METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Contents
I. SCOPE OF WORK........................................................................................................................... 4
1. GENERAL DISCRIPTION ............................................................................................. 4
2. BASES FOR ESTABLISHMENT OF CONSTRUCTION METHODS .............4
2.1 For formulation of construction method. .......................................4
2.2 Supplies and materials. .................................................................................. 5
2.2.1 TECHNICAL SPECIFICATIONS, ORIGIN AND STANDARDS APPLICABLE TO MAIN SUPPLIES,
MATERIALS AND EQUIPMENT USED FOR THE WORK. ..................................................................... 5
2.2.2 MEASURES TO ENSURE THE QUALITY OF EACH TYPE OF SUPPLIES, MATERIALS AND EQUIPMENT.
7
II. PREPARATION WORK ................................................................................................................. 8
1. PREPARATION ............................................................................................................ 8
2. EQUIPMENTS AND MACHINE ..................................................................................... 9
III. CONSTRUCTION ORGANIZATION METHOD ............................................................................ 9
2|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
3|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
I. SCOPE OF WORK
1. General discription
- Structural construction method of Family apartment, Management house, Multi-functional gym
and healthy care house, Supermarket and restaurant.
4|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
5|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
the main supplies and materials will be submitted samples together with the material certificates
and approved by the Investor and the Consultant before putting into use.
The main building materials.
(Please see List of main materials used for the project)
Cement: Cement used for construction is mixed Portland according to cement standards TCVN
6260:2009; Portland cement – Technical requirements TCVN 2682:2009.
The Bidder must at all times provide certification from the cement manufacturer to the required
standards for the period of use, which is issued and signed by an independent consultant. Each
batch of cement must be accompanied by a manufacturer's certificate indicating that the cement
has been tested and analyzed for its chemical composition and physical properties. Each batch of
cement after being brought to the site will be tested and reanalyzed according to current standards.
+ Cement should be kept at the site in the right conditions.
+ Hot cement needs to be stored, not used immediately but not longer than 28 days at the site
warehouse. Do not use cement that has been produced for more than 12 months.
+ Cement must be delivered in the form of intact packaging and labels on the bags, cement must
have enough at the site to ensure continuous construction and must be used in the shortest time
and rotated to avoid the case of storage for a long time, causing poor quality. Cement transferred
to the construction site must be well preserved to prevent water infiltration and humidity due to
climate. Cement stacked in warehouses must have a platform of 30cm above the ground, not more
than 09 bags. It must be well ventilated and moisture resistant. Cement before use must be
checked the quality. Any cement stored at the Site that does not conform to the current technical
standards and quality standards, the Bidder must remove from the Site.
Sand: Must be supplied from a specified source and in accordance with current technical
standards and must be washed when used, ensuring the correct distribution according to design.
Sand must be obtained from a source capable of providing sand of good quality regularly and
reliably throughout the construction process.
Stone: Must be supplied from a specified source in accordance with the standards "Complete
reinforced concrete structures", "Aggregate for concrete and mortar - Technical requirements
TCVN-7570: 2006".
+ Needs to be hard, durable, clean, not dirty by impurities that affect the strength and durability of
concrete, such as clay particles, mica particles, coal, organic impurities, iron ore, sulphate salt,
etc. calcium, magnesium. Aggregates must not be mixed with mollusc shells.
+ Inspector must check the supply of tests and requirements for materials before putting into
construction. Aggregates lacking test results are not used.
Commercial concrete: A certificate of quality and origin at the place of manufacture is required.
The technical requirements comply with the requirements of the Design. Before construction, the
Bidder must submit the distribution and source of input materials.
Steel: The steel put into use must conform to design requirements. Limit the change of type
compared to the design documents during construction, especially do not replace high strength
steel with lower intensity steel. All bearing steels must comply with the standard "Reinforced
concrete structures TCVN 5574: 2012" and "Concrete reinforcement - TCVN 1651-2008". No
rust, no oil or dirt. Steel must meet ISO 9001 standard.
+ When using imported steel, a technical certificate must be attached and it is necessary to take test
samples according to the standard "Metallic materials - Tensile test - Part 1: Test methods at
room temperature TCVN 197-1:2014" and "Metallic materials - Bending test TCVN 198-2008".
6|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Bolts: High-strength bolts (including nuts, washers) after being processed, before being
put into use, must be checked by the technical inspection department of the investor
and tested in qualified laboratories. If it passes, it will be tested and put into use.
