METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

FOR APPROVAL

0 04.04.22 L.V.DANH N.H.ANH T.N.Khoa FOR APPROVAL


Rev Date Prepared Checked Approved Details of Revision
Owner

VUNG ANG II THERMAL POWER LLC

Owner’s Engineer

TOKYO ELECTRIC POWER SERVICES CO., LTD

EPC Contractor

PACIFIC CORPORATION JSC

Subcontractor

HOP LUC CONSTRUCTION JOINT STOCK COMPANY

Project

VUNG ANG II THERMAL POWER PLANT PROJECT


Title

METHOD STATEMENT FOR STRUCTURE WORKS

Document No. Rev. Page No.


VA2-OM-MS-SW-01 0 39 page

1|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Contents
I. SCOPE OF WORK........................................................................................................................... 4
1. GENERAL DISCRIPTION ............................................................................................. 4
2. BASES FOR ESTABLISHMENT OF CONSTRUCTION METHODS .............4
2.1 For formulation of construction method. .......................................4
2.2 Supplies and materials. .................................................................................. 5
2.2.1 TECHNICAL SPECIFICATIONS, ORIGIN AND STANDARDS APPLICABLE TO MAIN SUPPLIES,
MATERIALS AND EQUIPMENT USED FOR THE WORK. ..................................................................... 5

2.2.2 MEASURES TO ENSURE THE QUALITY OF EACH TYPE OF SUPPLIES, MATERIALS AND EQUIPMENT.
7
II. PREPARATION WORK ................................................................................................................. 8
1. PREPARATION ............................................................................................................ 8
2. EQUIPMENTS AND MACHINE ..................................................................................... 9
III. CONSTRUCTION ORGANIZATION METHOD ............................................................................ 9

1. CONSTRUCTION SITE ORGANIZATION. ......................................................................... 9


2. REQUIREMENTS. ....................................................................................................... 10
3. MANPOWER AND SITE ORGANIZATION CHART. ..........................................................10
3.1 Site organization chart. ............................................................................. 11
3.2 Manpower for construction. ................................................................... 12

3.3 Construction machinery and equipment. ...........................................13


3.4 Method of selecting tower crane. ( Attachments 1) ...............................................14
3.5 Select method of placing concrete ..........................................................................15
IV. CONSTRUCTION METHOD FOR EACH ITEM .......................................................................... 17

1. CONSTRUCTION METHOD FOR FAMILY APARTMENT .................................................17


1.1. Diagram of foundation construction sequence to the elevation of
0.000 17
1.2. Sequence of construction from elevation 0.00 to the roof top
elevation (typically 1 floor) ..................................................................................... 18
2. CONSTRUCTION METHOD FOR MANAGEMENT HOUSE ...............................................19
2.1. Diagram of foundation construction sequence to the elevation of
0.000 Error! Bookmark not defined.

2|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

2.2. Sequence of construction from elevation 0.00 to the roof top


elevation (typically 1 floor) ..................................................................................... 20
3. CONSTRUCTION METHOD FOR MULTI-FUNCTIONAL GYM AND HEALTH CARE HOUSE 21
3.1. Diagram of foundation construction sequence to the elevation of
0.000 Error! Bookmark not defined.
3.2. Sequence of construction from elevation 0.00 to the roof top

elevation (typically 1 floor) ..................................................................................... 22


4. CONSTRUCTION METHOD FOR SUPERMARKET AND RESTAURANT .............................23
4.1. Diagram of foundation construction sequence to the elevation of
0.000 Error! Bookmark not defined.
4.2. Sequence of construction from elevation 0.00 to the roof top
elevation (typically 1 floor) ....................................... Error! Bookmark not defined.
5. TECHNICAL METHOD FOR FOUNDATION EXCAVATION...............................................24
6. TECHNICAL METHOD FOR BACKFILLING - COMPACTION ............................................25
7. TECHNICAL METHOD OF REINFORCING BAR ..........................................................26
8. TECHNICAL METHOD AND CALCULATE OF FORMWORK ........................................27
8.1. Calculate formwork of beam, floor (Attachments 1) .............................................27
8.2. Technical method of formworks............................................................................. 27
9. CONSTRUCTION METHOD OF CONCRETE ................................................................ 29
10. METHOD OF DISMANTLING FORMWORK ................................................................ 31
11. TECHNICAL METHOD OF CURING CONCRETE .........................................................32
12. TECHNICAL METHOD OF CONCRETE DEFECT TREATMENT ....................................33
13. CALCULATE OF LOAD-BEARING SCAFFOLDING AND COVERING SCAFFOLDING ....33
13.1. CALCULATE OF LOAD-BEARING SCAFFOLDING (ATTACHMENTS 1) ......................33
13.2. SCAFFOLDING COVER .............................................................................................. 34
V. HSSE MANAGEMENT PLAN ..................................................................................................... 36

3|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

I. SCOPE OF WORK
1. General discription
- Structural construction method of Family apartment, Management house, Multi-functional gym
and healthy care house, Supermarket and restaurant.

Symbol Floor Area


No. Items Floor Number Area (m2)
(m2)
1 Family apartment 1 5 11,525 2,240
2 Management house 2 2 2,870 1,428
Multi-functional gym
3 3 1 700 700
and health care house
Supermarket and
4 4 1 1,449 1,449
restaurant
Table 1: Parameter of items as a construction method

Pigure 1 : Construction layout plan

2. BASES FOR ESTABLISHMENT OF CONSTRUCTION METHODS


2.1 For formulation of construction method.
Technical methods for project construction: O&M accommodation is prepared on the following
bases:

4|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

 Construction technical design documents


 Construction Law No. 50/2014/QH13 dated June 18, 2014
 Bidding Law No. 43/2013/QH13 dated November 26, 2013
 Decree No. 63/2014/ND-CP dated June 26, 2014 of the Government detailing the
implementation of a number of articles of the Bidding Law on Contractor selection.
 Decree No. 06/2021/ND-CP dated January 26, 2021 of the Government: On quality
management and construction maintenance.
 Decree No. 59/2015/ND-CP dated June 18, 2015 of the Government: On construction
investment project management.
 Based on actual construction conditions, construction site and implementation schedule.
 Based on the Contractor’s capacity.
 Other regulations.

