.1 mortar in perfect line and level
including scaffolding, curing etc. all
complete as per drawing, specification &
instruction. 1 0.9 0.9 0.81
4 0.9 1 3.60
Total 4.41 m2

4.2 3mm cement punning Work (1:1) Same as Plaster 4.41 m2


Remarks
QUANTITY ESTIMATE
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Fire Hydrant
S.No. Description of Works No. Length Breadth Height Quantity Unit Remarks
1 Earthwork in excavation 1 2 0.60 0.90 1.08 m3
2 Back filling 1 2 0.6 0.9 1.08 m3
3 Concrete Work
3.1 M20 Concrete Work 1 0.6 0.6 0.15 0.054
1 0.07068583470577 0.05 0.003534
1 0.01767145867644 0.05 0.000884
1 0.44178646691107 0.15 0.066268
Total 0.124686 m3
Deductions
1 0.2355 0.075 0.15 0.002649
Total 0.122036 m3
Providing, placing, fixing centering and
shuttering of plywood or steel form
3.2 work
1 0.94248 0.05 0.047124
1 0.47124 0.05 0.023562
1 2.35619 0.15 0.353429
Total 0.424115 m2

4 Stone Work
4.1 Boulder Soling 1 0.07068583470577 0.15 0.010603
1 0.44178646691107 0.15 0.066268
Total 0.076871 m3
Deductions
1 0.2355 0.075 0.15 0.002649
Total 0.074221 m3

5 125mm dia road surface box with cover 1 Nos


6 150mm Extension CI/DI pipe 1 1 1m
7 Pipes and Fittings
90/80mm dia HDPE/GI Flange set 1 Nos
80mm dia GI Pipe 3m
80mm dia GI union 1 Nos
80mm dia GI nipple 2 Nos
80mm dia Gate valve 1 Nos
80mm dia GI Elbow 1 Nos
80mm dia DI flange 1 Nos
DN 80 post Fire Hydrant 1 Nos
QUANTITY ESTIMATE
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Pump House
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
A Building
1 Site clearance 1 4.50 3.50 15.75 Sqm
2 Earthwork in Excavation (Centre Line Length)
a)Main Foundation 1 15.00 0.60 0.60 5.40
b)Steps 1 1.60 1.50 0.13 0.31
Total 5.71 Cum
3 Flat Brick Soiling
a)In Foundation 1 15.00 0.60 9.00
b)In Floors of Room 1 4.00 3.00 12.00
c)Steps Foundation 1 1.60 1.50 2.40
Total 23.4 Sqm
4 Lean Concrete (1:3:6)
a)In Foundation (50mm Thick) 1 15.00 0.60 0.05 0.45
b)Base of Room (50mm Thick) 1 4.00 3.00 0.05 0.60
b)Base of Steps (50mm Thick) 1 1.60 1.50 0.05 0.12
Total 1.41 Cum
5 Brick Masonry Works in 1:6 C/S Ratio
a)In Foundation (200mm Thick) 1 15.00 0.38 0.20 1.14
b)In Foundation (220mm Thick) 1 15.00 0.25 0.22 0.83
c)In Super Structure (upto 4.15m Ht.) 1 15.00 0.25 4.15 15.56
d)Steps 1 1.60 1.50 0.58 1.38 Avg ht.
Total 18.91
Deductions
Window 3 1.20 0.25 1.50 1.35
Door 1 1.15 0.25 2.13 0.61
Tie Beam 1 15.00 0.25 0.25 0.94
DPC 1 15.00 0.25 0.05 0.19
Lintel Beam 1 15.00 0.25 0.15 0.56
Slab Beam 1 15.00 0.25 0.25 0.94
Net Quantity 14.32 Cum
6 Backfilling of Earth in Foundation 50% of Total Excavation 2.86
Earth filling and compaction for room 1.43
Total 4.28 Cum
7 PCC 1:2:4 for RCC Works
a)Slab 1 5.70 4.70 0.13 3.35
b)Periphery Beam 1 15.00 0.25 0.25 0.94
c)In Lintel Above Opening 1 15.00 0.25 0.15 0.56
d)Corner Columns
Base of Column 4 1.20 1.20 0.15 0.86
Trapezoidal Portion 4 0.75 0.40 1.20 Average
Area
Below Ground Level 4 0.60 0.25 0.25 0.15
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
Upto Plinth Level 4 1.15 0.25 0.25 0.29
Upto Slab 4 2.75 0.25 0.25 0.69
Above Slab 4 0.60 0.25 0.25 0.15
e)Tie Beams 1 15.00 0.25 0.25 0.94
Total 9.13 Cum
8 Reinforcement Bar for RCC Works
a)Periphery Beam
12 mm Diameter Bar 4 15.00 Unit Wt. 0.89 53.40
8 mm Diameter Bar for Stirrup 101 1.05 Unit Wt. 0.40 41.90
b)In Lintel above Door and Window
10mm Dia Bar 4 15.00 Unit Wt. 0.62 37.20
8 mm Diameter Bar for Stirrup 101 0.85 Unit Wt. 0.40 33.92
c)Tie Beam
10 mm Diameter Bar 4 15.00 Unit Wt. 0.62 37.20
8 mm Diameter Bar for Stirrup 101 1.05 Unit Wt. 0.40 41.90
d)Column Corner
12 mm Dia Bar 16 5.48 Unit Wt. 0.89
77.96
8 mm Diameter Bar for Stirrup 56 0.50 Unit Wt. 0.223
6.24
Development length for top bar 16 0.45 Unit Wt. 0.89
6.41
Footing Jali (10 mm dia bars) 18 1.32 Unit Wt. 0.62
14.73
Sub Total
350.86
Lap & Hooks 10 % of above 35.09
Total 385.94 Kg
C. Slab of Building 130 g/Cu.m. 3.35 435.34
Grand Total= 821.28 Kg
9 Form Work
a)For Tie Beam 2 15.00 0.25 7.50
b)Lintel for Opening
i) Side of Lintel 2 15.00 0.15 4.50
c)Room 1 5.70 4.70 26.79
1 20.80 0.13 2.60
d)For Slab Beam 2 15.00 0.25 7.50
e)For Column 4 5.48 0.25 5.48
Base of Column 4 4.80 0.15 2.88
Grand Total= 57.25 Sqm

