Professional Documents
Culture Documents
Kalam, Akhtar - Kothari, Dwarkadas Pralhaddas - Power System Protection and Communications-New Age Science LTD (2010)
Kalam, Akhtar - Kothari, Dwarkadas Pralhaddas - Power System Protection and Communications-New Age Science LTD (2010)
Protection and
Communications
AKHTAR KALAM
D P KOTHARI
Preface
Akhtar Kalam
D.P. Kothari
List of Acronyms
Preface ............................................................................................................. v
List of Acronyms .......................................................................................... vii
Recommended Protection Terminology ........................................................ xv
Part A
POWER SYTSEM PROTECTION
Chapter 1 Basic Principles 3–21
1.1 Introduction to Protective Relaying 3
1.2 Power System Plant and Layout 5
1.3 Switching Arrangements 8
1.4 The Function of Protective Relaying 13
1.5 Principles of Protective Relaying 14
1.6 Unit and Non-unit Schemes 17
1.7 Zones of Protection 19
1.8 Common Terminologies 20
Part B
POWER SYTSEM COMMUNICATIONS
1. INTRODUCTION
The purpose of this study was to compile a list of recommended terms to
enable authorities of ESAA to discuss protective schemes, with mutual
understanding of the terms used to describe these schemes and their
performance parameters.
No attempt has been made to categories the various terms, which
are set out in alphabetical order alone. Where possible, standard items of
terminology from either IEC or BS have been adopted in toto and the
appropriate reference appears in parentheses below the term.
Terminology of a purely telecommunications nature is not included
herein; reference for such terminology should be made to ESAA Publication
D (b) 7-1968: Communication Terms for Power System Telecommunications.
Terms associated with auto-reclosing applications, as contained in
ESAA Publication D(b) 12-1971: Guide to the Application of Auto Reclosing
to Radial Overhead Lines Supplying Urban and Rural Areas, are not
repeated herein.
The terms as listed below are commonly used by the larger supply
authorities in Australia.
xvi POWER SYSTEM PROTECTION AND COMMUNICATIONS
2. REFERENCES
The basic references used in this study were as follows:
BS 142-1966 Electrical Protective Relays
BS 3950-1965 Electrical Protective Systems for AC Plant
(withdrawn and not replaced October 1981)
IEC 50(16)-1956 Protective Relays
IEC 255.4-1976 Appx.E. Impulse Voltage Withstand and High
Frequency Disturbance Tests.
3. RECOMMENDED TERMINOLOGY
(Contd...)
xviii POWER SYSTEM PROTECTION AND COMMUNICATIONS
(Contd...)
RECOMMENDED PROTECTION TERMINOLOGY xix
(Contd...)
xx POWER SYSTEM PROTECTION AND COMMUNICATIONS
(Contd...)
RECOMMENDED PROTECTION TERMINOLOGY xxi
(Contd...)
xxii POWER SYSTEM PROTECTION AND COMMUNICATIONS
External Fault A fault outside the defined Preferred to the term ‘through
zone of protection. fault’.
Fast Transient A type test intended for ANSI 37-90-1978 and IEEE
Surge Withstand energised solid state relay Guide P472/D2-1982.
Capability Test systems, to determine whether
they will operate without
erroneous output, component
failure or calibration change
beyond normal tolerances
when specified high voltage
fast rising transients such as
occur during the interruption
of inductive devices in DC
circuits, are applied.
(Contd...)
xxvi POWER SYSTEM PROTECTION AND COMMUNICATIONS
(Contd...)
RECOMMENDED PROTECTION TERMINOLOGY xxvii
(Contd...)
xxviii POWER SYSTEM PROTECTION AND COMMUNICATIONS
Memory Relay A specific type of distance relay The term ‘Memory Trip’ is
whose polarising circuit is used when such a relay is
oscillatory in nature, so that a employed for switch-in fault
polarising signal persists in the protection, i.e. in distance
relay for a short time after the protection with bus VTs.
collapse of system voltage at
the instant of fault.
(Contd...)
RECOMMENDED PROTECTION TERMINOLOGY xxix
Oscillatory Surge A type test intended for Term used by ANSI 37.90-1978
Withstand energised solid state relay and IEEE guide P472/D2-1982
Capability Test systems to determine whether to describe the High
they will operate without Frequency Disturbance Test of
erroneous output, component AS 2481-1981.
failure or calibration change
beyond normal tolerances,
when specified oscillatory
surge voltages representative
of practical system conditions,
are applied.
(Contd...)
RECOMMENDED PROTECTION TERMINOLOGY xxxi
(Contd...)
RECOMMENDED PROTECTION TERMINOLOGY xxxiii
Relay Backup Protection located either locally May comprise part of a local
or remotely which will operate backup scheme.
for faults within the reach of
the relay being considered in
the event of its failure to
operate.
(Contd...)
xxxiv POWER SYSTEM PROTECTION AND COMMUNICATIONS
(Contd...)
xxxvi POWER SYSTEM PROTECTION AND COMMUNICATIONS
DEVICE NUMBERS
The following is a selected list of device numbers commonly used on
protection drawings:
2 Time delay starting or closing coil
3 Checking or interlocking relay
12 Overspeed device
14 Underspeed device
21 Distance relay
25 Synchronising or synchronism check relay
27 Undervoltage relay
30 Annunciator relay
32 Directional power relay/reverse power
37 Undercurrent or underpower relay
40 Field failure relay
46 Reverse phase or phase balance current relay
47 Reverse phase sequence voltage relay
49 Machine or transformer thermal relay
50 Instantaneous earth fault relay
50E Instantaneous earth fault relay
51 AC time overcurrent relay
52 AC circuit breaker
52(a) Circuit breaker auxiliary switch-normally open
52(b) Circuit breaker auxiliary switch-normally closed
55 Power factor relay
56 Field application relay
59 Overvoltage relay
60 Voltage and current balance relay
63 Buchholz gas device
64 Earth fault protection relay
67 AC directional overcurrent relay
68 Blocking relay
74 Alarm relay
76 DC overcurrent relay
78 Phase angle or out-of-step protective relay
79 AC reclosing relay
81 Frequency relay
83 Automatic selective control or transfer relay
85 Carrier of pilot receive relay
86 Locking-out relay
87 Differential protective relay
95 Neutral displacement relay
96 Undervoltage control for tap changers
This page
intentionally left
blank
PART A
POWER SYTSEM PROTECTION
This page
intentionally left
blank
CHAPTER
BASIC PRINCIPLES
• Maintenance requirements
• The consequences of equipment or plant failure.
Protection systems must not interfere with or limit the normal
operation of the system but must continuously monitor the system to detect
electrical failure or abnormal electrical conditions.
Further important aspects in the design of the power system are:
• Incorporation of features aimed at preventing failures, and
• Provisions for mitigating the effects of failure when it occurs.
Modern power system design employs both recourse as dictated by
the economics of any particular situation. Notable advances continue to
be made toward greater reliability. However also, increasingly greater
reliance is being placed on electric power. Consequently, even though the
probability of failure is decreased, the tolerance of the possible harm to the
service is also decreased.
The type of electrical failure that causes greatest concern is the
short-circuit, or ‘fault’ as it is usually called, but there are other abnormal
operating conditions peculiar to certain elements of the system that also
require attention. Some of the features of design and operation aimed at
preventing electrical failure are:
• Provision of adequate insulation
• Coordination of insulation strength with the capabilities of
lightning surge arresters
• Use of overhead ground wires and low tower-footing resistance
• Design for mechanical strength to reduce exposure, and to
minimise the likelihood of failure caused by animals, birds,
insects, dirt, sleet, bushfires, etc.
• Proper operation and maintenance practice.
Some of the features of design and operation for mitigating the effects
of failure are:
• Features that mitigate the immediate effects of an electrical failure
1. Design to limit the magnitude of short-circuit current
(a) By avoiding too large concentrations of generating
capacity
(b) By using current-limiting impedance
2. Design to withstand mechanical stresses and heating owing
to short-circuit currents
3. Time-delay undervoltage devices on circuit breakers to
prevent dropping loads during momentary voltage dips
4. Ground-fault neutralisers.
BASIC PRINCIPLES 5
1.2.3 Transformers
Power transformers of various sizes are located throughout the power
system. ‘Step-up’ transformers convert the generator voltage to levels
suitable for the transmission system which transmits bulk power to the
load centres. Depending on the size of the system, transmission voltages
will range from 132 kV to 500 kV. ‘Step-down’ transformers reduce the
voltages at the bulk load centres to typically 66 kV or 33 kV for distribution
through a ‘subtransmission network’ which supplies the high voltage
distribution system. The distributions system is typically 33, 22 or 11 kV
and supplies distribution substations that transform the voltage to the
customer level.
8 POWER SYSTEM PROTECTION AND COMMUNICATIONS
1.2.4 Lines
Impedances, for calculation of fault currents, are the most important line
parameter for protection purposes. These are usually calculated in resistive
and reactive ohms at system frequency and are expressed in the form R + jx
or Z∠Q. The R term is the resistance per phase and the jx term is obtained
from the basic equation of the type
jx = k log10
F Separation of conductors I
GH k × Radius of conductor JK
1
G1
Feeder 1
G2
is left with generator 2 disconnected. The mesh layout is flexible and uses
less CB’s than the double switched arrangement. There are no particular
12 POWER SYSTEM PROTECTION AND COMMUNICATIONS
1.3.4 1½ CB Switching
A more elaborate system than the mesh system is the 1½ CB arrangement
(Fig. 1.4).
This arrangement uses more CBs than the mesh arrangement but
gives better reliability for faults in the transmission lines or generation
plant. Again, provided current transformers and voltage transformers are
carefully located the protection arrangements is straight forward.
1.3.5 Transfer Bus Arrangement
This arrangement (Fig. 1.5) is applicable to stations where there are a large
number of feeders. It permits more flexibility than the single switched
arrangement as any feeder may be kept in service while its CB is out of
service, by using the transfer bus and connecting the feeder either in parallel
with another feeder or to a spare CB.
The system is more complex to operate and can require switching of
current transformers and protection circuits through auxiliary switches
on the transfer isolators, to maintain adequate protection on the feeders.
Problems can also arise with the operation of earth fault protection
when feeders are operated in parallel due to the unbalance in load currents
BASIC PRINCIPLES 13
giving rise to artificial ‘earth fault current’ in the relay circuits. Special
operating procedures may be required to overcome this problem.
Observation:
• Circuit breakers are located in close proximity to each power
system element. This provision makes it possible to disconnect
only a faulty element. Occasionally, a breaker between two
adjacent elements may be omitted, in which event both elements
must be disconnected for a failure in either one.
• A separate zone of protection is established around each system
element. The significance of this is that any failure occurring
within a given zone will cause the ‘tripping’ (i.e., opening) of all
circuit breakers within that zone, and only those breakers.
It will become evident that, for failures within the region where
two adjacent protective zones overlap, more breakers will be
tripped than the minimum necessary to disconnect the faulty
element. However, if there were no overlap, a failure in a region
between zones would not lie in either zone, and therefore no
BASIC PRINCIPLES 15
A C G I
E F
B D H J
Z1B
Z2B
Z3B
End Zone
Zone 1 = 80-90% of protected line
Zone 2 = Protected line + 50% of shortest line
Zone 1 = Protected line + longest second line + 25% of third line
X = Circuit breaker operating time
Y = Discriminating time
2. Unit Protection
These are schemes that respond to fault conditions lying within a
clearly defined zone. They utilise information from two or occasionally
more points in a system. In most cases a unit protection system involves
the measurement of quantities at each end of the zone, and the transmission
of information between the equipment at zone boundaries. Examples of
unit protection are differential current relays where the current entering a
zone is compared with that which leaves it. Also phase comparison carrier
protection is another example.
A B
Protected zone
A C
Y
R R
Protected Back up
zone zone
Standby protection
zone
Line
Voltage
transformer
X Y
Phase-earth
Phase-phase
Two phase-earth
Three phase
Time
FIGURE 1.12 Typical values of power that can be transmitted as
a function of fault clearance time
Fault currents can cause irreparable damage if allowed
to continue for more than a few seconds. Hence fast
fault clearance is imperative.
CHAPTER
2
Network Analysis and Fault
Calculations
XTH =
eNominal kV/ 3 j × 1000 Ω
I SC
(Nominal kV) 2
= Ω
Short-circuit MVA
NETWORK ANALYSIS AND FAULT CALCULATIONS 25
42.5 V
4 MVA 750 A
7% 3.3 kV
10
Fault at E= = 27.89 MVA
0.12 + 0.0033 + 0.175 + 0.0083 + 0.052
Tutorial problem Example 1, gives a further example of the
calculations.
For more complex networks with a larger number of components,
the process of ‘network reduction’ to obtain the Thevenin equivalent is the
same as in the above examples and is just a matter of applying normal
circuit analysis theorems. Tutorial Example 2 gives a worked example to
demonstrate the techniques commonly used.
1
Xd
Time
Two Pole Turbine Four Pole Salient Pole Salient Pole Synchronous
Generator Turbine Generator Generator Compensators
Generator with Dampers Without
Dampers
Low Av. High Low Av. High Low Av. High Low Av. High Low Av. High
Xd 0.95 1.2 1.45 1.0 1.2 1.45 0.6 1.25 1.5 0.6 1.25 1.5 1.25 2.65 2.65
Xd’ 0.12 0.15 0.21 0.2 0.23 0.28 0.2 0.3 0.5 0.2 0.3 0.5 0.3 0.48 0.6
Xd” 0.07 0.09 0.14 0.12 0.14 0.17 0.13 0.2 0.32 0.2 0.3 0.5 0.19 0.32 0.36
X_ 0.07 0.09 0.14 0.12 0.14 0.17 0.13 0.2 0.32 0.35 0.48 0.65 0.18 0.31 0.48
X0 0.01 0.03 0.18 0.015 0.08 0.14 0.03 0.18 0.23 0.03 0.19 0.24 0.025 0.14 .018
NETWORK ANALYSIS AND FAULT CALCULATIONS 29
i i
t
t
(i) (ii)
FIGURE 2.4 Short-circuit wave form for case (i) and (ii)
Looking at the response of the Figs. 2.3 and 2.4, we can note that the
reactance of the machine appears to be time varying. The symmetrical r.m.s.
short-circuit currents are usually desired. These are calculated using the
synchronous, transient and sub-transient reactance (Fig. 2.5).
30 POWER SYSTEM PROTECTION AND COMMUNICATIONS
i(t)
Xd
2l² x(t)
lmax(t)
2l¢
Xd¢
i(t)
2l
X²d t
has represented the reactances of one phase. However, the majority of faults
on the power system involve one or two phases and earth. This means that
the currents and voltages are no longer a balanced three phase system. The
maximum unbalance occurs at the fault point where one or more phases will
have their voltage reduced to near zero and fault current will flow.
A technique called ‘Symmetrical Components’ is used to represent
the unbalanced three phase currents and voltages as three symmetrical
systems, each of which can be solved using three phase calculation
techniques.
Symmetrical components were first proposed for the calculation of
fault currents and voltages in 1918, in a paper to the AIEE by C.L. Fortescue.
They have been a major tool for the calculation of fault currents since that
time.
