2nd Phase 6 Blocks Completion Schedule - 03.27.2022

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

Description IR 07 IR 08

S.No Category
Target Completion Dates 10-Apr-22 8-Apr-22
A PV Park 31-Mar-22 31-Mar-22

MMS MMS 29-Mar-22 28-Mar-22


1
2 MMS Module 31-Mar-22 31-Mar-22
3 DC Laying of DC cables - 400/500 Sq.mm Completed Completed
4 DC Solar 6 sq.mm Cable laying with HDPE Hose Completed Completed
5 DC SCB Installation Completed

DC DC Earth Pits & Earthing 31-Mar-22


6 31-Mar-22
7 DC MC4 & Y Connectors Termination Completed Completed
B IR Room 10-Apr-22 2-Apr-22
8 IR Floor Casting Completed Completed
9 IR Column upto Roof Beam Completed Completed
10 IR Brick Work Completed Completed
11 IR Roof Beam Completed Completed
12 IR Inner Plastering Completed Completed
13 IR Outer Plastering Completed Completed
14 IR Puff Erection 28-Mar-22 2-Apr-22
15 IR Painting Completed Completed
16 IR Louvers Erection Completed 25-Mar-22
17 IR Doors & Hand Rails 10-Apr-22 28-Mar-22
18 AC Room Electrification
C Yard Foundation 31-Mar-22 28-Mar-22
19 IR IDT Foundation Completed Completed
20 IR HT Panel Foundation Completed Completed
21 IR NIFPS Foundation Completed Completed
22 IR Burnt Oil Pit - IDT Completed Completed
23 IR Burnt Oil Pit - NIFPS Completed Completed
24 IR Yard Fencing 31-Mar-22 28-Mar-22
D Equipment Erection 30-Dec-99 30-Dec-99
25 AC IDT Erection Completed Completed
26 AC HT Panel erection Completed Completed
27 AC NIFPS Erection Completed Completed
28 AC Erection - ACDB, Battery, UPS & RTU Completed Completed
29 DC Inverter Erection Completed Completed
E Cabling & Earthing works 30-Mar-22 27-Mar-22
30 AC AC Earth Pits & Earthing Works 30-Mar-22 26-Mar-22
31 AC IDT to HT Panel HT Cable Laying Completed Completed
32 AC Aux. Cable laying Completed Completed
33 AC 1Cx400 Sq.mm Cable (IDT to Inverter) Completed Completed
34 AC Oil Filtration of IDT Completed Completed
35 AC Termination at Inverter End 29-Mar-22 27-Mar-22
36 AC Termination at IDT End 29-Mar-22 Completed
37 AC Termination at HT Panel 29-Mar-22 Completed
38 AC Aux. Cables Termination 29-Mar-22 Completed
F MV Cable laying 30-Dec-99 2-Apr-22
39 T&C IR to IR Cable Laying
40 T&C Tray Erection 29-Mar-22
41 T&C MV Cable 2-Apr-22
G Testing & Commissioning 8-Apr-22 8-Apr-22
39 T&C VOC Testing 3-Apr-22 4-Apr-22
40 T&C IDT Testing 31-Mar-22 5-Apr-22
41 T&C HT Panel & ACDB 5-Apr-22 5-Apr-22
42 T&C Cables Testing (LT, HT, MV) 5-Apr-22 5-Apr-22
43 T&C SCADA Commissioning 5-Apr-22 5-Apr-22
44 T&C Inverter Pre-Commissioning 7-Apr-22 7-Apr-22
45 T&C Final Stability Testing & Box up 8-Apr-22 8-Apr-22
IR 09 IR 10
13-Apr-22 12-Apr-22
5-Apr-22 10-Apr-22

29-Mar-22 30-Mar-22

4-Apr-22 5-Apr-22 IR No
Completed Completed MW
Completed Completed Target Completion Dates
Completed Completed Ready for Commissioning Dates

5-Apr-22 29-Mar-22 10-Apr-22 31apr


Completed Completed
31-Mar-22 31-Mar-22
Completed Completed
Completed Completed
Completed Completed
Completed Completed
Completed Completed
26-Mar-22 2-Apr-22 29-Mar-22 28-Mar-22
31-Mar-22 5-Apr-22 4-Mar-22 9-Apr-22
26-Mar-22 5-Apr-22 28-Mar-22 10-Apr-22
26-Mar-22 31-Mar-22 29-Mar-22 3-Apr-22
28-Mar-22 5-Apr-22 31-Mar-22 10-Apr-22

31-Mar-22 2-Apr-22
31-Mar-22 5-Apr-22 Completed 6-Apr-22
Completed Completed
Completed Completed
Completed Completed
Completed Completed
31-Mar-22 4-Apr-22 2-Apr-22
27-Mar-22 30-Mar-22
Completed Completed
Completed Completed
27-Mar-22 2-Apr-22 30-Mar-22 5-Apr-22
Completed Completed
Completed Completed
27-Mar-22 31-Mar-22
27-Mar-22 30-Mar-22 28-Mar-22 30-Mar-22
Completed Completed
Completed 28-Mar-22 27-Mar-22
Completed Completed
Completed 31-Mar-22 27-Mar-22
Completed 31-Mar-22 29-Mar-22
25-Mar-22 29-Mar-22 30-Mar-22 29-Mar-22
Completed 30-Mar-22 29-Mar-22
Completed 30-Mar-22 30-Mar-22
30-Dec-99 2-Apr-22
Completed
28-Mar-22
2-Apr-22
13-Apr-22 12-Apr-22
11-Apr-22 12-Apr-22
9-Apr-22 3-Apr-22 12-Apr-22
9-Apr-22 3-Apr-22 12-Apr-22
9-Apr-22 3-Apr-22 12-Apr-22
12-Apr-22 3-Apr-22 15-Apr-22
4-Apr-22 4-Apr-22 5-Apr-22
13-Apr-22 13-Apr-22 8-Apr-22 16-Apr-22
IR 01 to 06 IR 07 IR 08 IR 09 IR 10 IR 12 IR 13
54.0 9.0 9.0 9.0 9.0 9.0 9.0
Ready 10-Apr-22 8-Apr-22 13-Apr-22 12-Apr-22 18-Apr-22 17-Apr-22
Ready 30-Mar-22 27-Mar-22 27-Mar-22 31-Mar-22 15-Apr-22 14-Apr-22
scope mms module mms module
7 252 231 221 21 31 91.67% 87.70%
8 252 250 239 2 13 99.21% 94.84%
9 252 245 217 7 35 97.22% 86.11%
10 252 200 176 52 76 79.37% 69.84%
12 252 235 193 17 59 93.25% 76.59%
13 252 227 98 25 154 90.08% 38.89%

You might also like