1. Applicable technical standards


NO ITEM STANDARD
1. Organization construction TCVN: 4055-2012
Concrete and reinforced concrete structures of the whole
2. TCVN: 4453-2012
block - Code of construction and acceptance.
Welding- General tolerances for welded structures- Length
3. TCVN 7296-2003
and corner dimensions - Shape and position.
Compulsory standards for full application - Technical
4. TCVN 5380-1991
regulations on safety in construction.
5. Hot-rolled reinforced concrete. TCVN 1651 – 2008
6. Finishing work in construction.Construction and acceptance. TCVN 303 – 2006
7. Surveying work in construction. TCXDVN 309 – 2004
8. Earthworks. Rules for the construction and acceptance. TCVN 4447 – 2012
9. Foundation work – Construction and acceptance. TCVN 9361:2012
10. Portland Cement. TCVN 2682:2009
11. Portland-puzolan cement. TCVN 4033 : 1985
Water for mixing concrete and mortar - Technical
12. TCVN 4506:2012
requirements.
13. Construction sand. Technical requirements. TCVN 1770:1986
Crushed stone, gravel, crushed gravel used in construction -
14. TCVN 1771 : 1987
Technical requirements.
Brick and stone structure-Construction and acceptance
15. TCVN 4085: 2011
regulations.
16. Construction mortar- Technical requirements. TCVN 4314: 2003
In addition, the Contractor complies with the quality management of construction works, responsibilities
of construction contractors and relevant articles in the Construction Law, Bidding Law and the Decree
on Construction Quality Management. .
2.2 Supplies and materials.
2.2.1 Technical specifications, origin and standards applicable to main supplies, materials and
equipment used for the work.
 Based on the technical criteria and requirements of the Bidding Documents, Design Documents,

5|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

the main supplies and materials will be submitted samples together with the material certificates
and approved by the Investor and the Consultant before putting into use.
 The main building materials.
(Please see List of main materials used for the project)
 Cement: Cement used for construction is mixed Portland according to cement standards TCVN
6260:2009; Portland cement – Technical requirements TCVN 2682:2009.
 The Bidder must at all times provide certification from the cement manufacturer to the required
standards for the period of use, which is issued and signed by an independent consultant. Each
batch of cement must be accompanied by a manufacturer's certificate indicating that the cement
has been tested and analyzed for its chemical composition and physical properties. Each batch of
cement after being brought to the site will be tested and reanalyzed according to current standards.
+ Cement should be kept at the site in the right conditions.
+ Hot cement needs to be stored, not used immediately but not longer than 28 days at the site
warehouse. Do not use cement that has been produced for more than 12 months.
+ Cement must be delivered in the form of intact packaging and labels on the bags, cement must
have enough at the site to ensure continuous construction and must be used in the shortest time
and rotated to avoid the case of storage for a long time, causing poor quality. Cement transferred
to the construction site must be well preserved to prevent water infiltration and humidity due to
climate. Cement stacked in warehouses must have a platform of 30cm above the ground, not more
than 09 bags. It must be well ventilated and moisture resistant. Cement before use must be
checked the quality. Any cement stored at the Site that does not conform to the current technical
standards and quality standards, the Bidder must remove from the Site.
 Sand: Must be supplied from a specified source and in accordance with current technical
standards and must be washed when used, ensuring the correct distribution according to design.
Sand must be obtained from a source capable of providing sand of good quality regularly and
reliably throughout the construction process.
 Stone: Must be supplied from a specified source in accordance with the standards "Complete
reinforced concrete structures", "Aggregate for concrete and mortar - Technical requirements
TCVN-7570: 2006".
+ Needs to be hard, durable, clean, not dirty by impurities that affect the strength and durability of
concrete, such as clay particles, mica particles, coal, organic impurities, iron ore, sulphate salt,
etc. calcium, magnesium. Aggregates must not be mixed with mollusc shells.
+ Inspector must check the supply of tests and requirements for materials before putting into
construction. Aggregates lacking test results are not used.
 Commercial concrete: A certificate of quality and origin at the place of manufacture is required.
The technical requirements comply with the requirements of the Design. Before construction, the
Bidder must submit the distribution and source of input materials.
 Steel: The steel put into use must conform to design requirements. Limit the change of type
compared to the design documents during construction, especially do not replace high strength
steel with lower intensity steel. All bearing steels must comply with the standard "Reinforced
concrete structures TCVN 5574: 2012" and "Concrete reinforcement - TCVN 1651-2008". No
rust, no oil or dirt. Steel must meet ISO 9001 standard.
+ When using imported steel, a technical certificate must be attached and it is necessary to take test
samples according to the standard "Metallic materials - Tensile test - Part 1: Test methods at
room temperature TCVN 197-1:2014" and "Metallic materials - Bending test TCVN 198-2008".

6|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

 Bolts: High-strength bolts (including nuts, washers) after being processed, before being
put into use, must be checked by the technical inspection department of the investor
and tested in qualified laboratories. If it passes, it will be tested and put into use.
+ Bolts for the main structure have a strength of 8.8; yield limit 640; breaking strength 800.
+ Bolts for substructure and anchor bolts have a strength of 5.6; yield limit 300; breaking strength
500.
 Water: Must take samples for analysis and conform to the standards of water
regulations according to the standard TCVN 4506-2012.
 Tiles, paving stones of all kinds: Tiles and paving stones of all kinds must be of the
right type and size according to the design, ensuring quality without warping and must
have a clear origin;
 Seam-lock roofing sheet, thickness 0.53, AZ150
 EPS panel, compact partition, plaster ceiling, paint, door materials...: Must be of the
right type, meet the technical requirements of the design, have a clear origin.
 Painting supplies, electricity, water, lightning protection...etc: Requires the right type,
must have a certificate of quality and origin at the place of production. The technical
requirements comply with the requirements of the Design.
 The list of main materials the Bidder is expected to put into use for the work and the
commitments of the suppliers of materials for the work, presented in the List of main types of
materials and materials for the project. construction.
2.2.2 Measures to ensure the quality of each type of supplies, materials and equipment.
 In order to prevent and limit errors that occur during the construction process, we use the
method of inspection and review right from the first stage. For materials and construction
materials, when gathered on the construction site, they must have the norms and certificates
of meeting design requirements, and be brought to internal inspection first, then the Investor,
Supervision consultants will check. All types of materials and equipment, when brought to
the site for installation, are approved by the Investor, an authorized person or a supervisory
engineer to check the quality and design, to satisfy the requirements of the origin,
manufacturer, and manufacturer have all the characteristics and technical parameters such as
design requirements and requirements stated in the Investor's Bidding Documents for the
works. Materials and equipment used for the project, before installation, are checked for
details, removing all equipment, details that are not suitable or have defects due to
manufacturing quality, only equipment complete in terms of all requirements, especially the
newly installed technical features.
 All equipment has a certificate of origin, the manufacturer, the manufacturer has all the
characteristics and specifications and is installed for electrical testing, testing the operation
before being put into the installation location.
 For construction equipment, it is also periodically inspected and tested by competent
authorities. For people, the Bidder realizes that this is a very important issue in ensuring the
quality of the building. We bring into the project from the Project Manager to highly
qualified workers with experience in high-rise building construction that can meet the
demanding works, high art of the project.
 All kinds of supplies and equipment are stored in the warehouse and scientifically arranged in
rows to distinguish them by number, diameter, length and code for easy taking out, use and
storage. Do not mix rusted and unrusted reinforcement. When placing reinforcement in the
yard outside the field, put 1 high end, 1 low end on a hard foundation with no grass growing.
Steel millet is at least 30 cm higher than the foundation, not more than 1.2 m high and 2 m