The concepts of symmetrical components are relatively easy to
understand but the application, in dealing with different combinations of
phases and earth for different fault conditions, can be complex and very
time consuming.
As mentioned previously, there are many computer packages
available today to perform fault calculations and most protection
practitioners would have limited need to perform complex manual
calculations. Nevertheless, it is important to understand the concepts and
be able to employ the techniques to small systems.
An overview and some practice with the use of the techniques is
given in the following paragraphs. If the reader wishes to investigate the
technique further there are a number of texts that give a comprehensive
treatment, including the Westinghouse, Electrical Transmission and
Distribution Reference Book.
Symmetrical component analysis is based on the principle that three
sets of balanced (symmetrical) vectors can be used to represent an
unbalanced three phase voltage or current. One set (a, b, c) using the
impedances associated with the normal operation of the power system,
called the positive sequence impedances, a second set using impedances
that would be presented by the network to a set of vectors having a phase
sequence of a, c, b, called the negative sequence impedances and a third
with three vectors of the same angle called the zero sequence impedances.
The sequence impedance of plant in a network can be imagined as
the impedance derived from the equation of the voltage drop resulting
from the circulation of the sequence current through the network
impedance i.e., the voltage could actually be measured by measuring the
voltage drop when the current of a particular sequence is circulated through
the network element.
32 POWER SYSTEM PROTECTION AND COMMUNICATIONS
c b b c
a c b
Ic Ib
c b a
ln +
Ea
Zn Ec – – E
+ – b
+ lb
b
c
lc
la
1
a
Z1 Reference bus
lb1 Z2 Ve
2
Z1 Z1 b
c
a
le
2
lc1
la la0
0
lb0 – la a
0
lc0 – la0 Reference bus
Zg
0
3Zn
Zn Zg Z0
0 lb Ve0
0
Zg b Ze
c 0 0
a
le 0
lc 0
The reference bus for the positive and negative sequence networks
is the neutral of the generator. So far as the positive and negative sequence
components are concerned, the neutral of the generator is at ground
potential if there is a connection between neutral and ground having a
finite or zero impedance since the connection will carry no positive and
negative sequence current. Remember the negative sequence paths are the
same as those of positive sequence currents. However, the impedance to
the flow of negative sequence current in a rotating machine is not the same
as that of the positive sequence. This difference is not significant for most
fault calculations, and is usually neglected. Transformers and lines have
equal positive and negative sequence impedances.
The zero sequence currents are a single phase set, and must flow up
through the neutral from ground; consequently the zero sequence network
is different from the other two, both in the values of the impedances and
the structure of the network. In apparatus that has no neutral (i.e., delta
connected) or that has no connection between ground and neutral, there is
no path for the flow of zero sequence current. The zero sequence currents
from each of the three phases of the wye connected generator must flow
through the neutral impedance Zn. The current flowing in the impedance
Zn between neutral and ground is 3I0 and the voltage drop across the neutral
impedance is 3ZnI0. Since the current in the zero sequence network is I0,
the impedance must be 3Zn.
In case of an ungrounded wye connected load, the positive and
negative sequence networks are identical, whereas the zero sequence
network is not connected from the neutral, since the wye is ungrounded.
If the wye is grounded, then there is a path for zero sequence currents
to flow, and the neutral will be connected to the reference bus.
The positive and negative sequence networks for a delta connected
load have the same form as the wye connected load. The zero sequence
current is, however, different. No zero sequence current paths exist for
line currents, however, zero sequence currents may circulate around the
delta. This circulating, path is not normally energised, except in the case of
third harmonic exciting currents of transformer windings in a delta
winding. Third and its odd multiple harmonics are necessarily zero
sequence components.
2.6.1 Transformer
The positive and negative sequence networks of transformers are identical
to the per phase equivalent circuit used in normal balanced analysis. The
form of the zero sequence network is very much dependent on the actual
NETWORK ANALYSIS AND FAULT CALCULATIONS 35
Zero-sequence
Symbols Connection Diagrams
Equivalent Circuits
P Q Z0
P Q
P Q
Reference bus
P Q P Z0 Q
P Q
Reference bus
P Q Z0
P Q
P Q
Reference bus
P Q Z0
P Q
P Q
Reference bus
P Q P Z0 Q
P Q
Reference bus
ZHV ZLV
ZT
ZT
ZHV ZLV
the rotor surface at twice the synchronous speed; hence the effective
impedance, being the negative sequence impedance Z2 is different from
Z1. In the absence of information Z2 is approximately 70% of Z1, as the
system impedance will swamp the small difference for system fault
calculations.
The zero sequence impedance Z0 will depend on the nature of the
connection between the star point of the windings and earth and the single
phase impedance of the stator windings in series. Because zero sequence
currents are all in phase, there will be considerable demagnetisation of the
generator iron circuit which means that Z0 is very low, say half of Z1.
Resistors or reactors are frequently connected between the star point of
the windings and earth for reasons associated with protective gear and
limitation of overvoltages and this completely swamps the machine
impedance. Further as the machines are usually connected to the system
via delta-wye transformers, they cannot supply zero sequence currents to
system faults because they cannot flow outside the delta winding.
F1 F2 F0 F1 F2 F0
N1 N2 N0 N1 N2 N0
V V
a a
G b G b
c c
F1 F2 F0 F1 F2 F0
N1 N2 N0 N1 N2 N0
A B C
10 MVA 10 MVA 10 MVA
30% 30% 30%
FIGURE 2.10
Solution. Choose 5 MVA as the base value.
The percentage reactance of each generator on the base MVA
5
= 30 × = 15%
10
The percentage reactance of each reactor on the base MVA
5
= 10 × = 5%
10
The percentage reactance of each transformer on the base MVA
5
= 5 × = 5%
5
When a 3-phase short-circuit occurs at point F on the feeder near
the secondary of the transformer, the reactance diagram will be as shown
in Fig. 2.11(i). This circuit can be further reduced to Fig. 2.11(ii).
A B C
(i) (ii)
FIGURE 2.11 Reactance diagram for example 1
NETWORK ANALYSIS AND FAULT CALCULATIONS 41
D GC
GB Line K 66/3.3/6.6 kV
11/66 kV
Line L
Line
G M
Fault
GD
11/6.6/66 kV
(i) Power system
R
9.38 12.5
A
10 25
20 8 Line H
B 4
6 8
8 3 18.18
Line K Line L C
8 2.29 6.04 5
Line M
3.96
12.28 10 20.24
6 5
8
16.33
12.28 20.24
5
12.2 2.5
3.33
2
16.33
8% 3%
66 kV 6.6 kV
4%
3.3 kV
The impedances are obtained from the data provided, by solving
the three simultaneous equations
HV + LV = 11
HV + MV = 12
MV + LV = 7
The equivalent impedance obtained from reduction of the network,
Fig. 2.12 is:
12.2% on 25 MVA base.
25
Fault MVA = × 100 = 204.9 MVA
12.2
204.9 × 10 6
Fault current = = 1782 A.
3 × 66 × 10 3
Example 3. A wye connected balanced 3-phase load is shown in Fig. 2.13. This
load draws 90 A from a balanced 3-phase supply. There are fuses in phase B and Y.
Find the symmetrical components of the line currents.
R
Fuse
Y
Fuse
B
FIGURE 2.13
1
IR = [I + a IY + a2 IB]
1 3 R
1
= [90 ∠0° + 0 + 0]
3
= 30∠0°
IY = a2 IR = 1 ∠240° × 30 ∠0° = 30 ∠240°
1 1
IB = a IR = 1 ∠120° × 30 ∠0° = 30 ∠120°
1 1
1
IR = [I + a2 IY + a IB]
2 3 R
1
= [90 ∠0° + 0 + 0]
3
= 30 ∠0°
IY = a IR = 1 ∠120° × 30 ∠0° = 30 ∠120°
2 2
IB = a2 IR = 1 ∠240° × 30 ∠0° = 30 ∠240°
2 2
In spite of the fuse removal there are sequence currents in both the
Y and B phases. They are just mathematical components of the currents.
However the current in the phases are actually zero.
IY = IY + IY + IY
0 1 2
= 30 ∠0° + 30 ∠240° + 30 ∠120°
= 30 ∠0° + 30 ∠–120° + 30 ∠120°
=0
and similarly IB can be shown = 0.
Example 4. A 25 MVA, 11 kV, 3-phase generator has a subtransient reactance of
20%. The generator supplies two motors over a transmission line with transformers
at both ends as shown in the one-line diagram of Fig. 2.14. The motors have rated
inputs of 15 and 7.5 MVA, both 10 kV with 25% subtransient reactance. The
3-phase transformers are both rated 30 MVA, 10.8/121 kV, connection delta/wye
with leakage reactance of 10% each. The series reactance of the line is 100 W.
Note the following:
• Negative sequence reactance of each machine is equal to its subtransient
reactance.
• Omit resistances.
• Select generator rating as base in the generator circuit.
• Zero sequence reactance for the generator and motors are 6% each.
• Current limiting reactors of 2.5 W each are connected in the neutral of
the generator and motor number 2.
46 POWER SYSTEM PROTECTION AND COMMUNICATIONS
Mot
1
Gen
Mot
2
– – –
Eg Em1 Em2
+ + +
j0.345 j0.69
j1.548 j1.548
j0.082
j0.06 j0.164
L L L
X fr
I II
Line A
L
Line B
Source X Fault
3. General approach
Using Thevenin’s theorem a general procedure for obtaining fault
currents in any network can be evolved. In Fig. 2.20 a single phase
impedance diagram is shown where F is the fault point and N the
neutral. Find the Thevenin’s equivalent at point F in the absence of
a fault.
NETWORK ANALYSIS AND FAULT CALCULATIONS 49
0.5
0.1
0.25 0.25
V F
N
F
G
Heat
+
Light
X = 0.3 pu X = 0.3 pu
Alt Alt
at 50 MVA at 50 MVA
X = 0.3 pu
11/66 kV
at 100 MVA
Fault
X = 0.00 pu
33/132 kV
at 10 MVA
Fault
3.1 INTRODUCTION
Safety reliability (continuity) of supply and welfare of plant are the
fundamental reasons or justifications for the protection and control
arrangements provided in electric power systems.
Protection and control viewed in this context obviously covers a
broader field than that concerned with the workings of circuit breakers
relays and other devices used to sense and control faults and abnormalities:
It includes consideration of aspects of system design especially system
earthing; circuit breaker provision; safety earthing; prevention and/or
mitigation of interference with public or private facilities or systems e.g.,
telecommunication systems, pipelines, railway systems, swimming pools
etc.
The protection engineer by virtue of their need to study prospective
and actual faults and abnormalities, which effect a power system, is well
placed, indeed obliged, to be active and accept considerable responsibility
in ensuring that the power system with which they are concerned has been
designed and is operated in a manner which maximises safety, continuity
of supply and welfare of plant. This arises largely because considerations
in these areas are more intimately connected with their work of providing
protection systems than they are with other aspects of system design
construction and operation.
52 POWER SYSTEM PROTECTION AND COMMUNICATIONS
BKR
Power station
Subtransmission
1 CCT
Zone 1 If
If B BKR B
substation
W W
R R
1
If If If If
N
Resistance
to
Inset1 Earth
If
11
LV IR B IR¢ IR B
customer 11 W IW¢ IW W
IW
11 R IB¢ IB R
IB N
Metal
LV
structures Earthing system Fuses
Bon
d
e utral
LV n
A
N
Conducting
pole (concrete)
or metal
Bond
LV earthing system
HV earthing system
(case of separate HV & LV
earthing systems bonded
for conservation to CMEN)
(a) Some typical earthing systems—CMEN
(Common multiple earthed neutral) system
HV cable
Earthing
Station boundary
electrodes
Buried grid
LV earthing
system
(b) Some typical earthing systems— (c) Some typical earthing systems—
earthing for large station one type of kiosk substation
(Note: Hazard zone may earthing systems
extend beyond station boundary)
FIGURE 3.1B
EARTH FAULT AND INTERFERENCES 57
If
Station VR
earth grid E
(Resistance to E
earse RSE) (Remote point)
Fault point
Telephone
(Resistance to earth RFE)
cable
V
EPRFP Fault
point
A
Station
E
VAE Remote
EPRS earth
V
Power
system
impedance Fault point
IF
Power
source VS EPR of
voltage fault point
EPR of station relative to
Station remote earth
RSE grid relative to RFE
earth
grid REM earth
Remote earth
3.3.2 Magnitude
Various factors which influence the magnitude of earth potential rises are
discussed in the following paragraphs.
Earth System Resistances
The resistance to earth of the earthing system depends upon its size
and arrangement and the soil resistivity.
Resistances to earth of earthing systems vary from small fractions
of an ohm (0.001 Ω) for a large power or terminal station to perhaps several
hundred ohms for an isolated distribution structure without supplementary
earthing, e.g., a concrete pole in an area of high soil resistivity.
Station Earthing
Even low earthing system resistances may be associated with
significant voltage rises if the fault current is high enough, e.g., the earthing
system of a particular zone substation with a 40 m × 40 m earthing grid in
an area with 10 ohm metre soil resistivity (resistance to earth 0.2 ohms)
would rise to 2400 volts above remote earth for a maximum fault current
of 12,000 amps. [(refer Fig. 3.3a)]
Constant
voltage
contours
Earthing
grid 40 × 40 m
Earthing
grid 40 × 40 m
The extent of the hazard zone will depend on the fault current
available, the soil resistivity, the earthing system geometry and the safety
criteria used.
For the purpose of illustration we will use the criteria adopted by
ESAA and Telecom Australia in the ‘Earth Potential Rise Code’(1). The
relevant criterion for a distribution system earthing system is an EPR of
430 volts. For a high reliability system an EPR of 1000 volts is acceptable,
without special precautions being taken.
Fig. 3.4 illustrates the case of a conducting distribution or sub-
transmission pole, e.g., a concrete pole, in homogeneous soil.
lf Voltage above remote
earth (EPR)
1m VT
d rl
Hazard zone ERP = for d ® r
2pd
VT (See pS of code)
Voltage gradient
E1000
Surface 1 mm
of VS
I VS earth E430
I
0 r d1000 d430 d
Distance
from structure
(a) Constant voltage contours (b)
22 kV r = 100 Wm
20
d430 volt
15
10
5 22 kV r = 10 Wm
11 kV r = 10 Wm
0 5 10 15 20 kM
Distance from structure
(Fault levels at source
22 kV 500 MVA 11 kV 350 MVA)
(c)
FIGURE 3.4 Variation of extent of hazard zone with soil resistivity and fault
level for metal pole without supplementary earthing system
Note the considerable influence that fault current and resistivity have
on the extent of the hazard zone.
The physical arrangement of the earthing system and the differing
resistivities of the layers of soil, considerably modify the voltage gradients,
the step and tough potentials at the surface and the location and shape of
the 430, 1000 and 1500 volt hazard zone contours (refer Fig. 3.5).
EARTH FAULT AND INTERFERENCES 61
Wood
Transformer
pole
Insulated
earth
lead
Buried
earthing
Earthing system
electrodes
Control and Mitigation of Earth Potential Rises and Step and Touch
Potentials
Power authorities use safety criteria similar to those used by Telecom
to determine maximum step and touch potentials and earth potential rises.
These are discussed in more detail in the next section of these notes.