+ Bolts for the main structure have a strength of 8.8; yield limit 640; breaking strength 800.
+ Bolts for substructure and anchor bolts have a strength of 5.6; yield limit 300; breaking strength
500.
Water: Must take samples for analysis and conform to the standards of water
regulations according to the standard TCVN 4506-2012.
Tiles, paving stones of all kinds: Tiles and paving stones of all kinds must be of the
right type and size according to the design, ensuring quality without warping and must
have a clear origin;
Seam-lock roofing sheet, thickness 0.53, AZ150
EPS panel, compact partition, plaster ceiling, paint, door materials...: Must be of the
right type, meet the technical requirements of the design, have a clear origin.
Painting supplies, electricity, water, lightning protection...etc: Requires the right type,
must have a certificate of quality and origin at the place of production. The technical
requirements comply with the requirements of the Design.
The list of main materials the Bidder is expected to put into use for the work and the
commitments of the suppliers of materials for the work, presented in the List of main types of
materials and materials for the project. construction.
2.2.2 Measures to ensure the quality of each type of supplies, materials and equipment.
In order to prevent and limit errors that occur during the construction process, we use the
method of inspection and review right from the first stage. For materials and construction
materials, when gathered on the construction site, they must have the norms and certificates
of meeting design requirements, and be brought to internal inspection first, then the Investor,
Supervision consultants will check. All types of materials and equipment, when brought to
the site for installation, are approved by the Investor, an authorized person or a supervisory
engineer to check the quality and design, to satisfy the requirements of the origin,
manufacturer, and manufacturer have all the characteristics and technical parameters such as
design requirements and requirements stated in the Investor's Bidding Documents for the
works. Materials and equipment used for the project, before installation, are checked for
details, removing all equipment, details that are not suitable or have defects due to
manufacturing quality, only equipment complete in terms of all requirements, especially the
newly installed technical features.
All equipment has a certificate of origin, the manufacturer, the manufacturer has all the
characteristics and specifications and is installed for electrical testing, testing the operation
before being put into the installation location.
For construction equipment, it is also periodically inspected and tested by competent
authorities. For people, the Bidder realizes that this is a very important issue in ensuring the
quality of the building. We bring into the project from the Project Manager to highly
qualified workers with experience in high-rise building construction that can meet the
demanding works, high art of the project.
All kinds of supplies and equipment are stored in the warehouse and scientifically arranged in
rows to distinguish them by number, diameter, length and code for easy taking out, use and
storage. Do not mix rusted and unrusted reinforcement. When placing reinforcement in the
yard outside the field, put 1 high end, 1 low end on a hard foundation with no grass growing.
Steel millet is at least 30 cm higher than the foundation, not more than 1.2 m high and 2 m
7|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
wide. Cement is stored in the warehouse according to the prescribed standards to prevent
water penetration and moisture due to environmental climate. The storage time is guaranteed
not to exceed the specified period. The cement bags that have had the phenomenon of
clumping are absolutely not put and used. Cement must not clump, the amount of cement
passing through sieve No.008 is greater than 85% of the total weight. Cement is kept at the
site in a condition that does not alter its quality. Sealed, non-tear, puncture-proof cement bags
are placed above water and ventilated on a floor more than 30cm above the ground and
protected from water. Loose materials must also be poured in a clean, dry place with
separation to avoid contamination of materials by mud, grease, etc. Electrical supplies,
compact partition panels, gypsum ceiling panels... are stored in a closed, dry and cool
warehouse to ensure that weather factors do not affect the quality of the materials.
The construction site has from 1 to 2 storekeepers who are responsible for importing and
exporting materials daily. Storekeepers are responsible for making inventory cards in daily
books, regularly checking warehouses and yards to promptly handle problems that may occur
during the construction process.
Site security is responsible for standing 24/24h at the construction site to protect security and
order on the construction site to avoid loss and damage of materials.
Inspection and supervision of material quality, construction work is carried out both in the
field and in the laboratory using advanced tools and equipment to assess the quality of
building materials. We put in the works good engineers, experienced in construction and
supervision. A team of skilled workers has executed many projects and works with high
quality.
II. PREPARATION WORK
1. Preparation
- Temporary work preparation
Construction of temporary facilities for serving the construction: temporary road, temporary
fence, car wash bridge, rebar and formwork fabricating yard.
- Preparation of manpower
Construction staff:
Construction staff: The construction staff is a team of experienced staff and engineers, who
have constructed many projects of similar size and nature to this project. The site manager
and deputy site manager will be a person with 06 years of construction experience or more,
having constructed high-rise projects, large-scale renovation and repair in a similar position.