7|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

wide. Cement is stored in the warehouse according to the prescribed standards to prevent
water penetration and moisture due to environmental climate. The storage time is guaranteed
not to exceed the specified period. The cement bags that have had the phenomenon of
clumping are absolutely not put and used. Cement must not clump, the amount of cement
passing through sieve No.008 is greater than 85% of the total weight. Cement is kept at the
site in a condition that does not alter its quality. Sealed, non-tear, puncture-proof cement bags
are placed above water and ventilated on a floor more than 30cm above the ground and
protected from water. Loose materials must also be poured in a clean, dry place with
separation to avoid contamination of materials by mud, grease, etc. Electrical supplies,
compact partition panels, gypsum ceiling panels... are stored in a closed, dry and cool
warehouse to ensure that weather factors do not affect the quality of the materials.
 The construction site has from 1 to 2 storekeepers who are responsible for importing and
exporting materials daily. Storekeepers are responsible for making inventory cards in daily
books, regularly checking warehouses and yards to promptly handle problems that may occur
during the construction process.
 Site security is responsible for standing 24/24h at the construction site to protect security and
order on the construction site to avoid loss and damage of materials.
 Inspection and supervision of material quality, construction work is carried out both in the
field and in the laboratory using advanced tools and equipment to assess the quality of
building materials. We put in the works good engineers, experienced in construction and
supervision. A team of skilled workers has executed many projects and works with high
quality.
II. PREPARATION WORK
1. Preparation
- Temporary work preparation
 Construction of temporary facilities for serving the construction: temporary road, temporary
fence, car wash bridge, rebar and formwork fabricating yard.
- Preparation of manpower
 Construction staff:
 Construction staff: The construction staff is a team of experienced staff and engineers, who
have constructed many projects of similar size and nature to this project. The site manager
and deputy site manager will be a person with 06 years of construction experience or more,
having constructed high-rise projects, large-scale renovation and repair in a similar position.
A team of highly qualified staff, having enough specialties suitable to the nature of the
assigned work, with a sense of professional conscience, a high sense of responsibility and
discipline, always ready to receive and complete well assigned tasks.
 Construction worker
 The contractor's workforce expected to be put into the project is a team of workers who are
trained in a highly disciplined working environment, always have a sense of responsibility,
are trained to improve skills, have close supervision. annual assessment and skill check
before starting construction. The workforce is divided into groups under the guidance of the
construction team leaders to ensure the specialization as well as the transmission line in the
organizational chart of human resource arrangement.
 The identification and use of the number of workers, the structure of occupations and high
qualifications to implement the project increases labor productivity and ensures the planned
tasks.

8|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

 Take advantage of available local employees combined with highly skilled manpower to
execute the project
2. Equipments and Machine
- Based on the scale of the work, On the basis of design documents, construction site, as well as
technical features of the equipment and the progress of the work, the Bidder selects the
equipment to be put into use in the project according to each phase and shown in the machine
mobilization schedule that the Bidder will submit to the consultant.
- Certificates of machine and equipment used for the Project are inspected by HCA HSSE
department
III. Construction organization method
1. Construction site organization.
- The whole construction area is separated from neighboring areas by a corrugated iron fence and
covered with tarpaulin to cover dust from the roof of the building to the foot of the building to
ensure environmental sanitation for the construction area with the surrounding area.
- The entrance to this area is located at a convenient location to facilitate the circulation and
transportation of materials and personnel in and out of the construction site. At the entrance gate, a
guard station is arranged to monitor the import and export of materials and manage the entrance and
exit of the construction site. This station is permanently guarded 24 hours a day.
- At construction items, the Bidder arranges construction site warning signs and safety signs in
accordance with current standards and regulations of the state.
- In the total construction site of the project, there is a place to store cement, iron and steel, bricks and
construction equipment, the command house, the security room, the camp area... Reasonable with
production lines and construction site at the facilities in each stage. Mixing and material processing
areas, general power source to distribute electricity for construction and daily life, are arranged in a
very reasonable and safe manner to avoid causing unsanitary conditions and affecting the health of
workers and the surrounding area.
- The material processing area such as iron and steel and wood formwork must be rearranged when
the construction time is over to clear the ground for trucks carrying materials and waste. The storage
yards for materials, materials and processing yards are arranged without causing dust and noise,
usually at the end of the main wind direction and with measures to shield against dust, cushion to
reduce noise...
- Material handling: Transported by crane, winch with lifting capacity ≥ 0.5 tons. Horizontal
transportation using Cars and specialized vehicles (improved vehicles, wheelbarrows...). The closest
guaranteed transport distance, less vibration when transporting.
- At convenient locations, garbage bins and solid waste dumps are arranged to avoid littering and
indiscriminate dumping of waste on the construction site.

9|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Pigure 1 : – Foundation construction organization plan

Pigure 2: Structural construction organization plan


2. Requirements.
- When arranging the construction site, it does not affect the operation and general landscape,
ensuring traffic, safety and environmental sanitation. Ability to quickly adapt to unexpected
changes...
- The layout of the construction site must be reasonable and convenient, minimizing dust and noise
affecting the operation of the surrounding area and not obstructing the construction process.
- Ensure reasonable construction without overlap causing work stoppage and unsafety.
- Ensure safety during construction.
- Ensure security and order and good fire prevention.
3. Manpower and site organization chart.