It is only within ‘hazard zones’ that step and touch potentials are
significant. The control of these potentials to within acceptable limits is
usually the major objective in the design of earthing systems for HV
installations, since it is frequently economically impossible to keep the
potential rise with respect to remote earth to a safe value. As a consequence,
methods of working on power circuits which run to remote points, are
designed to ensure that personnel are not subjected to transfer potentials
caused by faults on adjacent circuits.
Fig. 3.6(a) illustrates a method of isolating workmen from transfer
and step and touch potentials.
Fig. 3.6(b) illustrates an arrangement used to facilitate work on
communication circuits entering a substation surrounded by a hazard zone.
In Fig. 3.5 the advantage of wood poles in respect to the avoidance
of touch potentials is clearly evident. The insulation of earth lead can also
help in reducing potential across the surface by deeper burial of the
electrodes.
62 POWER SYSTEM PROTECTION AND COMMUNICATIONS
Live
circuit
Circuit
under access
Safety earthing
Insulated arranged to keep
ladder out of service &
pole at same
potential if live
circuit faults to pole
Isolating links
Insulated
box Insulating
met station
earth grid
FIGURE 3.6 Safe working arrangements for work inside a hazard zone
2
3
4
101 –2 –1 0 1 2
10 10 10 10 10
Time (Seconds)
FIGURE 3.7
Commoning all pole and LV earths will reduce the touch voltages
to about 800 and 200 volts respectively.
Reducing the fault current by installing a resistor between the
transformer neutrals and earth, to limit the maximum fault current to say
2000 amps, together with CMEN (common multiple earthed neutral), will
reduce the prospective voltages to about 150 and 100 volts respectively,
i.e., within the limits previously postulated, when typical clearance times
apply.
The comparable voltages for 11 kV, and 6.6 kV systems for faults
distant 1km stations with maximum fault levels of 350 and 250 MVA
respectively and no CMEN or EFCL (earth fault current limitation) are of
the order of 2 kV and 1.5 kV respectively. Still a problem.
Subtransmission may also use similar poles and the maximum fault
currents are often high so solutions have to be found. In some respects the
difficulties are greater and CMEN and EFCL may not provide a solution.
In the case of main transmission other factors enable economically
practical solutions to be obtained e.g., specifically designed tower earthing
systems and ground wires are required for other reasons; the lines are run
in easements; faults are cleared rapidly; faults are rare.
3.5.2 Control of Step Potentials
These will usually be the major concern only where touch potentials have
been eliminated by appropriate insulation.
3.5.3 Control of Transfer Potentials
Communication circuits and other metallic services entering or passing
through hazard zones are prevented from transporting potentials out of
the hazard zone by suitable isolation and insulation, as mentioned earlier.
Where the means of transport could be the neutral of a CMEN system
the transfer potential may need to be kept within the voltage limits for
touch potentials.
Shorting switch
(Fault make capability)
Isolation of cap
bank neut
FDR FDR
(a) Arrangement of NER’s in a fully switched sub
with line CBs and no pilot cable system
Master
& BU E/F
X & Y Diff.
Res
E/F
Diff
O/C
20 MVA
Gas
MEF
1f – G
Fault
Dup diff.
20 MVA
66/22
Gas
MEF BU RCS
1f – G EF EF
Dup diff.
REF
I22
max 5 KA
FIGURE 3.11 Fault currents obtained with NER for a 66/22 kV 20 MVA transformer
70 POWER SYSTEM PROTECTION AND COMMUNICATIONS
I22
I66 =
3n
I22
Max
IF²
IF IF
IF¢
IF¢
IF
IA
IB
IC
IF IF
IF²
IF¢² IF
(Note: No zero sequence currents on high side for low side fault
May be a need for co-ordination of E/F prots on high and low sides
LFI and EPRs may need to be considered).
Ic¢
R
Ib¢ Ib
Y
Ic¢ Ia
B
IE
IE
(c) Two phase to earth fault fed through a delta/star transformer
(Note: No zero sequence currents on high side for low side fault.
Max current not as high as for single phase to earth fault.
No LF1 on high side.)
FIGURE 3.13
Except for the case of an earthed star connection on the input winding
of the transformers, currents flowing in the earth are confined to the low
side of the transformer.
The most common arrangements for zone substations and HV
customer substations fed from sub-transmission involve unearthed HV
windings.
Note: 1. Main transmission systems usually have earthed input and
output star connected windings consequently ‘reflected’ or
compensating currents flow in the earth for other parts of the
system in response to a fault on element of system, e.g., in the
system depicted in Fig. 3.13(c) compensating currents will flow
in both the sub-transmission and main transmission systems
(albeit of low magnitude compared with fault current).
2. Distribution substations have unearthed HV windings and
customer generators and SWER systems are isolated by
transformers with unearthed supply side HV windings.
Fig. 3.14 depicts a typical HV distribution system arrangement.
Master BU TP FDR
E/F E/F TP TR + B/T
CBs
FDR o/c
E/F
Zone
substation
LV customer
IL¢
SWER LV customer
ISOL,
substation IL SWER
LV Distr.
substation
ic ia ia 2 ia ib ic
1¢
ia¢ ib¢ 1 0 00
2 1
ia¢ ib¢ ic
2¢ ib1 ib2
ia¢ ib¢ ic¢ = 0 ic1 ic2
2 2
ib 1 ic 1
Ean ib
ic 1
ia = ia2 = ia0 = ic
0
1 Z1 + Z2 + Z0 + 3RF ib 2 ib 1 Ia
ic 2
IF = Ia = IN = ia + ia + ia0 ia 1
1 2
IB = 0 IC = 0
Z1 = Z1s + Z1T + Z1F
Z2 = Z2s + Z2T + Z2F
Z0 = Z0T + Z0F
FIGURE 3.15 Single phase to earth fault for fed through a delta/star transformer
IF
IF = 0.6IL IF
EF – E Load
IL = Normal load
current
IF
IF
FIGURE 3.16 Conductor on earth back fed from single phase substation
Fortunately this case has a low probability but it does illustrate the
desirability of arranging the system to minimise spurious currents and
hence be able to use low protection settings. One of the measures which
could be taken is to avoid long sections of fuse protected line: the blowing
of one fuse will unbalance the phase to ground capacitances and increase
the spurious earth currents.
3.6.5 Main Transmission Systems
There is obviously more need and justification for maximising the reliability,
security (stability) and selectability of protection systems in this type of
application.
Duplicated protection with back up for CB failure together with
various enhancements to achieve faster clearance are essential.
Automatic monitoring and self checking arrangements are quite
common.
into in service and out of service circuits during faults on adjacent circuits;
EPR's in the vicinity of out of service lines, etc. which are under access for
work; interference by low and high frequency noise signals generated by
faults and their associated arcs, in the power system's protection and control
circuits.
As mentioned earlier the protection engineer is usually in a good
position to deal with these problems because of the type of studies he must
do, to set and examine the performance of his equipment. Indeed it is
absolutely vital, in the interests of reliability of supply, that the protection
and control systems are immunised against interferences.
Some of these interferences are examined in the following
paragraphs.
Induced
longitudinal
voltage
E
0
Length of exposure l
Induced longitudinal
voltage in an open-circuit
telecommunication line
(b)
Induced
longitudinal + 1
voltage E
2
relative 1 0
E Length of
to earth 2 – exposure l
(c)
FIGURE 3.17 Induced longitudinal voltage between a
telecommuinication conductor and earth
EARTH FAULT AND INTERFERENCES 77
Earthing
system
PIT
or p Cable
illar
Exchange
During fault voltage
at this point exceeds
alloable voltage
Pipelines
Oil and gas pipelines are often insulated from earth for electrolysis
reasons and thus they need to be treated similarly to telecommunication
cables in respect to EPR’s and induced voltages.
3.7.3 Induction into Adjacent Lines
Voltages induced into adjacent lines are usually of little consequence, except
in a few circumstances, notably where an out of service circuit is being
worked on and where sensitive earth fault protection is applied to a line in
a network which shares poles with other lines, (which perhaps may be
operating at a different voltage level e.g., distribution HV often shares poles
with sub-transmission).
78 POWER SYSTEM PROTECTION AND COMMUNICATIONS
The diagram of Fig. 3.19 helps to explain how sensitive earth fault
protection, on lines in a network, can mal-operate during a fault on a feeder
running parallel to one of the lines in the network, viz. in each phase of the
network continuous paths can be traced, one leg of which is in close
proximity to the faulted feeder. Currents resulting from the voltage induced
in each of the phases will be summed in the earth fault protection circuits
associated with the network. If the exposure is long enough and the sub-
transmission protection is sensitive enough the relays will respond and
may operate before the feeder protection has been able to clear the fault.
Obtaining discrimination is usually fairly easy in this case, however in
cases where different networks are involved it is difficult to achieve
discrimination and retain sensitivity.
B
A Ei E/F C
OK
Zm
Earth
fault
Distribution feeder sharing poles with subtransmission
(a)
A
e
h as e B
P a s C
e
Ph as
P h Ii
C
Ii
A
I i I i Ii
Ii
3Ii
Induced current are summed into E/F pilot at both ends of each line
(b)
FIGURE 3.19 Induced currents interfering with protection on another pilot of system
EARTH FAULT AND INTERFERENCES 79
(Note: Problem only arises where exposure is long-earth fault too low for quick
operation for feeder protection-sensitive earth fault protection on loop).
Relaying Transducers
4.1 INTRODUCTION
In power systems, the levels of voltage or current are usually too high to
permit direct connection to measuring instruments or relays, coupling is
therefore made through voltage and current transformers that are designed
to reproduce an accurate scaled down replica of the input quantity.
Protective relays are required to measure during the transient period (which
invariably follows a fault) so that both accuracy and transient response of
the transducers are important. Errors in transformer output may
abnormally delay the operation of the protection, or cause unnecessary
operations. The functioning of such transformers must, therefore, be
examined analytically.
n:1
ZP ZS
Vp Ze Zb VS
Errors: Two errors are important. Firstly, the ratio error which is
defined as (n Vs – Vp)/Vp × 100%, where n is the turns ratio primary/
secondary. If the error is positive the secondary voltage exceeds the nominal
value. The turns ratio need not be equal to a whole number, some turns
compensation often being applied to ensure that error is positive for low
burdens and negative for high burdens. The phase error is the phase
difference between the primary and secondary voltages. Permissible errors
are +/– 3% (ratio) and +/– 2% (phase).
All voltage transformers are required by standards to have ratio and
phase angle errors within prescribed limits over a 80% to 120% range of
voltage and a range of burden from 25% to 100%. For protection purposes,
accuracy of measurement may be important during fault conditions when
the voltage is greatly suppressed. Therefore, a voltage transformer for
protection must meet the extended range of requirements over a range of
5% to 80% rated voltage and for certain applications, between 120% and
190% rated voltage.
4.2.1 Transient Performance of a Voltage Transformer
Transient errors cause few difficulties in the use of electromagnetic VTs
although some do occur. If a voltage is suddenly applied, an inrush transient
will occur, as with ordinary power transformers. The effect is however
less severe than the power transformers because of the lower flux density
for which the VT is designed. When the supply to a VT is interrupted (e.g.,
primary open circuited) the core flux will not immediately collapse and a
more or less exponential current flows in the burden. The condition must
not be confused with collapse of primary voltage due for example to a
system fault when the secondary voltage collapses also.
4.2.2 The Capacitor Voltage Transformer (CVT)
At voltages above 132 kV, the cost of conventional VTs is often prohibitive
because for higher voltages, the size becomes largely proportional to the
82 POWER SYSTEM PROTECTION AND COMMUNICATIONS
rated voltage. The CVT is a useful and more economical alternative, the
arrangement being as shown in Fig. 4.2.
C1 L T
C2 Zb
C = C1 + C2 L
C1
Vi = Vp Zb
C1 + C2
C1 RM Lm
Vi = V p Cm Vx
C1 + C2
Ideally one would want new purpose-built units of such CVTs but this is
not economically viable at present.
A closer approach to the response of a capacitor divider can be
achieved by modifying a conventional CVT to produce a capacitor divider
output in addition to the traditional output from the intermediate voltage
transformer. Such a scheme is shown in Fig. 4.6.
Ic
VC1 C1
L
VC2 C2 B Vs
Vp
Power
Pre-amplifier
VC3 C3 B
impedance circuits for the transfer load ampere-turns between stages and
ensure equal voltage distribution over the several primary windings. The
primary and coupling windings are connected to the cores of selected points
and all stages are housed in a vertical stack which is filled with oil and
sealed together with a cushion of nitrogen to permit expansion during
temperature changes. These cascaded devices are presently very expensive,
but in view of their superior transient response, they are likely to find
more widespread use in the future.
A
S n
N a
(a) minimum interference with power circuit i.e., Zp and Zs are made
very small by design.
(b) that Is is a faithful replica of Ip.
Ip Zp Ip¢ I:n Zs
Is = Ip¢/n
Rm Xm Es Vs Zb
4.3.1 Construction of CT
Current transformers are usually designed so that the primary winding is
the line conductor that is passed through an iron ring which carries the
secondary winding. They are mostly of this type and are known as bar-
primary or ring-wound current transformers.
The construction of a typical ring-wound current transformer is
shown in Fig. 4.9. Grain-oriented sheet-steel strip is wound to form a core
and is covered with a layer of insulation. The secondary winding is wound
over this and consists of the number of turns needed to produce the required
ratio of wire of sufficient cross-sectional area to carry rated current, followed
by a further layer of insulation which covers the secondary winding. When
installed, the primary conductor which acts as a single turn, is passed
through the centre of the ring. The making of the core by stacked annular
laminations has now been superseded by the wound-type method.
Core construction
P1
Insulation
Secondary
winding
Tape
S2 wound Insulator
S1
core
4.3.2 Design of CT
For protection purposes, current transformer specifications are normally
laid out in terms of the knee-point e.m.f. The knee point of the excitation
curve is defined as that point of which a further increase of 10% of secondary
emf would require an increment of exciting current of 50% (Fig. 4.10). We
can say that at voltages above knee point, saturation occurs quickly.
Vk 10% Vk
Exciting voltage (Vk)
50% Irk
Irk
Exciting current (Ir)
Ip
Vs
q
Is
Ie
F
impedance over the range of setting any relay. For example, the normal
burden of an overcurrent relay is 3 VA at setting. The normal setting range
of the relay is 50% to 200% of nominal current. Therefore, a 1 A relay set to
50% would have a setting current of 0.5 A and the voltage across the coil at
this current would be
3 VA
V= =6V
0.5 A
and the impedance would be
6V
Z= = 12 Ω
0.5 A
At a setting of 200% the setting current would be 2 A, the voltage
3 VA
V= = 1.5 V
2A
and the impedance
1.5 V
Z= = 0.75 Ω
2A
If the characteristic of the relay is to be maintained up to 20 times
the relay setting, then a knee point voltage of not less than
20 × 6 V = 120 V for a 50% setting
or 20 × 1.5 V = 30 V for a 200% setting
would be required. The former is more onerous and therefore the lowest
setting must be taken into account when specifying the knee point voltage.
There is, however, an alleviating factor in that a relay operating at 20 times
its setting will saturated magnetically and therefore the impedance will be
reduced. The reduction for an overcurrent relay is about half the impedance
at setting, which means that in the above case a knee point voltage of 60 V
would be satisfactory.
