1 Section 1-1: Approval by DMRC Officials

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

CL

1 2 3 5 6

80000

20000 20000 20000 20000

PEB ROOF AS/DETAIL

LIFT TERRACE
+235.170M
ROOF PORTAL AS
PER ROOF VENDOR
ROOF PORTAL AS
PER ROOF VENDOR

4600
ROOF PORTAL AS ROOF PORTAL AS ROOF PORTAL AS ROOF PORTAL AS
RAILING AS/ DETAIL PER ROOF VENDOR RAILING AS/ DETAIL PER ROOF VENDOR PER ROOF VENDOR RAILING AS/ DETAIL
PER ROOF VENDOR
PLATFORM LEVEL
+230.520M

1090
RAIL LEVEL
+229.430M

4650
3560
FOB CONNECTING CORRIDOR FOB LEVEL
+225.870M

7950
5500 (MIN)

5800
FOOTPATH LEVEL
+218.070M

ROAD LEVEL
+217.920M

1 SECTION
SCALE : 1/150
1-1

LEGEND

200 MM ACC BLOCK WORK

RCC WALL

PARAPET/ TOE WALL/BOUNDARY WALL

FILLED FLOORING

X
SEC./ELEV.NAME
00000
DRAWING NUMBER

EARTHMAT

NOTES-

1. ALL DIMENSIONS ARE IN MM, UNLESS OTHERWISE MENTIONED.


2. ALL DIMENSIONS ARE TO BE READ AND NOT MEASURED.
3. GROUND LEVELS ARE INDICATIVE, CONTRACTOR TO VERIFY EXISTING LEVELS AT SITE PRIOR TO COMMENCEMENT OF
CONSTRUCTION.
4. CONTRACTOR TO VERIFY THE LEVELS FOR STAIRCASE AND LIFT/ESCALATORS PRIOR TO COMMENCEMENT OF
CONSTRUCTION.
5. ALL LEVELS ARE IN METERS, INDICATING T.O.C. (TOP OF CONCRETE) WHEREVER APPLICABLE.
6. ABSOLUTE RAIL LEVEL SHALL BE TAKEN FROM DMRC ALIGNMENT DRAWING.
7. ALL MINIMUM INTERNAL CLEARANCES ARE MANDATORY AND SHALL BE PROVIDED.
8. THIS DRAWING MUST BE READ IN CONJUNCTION WITH ALL RELEVANT ARCHITECTURAL, STRUCTURAL, PLUMBING, FIRE
TYPICAL DRAWING REFERENCE NO:-
FIGHTING, ELECTRICAL AND TRAFFIC MANAGEMENT DRAWINGS.
9. ANY DISCREPANCIES MUST BE BROUGHT TO NOTICE OF THE ENGINEER BEFORE EXECUTION OF WORK AT SITE. 1). EIRA1DE005-DMRC-FDS-AR-DC03-TYP-40004 - PLATFORM LEVEL FLOORING PLAN
10. ALL DOOR'S/WINDOW'S SILL & LINTEL LEVELS ARE FROM MAIN FLOOR FINISH LEVEL.
2). EIRA1DE005-DMRC-FDS-AR-DC03-TYP-40005 - FLOORING DETAIL
11. COLUMN LOCATION AND STRUCTURAL ARRANGEMENT SHOWN ARE INDICATIVE ONLY.
12. ALL CUTOUTS AND FIRST FIX PROVISIONS FOR MEP/SYSTEMS REQUIREMENTS TO BE REFERRED FROM LATEST REVISION 3). EIRA1DE005-DMRC-FDS-AR-DC03-TYP-40006 - FLOORING DETAIL
OF DISCIPLINE DRAWINGS.
4). EIRA1DE005-DMRC-FDS-AR-DC03-TYP-40011 - ENTRY/EXIT DETAIL
13. ROOM SIZES/MASONRY WORK AT THE STATION MAY VARY AS PER DETAILED ARCHITECTURAL LAYOUT OF THE STATION.
14. FOR LIGHTING ARRANGEMENT & ELECTRICAL DETAILS, PLEASE REFER SPECIFIC ELECTRICAL DRAWINGS. 5). EIRA1DE005-DMRC-FDS-AR-DC03-TYP-40012 - ENTRY/EXIT DETAIL
15. EARTH MAT SIZE AND LOCATION TO BE GOT CONFIRMED FROM E&M (DMRC).
16. VENDOR SPECIFIC DRAWINGS FOR PIT SIZE AND STRUCTURAL ARRANGEMENT FOR LIFT / ESCALATOR,AS FINALIZED BY
DMRC, TO BE REFERRED.
17. ALL THE WORK ARE IN LUMPSUM SCOPE UNLESS OTHERWISE MENTIONED
FIRST DESIGN SUBMISSION- FINISHES
REVISION NOTE - R1
18. ALL THE COMPONENTS LIKE RAMPS,DROP OF ETC COMPLETE FOR MMI INTEGRATION UTTIPEC
GUIDELINES & APPLICABLE CODES TO BE CONSIDERED UNDER RELEVANT
This drawing must not be loaned, copied or otherwise reproduced in whole or in part or used for
1. Staircase 3 & 4 from platform to fob added any purpose without the prior written permission of DMRC.
BOQ OR DMRC AGREEMENT.
CLIENT: DELHI METRO RAIL CORPORATION LTD. PROJECT: Certified that this document has been designed and checked in accordance with DDC Quality
Contract DC03- : Part Design and Construction of Elevated
APPROVAL BY DMRC OFFICIALS Assurance Plan.
NORTH DELHI METRO PROJECT - PHASE -4
Metro Bhawan
Fire Brigade Lane, Barakhamba Road, Viaduct from Rithala to Narela 14 Elevated Stations and 5