10 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

3.1 Site organization chart.


TRINH NGOC KHOA
Site Manager
0903468016

HOANG TRUNG DUNG


Deputy Site Manager
0836333558

P.T.DONG D.H.HUNG TR.V.QUAN


Team Leader Surveyor Manager HSSE Manager
0778408386 0333519957 0979498881

D.T.TUAN L.D.HOA NG.H.ANH TR.D.LAP


Site Engineer Site Engineer Site Engineer Team Leader
0943666338 0387283606 0357994057 0973710987

- To operate the project, the Contractor establishes a Project Management Unit. Under the executive
board are the assisting department and direct construction teams, performing the construction of
specific items of the work.
Relationship between the Board of Management and the site management department
- The Board of Directors of the Company directly guides the departments and the Site Management
Unit, assigns departments in the field of expertise, directly guides and inspects the site manager to
effectively execute the contract, take appropriate construction methods, processes, regulations,
quality acceptance, technical handling, equipment and construction safety, supply of materials and
human resources.
- The site management department, which is directly the site manager, must regularly report to the
Board of Directors on the construction situation and management aspects on the site. The Site
Manager is responsible for regularly coordinating with relevant departments to fully implement the
requirements. Ensure the construction works continuously according to the Design documents to
ensure the technical quality of the project, at the same time coordinate to solve problems in each
construction area in th best timely and effective manner.
Site manager
- Perform the tasks assigned by the Board of Directors and take responsibility for the organization of
human resources, techniques, quality and progress of the project, check and urge daily on the
construction process, ensure the right design. Coordinate with the Owner, design consultant,
Owner’s engineer and related parties on issues in the construction site.
Site deputy manager
- Perform the tasks assigned by the site manager, to act on behalf of the site manager in charge of all
work of the construction site in the absence of the site manager.
Department of Progress, Technical and Quality Management
- The head of this department is the construction technical manager - responsible to the Site
Management Unit for the technique, progress and quality of the work.
- The technical department is directly in charge of the progress, construction techniques, quality of
each job, assisting the Site manager and technicians who are always present at the construction site,
and the relationship with Party A and the engineer, consulting engineers in construction technical
solutions, doing the acceptance work, making as-built documents, and daily monitoring diary.

11 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Safety, security and environment management department


- Gather, research and disseminate legal documents on labor protection work to teams. Organize
training courses on labor protection for employees throughout the construction site. The safety
department is managed by a full-time officer and part-time site technicians.
- As officers are directly in charge of safety, security and environment on the construction site and
around, assisting the Site Manager and technicians, always present at the construction site. Take
measures to ensure the safety of people and equipment and ensure a good working environment.
- Responsible for taking care of the health of staff and construction workers. Dispensing drugs for
minor illnesses. When an accident occurs, the medical department will conduct first aid, give first
aid to the patient, and depending on the case, they will transfer to the hospital for emergency. Report
regularly to the site Management Unit, the company's board of directors on the situation of
occupational accidents in the construction site.
Administration and finance department
- As the department responsible for monitoring and supervising the use of people, such as paying
workers, providing money for the material and equipment department, this department is closely
related to the direct construction teams and equipment parts.
- Responsible for the supply of materials and equipment reported by the technical management
department, this department basically determines the quality of the product, this department is one
of the important factors determining the construction progress.
Production teams
- Follow the direction of the technical management department for each work area.
- Includes teams: Construction motorbike, formwork + scaffolding + reinforcement + concrete,
masonry + finishing, mechanical group, aluminum and glass, plaster + paint, electricity and water
team, construction team.
- Each team will include 01 team leader and 01 supervisor who is responsible for managing the team's
human resources, progress, and quality before the project Management Unit.
- The above field organization model always puts the quality and construction progress on top. It
shows the scaled work and planned organization, there is the expertise of each production team, on
the other hand it ensures the dynamism of each production team.
Workforce management
- Well perform the registration of temporary absence with local authorities.
- Ensure absolute security and order, social safety in the area
- Establish site rules and regulations on labor safety, organize for workers to study and strictly
implement the set rules.
- Workers entering and leaving the construction site must have a card provided by construction unit.
3.2 Manpower for construction.
- Workforce serving the construction of Family apartment, Management house, Multi-functional
gym and health care house, Supermarket and restaurant.

12 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

No Site Construction Team QS,QA,QC, Surveyor


Work item Engineer
. manager manager leader Shopdrawing
1 Family apartment 1 1 2

2 Family apartmen 2 1 2

3 Management house 1 4
1 1 6 3 (team)
Multi-functional
4 gym and health 1 3
care house
Supermarket and
5 1 3
restaurant
Table 3.1 Construction staff

No. Work item Quantity Scope of work


1 Formwork worker 50
2 Rebar worker 30 Workers are rotated
3 Formwork erector 15 from one item to another
depending on the actual
4 Concrete worker 20
construction
cleaning workers, concrete curing
5 20
worker...……
Table 3.2 Construction worker
3.3 Construction machinery and equipment.
 Mobilizing machine and equipment serving the construction of Family apartment, Management
house, Multi-functional gym and health care house, Supermarket and restaurant.

No. Type of machine Quentity (set) Scope of work


1 Excavator 5 Foundation, road
2 Bulldozer 2 Foudation, road
3 Concrete mixer 4 Brick work
4 Roller 2 Foudation, road
5 Bending machine 2 Rebar fabrication
6 Self-propelled crane 1 Material unloading
7 Tamping rammer 4 Soil foudation
8 Hoist 2 Material movement
9 Tower crane 1 Material lifting
10 Welding machine 8 Formwork…..
11 Drilling machine 4 Formwork, concrete
12 Air compressor 1 Formwork cleaning
13 Common portable tools 6 Formwork ….
14 Dump truck 3 Foundation, road
15 Oxyacetylene cutter 4 Formwork ….
Table 3.3 List of Machine

13 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

3.4 Method of selecting tower crane. ( Attachments 1)

14 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Figure 3.1: Tower crane foundation


3.5 Select method of placing concrete
- Concrete placing using concrete pump with a length of 27(m), 29(m), 33(m), 47(m), 51(m) brand
ISUZU, year, place of manufacture :2010, Japan – China. Depending on the construction item to
choose the pump length