In many cases the current transformers associated with the over
current protection must also cater for earth-fault relays. An earth-fault relay
having a minimum setting of 20% would have voltage at setting of
3 VA 15 V
= 15 V and impedance of = 75 Ω
0.2 A 0.2 A
The maximum earth-fault level may be restricted to, say, twice the
CT primary rating and therefore 10 times the relay setting. The knee-point
voltage should therefore be greater than 10 × 15 V = 150 V, or allowing for
saturation, 75 V.
92 POWER SYSTEM PROTECTION AND COMMUNICATIONS
Class PL
Spaces (optional)
P2 P1
S2
P1
S1
S1 P2
CDG11 CDG14
2.5-10 A 0.5-2 A
0.4 1.4
3 VA 0.5 A
Impedance (W)
Impedance (W)
1A
2.5 A
5A 0.2 2A
10 A
1 Log-current 20 1 Log-current 20
times plug setting times plug setting
If a 1 amp relay is used rather than a 5 amp relay then the secondary
reference voltage will be 5 times that of the equivalent 5 A secondary CT.
Saturation CTs with low accuracy limit factors should be used for
thermal relays (or devices) as heating is proportional to the square of the
CT output current.
4.4.7 CT Secondary Currents other than 5 A
Throughout most of the world CT ratings of 5 A or 1 A prevail. North
American utilities use the 5 A rating almost exclusively, however, elsewhere
lower ratings predominate.
It is worth examining the factors and relationships which influence
the decision to select a particular rating.
Overcurrent Protection
5.1 INTRODUCTION
This type of protection which was developed some 70–80 years ago, is the
earliest, cheapest and simplest form of protection still widely used in the
power industry today. It operates on the principle that once a
predetermined level of current is reached the relay will operate in a
predetermined time. These relays are generally classified broadly in terms
of their time characteristic e.g., instantaneous, inverse time, extremely
inverse time, fixed or definite time.
Overcurrent protections should not be confused with ‘overload’ type
protections which consider the thermal capability of the plant to be
protected. The overcurrent protections are directed entirely to the clearance
of faults, although with the settings usually adopted some sort of overload
protection is normally provided.
These overcurrent protection schemes are commonly used to provide
short-circuit protection for many different types of plant. As well as being
applied to detect phase-phase short-circuits, such relays can be used to
provide earth leakage (phase-ground fault) protection. The overcurrent
relay in this case is connected in the neutral of the current transformer
secondary circuit.
Although the overcurrent protections are inherently non-directional
(i.e., they will operate for primary current flow in either direction), it is
possible for them to be controlled so that they effectively respond to primary
current in one direction only and this is done using a separate ‘directional’
relay to control the ‘secondary’ circuit of the overcurrent protection. A
102 POWER SYSTEM PROTECTION AND COMMUNICATIONS
50
Pick-up 1.05-1.3 Times setting
40
30
20
Time (Seconds)
10
8
7
6
5
4
3
1
2 3 4 5 6 7 8 10 20 30
Current (multiples of plug setting)
• lower ac burdens,
• wider application ranges,
• more accurate, not affected by mechanical problems such as pivot
friction,
• can be utilised to provide disturbance records, event records,
system load data and fault quantities,
• has communication capability to enable remote interrogation,
• self monitoring to ensure improved reliability and availability
capabilities.
2
10
1
10 Definite
8 seconds
Operating time, t(seconds)
Definite
4 seconds
Long time standby
Earth fault
Definite 120
t=
2 seconds I–1
Standard inverse
0.14
t = 0.02
0
10 I –1
Very inverse
13.5
t=
I–1
Extremely inverse
80
t= 2
10
–1 I –1
0 1 2
10 10 10
Current (multiple of setting)
10
8
6
5
4
3
2 1.0
Time (Seconds)
0.9
0.8
0.7
0.6
1 0.5
0.8 0.4
0.6 0.3
0.5
0.4 0.2
0.3
inst = 1 × Is
0.2 0.1
inst = 2 × Is
0.1 0.05
inst = 3 × Is
0.08
0.06 inst = 4 × Is
0.05 inst = 5 × Is to 31 × Is
0.04
0.03 Instantaneous
0.02 Unit
0.01
1 2 3 4 5 6 8 10 20 30 40 5060 80100
Current (multiple of setting)
10 10
9 9
Time current characteristic Time current characteristic
8 8
inverse time relay CDGIl inverse time relay CDGII
7 7
1-3 sec 3 sec to B.S.142
6 6
5 5
4 4
3 3
1.0
2 2 0.9
0.8
Operating time in secs
T 0.4
TMS = = = 0.1
Tm 4.0
Increasing the TMS has the affect moving the curve higher on time
scale.
5.4.2 PSM Examples
Consider the situation where the maximum fault current flowing through
the relay location is 3000 A (primary) and the relay is set to operate at
200 A (primary),
then PSM = 3000/200 = 15
Consider the same example, but in this case the relay setting has
been given as a tap/plug setting of 50% and the CT ratio of 400/5, then to
calculate PSM it necessary to refer all currents to either primary or
secondary values. If currents are referred to the primary,
3000 3000
then PSM = = = 15 (as above)
(0.5 × 5) × (400 / 5) 200
However, if the same primary current was considered but with a
relay current setting of 200%,
3000 3000
then PSM = = = 3.75
(2.0 × 5) × (400 / 5) 10 × 80
FIGURE 5.3 Simple radial case (time grading assumed 0.4 seconds)
FIGURE 5.3 (a) Simple radial case (time grading assumed 0.5 seconds)
When the formula for the static/digital relays is used, the same result
is obtained.
Tm = 0.14/((PSM)0.02 – 1.0) = 2.3 seconds
T
as TMS =
Tm
T = 2.3 × 0.1 = 0.23 seconds
T = K × [TMS]/[(I/IS)α – 1.0] = (0.14 × 0.1)/[200.02 – 1.0]
= 0.23 seconds
Continue with the relay at ‘C’
Now, for the same current of 2000 A the relay at ‘C’ must be set to
operate at 0.5 seconds (time delay step) longer than the relay at ‘D’, i.e.,
0.23 + 0.5 = 0.73 seconds.
If one assumes that the load at ‘C’ is higher than the load at ‘D’, then
the current setting at ‘C’ must be increased as compared to that of ‘D’.
Assume that the setting at ‘C’ needs to be 100% and uses 300/5 CT, then
Fault current 2000 (primary)
PSM = = = 6.67
Realy current setting 5.0 × 60 (primary)
If reference is made to the standard IDMT curve (at TMS= 1.0), it
can be seen that with PSM equal to 6.67, the corresponding Tm is 3.6 seconds.
When the formula for the static/digital relays is used, the same result
is obtained.
Tm = 0.14/((PSM)0.02 – 1.0) = 3.6 seconds
Hence for the required operating time of 0.73 seconds, the value of
T
TMS = = 0.73/3.6 = 0.20 seconds
Tm
When the formula for the static/digital relays is used, the same result
is obtained for TMS.
TMS = (T × [(I/IS)α – 1.0])/K =(0.73 × [6.670.02 – 1.0])/0.14
= 0.20 seconds
When faults occur close to ‘C’ the fault current is 3000 A, the
corresponding PSM value for the relay at ‘C’ is,
3000
PSM = = 10
5 × 60
With PSM equal to 10, the corresponding Tm is 3.0 seconds and,
with TMS = 0.20 seconds the actual operate time for the relay is
112 POWER SYSTEM PROTECTION AND COMMUNICATIONS
F1 F2 F3 F4
C B A
1 (Z S + Z11 )
where Vf = Source phase to ground voltage
1
is possible that the source fault level is reduced from 250 MVA
to 130 MVA.
Under these conditions the source impedance would increase
and the fault levels would reduce accordingly.
Zs = 112/130 = 0.93 ohms
6350
∴ IF = = 5.43 kA
1 (0.93 + 0.24)
At the lower fault level IF = 5.43 kA, the relay if it had been set
1
for 8.77 kA would not protect the cable section. Hence, in this
case current grading would not be a practical solution.
Consider the three phase fault levels at F4 (assume the source fault level to
be 250 MVA)
6350
∴ IF =
4 (Z s + Z L1 + Z L2 + Z T )
where ZL = Positive sequence line impedance = 2 × 0.02 = 0.04 ohms
2
ZT = Positive sequence transformer impedance
= 0.07 × [(112)/4 = 2.12 ohms
6350
∴ IF = = 2200 A
4 (0.484 + 0.24 + 0.04 + 2.12)
The relay controlling the CB at ‘B’, if set to operate at 2.2 kA, would
in theory protect the whole of the cable/transformer section between ‘B’
and ‘A’. However, it would not discriminate with the relay controlling the
CB at ‘A’.
If discrimination were to be achieved, a safety margin of say 30%
would need to be allowed for (assume 20% for relay error and 10% for
variation in the system impedance values).
∴ Choose a relay setting of 1.3 × 2.2 kA = 2.86 kA (relay at ‘B’)
However, the increased setting for the relay at ‘B’ would create a
‘blind’ spot where no protection was being provided. Again this would
not be a practical solution.
Consider the three phase fault levels at F3 (assume the source fault level to
be 250 MVA)
6350 6350
∴ IF = =
3 (Z s + Z L1 + Z L 2 ) (0.484 + 0.24 + 0.04)
= 8.3 kA
116 POWER SYSTEM PROTECTION AND COMMUNICATIONS
1000
Relay Relay
100 C A
Relay Relay
D B
10
Time (seconds)
200 A
fuse
0.1
3500 MVA 1540 MVA 123 MVA 98.7 MVA 35.7 MVA
150 A
500/1 A 150/1 A 500/5 A 250/5 A 4 MVA
A B 11/3.3 kV
C D E
7%
132 kV 11 kV 3.3 kV
In addition for the purposes of this example, all the fault calculations
demonstrated below are all referred to a common 10 MVA base.
Per cent impedance of the system elements on l0 MVA base
4 MVA transformer = 7 × 10/4 = 17.5%
10
11 kV cable (ED) = 0.04 × × 100 = 0.33%
112
10
11 kV cable (DC) = 0.24 × × 100 = 1.98%
112
30 MVA transformer = 22.5 × 10/30 = 7.5%
10
132 kV overhead line = 6.2 × × 100 = 0.36%
132 2
10 × 100
132 kV source = = 0.29%
3500
Consider SUBSTATION ‘D’
The protection at this substation is the first relay that must
discriminate with the 200 A fuse at fault levels up to:
10 × 100
= 35.77 MVA
17.5 + 0.33 + 1.98 + 7.5 + 0.36 + 0.29
35.77 × 1000
i.e., If = = 6258 A at 3.3 kV
3 × 3.3
35.77 × 1000
or If = = 1877 A at 11 kV
3 × 11
For satisfactory coordination between the fuse and the relay, the
primary current setting of the relay should be approximately three times
the current rating of the fuse and, the time grading margin, when expressed
as a fixed quantity should not be less than 0.4 seconds, or when expressed
as a variable quantity should have a minimum value of (0.4t + 0.15)
seconds, where ‘t‘ is the nominal operating time of the fuse.
For the above fault condition the fuse operating time at 6258 A is
approximately 0.01 seconds, therefore the required operating time of the
relay should be equal to or greater than (0.01 × 0.4 + 0.15) = 0.154 seconds.
The relay current setting must also accommodate a safe load of
4 MVA (the rating of the 11/3.3 kV transformer). By selecting a 100% plug
setting i.e., 250 A and 4.76 MVA at 11 kV this requirement will be satisfied
(19% safety margin), also the requirement of three times the current rating
of the fuse is satisfied (i.e. [250 × (11/3.3)]/200 = 4.2). As a consequence
PSM = 1877/250 = 7.51.
OVERCURRENT PROTECTION 119
From the above data, the time multiplier setting can then be selected
using the following formula:
TMS = T/Tm for electromechanical relays
= T/Tm = (T × [(PSM)2 – 1.0])/80
(for static/digital based relays)
From the characteristic curve of the extremely inverse relay for
1.0 TMS, the Tm for PSM of 7.51 is 0.9 seconds, therefore
TMS = 0.154/0.9 = 0.17
Select the next highest available time multiplier setting, in this case
0.2, this setting will ensure that suitable discrimination with the fuse is
achieved.
Consider SUBSTATION ‘C’
The relay in this case must discriminate with the relay in substation
‘D’ at fault levels up to:
10 × 100
= 98.7 MVA
1.98 + 7.5 + 0.36 + 0.29
i.e., 17.27 kA at 3.3 kV or 5180 A at 11 kV
In addition to providing primary protection to the section ‘C’ to ‘D’,
relay ‘C’ must also provide backup protection to relay ‘D’ protection
covering the section ‘D’ to ‘E’.
By selecting 100% plug setting i.e., 500 A and 9.33 MVA at 11 kV
(1667 A at 3.3 kV ) the sensitivity of the relay meets both the primary and
backup requirements.
Following the same procedure as was detailed for SUBSTATION
‘D’ by selecting a time multiplier setting of 0.7 for relay ‘C’, the required
discrimination with relay at substation ‘B’ is achieved.
Consider SUBSTATION ‘B’
The relay in this case must discriminate with the relay in substation
‘C’ at fault levels up to:
10 × 100
= 123 MVA
7.5 + 0.36 + 0.29
i.e., 21.5 kA at 3.3 kV or 6.46 kA at 11 kV or 537 A at 132 kV.
In addition to providing primary protection to the section ‘B’ to ‘C’,
relay ‘B’ must also provide back up protection to relay ‘C’ protection
covering the section ‘C’ to ‘D’.
120 POWER SYSTEM PROTECTION AND COMMUNICATIONS
Consequently for faults close to the relaying points, the inverse time
characteristic can achieve SIGNIFICANT reductions in fault clearance
times. Even for faults at the remote end of the line, considerable time
reductions are also achieved.
OVERCURRENT PROTECTION 121
E/F
Figure 5.5 is basically the extension of Fig. 5.4. Here the phase
overcurrent elements are connected in the individual phases and the earth
fault relay is connected between the star point of the relay group and the
neutral of the CTs. A current will flow through the relay winding only
when a fault involving earth occurs.
124 POWER SYSTEM PROTECTION AND COMMUNICATIONS
O/C
E/F
O/C O/C
E/F
not be seen by the earth fault relays on the ∆ side of the transformer, hence
the grading between earth relays on different voltage systems may not be
required (grading would be required if Y/Y transformers with neutrals
earthed are involved). However grading between the phase fault relays
on the ∆ side of the transformer and the earth fault relays on the Y side of
the transformer will be necessary, since phase currents are present in the ∆
side of the transformer.
CHAPTER
Fuses
6.1 INTRODUCTION
Fuses are the best known electrical devices and most of us at sometime or
the other have been made aware of their presence when one must be
replaced because it has blown/operated. They are basically simple and
relatively cheap devices although their behaviour is much more complex
and quite deceiving. Fuses perform the important duty of protecting the
equipment cheaply, efficiently and quickly and ensure that the effects of
faults are limited and that the continuity of supply is retained at all times.
Although the construction of fuses are not all that complex, but their design
and construction must be carried out with utmost care and precision so
that its reliability of operation is ensured.