ARCHITECTURE
DESIGNATION NAME/ SIGNATURE DESIGNATION NAME/ SIGNATURE
New Delhi - 110001,India At-Grade Stations viz. Rithala Interchange, Rohini Sector 25, RITHLA-BAWANA-NARELA
AM/MGR ARCH DY CA CA PM CPM
Board No. - 23417910/12 26, 31, 32, 36, Barwala, Pooth Khurd, Bawana Ind-I, Bawana APPROVED BY DESIGNED BY
Ind-II, Bawana, Bawana JJ Colony, Sanoth, New Sanoth, STATION:
Fax No. - 23417921
Depot Station, Bhorgarh, Anaj Mandi, Narela DDA Sports
PROJECT SENIOR BAWANA INDUSTRIAL AREA - I STATION
DY CEE/ E&M CEE/ E&M DY CE/ TRACK CE/ TRACK DIRECTOR V. RAJENDRAN ARCHITECT R.SHARMA
Complex and Narela (including Entry & Exit structures at
CONSULTANT: stations but excluding Architectural finishing, Pre-engineered CHECKED BY DRAWN BY TITLE : LONG SECTION
R1 REVISED AS PER DMRC COMMENTS A.KUMAR R.SHARMA A. SAINI 03/08/2021
egis rail steel roof structure and roof sheeting of stations) from
Chainage 0.0 M to 23449.287 M of Rithala - Bawana-Narela
DY CSTE/ TELE CSTE DGM/ DESIGN GM/ TECH
A.CHIEF
ARCHITECT A. SAINI ARCHITECT
A.KUMAR DRG NO: REVISION NO. : SCALE : SIZE : STATUS:
Corridor of Delhi Metrolite Phase-IV project" R0 FIRST ISSUE A.KUMAR R.SHARMA A. SAINI 28/04/2021
egis india DY CSTE/ SIG GM / IT DY CEE/TRACTION GM / TRACTION
MEPF
EXPERT
DATE
03/08/2021 EIRA1DE005-DMRC-FDS-AR-DC03- IA1-09303 R1 A1 FIRST DESIGN
DY CSTE/AFC DY CEE / L&E CEE/ PLANING AM/ CIVIL REV. PARTICULARS DRN. DGN. CHD. DATE A.KUMAR