Figure 3.2 : Concrete pump truck

- Depending on the volume of each batch to choose concrete mixer truck, the contractor has
concrete mixer trucks with a transport volume of 9(m3), 12(m3). There are 20 mixer trucks
running in total

Pigure 3.3 : Concrete mixer truck

15 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Figure 3.4 : Transport concrete from the batching plant to the site

16 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

IV. Construction method for each item


1. Construction method for Family apartment
1.1. Procedure of foundation for Family apartment

Construction layout plan

Pile driving construction

Foundation excavation

Lean concrete work of foundation, beam

Cutting pile head

Foundation rebar fabrication and installtion

Foundation formwork fabrication and instalation

Concrete work of foundation, beam

Column rebar fabrication and installation

Column formwork fabrication and installation

Column concrete work

Foundation wall construction

Sand backfilling and compaction

Rebar fabrication and installation of foundation beam

Formwork fabrication and installation of foundation beam

Concrete work of foundation beam

Base gravel bacfilling and compacting

Indoor anti-termite

Rebar fabrication and installation of floor slab

Concrete work of floor slab

17 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

1.2. Procedure of structure from cos 0.00 for Family apartment (typical 1 floor)

Column layout plan

Column rebar fabrication and installation

Column formwork fabrication and installation

Column concrete work

Installation of scaffolding support floor beam

Formwork fabrication and installation of floor beam

Rebar fabrication and installation of floor beam

Floor beam concrete work

Dismantle formwork

18 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

2. Construction method for Manager house


2.1. Procedure of foundation for Manager house

Construction layout plan

Foundation excavation

Lean concrete work

Rebar fabrication and installtion

Formwork fabrication and instalation

Foundation concrete work

Column rebar fabrication and installation

Column formwork fabrication and installation

Column concrete work

Foundation wall construction

Soil compaction

Sand backfilling and compaction

/Rebar fabrication and installation of foundation beam

Formwork fabrication and installation of foundation beam

Concrete work of foundation beam

Base gravel bacfilling and compacting

Indoor anti-termite

Rebar fabrication and installation of floor slab

Concrete work of floor slab

19 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

2.2. Procedure of structure from cos 0.00 for Manager house (typically 1 floor)

Column layout plan

Column rebar fabrication and installation

Column formwork fabrication and installation

Column concrete work

Installation of scaffolding support floor beam

Formwork fabrication and installation of floor beam

Rebar fabrication and installation of floor beam

Floor beam concrete work

20 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

3. Construction method for Multi-functional gym and health care house


3.1. Procedure of foundation for Multi-functional gym and health care house

Construction layout plan

Foundation excavation

Lean concrete work of foundation

Foundation rebar fabrication and installtion

Foundation formwork fabrication and instalation

Concrete work of foundation

Column rebar fabrication and installation

Column formwork fabrication and installation

Column concrete work

Soil backfilling and compaction

Rebar fabrication and installation of foundation beam

Formwork fabrication and installation of foundation beam

Concrete work for foundation beam

Base gravel bacfilling and compacting

Indoor anti-termite

Rebar fabrication and installation of floor slab

Concrete work of floor slab

21 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

3.2. Procedure of structure from cos 0.00 for Multi-functional gym and health care house
(typical 1 floor)

Column layout plan

Column rebar fabrication and installation

Column formwork fabrication and installation

Column concrete work

Installation of scaffolding support floor beam

Formwork fabrication and installation of floor beam

Rebar fabrication and installation of floor beam

Floor beam concrete work

Column rebar fabrication and installation

Column formwork fabrication and installation

Anchor bolts installation

22 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

4. Construction method for Supermarket and restaurant


4.1. Procedure of foundation for Supermarket and restaurant

Construction layout plan

Foundation excavation

Lean concrete work of foundation

Foundation rebar fabrication and installtion

Foundation formwork fabrication and instalation

Concrete work of foundation

Column rebar fabrication and installation

Column formwork fabrication and installation

Column concrete work

Soil backfilling and compaction

Rebar fabrication and installation of foundation beam

Formwork fabrication and installation of foundation beam

Concrete work for foundation beam

Base gravel bacfilling and compacting

Indoor anti-termite

Rebar fabrication and installation of floor slab

Concrete work of floor slab

23 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

4.2. Procedure of structure from cos 0.00 for Supermarket and restaurant

Column layout plan

Column rebar fabrication and installation

Column formwork fabrication and installation

Column concrete work

Installation of scaffolding support floor beam

Formwork fabrication and installation of floor beam

Rebar fabrication and installation of floor beam

Floor beam concrete work

5. Technical method for foundation excavation


 In order to ensure the safety of the building and suit the actual conditions, proceed to choose the
solution of excavating soil by an excavator combined with repairing manually the excavated
foundation pit by the excavator to about 10cm from the design depth - :- 15cm then stop and
proceed to manual repair of foundation pit.
 From the excavation ground, we choose the method of excavation as follows: the excavator goes
along the axes. The excavated soil is poured onto the dump truck, the direction of soil
transportation and excavation is perpendicular to each other.
 The foundation pit is excavated with a 45-degree bevel, limiting the subsidence.
 After the excavator is finished, we proceed to excavate the soil manually
 Excavating tools are: shovel, hoe, trowel, soil pipe cutter
 Manually excavated soil is poured at the yard, not transported to another place.
 Excavation construction
 The volume of soil excavated manually is relatively big, so it is necessary to organize the
construction appropriately to avoid crowded people in one place and clear construction line
segregation
 Excavating sequence is similar to the excavator
 When repairing the foundation pit is completed, we proceed to make the foundation layer to
avoid the aggressiveness of the environment that disrupts the soil structure, especially rainwater.

24 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Pigure 5.1: Foundation excavation plan

Figure 5.2: Foundation pit excavation

Figure 5.3: Manually repair and compaction of foundation


6. Technical method for backfilling - compaction
- Backfilling can only be carried out after concrete pouring, foundation wall bracing, underground

25 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

pipes installation have been completed and accepted by the Owner and allows moving to the next
construction step.
- Backfilling is carried out in the following order:
 Check the area to be filled, remove all excess materials and waste of previous construction stages
such as construction debris...
 Mark the level of foundation to be filled with red paint on the foundation or wall
 Level the areas to be filled to create a relatively flat and compact
 Spread the soil in layers with a thickness of 35-40cm. During spreading, it is necessary to remove
impurities and unsuitable blocks of material.
 Use Mikasa tamping rammer to compact. The turns of compaction must overlap at least 10cm.
The compaction process can be considered to add water to achieve optimum moisture content.
 Density check must be done regularly and deal with unsatisfactory areas.
 After completing the compaction for the first layer, spreading and compacting for the next layers
can be carried out.
 The process of backfilling and compacting must ensure that the compaction coefficient is not
lower than 0.95.