The International Electrotechnical Commission (IEC) defines fuses
as “a switching device that, by the melting of one or more of its specially
designed and proportioned components, opens the circuit in which it is
inserted and breaks the current when this exceeds a given value for a given
time.” Australian Standards 1033 and 1034 cover the high voltage range of
the fuses.
The fuse is said to comprise all the parts that form the complete
device. The complete device being: (a) the fuseholder, which carries the
base and carrier and (b) the fuselink. The fuselink is a device comprising
of a fuse element or several fuse elements connected in parallel enclosed
in a cartridge, usually filled with an arc extinguishing medium and
connected to terminations. The fuselink is the part of a fuse which requires
replacement after the fuse has operated/blown.
FUSES 127
The fuse is a weak link and hence it has advantages over circuit
breakers. Generally the circuit breaker interrupts the current one to five
cycles after initiation at a natural current zero, whereas the fuse can operate
faster at any time and at any point on the current wave depending on the
magnitude of the overcurrent and the fuse characteristic. As element of
fuse is smaller in cross sectional area than the cable it protects, hence it
reaches melting point prior to the cable (provided both cable and fuse
element are of the same type of material). As the current increases the
element melts fast. Unlike circuit breaker, on deterioration it has tendency
of still faster operation. Hence ensuring its ‘fail-safe’ nature at all times.
The operation of the fuses can be made tamper proof when it is in sealed
and the cartridge type makes it silent and non-flammable. Hence the sealed
cartridge type which have element of silver (say) can be non-deteriorating
and gives consistent and reliable performance. The biggest advantages fuses
have is the devices are much cheaper than the circuit breaker of similar
rating and breaking capacity. Also the maintenance cost is much lower.
The disadvantage of fuses is the replacement time, although modern
cartridge fuses can easily be replaced, but the time to detect the faulty fuse
may be an added liability. Also, it has no switching ability at normal currents
and must be replaced after each fault operation. Hence if the fault in the
system occurs quite frequently, its replacement cost may make the device
quite expensive. However, a fuse-switch combination may overcome the
poor protection performance against small overcurrent.
6.1.1 Basic Definitions
The minimum fusing current is the minimum current at which a fuse
element will melt, which is the asymptotic value of current shown by the
time/current characteristic. (refer Fig. 6.30)
A conventional current rating is normally used under classification
of fuses which are reproducible under standard conditions.
The service rating is used for special type of fuselink which are to
perform unusual duties. These types of fuses must be used with the advice
of the manufacturer.
The current rating is the rating less than the minimum fusing current,
stated by the manufacturer. This is the current that the fuselink will carry
continuously without deterioration.
Fusion factor is the ratio of minimum fusing current to that of the
current rating.
128 POWER SYSTEM PROTECTION AND COMMUNICATIONS
minimum fusing current. Thus a thinner wire may be used for a given
current rating. When the wire is flattered into a tape the heat dissipation is
much faster. If the width at sectors along its length is increased, the heat
dissipation from the constriction is still faster. By such means the cross-
sectional area of the constrictions can be considerably reduced for a given
rated current which makes the fuse operate much faster than on a uniform
element as shown in Fig. 6.2.
Closing angle g
Supply
Voltage zero voltage
Cut-off current
Prospective current
5,000 A 22x
5000 A Current
Approx. Recovery
1000 V voltage
Volts across fuse terminals
2
Total i t
Pre-arcing
2 (limits heating of ò i2dt
it conductors etc.)
Actual pre-arcing Joule integral
time
Wire
Low melting
point high thermal
capacity insert.
Melts on small
overcurrent
if sustained
Dual element
time tag
M-effect additions
(fuse on small overcurrent if sustained)
Region which melts on high overcurrent
Besides the time delay provision, both the above methods have other
advantages. It reduces the temperature at which the element opens the
circuit. Therefore, it reduces the temperature of the ‘blown’ cartridge
immediately after clearing a fault at small overcurrent. Under high over
current conditions, the fuse will melt at the most constricted points and by
designing these carefully and manufacturing them to high precision, the
pre-arcing time can be controlled.
FUSES 131
The miniature cartridge type of fuselink may be of two types (i) filled
and (ii) unfilled type. They are basically small in size and used for the
protection of electric appliances, electronic equipment and component
parts, normally intended for use indoors. Many such varieties are available
as shown in Fig. 6.5. Powder is used as filler for the filled type and it has
high breaking capacity (in order of 1500 A). However, in the unfilled type
the element is supported in air inside the glass cartridge. It has low breaking
capacity (in order of 35 A). It is also possible to enclose huge variety of
element shapes, time delay springs, thermal sinks etc. in the glass cartridge.
The categories of speed of operation are signified by internationally
accepted letters that are marked on the fuselink bodies, viz.,
FF = super quick acting
F = quick acting
M = medium time lag
T = time lag or anti surge
TT = super time lag.
132 POWER SYSTEM PROTECTION AND COMMUNICATIONS
100
10 FF F M T TT
Time
0.1
0.01
1 2 3 4 5 6 7 8 910
Current
The quick acting type of fuselinks are F and FF. The F type have
single wire construction e.g., silver, copper and its alloy, nickel and nickel
chromium. The FF type is similar to the F type except that the elements
have a restricted section in them. The time lagging types are M, T and TT.
These are all of low-breaking capacity type and have glass bodies and of
the unfilled type.
6.2.2 The Semi-Enclosed Type of Fuse
Fig. 6.7 illustrates the semi-enclosed type of fuse. This type is very widely
used and they are in the low voltage category. The re-wirable fuse consists
of a base, a carrier, the fuse element and an arc resistant tube (to limit the
expulsion of flame). The element material is tinned copper, which has a
melting point of 1083°C, but it cannot be run for any length of time at
temperatures approaching the melting point and rapid oxidation takes
place above 250°C. Hence, the semi-enclosed fuse requires a large
overcurrent to blow it. The fusing factor is about 1.75. The performance
depends on how the fuse is wired (may/may not touch the tube sides)
and on the state of the tube. Care should also be taken as to ensure that it
is free of kink and the correct size of fuse wire should be used.
Fuse carrier Fixed
terminal Fixed contact
Fuse
element
The cylindrical cap contact or ‘B’ type fuses are widely used in France
for both domestic and industrial applications. The fuselinks have copper
wire or wire elements and are filled with quartz and have ceramic bodies.
These fuselinks are available with visual operational indicators, if required.
For domestic applications, the fuselinks are produced in a range of
diameters and lengths, each rating having its own unique dimensions to
prevent incorrect replacement after operation.
Fuse switch units having ‘B’ type fuselinks are available for industrial
use. Strikers, operating in a similar way to operation indicators may be
incorporated in these fuselinks. When a fuselink melts, the striker moves
out through the end cap and actuates a micro-switch which may initiate
an alarm.
6.2.4 North American Fuses
The various fuses are divided into classes, the main one being:
Class K — up to 600 A, 250 V and 600 V
Class H — up to 600 A, 250 V and 600 V
Class J — up to 600 A, 600 V
Class L — above 600 A and up to 6000 A, 600 V.
Fuselinks with current ratings up to 60 A are generally fitted with
cylindrical end contacts as illustrated in Fig. 6.13. Fuselinks for higher
ratings are provided with either blade-type terminations for mounting in
spring contact or blade terminations containing holes or slots which allow
bolted connections to be made (Fig. 6.14).
At currents above the minimum fusing level the solder melts, its
temperature rise being slowed by the adjacent masses of the metal. To
provide an adequate break, the two metal parts are pulled away from each
other by springs when the solder melts. The centre section does not contain
FUSES 139
filling material as this would prevent movement of the metal parts and it
is not required for arc-quenching purposes at that current levels. Other
types of Class K fuselink use the M-effect principle.
The Class H fuselinks have a low breaking capacity (about 10 kA).
They employ cylindrical fuse bodies in the high-breaking capacity fuselinks
and the connection arrangements and dimensions are also interchangeable.
There are two types of Class H fuselinks being non renewable and
renewable. The former uses copper elements and fillers whereas the latter
do not contain filling and use replaceable zinc elements with restricted
section. The end cap of the renewable type are removable (Fig. 6.16) so as
to allow the elements to be replaced when necessary.
Screw on end cap
Element
Inner cap Body
by Class R fuselink. The Class R type of fuselink is shown in Fig. 6.18 and
they contain features which prevents the insertion of Class H or Class K
fuselinks.
The Class J fuselinks are more compact than both the Classes K and
H. They have a breaking capacity of 200 kA and a high speed operation
under higher fault levels. Recently Class J has been replaced by Class T
fuselinks which has smaller dimensions.
The Class L fuselinks are used for all applications for current ratings
above 600 A. They have a breaking capacity of 200 kA.
In North America for domestic, commercial and light industrial
distribution applications Class G fuses are available. They have a rating of
300 V up to 60 A with a breaking capacity of 100 kA. In domestic premises,
the fuses are incorporated in the sockets from which the supplies are
obtained. As the fuselinks are screwed or plugged into their holders they
are known as ‘plug’ fuses. They generally have ratings up to 36 A and
operate at 125 V. Three types of such plug fuses are used:
(i) the ordinary
(ii) the dual type
(iii) the S type.
The ordinary plug type is as shown in Fig. 6.19 and contains an
element either in strip or wire form. The element can be seen through a
mica window set in the end of the body. The body has no filling material
and is made of glass. It has a metal contact in one end and a threaded brass
section around it which acts as a second contact and a means for screwing
the fuselinks into its base or holder. The fuselink can be replaced after
operation but there are some which allow replacement of the element.
Mica cover
Edison screw base
Contact
Fuse element
The dual element plug fuse has the same basic construction as the
ordinary plug fuse except that it contains two copper strips of which each
have one of their ends soldered to the other. A spring is incorporated to
separate the strips when the solder has melted as a result of the passage of
overloads. The operation is not produced by high transitory surge currents
but rapid clearance is obtained in the event of very high currents flowing
during the short circuits.
Both the plug type of fuse is fitted into standard Edison screw fuses
(Fig. 6.19). It is possible for users to make contact with live parts when the
fuselink is removed and a fuselink of any rating may be fitted into the
base.
The type S plug fuse is similar to the dual-element fuse but it is
designed for use with an adaptor which performs a role similar to the
gauge rings as mentioned earlier with the D type fuses. The adaptor has
an external screw thread which will mate with
the internal thread of a standard Edison screw Diaphragm
fuses and when fully secured it can be locked.
The adaptors are produced with several
different internal threads, one for each fuse
rating, hence the insertion of an incorrect Element
fuselink is prevented.
6.2.5 Liquid Type of Fuse
The liquid fuses are used for high voltage
application and utilises spring tension to assist
with arc extinction and to provide an adequate
physical break in the circuit to withstand the
Arc extinguishing
service voltage after operation. It consists of liquid
a toughened glass tube with metal end caps,
to the upper of which is secured by the short Spring
element (Fig. 6.20). This element has a high
tensile strain wire in parallel with the silver
fuse wire, as the latter is not strong enough to
withstand the tension of the spring securing Glass tube
from the upper contact and to fall, under the influence of gravity, about
the lower hinged contact.
Screwed terminal
cap
Upper Eye for
contact operating rod
Element
Inner tube
S.R.B.P. tube
Standard
flexible
lead
Lower
contact
Pivot pin
Hinge pin
Spring loaded
quadrant
Fibre Copper
sleeve sleeve Copper
Flex
sleeve
T-slow
T-slow
K-fast
FIGURE 6.22
It can be seen that all of them have braid at the lower end, the only
difference being the upper termination. The fuse carrier has pins at the
lower end which act as a hinge when it is mounted on the lower contact of
the fuse unit. In the service position the fuse carrier is tilted from the vertical
as seen in Fig. 6.23.
The main advantage of expulsion fuses is that they are cheap and in
most cases can be reused by fitting replacement links. In addition, as they
interrupt at current zero, they do not chop and do not produce excessive
switching voltages.
Their disadvantages are that they do not have the high breaking
capacities of powder filled fuses and are not current limiting.
FUSES 145
Terminal
Fuse element
Fusible section
(enclosing tube
often omitted)
Fuse link
(includes fusible
section and tails)
Fuse base Fuse-carrier Fuse-carrier
Fuse-base contact
contact
In some applications they have been known to cause fires due to the
expulsion of incandescent particles during operation.
Current zero
Peak arc
Relatively long voltage
Recovery
Pre-arcing time
Voltage zero Arc voltage voltage Recovery
voltage
Voltage zero
a b c
b a c
d.c.
d.c.
a—Initiation of current; b—Initiation of arcing; c—Final clearance
(a)
146 POWER SYSTEM PROTECTION AND COMMUNICATIONS
Current zero
Current zero
Peak arc
voltage
After
Large overcurrent Small overcurrent
FIGURE 6.25 Fulgurite structure-fuse without M-effect (with M-effect the fuse will
operate at the M-effect on small overcurrent)
1000 V
500 V
Applied voltage
It is, therefore, clear that a fuse of higher voltage rating should not
be used to replace a blown fuse of lower voltage rating unless due
cognisance is taken of the fact that its peak arc voltage will be greater. Peak
arc voltage must not exceed the dielectric withstand of the system in which
the fuse is placed.
Fuses for 11 kV use are frequently designed to produce low arc
voltages, in order that they may also be used on 6.6 kV systems. It should
not be assumed that this is the case without first consulting the
manufacturer on this point.
148 POWER SYSTEM PROTECTION AND COMMUNICATIONS
in time t is equal to z
0
i 2 R dt , where R is the resistance of the fuse element.
Further, at sometime t1 the element will reach the boiling point of the
t1
material and for large currents the total heat generated will be z
0
i 2 R dt
from this it can be deduced that, for a given element, under adiabatic
conditions, the total amount of heating required to fuse the element can be
t1
the Joule-integral and is denoted by I2t, where t is the virtual time defined
as the value I2t divided by the square of the breaking current.
Joule-integral can be used to accurately predict the cut off current
for a given prospective short-circuit current.
The pre-arcing I 2t of a fuse element is directly proportional to the
square of its smallest cross-sectional area. Consider the section of a fuse
element shown in Fig. 6.27 of length l and cross-sectional area A; carrying
a current i.
Mass m
Temperature q°C
Specific Heat s joules/gm
Current i Resistivity r0 ohm mm at 0°C
Temperature coefficient of
I resistance = a per degree
Resistance R centigrade
Hence, m=DAl
3
where D = density (kg/m )
and m = mass (kg)
A × l = volume (m3)
i 2 ρ 0 (I + αθ)l
dt = DAl.σ dθ
A
Dσ
or i2 dt = A2 dθ
ρ0 α (θ + 1 / α)
On integrating both sides
Dσ F
(θ 2 + 1/α ) I
z i 2 dt = A
2
ρ0 α
ln GH
(θ 1 + 1/α ) JK
where θ2 = melting point of the element
and θ1 = 20 °C
z i 2 dt = KA2
where K is the constant of the metal and can be directly calculated from
the known values.
For typical metal like silver and copper, normally used as fuse
elements, the pre-arcing I2t is 6.6 × 106 A2 (Amp2 sec) and 9 × 104 A2
(Amp2 sec ) respectively, where A is the cross-sectional area of the conductor
at narrowest point in mm2. Silver is very commonly used as a fuse element
due to its non-deteriorating, low oxidation properties. It also has good
M-effect with tin and its alloy.