A team of highly qualified staff, having enough specialties suitable to the nature of the
assigned work, with a sense of professional conscience, a high sense of responsibility and
discipline, always ready to receive and complete well assigned tasks.
Construction worker
The contractor's workforce expected to be put into the project is a team of workers who are
trained in a highly disciplined working environment, always have a sense of responsibility,
are trained to improve skills, have close supervision. annual assessment and skill check
before starting construction. The workforce is divided into groups under the guidance of the
construction team leaders to ensure the specialization as well as the transmission line in the
organizational chart of human resource arrangement.
The identification and use of the number of workers, the structure of occupations and high
qualifications to implement the project increases labor productivity and ensures the planned
tasks.
8|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Take advantage of available local employees combined with highly skilled manpower to
execute the project
2. Equipments and Machine
- Based on the scale of the work, On the basis of design documents, construction site, as well as
technical features of the equipment and the progress of the work, the Bidder selects the
equipment to be put into use in the project according to each phase and shown in the machine
mobilization schedule that the Bidder will submit to the consultant.
- Certificates of machine and equipment used for the Project are inspected by HCA HSSE
department
III. Construction organization method
1. Construction site organization.
- The whole construction area is separated from neighboring areas by a corrugated iron fence and
covered with tarpaulin to cover dust from the roof of the building to the foot of the building to
ensure environmental sanitation for the construction area with the surrounding area.
- The entrance to this area is located at a convenient location to facilitate the circulation and
transportation of materials and personnel in and out of the construction site. At the entrance gate, a
guard station is arranged to monitor the import and export of materials and manage the entrance and
exit of the construction site. This station is permanently guarded 24 hours a day.
- At construction items, the Bidder arranges construction site warning signs and safety signs in
accordance with current standards and regulations of the state.
- In the total construction site of the project, there is a place to store cement, iron and steel, bricks and
construction equipment, the command house, the security room, the camp area... Reasonable with
production lines and construction site at the facilities in each stage. Mixing and material processing
areas, general power source to distribute electricity for construction and daily life, are arranged in a
very reasonable and safe manner to avoid causing unsanitary conditions and affecting the health of
workers and the surrounding area.
- The material processing area such as iron and steel and wood formwork must be rearranged when
the construction time is over to clear the ground for trucks carrying materials and waste. The storage
yards for materials, materials and processing yards are arranged without causing dust and noise,
usually at the end of the main wind direction and with measures to shield against dust, cushion to
reduce noise...
- Material handling: Transported by crane, winch with lifting capacity ≥ 0.5 tons. Horizontal
transportation using Cars and specialized vehicles (improved vehicles, wheelbarrows...). The closest
guaranteed transport distance, less vibration when transporting.
- At convenient locations, garbage bins and solid waste dumps are arranged to avoid littering and
indiscriminate dumping of waste on the construction site.
9|Page
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
10 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
- To operate the project, the Contractor establishes a Project Management Unit. Under the executive
board are the assisting department and direct construction teams, performing the construction of
specific items of the work.
Relationship between the Board of Management and the site management department
- The Board of Directors of the Company directly guides the departments and the Site Management
Unit, assigns departments in the field of expertise, directly guides and inspects the site manager to
effectively execute the contract, take appropriate construction methods, processes, regulations,
quality acceptance, technical handling, equipment and construction safety, supply of materials and
human resources.
- The site management department, which is directly the site manager, must regularly report to the
Board of Directors on the construction situation and management aspects on the site. The Site
Manager is responsible for regularly coordinating with relevant departments to fully implement the
requirements. Ensure the construction works continuously according to the Design documents to
ensure the technical quality of the project, at the same time coordinate to solve problems in each
construction area in th best timely and effective manner.
Site manager
- Perform the tasks assigned by the Board of Directors and take responsibility for the organization of
human resources, techniques, quality and progress of the project, check and urge daily on the
construction process, ensure the right design. Coordinate with the Owner, design consultant,
Owner’s engineer and related parties on issues in the construction site.
Site deputy manager
- Perform the tasks assigned by the site manager, to act on behalf of the site manager in charge of all
work of the construction site in the absence of the site manager.
Department of Progress, Technical and Quality Management
- The head of this department is the construction technical manager - responsible to the Site
Management Unit for the technique, progress and quality of the work.