Figure 6.1 Backfilling - compaction

7. Technical method of reinforcing bar


 The reinforcing bar used in concrete is strictly according to the design drawings in terms of type,
quantity, quality and diameter.
 Before using, the Contractor will send the quality inspection results to the Owner’s engineer, the
Owner.
 Before fabricating, rebar is prepared and checked according to the following regulations
 Surface must be clean, free of mud, soil, grease or paint
 No surface defects.
 Steel grade and rebar diameters must be in accordance with the design.
 Before fabticating, rebar is straightened, checked before concrete is poured. Check the size of
rebar, welds (no foam, smooth & seamless surface), inflection point, quantity of steel, starter
bar... Rebar must comply with the design
 Checking rebar: having certificate of rebar provided with correct requirement, uniformity in size
and section, correct required diameter, ensuring design requirements;
 Rebar outer surface: clean surface, no reduction in local cross section over 2% of diameter;

26 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

 Cutting and bending: technical process guarantee


 Bending reinforcement: deviation does not exceed the allowable tolerance;
 Starter bar and pre-set details: ensure the specified requirements of the design
 Rebar tying: ensure the overlapping tying length according to regulations;
 Installing rebar: installing in accordance with the technical process; type, location, quantity and
size according to the design; tolerance within the allowable range;
 Concrete spacer: Cast with XM mortar, with the thickness of the reinforcement covering layer
such as foundation braces, 35mm thick foundation, 20mm thick floor beams
 Thickness of concrete layer protecting reinforcement bar: According to design regulations and
deviation within allowable range;

Figure 7.1 Filling - compaction

8. Technical method and calculate of formwork


8.1. Calculate formwork of beam, floor (Attachments 2)
8.2. Technical method of formworks.
 In this project, we use film-coated plywood formwork for construction.

Figure 8.1 Film-coated plywood formwork use the construction


 Formwork and brace, support system are designed in advance and will be fabricated according to
drawings. The Contractor is responsible for the structural design and dismantling of the
formwork. Defective, improperly cleaned and unsuitable formwork shall not be used. Warped,
damaged, broken or defective formwork will be removed out of the construction site
 The formwork for beams and floors is designed with a curvature according to the formula

27 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

f=3L/1000. The bearing parts of the falsework are not connected. The braces are calculated and
arranged appropriately to ensure the entire system of formwork, falsework is stable.
 Formwork blocking the end of pouring blocks ensures tightness and stablity, ensures the shape
and size of the stop circuit as specified by the design.
 Before placing concrete, the concrete surface will be cleaned with a water pump.
 Formwork will be checked before placing concrete
 Formwork must be tightly joined so as not to lose cement water
Inspection requirements for installed formwork
 The installed formwork needs to be checked according to the following requirements and the
deviation must not exceed the allowable value.
 Shape and size, structure
 Formwork structure: firm, stable
 Flatness between joining plates
 Tightness between the formwork panels, formwork and ground surface;;
 Non-stick formwork;
 Clean formwork surface
 Inclination, position, elevation and formwork size
Stiffness and stability.

Figure 8.2 Install floor formwork

28 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Figure 8.3 Install column formwork

Figure 8.4 Install beam formwork

9. Construction method of concrete


- Before placing concrete, the Contractor will prepare and submit to the Management Board for
approval, the Contractor will be responsible for the quality of concrete.
- Do not place concrete for columns, floors... without the acceptance and approval of the Owner.
- Concrete is mixed according to the design grade. The concrete mixing and density are calculated
and determined by the Contractor's laboratory or the laboratory designated by the Owner. The
Contractor and the concrete supplier are jointly responsible for overseeing the performance of
mixing and concrete production. The density and results given by the laboratory must be
accepted. Concrete density is the minimum acceptable strength according to the specification on
the basis of test results.
- The Contractor will mix the concrete with a mixer at the batching plant and deliver it to the site
by a dedicated trucks

29 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

- Slump is checked in each batch. (taken by frequency)


- Time from mixing to placing concrete should not exceed 45 minutes.
- Concreting must avoid stratification and displacement of reinforcement bar and formwork
- Concrete is poured continuously and if there is a stop circuit, let the stop circuit according to the
design position
- Rain cover will be prepared in case it rains
Concrete work includes: Preparation of materials for concrete; Determine the mix composition
for each concrete grade and batch.
 Mixing concrete
 Transporting concrete from the place of mixing to the place of pouring
 Placing concrete into formwork, leveling and compacting the concrete
 Curing concrete
 Dismantling formwork
- Before placing concrete, must check and accept formwork, reinforcement bar, working floor
system to ensure technical requirements;
- Clean formwork, reinforcement bar, repair defects and mistakes.
- Pre-water the formwork, use thin material to coat anti- stick agents to prevent the concrete from
sticking to the formwork.
- Before placing concrete on the dry mortar that has been previously poured, the concrete surface
must be cleaned, polished, and watered with cement water on it.
- Before placing concrete on the dry mortar that has been previously poured, the concrete surface
must be cleaned, polished, and watered with cement water on it.
 Limit the height of concrete placing to not exceed 4.0 m;
 Concrete must be poured from the top down; do not distort the rebar
 Concrete must be placed from far to close compared to the receiving position of concrete
mortar, do not use a needle vibrator to move concrete;
 When concreting large blocks, structures with large thickness must be poured into several
layers, the maximum allowable thickness of each layer according to the above table. The time
to stop pouring between layers of concrete without admixtures should not be greater than the
value of the following table
Allowable stopping time when placing concrete without admixtures (minute)
Temperature in the block Portland slag cement,
Porland cement
when placing concrete Puzolan Cement
Bigger than 30 60 90
20 – 30 90 120
10 – 20 135 180
Concrete compaction work
- The concrete compaction will ensure the following requirements:
 Use different types of compaction, but make sure that after compaction, the concrete is
compacted and free of pits.
 The time of compaction at each position, the distance between the positions must be suitable
with the performance of compaction and must ensure that the concrete is thoroughly
compacted (when the cement mortar floats to the surface and the air bubbles are gone) and
must finish compacting concrete before cementation begins .
Handling defects in concrete:
- The Contractor applies all concrete construction methods so that the concrete structure after

30 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

dismantling formwork has no defects. If there are small defects and do not affect the bearing
capacity of the structure, the Contractor will have a treatment plan as part of handling defects
in construction.

