Professional Documents
Culture Documents
Segunda Sesión - Introducción A Contratos NEC
Segunda Sesión - Introducción A Contratos NEC
Estándares Internacionales de
Construcción
Programa Especializado en Derecho de la
Construcción
2
§ Martin Barnes designado para elaborar “a
radical new contract which would stimulate
and not frustrate the application of good
project management”.
3 4
Barnes recuerda que:
“our philosophy was to produce something which cured every known ill of traditional
contracts. We did not have to compromise. Everything we thought would be a good idea
went in – and we could decide what to put in solely on the basis of what would stimulate all
those who used it to manage their contribution well”.
1 § Reporte Latham:
“Endlessly refining existing conditions of contract
will not solve adversarial problems. A set of basic
principles is required on which modern contracts
3 4
can be based. A complete family of interlocking
documents is also required. The NEC fulfils many of
these principles”.
1 2 § Barnes señaló:
“We expected to get some flack from the lawyers
but we under-estimated how much there would be
and how long it would be sustained. Lawyers
generally have nothing to say about how to
4
manage a contract well, but they do know how to
sustain an argument about what the tortuous
language of traditional contracts might mean or
has been ruled to mean”.
§ Gobierno Británico lo respaldó.
1 2
§ Cuarta versión del NEC: 2017.
Falta de
Enmiendas etc.
cohesión
SIMPLICIDAD Y CLARIDAD
A Fácil de usar, escrito en tiempo presente, inglés simple.
FLEXIBILIDAD
C 9 cláusulas esenciales, 6 opciones principales, 3 opciones de prevención y
resolución de disputas, 21 opciones secundarias. Se busca evitar la necesidad de
enmiendas hechas a medida, reducir los =empos de negociación y reducir las
disputas. Se busca ser u=lizado en variedad de proyectos y países.
Cláusulas Esenciales.
Opciones Principales.
Opciones Secundarias.
Cláusula 1 – General
Cláusula 3 – Tiempo
Cláusula 5 – Pago
Cláusula 7 – Derechos
Cláusula 9 - Terminación
Opción X1 – Ajuste de Precios por Inflación (para ser usado solo con la Opción A,
B, C y D).
Opción X3 – Múltiples Monedas (para ser usado solo con la Opción A y B).
Opción X20 – Indicadores claves de ejecución (KPI’s) (no usar con Opción X12).
Opción X22 – Involucramiento temprano del contratista (ECI) (para ser usado solo con
Opción C y E).
Opción Y(UK)2 – The Housing Grant, Construction and Regeneration Act 1996.
Para decidir qué opción es la más adecuada para el Proyecto (estrategia), el Cliente
debería considerar lo siguiente:
E Cost-reimbursable contract
Contratos a Costos Reembolsables, en
los que el riesgo financiero es
F Management contract asignado en gran parte a cargo del
Cliente.
• Ubicación:
Battersea, London, UK
• Valor:
£9 million
• Contrato Usado:
PSC, ECC Option A
• Inicio-Final:
2016-2017
• Cliente:
UK Power Networks’ Ed1son
Alliance
• Contratista:
COWI and Joseph Gallagher
Ltd
• Project Manager:
Ed1son Alliance
• Ubicación:
Guy's Hospital, Great Maze Pond,
London, UK
• Valor:
£100 million
• Contrato Usado:
NEC3 ECC Option A
• Inicio-Final:
2013-2016
• Cliente:
Guy’s and St Thomas’ NHS
Foundation Trust
• Contratista:
Laing O’Rourke
• Project Manager:
Aecom
• Ubicación:
Rushbottom Lane, New
Thundersley, Benfleet, Essex, UK
• Valor:
£15.4 million
• Contrato Usado:
ECC Option A
• Inicio-Final:
2016-2017
• Cliente:
Essex County Council
• Contratista:
Morgan Sindall
• Project Manager:
Pick Everard
• Ubicación:
Grafham Water Treatment Works,
Huntingdon, Cambridgeshire, UK
• Valor:
£28 million
• Contrato Usado:
ECC Option C and A
• Inicio-Final:
2012-2017
• Cliente:
Anglian Water
• Contratista:
JN Bentley
• Project Manager:
Anglian Water
• Ubicación:
Kirkthorpe Weir, Wakefield, UK
• Valor:
£5.3 million
• Contrato Usado:
NEC3 ECC Option A
• Inicio-Final:
2015-2016
• Cliente:
Barn Energy/Yorkshire
Hydropower
• Contratista:
Eric Wright Civil Engineering
• Project Manager:
Cobalt Project Management
• Ubicación:
Tuen Mun, Yuen Long, North and Tai
Po districts, New Territories, Hong
Kong
• Valor:
£60 million
• Contrato Usado:
TSC option A
• Inicio-Final:
2015-2019
• Cliente:
Drainage Services Department
(DSD), The Government of the Hong
Kong Special Administrative Region
• Contratista:
China Road and Bridge Corporation
• Project Manager:
DSD
• Ubicación:
Selkirk, Scottish Borders, Scotland
• Valor:
£32.1 million
• Contrato Usado:
PSC, ECC Option A
• Inicio-Final:
2009-2017
• Cliente:
Scottish Borders Council
• Contratista:
CH2M / RJ McLeod
• Project Manager:
CPE Consultancy
• Ubicación:
Kimberley and Mbombela, South Africa
