Professional Documents
Culture Documents
Ce168p-2 E01 Policarpio Report
Ce168p-2 E01 Policarpio Report
FORMWORKS
• Sometimes, In the desire of the engineer to save and have income in the project, the materials
he was purchasing is low and the quality of the structure become so low that it become prone to
damages
• Tipid-loko
MATERIALS:
• Scaffolding – assemble and design its placement thoroughly so that it will not fall off when in
use; good working designed formworks = durable
- A-Frame – (Japanese) light – Asian countries
- End frame – it is joint, used, and placed above
- Cross brace – it is the lock in the scaffolding so that it will not move
- Coupling/joint pin – used as a joining material to other scaffolding
• Aluma Beams – reusable, durable than wood, lightweight but expensive
• A-clamp – beam clamp, has different sizes
• Progress Billing:
- No work, no pay
POLICARPIO, Myka Ann P. APRIL 28, 2022
CE168P-2/E01 PROFESSOR: ENGR. ELMER CIVIL
MASONRY
Tiling Works – the marking on the floor will help the tiller/worker to distinguish and to avoid the
utilities and parts of the floor that should be avoided.
Dowel Bar - help transfer load but allow adjacent slabs to expand and contract independent of one
another.
CONCRETING
• Concrete solidifies and hardens after mixing with water and placement due to chemical process
known as hydration.
POLICARPIO, Myka Ann P. APRIL 28, 2022
CE168P-2/E01 PROFESSOR: ENGR. ELMER CIVIL
• Batching plant
- This is where the materials in concrete make.
- You can also see here the different equipment used in the construction like trucks
- The batching plant has operator to check and operate the production of te materials in
concrete
- There are different types of tanks used in storing different admixtures
- Batching plant is also a stockpile for the materials needed in the site
• Slump test
- measures the consistency or workability of concrete. It is used to check the workability of
freshly made concrete for the easy placement of concrete. This test indicates the water-
cement ratio and the properties of materials and admixture etc.
• Large scale concreting
- crane and buckets are used when the workers need to pour into the high part of the site
which is unreachable to the mixer, it's also more convenient.
- Mobile pumpcrete has a crane attached to the truck and can move depending on which part
of the building needs to be poured
- Stationary pumpcrete is fixed, it uses pipes to reach the area that needs to be poured by
cement
POLICARPIO, Myka Ann P. APRIL 28, 2022
CE168P-2/E01 PROFESSOR: ENGR. ELMER CIVIL
• Concrete defects
- Cold joint
- Honeycomb – (ampaw) happens when the concrete poured is not vibrated enough
- Crazing/hairline cracks
- Blister/bleeding
-
• Retrofitting
- In retrofitting, you can also use carbon fiber, it is used by sticking it t the beams, expensive.
WATERPROOFING
• Waterproofing is done to make the part of the house waterproof and do not leak inside the
house.
• Waterproofing is one of the fastest but most critical jobs in the site
• Leaks are hard to find
• Waterproofing preparation
- clean the area that need to be waterproof (vacuum), there should be no dust.
POLICARPIO, Myka Ann P. APRIL 28, 2022
CE168P-2/E01 PROFESSOR: ENGR. ELMER CIVIL
- the cracks that appeared in water tightness are be filled with epoxy, it is also placed in the
electricity pipes
- pull-off test is needed after the application of the water proofing to check how adhesive and
cohesive and how thick it is.
- Flood tests are also need to be executed once the coating is finished to check if there are
leaks
POLICARPIO, Myka Ann P. APRIL 28, 2022
CE168P-2/E01 PROFESSOR: ENGR. ELMER CIVIL
- Sand broadcasting are distributed to the floor usually before the waterproofing has finally
set to make the cement stick to the floor. The waterproofing makes the floor smooth.
- Post applications are conducted when there are areas that needs to be waterproof, or it is
inadequate. There should be no gaps, all should be coated. Pipes should also be coated with
a high of 50mm and walls should be 2-3 m.
CONSTRUCTION SEQUENCE
• MASONRY
- There should be allotted time every activity
- Exact people every type of work. More efficient than having many. hard to supervised
- Construction is not for everyone
- Wet works- chb layering, plastering
• Finishing
- Doors, hardware, painting
- Dry works
- The building should be water type (already waterproofed), has windows
• Bare unit
- No fixtures, water closets
- No equipment/utilities that are easily robbed or broken
• TOG (Turnover Group)
• Wet works
- Stripping of formworks
- Rubbed concrete – fixing the honeycombs (if there’s any), any imperfections in the beams
and columns
- Box setting
▪ For panel boards
▪ Zocalo – for water proofing, 1 inch thinner than chb, flushing, expensive
- Plumbing/ sanitary
POLICARPIO, Myka Ann P. APRIL 28, 2022
CE168P-2/E01 PROFESSOR: ENGR. ELMER CIVIL