The usefulness of virtual time is shown in Fig. 6.28 which represents
a typical fuse. It will be seen that the time less than about 5 × 10–1 s, there
is a spread in the normal current-time curve (shown shaded) and with the
larger currents there is considerable variation in the time, the ratio of the
largest to the smallest being about 5. There is however, no spread in the
curves of virtual time, and discrimination will be achieved between two
fuses provided that the curve of virtual total operating time of the minor
fuse lines below the curve of virtual pre-arcing time of the major fuse.
150 POWER SYSTEM PROTECTION AND COMMUNICATIONS
100
50
10
5
1
–1
5 × 10
Time (sec)
–1
Limits of actual
10 pre-arcing time
–2
5 × 10
–2
10
–3
5 × 10
–3 Virtual pre-arcing
10 time
–4
5 × 10
Virtual total
operating time
–4
10
–5
5 × 10
–5
10
50
100
200
300
400
500
1000
2000
3000
4000
5000
10000
20000
30000
40000
50000
since the arcing time varies with the power factor and transient
characteristic of the circuit, the supply voltage, the electrical angle at which
arcing commences and other factors. When operated within the voltage
limits prescribed by the manufacturer, the arcing time is only significant
for large overcurrents, where there are short operating times.
The current usually plotted on the time/current characteristic is the
prospective current i.e., the current which would flow in the test circuit if
the fuse were replaced by a link of negligible impedance. The time for
short-circuit operation is usually the virtual time, because of the variation
of actual time with the point on the voltage wave and other variables. On
small over currents, however, where the pre-arcing time is long and the
arcing time negligible by comparison, the times shown can be taken as the
total operating times at the currents shown.
A fuselink which is to protect Supply Connecting
a particular piece of equipment or cable A cable
circuit should ideally satisfy a Item of
number of criteria. This is illustrated B
equipment
Withstand curve of
protected circuit
Fuselink characteristic
Current
minimum fusing value. The ratio of the minimum fusing current to the
rated value, which is defined as the fusing factor, usually has values in the
range 1.2–2. The significance of this factor is that protected circuits must
be able to operate continuously at levels appreciably above the rated current
of the fuse in the first criterion above, namely that the circuit continuous
rating must exceed the minimum fusing current is to be satisfied. This is
an uneconomic situation which arises with many protective arrangements,
because it is necessary to have current settings above the full-load value of
the circuit unless discrimination is achieved by differential methods. It is
clear that it is particularly desirable to use fuselinks of low fusing factor
when the cost of the protected circuit and equipment rises significantly
with its current-carrying capacity. Another factor which must be borne in
mind is that many fuselinks do not provide full-range protection, i.e., they
will not operate satisfactorily, at all current levels from their rated breaking
capacities down to the minimum fusing values. As stated earlier,
satisfactory arc extinction may not be achieved in some fuselinks at
relatively low over currents. Care must always be taken to see that such
fuselinks are only used in applications where currents of these magnitudes
will not be experienced or, if this cannot be guaranteed, then an associated
protective scheme must be provided to interrupt these currents before the
fuse can operate.
have been flowing in it. The two effects will not usually be equal but they
nevertheless reduce the significance of this factor.
Pre-arcing time, (sec)
5000
1000
100
10
100A
40A
1 16A
0.1
0.01
10 100 1000 10,000 50,000
Prospective current in amps
[r.m.s. Symmetrical]
sh
Characteristics
al
ric
for different
et
m
rated currents
ym
As
6.5 DISCRIMINATION
Most circuits contain several protective devices and some of these are
effectively in series. They must all be coordinated so that correct
discrimination is achieved under all fault conditions and only the minimum
of interruption should occur to clear any fault condition.
6.5.1 Discrimination between Fuse Links
In domestic, and in many industrial installations, it is usual for the supply
authority to provide the main fuses, and consumers’ branch circuits are
protected by fuses of smaller rating. In the event of a fault in a branch
circuit the branch-circuit fuse should blow but not the supply authority’s
fuse, that is to say there should be discrimination. It is usual to call the
fuses the major fuse and the minor fuse, respectively. If there were no arcing,
and the fuses were of the same design, the minor fuse could be 90% of the
rating of the major fuse and there would still be perfect discrimination. In
practice, however, it is possible for a fuse to pass more I2t during arcing
than is passed during melting (termed more correctly, the pre-arcing
period), especially with large overcurrents in inductive circuits. If the major
fuse is to remain intact its pre-arcing I2t must not be exceeded: Hence to
achieve discrimination the pre-arcing plus the arcing I2t of the minor fuse
must not exceed, and preferably should be less than, the pre-arcing I2t of
the major fuse. This usually means that the rating of the major should be
not less than twice that of the minor fuse.
For convenience in ensuring discrimination between fuses,
manufacturers publish I2t characteristics similar to those shown in Fig. 6.33.
156 POWER SYSTEM PROTECTION AND COMMUNICATIONS
In these curves the minimum pre-arcing I2t is measured for every fuselink
at high prospective current, and the maximum total let-through I2t, pre-
arcing and arcing, will often occur at the condition of maximum arc energy.
To select a minor fuselink which will discriminate with a major
fuselink under all conditions, following two examples show the use of
these curves.
7
10
Total operating
2
I t (at 415 V)
6
10
Total operating
2
I t (at 240 V)
5
10
I t (Amp sec)
2
2
4
10
2
Pre-arcing I t
3
10
2
10
12
32
25
125
315
10
16
20
40
50
80
100
160
200
250
400
500
630
800
63
too large a current rating for the minor fuse, because the element of the
major fuse would just melt with the maximum let-through of the minor
fuse. In practice, discrimination would probably not be lost, because the
condition of maximum arc energy is very unlikely. To be sure that no
deterioration of the major fuse can take place, the 2 : 1 ratio is to be preferred.
We see that for the 80 A fuselink the I2t let-through is only 4.5 × 104 A2s,
giving such a wide margin that the major fuse cannot suffer any permanent
effect.
It is evident from the foregoing that, if the rating of the major fuse is
not too close to that of the minor, discrimination will be assured, provided
that the fuses are of the same design. If the supply authority fits cartridge
fuses at the incoming feeder and the user installs semi-enclosed fuses in
the branch circuits, a larger ratio than two may be necessary to ensure that
the major fuse will not blow in the event of a fault in the branch circuit.
Circumstances can occur in which the major fuse is at approximately
its working temperature when a fault occurs in a sub-circuit containing an
unloaded minor fuse. Obviously the pre-arcing I2t of a hot fuse is less than
that of a cold one, but if the minimum ratio of two is maintained the major
fuse would not normally be more than 50% loaded and the corresponding
reduction in I2t would be insignificant. Tests have shown that even if a
cartridge fuse is preheated for a considerable time by a current not sufficient
to melt the element, the reduction in I2t is usually small, in the context of
discrimination.
Example 2. It is very common to employ the radial system as shown
in Fig. 6.34 which may contain a number of fuses which must be chosen to
discriminate or alternatively a fuse may have to operate in series with a
circuit which is tripped by a protective relay.
PD 1 Load 1
PD 4 PD 2 Load 2
Supply
PD 3 Load 3
Here the major fuse in the supply connection (PD4) and minor fuses
in the individual load circuits (PD1, 2 and 3).
Clearly each minor fuse must have the time/current characteristic
needed to protect its load circuit and a fault on a particular load should
only cause its associated minor fuse to operate. The major fuse (PD4) will
also carry the fault current but it must not operate or be impaired.
158 POWER SYSTEM PROTECTION AND COMMUNICATIONS
For faults which cause relatively small currents to flow, the arcing
times, as proportions of the pre-arcing times, are small and consequently
discrimination can be predicted by comparing the time/current curves of
the major and minor fuses. Provided that the curves for the minor fuses
are to the left of that for the major fuse, that is the minor fuses operate
more quickly, then discrimination should be obtained. A significant margin
should nevertheless be allowed for fuse tolerances and because the major
fuselink may be carrying currents fed to healthy circuits as well as the
fault current. If these load currents may be large, then calculations should
be done to determine the possible currents in the major fuselink for given
fault currents and adequate time differences should still be present between
the operating times of the fuses concerned. This situation is illustrated in
Fig. 6.35.
Time, (sec)
tb
a
ta
Ia Ib Current
a = Minor fuselink
b = Major fuselink
Ib = Current in major fuselink when fault
current Ia flows in minor fuselink
tb = Must exceed ta characteristic
major fuse. This is because the minor fuse will be operating at lower
temperatures than the major fuse at the instant of fault occurrence. A
suggested rough, but general guide, for the extreme case of the minor fuse
being on no load and the major fuse on full load when the fault occurs, is
that the rating of the major fuse should be increased by a further 25%.
100
Time, (sec)
a
10
0.1
Current
100
10 Max breaking
current of
expulsion fuse
1
A b
0.1
Current
a—Expulsion fuse characteristic
b—Current-limiting fuse characteristic
(a) The take-over point (A) at which the curves intersect must be at
a current level below the breaking capacity of the other device
and above the minimum value which the current-limiting fuse
FUSES 161
vary between values of one and four hours, depending on the current rating,
is specified in the standards.
The concept of conventional currents has been used on the continent
for several years and it is likely that the present usage of the term
‘minimum-fusing current’ will be phased out.
Fuse
voltage
under
test
b1 b2
a2 c2
FIGURE 6.40 Fuses blowing on high current, low power factor within
prescribed limits for breaking capacity.
Test No. 1 at maximum breaking capacity
Distance/Impedance Protection
relay end, and the faults on the adjacent plant which should be left to the
protection of that plant to clear. This discrimination is achieved by
measurement of the distance from the relay location to the fault location.
This distance, when compared with the length of the protected line, should,
ideally, determine whether the fault location is nearer than or beyond the
other end of the line.
7.2.1 Zones
Using voltages supplied from the voltage transformers and currents from
the current transformers, the distance relay measures the impedance of
the line section from its location, at A, (Fig. 7.1), to the fault at K1. This
impedance is proportional to the fault distance A-K1. The distance relay
trips the circuit breaker at A instantaneously if the impedance measured is
less than a reference impedance e.g., the known impedance of line A-B .
Such a measurement cannot discriminate between the faults K2 just before
the busbar B in the station at the other end of the line, and those on or
beyond the busbars, like at K3 and K4 respectively, because the distance
from A to these points is practically the same. The protection engineer has
to make sure that the relay does not over-reach i.e., does not trip at A for a
fault on or beyond bus B even if the measurement of the impedance is
laden with some error. To prevent over-reaching, the reference impedance
for the instantaneous tripping is selected so that it corresponds only to
80% of the line length with a 20% safety margin left for all possible errors.
This creates a zone of 80% of the line, such that faults in that zone are
isolated instantaneously from end A. This zone is called Zone 1 of relay A
and the reference setting which determines the length of that zone is called
Zone 1 setting.
B
A K4 C
Ct K1 K2
G
K4 D
Vt
Distance
relay
Distance
Zone 1
60%
Stat. A Stat. B Stat. C
Time at C
Ra Load
Zd impedance
Za
area
30°
Line angle
A R
M
7.2.4 Directionality
Change of the current direction with respect to voltage reflects in the
impedance plane as a change of the angle of the impedance seen. Faults
behind the relay, e.g., M in Fig. 7.1, fed via the protected line, correspond
to points in the third quadrant of the plane. Zones 1 and 2 in Fig. 7.4 are
directional because no point of the third quadrant is inside Zone 1 or 2
characteristics. A circular characteristic passing through the origin like those
of Zones 1 and 2 in Fig. 7.4, is known as a ‘mho’ characteristic.
jX
C
3
ne
Zo
B
ne
Zo
K2
ne
Zo
O
A R
R R R
jX
jX
R
R
Lens Quadrilateral
reliability and speed. The numerical methods are used in digital relays
which, have already won enough confidence in the market to be exclusively
purchased by more and more utilities who appreciate the additional benefits
of digital technology.
v K1 K3 v
S1 Comparator S2
I K2 K4 I
S 1 = K1 V + K 2 I ...(1)
S 2 = K3 V + K 4 I
where K1 and K3 are scalar constants and K2 and K4 vector constants with
angles θ2 and θ4 respectively. Taking V as the reference vector and vector
I to lag V by an angle φ equation (1) reduce to
S1 = K1|V| + K2|I|{cos(θ2 – φ) + j sin(θ2 – φ)} ...(2)
S2 = K3|V| + K4|I|{cos(θ4 – φ) + j sin(θ4 – φ)}
174 POWER SYSTEM PROTECTION AND COMMUNICATIONS
| I |2 |I|
or +2 {x cos φ + y sin φ} + z = 0
V |V|
where x = (K1K2 cos θ2 – K3K4 cos θ4)/(K22 – K42)
y = (K1K2 sin θ2 – K3K4 sin θ4)/(K22 – K42)
K 12 − K 23
z=
K 22 − K 24
Equation (5) represents the equation of a circle on the β-plane having
|I/V|cos φ and j|I/V| sin φ as coordinates represented as
|I V|p + j|I V|q.
This circle as shown in Fig. 7.7 has radius
{K 12 K 24 + K 22 K 23 − 2K 1K 2 K 3 K 4 cos (θ 2 − θ 4 )}
r=
K 22 − K 24
{K 12 K 22 + K 23 K 24 − 2K 1K 2 K 3 K 4 cos (θ 2 − θ 4 )}
and d=
K 22 − K 24
DISTANCE/IMPEDANCE PROTECTION 175
K 1K 3
+ =0
K 2 K 4 cos (θ 2 − θ 4 )
| I |2 |I|
or + {x cos φ + y sin φ| + z = 0
V |V|
where
K 1K 4 cos θ 4 + K 2 K 3 cos θ 2
x=
K 2 K 4 cos (θ 2 − θ 4 )
176 POWER SYSTEM PROTECTION AND COMMUNICATIONS
K 1K 4 sin θ 4 + K 2 K 3 sin θ 2
y=
K 2 K 4 cos (θ 2 − θ 4 )
K1 K 3
z=
K 2 K 4 cos (θ 2 − θ 4 )
The circle has
{K 12 K 24 + K 22 K 23 − 2 K 1K 2 K 3 K 4 cos (θ 2 − θ 4 )}
Radius r =
2 K 2 K 4 cos (θ 2 − θ 4 )
{K 12 K 24 + K 22 K 23 − 2 K 1K 2 K 3 K 4 cos (θ 2 − θ 4 )}
and c=
2 K 2 K 4 cos (θ 2 − θ 4 )
Values of r and c for plot on the α-plane can be obtained, similarly.
In most relays at least one of the constants K (i.e., K1, K2, K3, K4) is
zero and two of them are often equal. Also the angle of the two vector
constants is usually the same. This makes the practical case relatively
simple. If θ2 = θ4 the values of r and c in the two cases are tabulated as
shown in Table 1.