• Valor:
R1.6 billion (£90 million)
• Contrato Usado:
PSC, ECC Options C and F, ECSC, SC,
SSC
• Inicio-Final:
2011-2017
• Cliente:
University of Witwatersrand, representing
the Department of Higher Education
and Training (DHET)
• Contratista:
Murray and Dickson Construction,
Trenton Construction and Qualco
Construction
• Project Manager:
DHET New Universities Project
Management Team
• Ubicación:
Cathedral Square, Christchurch,
New Zealand
• Valor:
£48 million
• Contratos Usados:
PSC, ECC Option A
• Inicio-Final:
2016-2018
• Cliente:
Christchurch City Council
• Contratista:
Southbase Construction
• Project Manager:
Aecom
• Ubicación:
London, UK
• Valor:
£812 million
• Contrato Usado:
ECC Option C
• Inicio-Final:
May 2010 - June 2014
• Cliente:
Heathrow Airport Limited
• Contratista:
Hetco (Ferrovial Agroman
Airports (UK) Limited and Laing
O’Rourke Holdings Limited joint
venture)
• Project Manager:
Duncan Pickard, BAA
• Ubicación:
Cheung Chau and Chi Ma Wan,
Hong Kong
• Valor:
£16.5 million
• Contrato Usado:
ECC option C
• Inicio-Final:
2013 − 2016
• Cliente:
Water Supplies Department,
Hong Kong Special
Administrative Region
Government
• Contratista:
China Road–China Pipeline Joint
Venture
• Project Manager:
Black & Veatch
• Ubicación:
Hong Kong
• Valor:
170 M
• Contrato Usado:
ECC option B
• Inicio-Final:
2012-2014
• Cliente:
CLP Power Hong Kong
Ltd
• Contratista:
Hip Hing Construction
Company Ltd
• Project Manager:
Andrew Chan, CLP
POWER HK
• Ubicación:
Lima, Peru
• Valor:
£400 million
• Contrato Usado:
ECC Option F
• Inicio-Final:
2017-2019
• Cliente:
PEJP Lima 2019
• Contratista:
Besco−Besalco, Cosapi,
Sacyr−Saceem, OHL−JEE
• Project Manager:
PEJP Lima 2019
El Supervisor debe:
a) Verificar si las obras están construidas de conformidad con el contrato.
b) Verificar las condiciones de calidad que haya impuesto el Cliente.
c) Supervisar la identificación y rectificación de defectos.
d) Otras funciones permitidas en el contrato.
Su rol está descrito entre el tradicional de un arquitecto, un ingeniero residente, un representante
del Cliente y el rol de un inspector.
El Contratista.
Subcontratistas y proveedores.
“10.1 The Parties, the Project Manager and the Supervisor shall act as stated in this
contract.
10.2 The Parties, the Project Manager and the Supervisor act in a spirit of mutual trust and
cooperation.”
Código civil
Aún con esta opción, el contrato no llega a ser uno colaborativo al 100%.
NO ES UN CONTRATO COLABORATIVO
No son reclamos.
En general cualquier riesgo que pueda i) aumentar el total de los precios, ii) demorar la
culminación, iii) retrasar el cumplimiento de alguna Fecha Clave, o iv) perjudicar la
ejecución de las obras.
h) Este supuesto no aplica para los eventos compensables que surjan de supuestos atribuibles al
Gerente de Proyecto o al Supervisor.
Código civil
OPCIÓN W1
Adjudicación y no aplica Housing Grants, Construction
A and Regeneration Act 1996 (UK).
OPCIÓN W2
B Adjudicación y sí aplica Housing Grants, Construction
and Regeneration Act 1996 (UK).
OPCIÓN W3
C Dispute Avoidance Board y no aplica Housing Grants,
Construction and Regeneration Act 1996 (UK).
Dispute Review Board (DRB): un tipo de Dispute Board mediante el cual se designan
a lo(s) miembro(s) desde la celebración del contrato de construcción. Se previene
y resuelven reclamos en campo y con información contemporánea. Lo(s)
miembro(s) van a obra regularmente y emiten recomendaciones no vinculantes.
Dispute Combined Board (DCB): una combinación entre DAB y DRB impulsada por
la ICC mediante la cual los miembros pueden emitir decisiones vinculantes o
recomendaciones de acuerdo a lo que las partes consideren más conveniente.
Dispute Avoidance/Adjudication Board (DAAB): creado por FIDIC 2017 para hacer
énfasis en la principal función de los miembros: prevenir antes que solucionar
reclamos. Sigue siendo un DAB.
Código civil
La información es
proporcionada por el
NEC señala que se Contratista, el Cliente, Efectos en la asignación
refuerza la idea de Subcontratistas y de responsabilidades
colaboración. Proveedores para crear la bajo ley peruana.
base del Modelo de
Información.
NEC solo lo
recomienda con
Participación la Opción C –
temprana del Contrato a Intención de
Conocido como
Contratista Precio Meta y usarlo por
“ECI” (Early
para participar Plan de empresas
Contractor
en el desarrollo Actividades y privadas en
Involvement)
del diseño y Opción E – el Perú.
propuestas. Contrato a
Costos
Reembolsables.
No repetir experiencia de
Contratos FIDIC.
§ Evitar incorporar términos subjetivos: “justo”, “razonable”, “a jucio de”, “en opinion de”, etc.