Figure 9.1 : Pouring concrete of floor beams

Figure 9.2 : Pouring column concrete


10. Method of dismantling formwork
- Formwork, falsewwork are removed when the concrete reaches the structural design strength of
to withstand its own weight and other impact loads in the later construction phase, possibly
according to the instructions of the tables in TCVN standards;
- When dismantling the formwork, falsework, avoid causing sudden stress or strong impact to

31 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

damage the concrete structure.


- Concrete strength when it is allowed to remove formwork, if the design does not have special
instructions, the Contractor shall comply with TCVN 4453-2012.
- Overhang, console, and eaves structures only remove support poles and bottom formwork
when the concrete strength reaches the design grade and has anti-roll counterweights.
- When dismantling the formwork, falsework in the whole block concrete slabs, do the
following:
 Dismantle the formwork poles of the lower floor slab one by one and keep the safety
poles 3 m apart below the beams.
 The partial loading of the structure after dismantling the formwork, falsework will be
calculated according to the achieved concrete strength, structure type and load
characteristics to avoid cracks. cracks and other damage to the structure.
 The full loading on the structure after dismantling the scaffolding formwork is only done
when the concrete has reached the design strength.

Figure 10.1: Structure after dismantling formwork

11. Technical method of curing concrete


 Concrete curing creates favorable conditions for concrete to harden: not to lose surface water, not
to bear the impact force when the concrete has not yet been able to withstand the impact force. ,
no vibration reduces the bond between concrete and reinforcement bar.
 Moisture curing time according to TCVN 5592:1991, TCXDVN 305:2004
 The project belongs to the climate zone of B
 Dry season: maintain watering at least 4 days
 Rainy season: maintain watering for at least 2 days
 Always keep the surface of the structure moist (use nylon coating to keep the surface moist)

32 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Figure 11.1 Curing concrete


12. Technical method of concrete defect treatment
- The Contractor applies all concrete construction methods so that the concrete structure after
dismantling the formwork has no defects. If there are small defects and do not affect the bearing
capacity of the structure, the Contractor will have a treatment plan as part of handling errors in
construction.
- In case of pitting <= 3cm
Step 1: Sanding the concrete surface with defects + cleaning
Step 2: Use patch mortar equivalent to beam grade to finish the surface
- In case of pitting >3cm
Step 1: carve and erase the entire porous concrete to the solid, homogeneous concrete
Step 2: Clean the surface with water, apply the approved material bonding layer on the carved
position after dry cleaning the surface.
Step 3: Install the formwork for non-shrink grout
Step 4: Moisten the surface before grouting
Step 5: Pour non-shrink self-flowing mortar, grade is equivalent to the pitted structural grade
Step 6: Dismantle the formwork, grind, finish the surface to ensure flatness

Figure 12.1: Defective concrete treatment


13. Calculate of load-bearing scaffolding and covering scaffolding
13.1. Calculate of load-bearing scaffolding (Attachments 1)
Follow the scaffolding procedure VAII-GA04-P0ZEN-71HCA08 has approved by VAPCO

33 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Fifure 13.1: Technical method of install load-bearing scaffolding


13.2. Scaffolding cover
13.2.1. Regulations on scaffolding cover for works include:
+ When constructing works, it is mandatory to use scaffolding covering with nets around. To
ensure the safety of materials and people. For higher constructions, it is necessary to use an
additional layer of mesh on the outside of the scaffolding. For the purpose of ensuring absolute
safety.
+ Scaffolding covering high-rise buildings needs to meet the requirements of structure and
design. As well as construction, operates just like in technical design drawings.
+ In addition, the standard of scaffolding covering for bearing capacity must ensure safety
according to the prescribed tonnage.
+ Workers who install scaffolding cover need to be properly trained. At the same time, comply
with the requirements of the process, techniques. When constructing, workers must be equipped
with adequate protective equipment.
+ The premises where scaffolding is constructed need to be stable, have good drainage grooves.
Scaffolding racks and supports need to be placed vertically. Besides, they need to be anchored
according to the design.
+ When the size of the scaffolding covers more than 6m, it is necessary to have at least 2
working scaffolding. When the scaffolding has a height of over 12m, you need to use the
scaffolding rig as an stairs up and down.
+ Follow the scaffolding procedure VAII-GA04-P0ZEN-71HCA08 has approved by VAPCO

34 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Figure 13.2: Typical of scaffolding cover


13.2.2. Steps to install scaffolding covering
+ To ensure safety during construction, scaffolding covers the works that need to be installed in
accordance with the standards. Concrete:
+ First you need to erect the base of the support column of the scaffolding along with the
padded rack. At the same time, you should resist slippage, anti-subsidence for support columns
+ Next, insert the support column into the base of the column based vertically. Why, you should
anchor according to the design drawing.
+ Erect the legs of the cross-bracing frame of the scaffolding cover. For the purpose of ensuring
the certainty of scaffolding
+ Install the operation floor for workers to move during construction. The floor needs to be
fixed to the scaffolding frame to ensure safety during construction
+ Finally, strain the cover net until you hand over the work to the owner.