TABLE 1: Comparative values of r and c for amplitude and phase
comparators (Fig. 7. 7)
K 1K 4 − K 2 K 3 K 1K 4 − K 2 K 3
r
K 22 − K 24 2 K 2K 4
K 1K 2 − K 2 K 4 K 1K 4 + K 2 K 3
c
K 22 − K 24 2 K 2K 4
f I
V p
D¢
X = K¢
K
O R
i.e., K1 = – K
K2 = K2 ∠ θ
K3 = K
K 4 = K4 ∠ θ
Substituting these conditions, we have
– K2 |V| 2 + {– K1K4 cos (θ – φ) + K2K cos (θ – φ)} |V| |I|
+ K2K4 |I| 2 = 0
V
Let be Z
I
and we get
– K2Z2 + K2K4 + KZ (K2 – K4) cos (θ – φ) = 0
Also, as Z2 = R2 + X2
Therefore,
K 2 K 4 (K 2 − K 4 )
R2 + X2 (R cos θ + sin θ) = 0
K2 K
(K 2 − K 4 ) cos 2 θ ( K 2 − K 4 ) sin 2 θ (K 2 + K 4 ) 2
or R– × ≤
2K 2K 2K
This equation represents a circle, with centre at (K2 – K4)/2K∠ θ on
the R-X plane, the radius being of magnitude (K2 + K4)/2K. The offset
threshold characteristic is shown in Fig. 7.13.
X
K2 Ðq
K
q
R
K1 Ðq O
K
Faults are
coverage
When protecting long lines, the reach of the polar characteristic along
the resistive axis can be many orders greater than the maximum fault arc
resistance. Even under normal conditions, when the line is transferring
power, some impedance is measured by the relay and this is generally
resistive but outside the characteristic. However, for long lines and heavy
circuit loading, healthy circuit tripping may occur, and it is necessary to
restrict the characteristic as shown in Fig. 7.16.
DISTANCE/IMPEDANCE PROTECTION 183
er
Blind
Typical load
impedance
area
R
b z
c z
e zg
method of earthing at either end of the feeder, and we cannot use just Va
and Ia to cover this fault. In practice we feed the relay with a current Ia + KIg
(Ig = residual current = Ia + Ib + Ic) and so the relay measures an impedance.
Va I a Z + I g Z g Z(I a + I g Z g/z )
= =
I a + KI g I a + KI g I a + KI g
Now the ratio Zg/Z does not vary with the position of the fault, and
if we make the residual compensating factor K = Zg/Z the relay always
measures the line impedance to the point of fault irrespective of the current
actually flowing in the earth return.
Likewise care has to be taken in the relaying qualities used in respect
of phase-faults, as shown in Fig. 7.18.
Ia z
Vab
z
Ib
zg
Here we see Vab = IaZ – IbZ, and provided we feed a voltage Vab and
Ia – Ib to the relay the impedance measured is again the impedance Z to the
point of fault.
The various voltages and currents used in distance protection are thus:
For Earth faults a–e Va → Ia + KIg
b–e Vb → Ib + KIg
c–e Vc → Ic + KIg
For Phase faults a–b Vab → Ia – Ib
b–c Vbc → Ib – Ic
c–a Vca → Ic – Ia
In schematic form the signals are derived from the system as shown
in Fig. 7.19.
DISTANCE/IMPEDANCE PROTECTION 185
CT
VT
CT
VT
CT
Trip
VT
Relaying
signals
S1 S1
Phase comparator Output Amplitude comparator Output
S2 S2
Inherent Inherent
phase phase
comparator comparator
S1-S2 S1-S2
S1 S2
S2
S1
The output voltage = (I1 – I2)R and the average volts are seen to be
positive if |I1| > |I2| , where the average is taken by means of integrator
circuit. Note: That the operating criterion is independent of the phase of S1
and S2.
I1 I2
S1 S2
+ +
– –
S1
I1
I2
S2
(b) Waveforms
FIGURE 7.23
S1 + S2
S2 1 : 1
To integrator
Va trips when
ò Va dt is + Ve
S1 – S2
2S1
1:2
S1
It can be seen that the average output volts are positive (i.e. trip)
when –π/2 < S2/S1 < + π/2 but the transformer arrangements are really a
crafty way of providing the signals (S1 + S2), (S1 – S2) which are compared
in amplitude therefore. Some proposed methods of providing inherent
amplitude comparators using transistors have been made, but with
reference to high speed methods problems clearly arise. It is necessary to
locate the maxima of the signals and compare, and this makes the circuitry
involved quite complex. Also as we shall see later there is a large dynamic
range of relay signals, and this aggravates the situation. We will not
therefore consider amplitude comparators further.
S1 Sine/square A
conversion
AND E
Gate
B C D
S2 p/2 Sine/square
Phase shift Differentiator
conversion
(a)
DISTANCE/IMPEDANCE PROTECTION 189
v S2
S1
t
A t
B t
C t
D t
E t
(b)
S1
AND Time AND
S2
gate A delay (T) B gate C
(a)
v S2 v S2
S1
S1
t t
v v
A t A t
v v
B t B t
w 0T = d w0T = d
v v
C t C t
(b)
v v v
t t t
v v v
A t t A t
v v v
B t t B t
VR VR VR
VS VS
VS
v v v
C t t C t
off ratio of the level detector exceeds about 2.5 (theoretically two is a
transient exists in only one signal). This comparator is extensively used
due to its desirable response. Its only disadvantage is that it is rather
inflexible from in that it is only possible to produce simple shapes of
characteristic (e.g., mho) which nevertheless are satisfactory for the majority
of lines. Other more flexible methods to cater for the requirements of long
and very important lines have been developed.
Block Average Arrangement
The relaying signals compared in a block average comparator arrangement
to produce the polarised mho characteristics are of the well-known form
of equation (14).
S1 = IZr – V ...(13)
S2 = V + Vp ...(14)
where I, V are the relaying current at CT secondaries and the relaying
voltage at the VT secondaries respectively. Vp is the sound phase polarising
voltage and Zr is the replica impedance, the former is obtained using the
192 POWER SYSTEM PROTECTION AND COMMUNICATIONS
K=
F
1 | Z LO |
−1
I ...(16)
GH
3 | Z LI | JK
where ZLO and ZLI are the z.p.s. and p.p.s. line impedances.
It is common practice to place replica impedances in the secondary
of the current transformers in order to generate the relaying signal S1 as
given by equations (14) and (15).
The transactor which is basically a transformer with a core having
air gaps and is extensively used in protection equipment using the block
average comparator arrangement and has a circuit as shown in Fig. 7.28(a).
Rb is a burden resistance so that neglecting the secondary winding reactance
(which is relatively low because of the air gap) yields the equivalent circuit
of Fig. 7.28(b) referred to the primary. With reference to Fig. 7.28(b) it can
be shown that the magnitude of the Zr the replica impedance referred to
the primary of the transactor, is given by equation (17).
I IP¢ I : nt
Lm R1 Va
Rb Va
Vi Xm = Rb¢ = Va¢
n2t nt
Vo′ Xm
Zr = = ...(1)
I [1 + cot 2 φ T ]
where φT = tan–1 (Rb/nt2 Xm).
The relaying signal produced by the transactor (e.g., for an ‘e’-earth
fault) is therefore S = I Zr – Va or in the transduced form, it can be shown
that:
nc
S1′ = nt2 Z I – Va′
nv r
where nc, nv are the turns ratio of the CT and VT respectively, which are
typically 1200/1 and 500/0.11 (for a 500 kV system) respectively. nt is
normally taken as 1/1.
It can thus be seen that the Zr′ replica impedance referred to the
secondary is given by equation (18).
nv
Zr′ = Z ...(18)
nc r
7.7 SIGNAL S2
As regards signal S2, there are essentially three basic types:
(a) self-polarised
(b) fully cross-polarised
(c) using the memory circuit.
7.7.1 Self-Polarised Type
In this case, the polarising signal is obtained from the same faulted phase
and is not very satisfactory, mainly because for close-up earth faults the
faulted phase voltage is close to zero, which gives unsatisfactory S2 signal.
However, it can have certain advantages for other fault positions. For an
‘a’-earth fault, for example, the S2 signal is given by equation (19).
S2a = Va + kp Va ...(19)
where kp is a constant.
7.7.2 Fully Cross-Polarised Type
The fully cross-polarised type is the most commonly used. In this case, the
polarising signal is obtained from the healthy phases and for an ‘a’ earth
fault, for example, it is given by equation (20).
S2a = Va + kp Vbc ...(20)
where kp is the polarising constant and is equal to kp ∠ 90°.
194 POWER SYSTEM PROTECTION AND COMMUNICATIONS
Transactor
CVT
Phase shift
circuit
Missing
circuit S1
Second order To
filter comparator
S2
The gain of the low pass filter is the value of its transfer function at p = 0
and is given in the case of equation (22) by gain = K1/b.
There are a number of ways of obtaining low pass filters using active
devices instead of inductors. The method commonly used is that of Sallen
and Kelly, in which the active device is an operational amplifier (op-amp).
Vc(t)
R1 R2 Cf
+ +
+
–
Vi(t) V(t) C1
V¢(t) R3 Va(t)
R4
–
(a) Actual circuitary
i2(t) Vc(t)
R1 R2 Cf
+ +
i1(t) +
–
Vi(t) C1
V(t) Va(t)
FIGURE 7.30 Sallen and Kelly second order low pass filter
A Sallen and Kelly second order low pass filter is shown in Fig. 7.30(a),
where the resistors and capacitors are properly chosen to realise given
values of ‘a’ and ‘b’ in equation (22). The op-amp, together with the resistor
R1 and R2, constitutes a voltage-controlled voltage source (VCVS) and hence
the Sallen and Key network is of the VCVS type.
The value of the constants are as follows:
µ × 10 6
K1 =
R 1 R 2 C 1C f
1 1 1
a= (1 − µ ) + +
R 2 C1 R 1C f R 2 C f
1
b=
R 1 R 2 C f C1
196 POWER SYSTEM PROTECTION AND COMMUNICATIONS
The quantity l = 1 + R4/R3 is the gain of the VCVS and is also the
gain of the filter since K1/b = µ
There are many types of low pass filter, but the two most commonly
used are the Butterworth and Chebyshev types.
VR = IR ZL
V
where Ir =
ZS + ZL
ZL
Thus Vr = V
ZS + ZL
1
Vr = V ...(23)
( Z S /Z L ) + 1
Equation (23) is true for all types of faults with the following rule
being observed:
1. For phase-faults V is the delta voltage and ZS/ZL is the positive
sequence source impedance/positive sequence line impedance,
V∆
i.e., VR = ...(24)
(Z S1/Z L1 ) + 1
DISTANCE/IMPEDANCE PROTECTION 197
and of course VY = V∆ / 3 .
Fig. 7.32 illustrates the effect of ZS/ZL ratio on the voltage at relay position
R. Three fault locations are shown: Fault outside the zone of protection,
fault at setting distance, and fault in the protected zone. The ordinate at R
represents the voltage applied to the relay VR for various fault locations,
for the relay to restrain VR should be greater than the preset value of
VR = IR ZL and for operation V should be less than the preset value of
VR = IRZL.
VS VL = VR
R IR
ZS ZL
V VR
For finding the pickup value of the impedance in section n let us say
Zone 1 is 80% of the protected section.
Z(n)
pickup (1) = 0.8 ZL
(n)
where Z(n)
pickup (1) = Setting value of pickup impedance of the Zone 1
impedance element.
ZL(n) = Line impedance of the protected section n
Therefore, any phase-fault for which the impedance seen by the relay
is less than the setting value of pickup impedance for Zone 1 will belong
to Zone 1 and is cleared instantaneously.
The Zone 2 includes the whole length of protected section plus up
to 40% of the next adjacent section. The clearing time for the Zone 2 is
taken as
t2 = t1 + ∆t
Analog input
Sample hold
CLOCK
control signal
MPX Microprocessor
address
Input
transformer CPU
1 ch M
Filter SH
U
2 ch L Setting
Filter SH
T Parallel
3 ch DI
Filter SH I ROM condition
P Trip
L DO output
E A/D DMA RAM
X
n ch E
Filter SH R
2 ch 1 ch n ch 1 ch 2 ch n ch
1 2 1 1 1 1 ch Data
ch n ch ch 0 0 0 2 ch Data
0 0 0
10
1 1 1 12 bit
10 11 n ch Data
0 0 0 1 ch Data
1 1 1 2 ch Data
11
t
10
P P¢
q
O O¢ R
B
area OPP’O’ is known as fault area. The impedance seen for differing fault
positions will lie inside the shaded area. To protect against all faults the
relay must operate if the measured impedance lies within the fault area.
Hence relays at O with characteristics which completely enclose the fault
area are suitable for protection of feeder OA.
Fault Resistance
Fault resistance consists of two components, the resistance of the
arc and the resistance of earth. The second component is present only when
it involves an earth-fault. In such a case the resistance of earth would mean
the resistance of fault path through the tower, tower footing resistance
and earth return. An approximate value of arc resistance is to be obtained
by empirical relations. Warrington gives the expression
Rarc = 2.9 × 104 L /I1.4 ohms
where L = length of arc in metres in still air
I = fault current in amperes
The arc resistance formula developed in Russia is:
L
Rarc = 1050 ohms
I
L will initially be equal to conductor spacing in the case of phase-
faults and distance from conductor to tower in case of earth faults. With
cross wind, when there is a time delay in fault clearance such as in Zones 2
and 3, the arc is extended considerably, and the resistance is increased. For
Zone 1 where the tripping is instantaneous, the effect of arc resistance is
small and may be neglected except on very short feeders; but for Zones 2
or 3 high velocity winds may cause the relay to underreach seriously.
When both wind and time are involved, Warrington’s formula for
arc resistance is:
50
Rarc = (VL + 47 vt) ohms
I
where VL = nominal system interphase voltage, kV
v = wind velocity in km per hour
t = time in second
I = fault current in amperes
20
10
10 20 30 40 50 60 70 80 90
System angle degrees
X¢
A
P
P¢
R
O O¢
Occasionally a fault may occur in the Zone 1 and the relay may begin
to operate. If the fault impedance now increases due to the arc resistance
the total impedance seen by the relay will be the sum of the line impedance
up to the fault and the arc impedance. This sum may be more than the
impedance setting of the relay in which case the first stage operation will
stop and the fault will be cleared as if it is located in the second or third
zone. In order to prevent this, impedance relays are locked once they begin
to operate on the basis of the true impedance up to the fault. Any increase
in impedance due to arc will not affect the relay once it is locked.
location during faults are often heavily distorted and laden with high
frequency noise. Filtering of the signals and mathematical processing of a
greater number of samples are, normally, necessary to make sufficiently
accurate estimate of the fault distance.
The error signals superimposed on the input quantities come from
several sources and are only partly predictable. DC and low frequency
transients are produced by instrument transformers and free oscillations
between system inductances and capacitances, higher harmonics are
generated in transformers , generators, static VAR compensators and non-
linear loads, non-harmonic high frequency random noise is produced by
multiple reflections of travelling waves initiated by faults and switching
operations. On top of these primary distortions there are also non-linearities
of the instrument transformers and interferences generated in the secondary
systems. The ability of the relay to extract the fundamental frequency
components from the noisy signals greatly increases with the time available
for filtering and the number of samples available for mathematical
processing. The rule known from application of all previous technologies
that the high accuracy and the high operating speed are conflicting
requirements applies also to digital technology and the practical solutions
are always results of compromises between these requirements.
In all practical digital relays the input quantity signals, voltage and
current, are passed through analog filters to eliminate any components of
frequencies higher than half of the sampling frequency to prevent errors
called aliasing. After the anti-aliasing filters the signals are sampled and
converted to digital form.