10 Earth Filling & Compaction up to 500mm


a)In Floors of Central Room 1 4.50 3.50 0.35 5.51
Total 5.51 Cum
11 Sand of 75 mm Thick Filling in Floor
a)In Floors of Central Room 1 4.50 3.50 0.075 1.18
Total 1.18 Cum

12 Cement Sand Plaster of 12.5mm Thick of 1:4 C/S ratio


a)In Floors and Ceilling of Central Room 1 4.00 3.00 12.00
2 7.00 3.00 42.00
b)Outer Walls 2 7.00 4.15 58.10
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Depth
Total 112.10
Deduction
Window
W 3 1.20 1.50 5.40
Door
D 1 1.15 2.13 2.45
Total Deduction 7.85
Net Quantity 104.25 Sqm
13 Neat Cement Punning of 3 to 3.5mm Thick
a)In Floors and Cilling of Central Room 1 4.00 3.00 12.00
2 7.00 3.00 42.00
Total 54.00 Sqm
14 Doors & Windows Frame of Sal Wood
Door-D
Long Wood 2 0.10 0.07 2.13 0.03
Short Wood 1 1.15 0.07 0.10 0.01
Window-W
Long Wood 4 0.10 0.07 1.50 0.04
Short Wood 2 1.20 0.07 0.10 0.02
Total 0.10 Cum
15 38mm panelled Shutter Sal Wood For Door 1 1.00 2.06 2.06
2.06 Sqm
16 Glazed Shutter in Window
Window-W 3 0.40 1.40 1.68
Total 1.68 Sqm
17 Cement Wash on Inner & Outer Walls 104.25 Sqm
18 Enamel Paint Works in Doors & Windows(Double the Area of Flush Door) 3.74 Sqm
19 MS Grill Work for Window 1 13.50 Sq.m. 1.68 22.68 Kg
QUANTITY ESTIMATE
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Pipe for Distribution Pipelines

S.No. Description of Items Quantity Unit Remarks


A Pipes
HDPE Pipes Designed
1 110mm φ PN-6 147 m
2 90mm φ PN-6 248 m
3 75mm φ PN-6 653 m
4 63mm φ PN-6 291 m
5 50mm φ PN-6 152 m
6 40mm φ PN-10 591 m
7 32mm φ PN-10 66 m
Total 2,148.00
QUANTITY ESTIMATE
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Road Crossing
S.No. Description of Works No. Length Breadth Height Quantity Unit Remarks

Earthwork excavation in gravel mixed


1 soil 1 6.45 0.45 0.9 2.61225
2.61225 m3
Earthwork in backfilling in gravel
2 mixed soil 1 6.45 0.45 0.6 1.7415
1.7415 m3
3 P.C.C. M15 in crossings 1 6.45 0.45 0.3 0.87075 m3
Cutting of black topped area including
4 reinstatement works 1 6.45 0.45 2.9025 m2

Cutting of shoulders of Highway (sub-


5 base) including reinstatement works 2 0.45 0.6 0.54 m2

6 Dismantling of Stone Masonary Works 1 0.45 0.5 1.5 0.3375 m3


7 Dismantling of Concrete Works 1 0.45 0.5 0.1 0.0225 m3

You might also like