- The technical department is directly in charge of the progress, construction techniques, quality of
each job, assisting the Site manager and technicians who are always present at the construction site,
and the relationship with Party A and the engineer, consulting engineers in construction technical
solutions, doing the acceptance work, making as-built documents, and daily monitoring diary.
11 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
12 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
2 Family apartmen 2 1 2
3 Management house 1 4
1 1 6 3 (team)
Multi-functional
4 gym and health 1 3
care house
Supermarket and
5 1 3
restaurant
Table 3.1 Construction staff
13 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
14 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
- Depending on the volume of each batch to choose concrete mixer truck, the contractor has
concrete mixer trucks with a transport volume of 9(m3), 12(m3). There are 20 mixer trucks
running in total
15 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Figure 3.4 : Transport concrete from the batching plant to the site
16 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Foundation excavation
Indoor anti-termite
17 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
1.2. Procedure of structure from cos 0.00 for Family apartment (typical 1 floor)
Dismantle formwork
18 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Foundation excavation
Soil compaction
Indoor anti-termite
19 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
2.2. Procedure of structure from cos 0.00 for Manager house (typically 1 floor)
20 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Foundation excavation
Indoor anti-termite
21 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
3.2. Procedure of structure from cos 0.00 for Multi-functional gym and health care house
(typical 1 floor)
22 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Foundation excavation
Indoor anti-termite
23 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
4.2. Procedure of structure from cos 0.00 for Supermarket and restaurant
24 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
25 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
pipes installation have been completed and accepted by the Owner and allows moving to the next
construction step.
- Backfilling is carried out in the following order:
Check the area to be filled, remove all excess materials and waste of previous construction stages
such as construction debris...
Mark the level of foundation to be filled with red paint on the foundation or wall
Level the areas to be filled to create a relatively flat and compact
Spread the soil in layers with a thickness of 35-40cm. During spreading, it is necessary to remove
impurities and unsuitable blocks of material.
Use Mikasa tamping rammer to compact. The turns of compaction must overlap at least 10cm.
The compaction process can be considered to add water to achieve optimum moisture content.
Density check must be done regularly and deal with unsatisfactory areas.
After completing the compaction for the first layer, spreading and compacting for the next layers
can be carried out.
The process of backfilling and compacting must ensure that the compaction coefficient is not
lower than 0.95.
26 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
27 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
f=3L/1000. The bearing parts of the falsework are not connected. The braces are calculated and
arranged appropriately to ensure the entire system of formwork, falsework is stable.
Formwork blocking the end of pouring blocks ensures tightness and stablity, ensures the shape
and size of the stop circuit as specified by the design.
Before placing concrete, the concrete surface will be cleaned with a water pump.
Formwork will be checked before placing concrete
Formwork must be tightly joined so as not to lose cement water
Inspection requirements for installed formwork
The installed formwork needs to be checked according to the following requirements and the
deviation must not exceed the allowable value.
Shape and size, structure
Formwork structure: firm, stable
Flatness between joining plates
Tightness between the formwork panels, formwork and ground surface;;
Non-stick formwork;
Clean formwork surface
Inclination, position, elevation and formwork size
Stiffness and stability.
28 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
29 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
30 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
dismantling formwork has no defects. If there are small defects and do not affect the bearing
capacity of the structure, the Contractor will have a treatment plan as part of handling defects
in construction.
31 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
32 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
33 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
34 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
35 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Figure 13.4: Detail for typical façade and grounds of install scaffolding covering
36 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
37 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
Almost certain to
5 The event is expected to occur in most circumstances.
occur
Almost certain
5 5 10 15 20 25
to occur
Likelihood
Likely to occur 4 4 8 12 16 20
Could occur 3 3 6 9 12 15
Unlikely to
2 2 4 6 8 10
occur
Very unlikely
1 1 2 3 4 5
to occur
1 2 3 4 5
Catastrophi
Risk Matrix Negligible Minor Moderate Major
c / Fatal
Consequence
Risk Level Matrix
A combination of Tables 1 and 2 can be used to evaluate the risk by determining the overall risk
level of a particular outcome eventuating.
The matrix (Table 3 - Risk Level Matrix) below is shown in the conventional format of
Consequence on the horizontal axis increasing to the right and Likelihood on the vertical axis
increasing with height.
Escalation of Risk is determined by risk score
Table 4: Escalation of Risk
38 | P a g e
METHOD SATEMENT OF STRUCTURE FOR O&M ACCOMODATION
39 | P a g e