Figure 13.3: Detail of install scaffolding covering

35 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Figure 13.4: Detail for typical façade and grounds of install scaffolding covering

V. HSSE MANAGEMENT PLAN


Evaluate the risk and decide on precautions.
The Risk (r) = severity (s) x likelihood (l)
Table 1 - Consequence Levels below assigns a number to a consequence level, but offers some
useful definitions as to what that level means for impacts to environmental, health and safety,
production loss and property damage. Where there is doubt as to which outcome would have the
highest risk level, both should be considered, with the highest one being selected.
Where there is doubt as to which outcome would have the highest risk level, both should be
considered with the highest one being selected.
Table 1: Severity /impact description
Descriptor SEVERITY / CONSEQUENCE/IMPACT DESCRIPTION
/ Grade
Negligible impact on strategic objectives
Negligible Nil/negligible:
Injury, loss, service interruption, environmental/estate impact, impact
(1)
on reputation impact on quality. litigation or complaint
Small variance from overall strategic objective
First aid treatment with full recovery
Low Complaint possible
(2) Local low key external interest
Minor: financial loss (up to 5K),service interruption
,environmental/estate impact, impact on reputation, impact on quality

36 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Notable variance from overall strategic objective


Medical treatment required up to 3 months to recover
Reportable under RIDDOR(Reporting of Injuries, Diseases and
Moderate Dangerous Occurrences Regulations)
(3) Complaint probable
Moderate: financial loss (5K – 200K), service interruption for more
than one week, environmental/estate impact, Impact on reputation.
Local press, stakeholders express concern, impact on quality moderate
loss of information (recoverable), moderate risk of low value claim
Significant variance from overall strategic objective
Long term illness or injury (up to one year)
Reportable under RIDDOR
Complaint expected/received
Major : financial loss (200K – 3M) , service interruption of more
than one month, environmental/estate impact leading to loss of
Major
service, significant impact on reputation, significant medial interest
(4)
more than one week, significant concerns raised by stake holders ,
significant impact on quality including risk of failing to achieve
‘excellent’ in annual health check in one or more standards, major loss
of information (recoverable) , high value claim or action by HSE
anticipated, moderate risk of low value claim
Failure to meet strategic objective threatens independent functioning
or stability.
Death, Financial loss3M+, Certain risk to reputation, national press3+
Extreme/ days, of C questions Serious/long term and/or permanent loss of
Catastrophic information that impacts directly on service delivery, Quality-
(5) External controls exerted, Threat of Judicial review, expected
litigation valued at 1M+,High profile breach of confidential
information (eg patient identity) Buildings/property condemned
leading to major loss of service
Determination of Likelihood
Likelihood can be examined with regard to the chance that a particular outcome will happen to
any of the following:
• A single person or member of the general public
• The project (more persons potentially exposed)
Table 2 – Likelihood Levels below assigns a number to the likelihood. As can be seen,
likelihood can be very variable. In order to protect people on a Project, the Likelihood Level for
“Project” should be used.

LIKELIHOOD OF REPEAT EVENT


Score Descriptor
DESCRIPTION
Very unlikely to
1 Will only occur in exceptional circumstances.
occur

2 Unlikely to occur Unlikely to occur but the potential exists

37 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Reasonable chance of occurring – has happened before


3 Could occur
on occasions

4 Likely to occur Likely to occur – strong possibility.

Almost certain to
5 The event is expected to occur in most circumstances.
occur

Table 3 – Likelihood Levels


• Use the Risk Matrix Tool and guidance in the Risk Assessment pro forma to grade the
risk.

Table 3: Risk Score Matrix

Almost certain
5 5 10 15 20 25
to occur
Likelihood

Likely to occur 4 4 8 12 16 20

Could occur 3 3 6 9 12 15

Unlikely to
2 2 4 6 8 10
occur
Very unlikely
1 1 2 3 4 5
to occur
1 2 3 4 5
Catastrophi
Risk Matrix Negligible Minor Moderate Major
c / Fatal
Consequence
Risk Level Matrix
A combination of Tables 1 and 2 can be used to evaluate the risk by determining the overall risk
level of a particular outcome eventuating.
The matrix (Table 3 - Risk Level Matrix) below is shown in the conventional format of
Consequence on the horizontal axis increasing to the right and Likelihood on the vertical axis
increasing with height.
Escalation of Risk is determined by risk score
Table 4: Escalation of Risk

Risk level Risk score Escalation level

Extreme Board of Directors


15- 25
Red
High Management committee (reporting to Board)
9-12
Orange

38 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION

Moderate Yellow 6-8 Directorate/Department

Low Department but monitored at


Green 1-5 Directorate level
(tolerated risks)

A note regarding terminology:


• For an initial risk assessment, the Risk Level is known as the Risk Factor Number
(RFN).
• For a residual risk assessment, the Risk Level is known as the Residual Risk Number
(RRN).
• In both cases, the risk level dictates the response and timing of risk controls required.
Management of Risk Assessment
The management of risks identified through the risk assessment process will be determined by
the risk rating.
The amount of effort/resources that are to be committed to an identified risk is determined by the
risk score. The Contractor has a scheme of escalation.
• Risks scored 1-5: are considered low risk (L) and therefore risks are accepted (tolerated)
by the Contractor. No more countermeasures are required.
• Risks scoring 6-8: are considered moderate risks (M) and should be managed /treated so
that they are made as ‘low as reasonably practicable’. These risks will usually be managed
locally. more countermeasures are required. More actions are required to eliminate or
minimize the risk using the Hierarchy of Controls.
• Risks scoring 9-12 are considered high risks (H). Actions needed quickly (within 1-2
days). The task should not proceed unless the risk is assessed and control options selected
based on the Hierarchy of Controls. These risks must be treated, i.e. an action plan should
be developed and implemented that seek to reduce the potential impact of the risk (i.e.
reduces the risk score). These risks will be added to the risk register and will be reviewed
by the Management Committee and overseen by the Clinical Quality, Safety, and
Governance Committee High risks scoring 12 will also be reviewed by the Board.
• Risks scoring 15-25 are considered as extreme/catastrophic risks (EH). Stop the activity,
as it is too risky to do anything else. These risks must be treated, i.e. an action plan should
be developed and implemented that seek to reduce the potential impact of the risk (i.e.
reduces the risk score). These risks will be added to the risk register and will be reviewed
by the Management Committee and the Clinical Quality, Safety, and Governance
Committee High risks scoring 12 will also be reviewed by the Board.
Risk treatment plans have to be developed according to the level of risk and the needs of the
organization. In broad terms the Contractor will seek to tolerate risks (1-5), and treat risks with a
score of 6 or more, and where appropriate will seek to transfer risk to another provider, or may
consider the need to terminate the risk by terminating the aspect of service affected if no other
solution can be identified, and the risk is extreme (i.e. 15+).
Risk Assessment Analysis (Attachments 3)

VI. SCHEDULE CONSTRUCTION AND MAN POWER AND EQUIMENT FOR


STRUCTURE OF O&M ACCOMODATION ( Attachments 4)