A simplified block diagram of a digital relay is shown in Fig. 7.33.
The sampling is controlled by a clock. The sampled values are held constant
for a short-time by sample-hold modules in order to provide for calculation
the voltage and current values corresponding nearly to the same instant
although the sampling takes place at a slightly different time. Sampling
exactly at the same time is possible but requires multiplication of A/D
(Analog to Digital) converters which is more expensive than using one
converter fed from multiplexed inputs as shown in the diagram.
Further processing of the digital values representing voltage and
current at the sampling instants may lead to estimation of magnitudes
and angles (vectors) of their fundamental frequency components and
subsequently, to determination of the fault impedance from these
components. These methods may utilise fast but less accurate algorithms
based on a short data window e.g., three samples, or more accurate longer
window algorithms. Some relays have both fast and slow algorithms
running in parallel to increase the speed for faults deep within Zone 1 and
to provide accurate borders between the zones.
204 POWER SYSTEM PROTECTION AND COMMUNICATIONS
squares of voltage and current magnitudes one can calculate the square of
impedance magnitude by division:
Vp2 v(t )2 + [v’(t)/ω]2
Z2 = =
I 2p i(t )2 + [i’(t)/ω ]2
nω = ωn = 2π/Tn
where n = the order of the harmonic, for n = 1 (the fundamental frequency
of 50 Hz) T = 20 ms, for n = 2 (second harmonic) Tn= 10 ms etc.
The coefficients Ir and Ix can be calculated from the following
formulas:
Fundamental frequency:
T
Ir = 2/T zt=0
i(t ) cos (ωt) dt
T
Ix = 2/T zt=0
i(t ) sin (ωt) dt
T
Inx = 2/T zt=0
i(t ) sin (nωt) dt
206 POWER SYSTEM PROTECTION AND COMMUNICATIONS
K
Ix = 2/K ∑ i(k ) sin (2πk/K)
k =1
t2
v(t) dt = R
z
t0
t2
i(t) dt + L[i(t1) – i(t0)]
z t1
v(t) dt = R
z
t1
i(t) dt + L[i(t2) – i(t1)]
For the samples of voltage and current taken at any three consecutive
instants k, k + 1, k + 2 the line equations may be written as:
LM ∆t (i k+1 + ik )/2 (i k + 1 − i k ) OP LR O = LM ∆t (v k +1 + v k )/2 OP
N ∆t (i
k+2 + i k + 1 )/2 (ik + 2 − ik + 1 ) Q MNL PQ N∆t (v k+2 + v k + 1 )/2 Q
The fault resistance and inductance from the above equations are:
( v k + 1 + v k ) (i k + 2 − i k + 1 ) − ( v k + 2 + v k + 1 ) (i k + 1 − i k )
R=
(i k + 1 + i k ) (i k + 2 − i k + 1 ) − (i k + 2 + i k + 1 ) ( i k + 1 − i k )
Differential Protection
8.1 INTRODUCTION
Differential protection is a unit type protection scheme that uses a
comparison between the current entering the protected zone and the current
leaving the protected zone, to determine if there is a fault. The comparison
can be made on the magnitude of the difference between the currents, the
phase difference or a combination of both.
Differential protection, in its various forms, is widely used in
protection systems for generators, transformers, busbars and lines.
The objective of this chapter is to examine the operating principles
and design of the various schemes.
The principle forms to be discussed are:
• circulating current differential protection (low impedance),
• biased differential protection,
• high impedance current differential,
• pilot wire, and
• phase comparison.
R R R
external fault, will not result in operation of the relay. All current
transformers must be connected on the same ratio, have similar
performance specifications and similar lead burdens between the CT and
the secondary summation point. To achieve the latter, it is usual to make
the CT summation as close to the primary plant as possible (e.g., in the
switchyard close the CBs). The summation is then cabled to the protection
panel.
In practice, there will always be some ‘spill’ current under external
fault conditions, particularly during the sub-transient and transient periods
of the fault. The precise level of these currents is difficult to predict so it is
usual to introduce a time delay into the relay and ensure that the minimum
operating level is not too sensitive. An inverse overcurrent relay, set on a
Short Time Multiplier Setting, gives a satisfactory performance. Even with
the use of an inverse overcurrent relay, the operating times that can be
achieved with this protection are far superior to what would be the case if
remote overcurrent or distance protections were relied upon to clear the
fault.
One difficulty that can arise with the application of low impedance
schemes is CT saturation. The most likely situation where this will occur is
where one of the primary circuits in the protected zone contributes a higher
level of current to an external fault than other circuits in the zone. If
saturation does occur, the CT will not contribute to the summation and
the magnetising impedance will appear as a zero impedance. As a result,
the circuit containing the saturated CT (including its cabling) will appear
as a resistance across the summation, in parallel with the relay. The
summated current from the unsaturated CTs will divide between the relay
and the saturated CT circuit according to the relative resistances of the
relay circuit and the saturated CT circuit i.e., spill current will flow through
the relay and most likely cause incorrect operation.
Referring to Fig. 8.2, it can be seen that the current through the relay
can be represented by:
I sec (Rlb + Rctb)
IRelay =
R Relay
From this formula, it can be seen that if RRelay is small compared
with (Rlb + Rctb) incorrect operation is likely to occur . One technique to
overcome the problem is to connect a ‘stabilising’ resistor series with the
relay. In the extreme, this approaches the high impedance scheme described
in section 8.4 and is not frequently seen in Australian practice; the preference
being to use the high impedance scheme.
212 POWER SYSTEM PROTECTION AND COMMUNICATIONS
a b
Relay
Bias Bias
Operate
tes
ra
8
ope
n
tio
ec
ot ea
6 Pr ar
e
tiv
Current, I1 ra
ope
4 In
tes
e ra
op
on
2
ecti
ot
Pr
0 2 4 6 8
Current, I2 (% rated secondary current)
(b) Typical biased characteristic relay
The concept of the biased relay is as shown in Fig. 8.3(a). This form,
known as percentage bias, operates on the principle that if the two currents
entering and leaving the protected zone are I1 and I2, then:
The operating quantity = K1 (I1 – I2)
The biasing quantity = K2 (I1 + I2)
Suitable choice of constants K1 and K2 ensures stability for external
fault conditions despite measurement errors, while still retaining adequate
sensitivity for operation on internal faults. Fig. 8.3(b) shows a typical
characteristic.
In electromechanical terms the relay can be thought of as having
bias coils in the circulating current path that exert a restraining torque on
relay operation and on coil in the operating leg that produces an operating
torque.
Where the protection is used on transformers, the CTs associated
with star connected windings are usually connected in delta and those for
delta connected windings in star. This corrects the power transformer line
current phase shift and eliminates the zero sequence currents on the star
side which might otherwise upset the stability due to the lack of a
corresponding zero sequence component on the delta side. Bias settings
are chosen to ensure that the relay will remain stable with the transformer
at the extremes of the tapping range.
Vp = 2 2 Vk ( Vf − Vk ) ...(1)
Line
I I
R R
Summation V Pilots Summation
transformer V transformer
Relay Relay
Line
I I I
A
T1
B
T2
N
The interphase sections of the winding A-B and B-C are often given
equal numbers of turns, the neutral end of the winding C-N will generally
have a greater number of turns.
Unbalanced fault currents will then energise different number of
turns according to which phase is faulted. This leads to relay settings which
are in inverse ratio to the number of turns involved. If the relay has a setting
of 100% for an A-B fault, the following proportionate phase settings will
apply.
Phase A-C 100%
Phase A-C 50%
Phase A-B 100%
Three phase 58%
The earth fault settings will depend on the relative number of turns
in section C-N but will also depend on which phase is faulted.
With an external fault, the transmission from one end fills in the
gaps at the other end resulting in a continuous signal on the line, when
observed by the measuring equipment at one end. Signal attenuation does
not affect the measurement. The continuous signal blocks operation. For
an internal, fault the resultant signal on the line has half-period gaps during
which the tripping function is initiated. Time delay circuits are included in
the protection to compensate for the transmission time of the carrier (0.33
milliseconds or 6 electrical degrees per 100 km of line for power line carrier).
Starting relays using current level, rate of change of current or
impedance measurement are used to initiate the comparison
(telecommunications regulations usually do not allow continuous
transmission of power line carrier) and to interlock the tripping circuit.
The tripping function is set so that operation will not occur until the
gap corresponds to a specific phase difference between the currents at each
end of the zone - usually in the range 18°–30°.
As with pilot wire schemes, separate comparison for each phase is
usually uneconomical and some arrangement for combining the phase
currents are made.
Modern developments, with the advent of digital transmission
systems and particularly the availability of fibre optic transmission systems
on transmission lines, has generated a renewed interest and there are
schemes available on the market.
Internal fault Internal fault
30° tripping 180° tripping
Through fault angle angle
Hf signal transmission at A
Hf signal transmission at B
9
Unit, Remote and Back Up
Protection
From the above comparison, it can be seen that each category has its
advantages/ disadvantages for particular applications but overall cost is
generally the biggest factor in applying unit-type schemes, particularly
where it becomes necessary to provide interstation signalling.
Distance protection does overcome to a large extent one of the main
disadvantages of non-unit schemes (i.e., limited sensitivity) and therefore
it is becoming the most common choice for the protection of lines in the
sub-transmission system along with almost universal use, with associated
signalling, at the main transmission level for which it was originally
developed.
The typical application of Unit and Non-Unit type Schemes are
demonstrated in Figs. 9.1 and 9.2. The typical type of schemes used are as
follows:
Unit Type Schemes
• Pilot wire
• Transformer differential
• Bus protection (high impedance, medium impedance, low
impedance)
• Phase comparison
• Distance protection with associated signalling
• Directional comparison
• Restricted earth fault etc.
222 POWER SYSTEM PROTECTION AND COMMUNICATIONS
220 kV Bus
Microwave
PLC
optic fiber
66 kV Bus
Pilot
wire
Unit schemes
Non-unit schemes
G GEN
Transformer
protection
zone
GEN TR
High impedence
protection zone
No. 1 Bus
No. 2 Bus
LINE
Non-Unit Schemes
Feeder Overcurrent
Transformer H.T. Overcurrent
Bus Overload
Earth Leakage Protection
Distance Protection without Associated Signalling
Fuses etc.
224 POWER SYSTEM PROTECTION AND COMMUNICATIONS
Clearance
time
Dt Dt
A B C
I I I
R1 R2 R3
Overcurrent protection
Clearance
time
0.5 S
Dt Dt
Zone 1 Zone 1 Zone 1
0
A B C
Z Z Z
Distance protection
Dt-discrimination margin
Local Back up
Back up to Protection Scheme Failure
The back up scheme to be provided must ensure, as a minimum,
that the performance and reliability of the overall protection system to
clear a fault is maintained for the failure of any single element.
To achieve the above requirement, the practice of organisations is,
in general, to have a philosophy similar to the following:
• Provision of two independent protection relay equipments on all
protection zones (e.g., lines, busbars, transformers etc.).
• Where possible, duplicated primary protections on a plant item
should use, equipment operating on different measuring
principles and/or design. The exception being duplicate
electromechanical protection schemes where in-service experience
has shown that such relays have displayed a high level of stability
and reliability.
• Provision of independent inter-station signalling links, where
required, preferably on different routes for the two independent
protection schemes.
UNIT, REMOTE AND BACK UP PROTECTION 227
Line X Y Y CB fail
X
Relay Trip Relay Trip (back up)
Y
To other
X To other X prots
X prots
Comm
Comm
Seal in Seal in Seal in
relay relay relay
X line Y line CB fail
protection protection protection
If applicable
Line X Initiate tirp
protection Y of bus via
CTs X bus prot.
Trip relay
X CB CB ‘A’ SW
trip Initiate trip
coil of adjacent
Y CB CB ‘A’ SW CB for 1.5 CB
trip arrangement
coil via X trip coil
FIGURE 9.4 Design practice providing back up for failure of protection-partial duplication
UNIT, REMOTE AND BACK UP PROTECTION
X Battery Y Battery
Line
X X Y Y
Y Relay Trip Relay Trip
To other
To other Y prots
X X prots
Comm
Comm
If applicable Seal in Seal in If applicable Seal in Seal in
relay relay relay relay
X line X CB Y line Y CB
protection fail protection fail
If applicable
If applicable
CTs X Prot & Initiate trip Initiate trip
X CB fail of bus via of bus via
X bus prot. Y bus prot.
X CB CB ‘A’ SW Trip relay
trip Trip relay
coil
Y CB CB ‘A’ SW
trip
coil Note: Note:
CB fail logic not included Initiate trip CB fail logic not included Initiate trip
for failure of CB for: of adjacent for failure of CB for: of adjacent
‘X’ bus protection operation CB for 1.5 CB ‘Y’ bus protection operation CB for 1.5 CB
Recieve X back up trip from arrangement Recieve Y back up trip from arrangement
remote end of line. via X trip coil remote end of line. via Y trip coil
Bus
229
FIGURE 9.5 Design practice providing back up for failure of protection-full duplication
230 POWER SYSTEM PROTECTION AND COMMUNICATIONS
DC supply
+ –
Timer
Protection
Current
check
Trip A
relay
Preferred
circuit Trip
appropriate
DC supply CBs or
+ – send remote trip
Current
check
Protection
Timer
Trip A
relay
Alternative
circuit Trip
appropriate
CBs or
send remote trip
DC supply
+ –
Current
check
Timer
Protection
Trip A
relay
Trip
appropriate
CBs or
send remote trip
Where the fault current is less than the load current, different
arrangements may be necessary, these would include the use of high set
current checks with other sensitive fault detectors interlocked by low set
overcurrent check relays.
In these applications the high set current check is set above the load
and would cover the high level faults, the low set current check arrangement
would cover low level fault conditions. Typical examples of local back up
protection used on EHV systems refer to Fig. 9.7.
R OR
HOC
B
LOC N
Local back up EHV lines (Initial three pole trip future provision
for single pole trip)
AND
R
OR Timer
Line
W Trip all
prot
bus CBs
S
OR
R
HOC W
OR
S
Deleted when single
pole trip required
LOC N
AND Timer Trip adjacent CBs
RWB initiate remote trip
Bus prot
as required
(b)
AND OR Timer
R Trip all
Line OR bus CBs
W
prot
B
OR
R
HOC W
B
AND OR
R
LOC W
S
NEG SEQ
AND Timer Trip adjacent CBs
RWS initiate remote
Bus prot
trip as required
(c)
UNIT, REMOTE AND BACK UP PROTECTION 233
Reactor RWS
prot
AND Timer
R OR Trip all bus
Line OR
CBs
prot W
B
R OR AND
LOC W
B
(e)
Timer Timer
Remote trip
receive AND
Under voltage
3f impedance
Zero sequence
Negative sequence
Trip appropriate
CBs
(f)
the circuit breakers and relays involved, will then initiate the trip of the
circuit breakers A, B, and C if the protection does not reset in that time,
indicating that the circuit breaker has failed to trip.
E G
CC F
B
P1 P2
C
(a) Schematic
X+ Y+ B/U+
P1 P2
+
CC
Trip relays – +
– –
Time
C.B. ‘E’ X Y
– delay
trip coils relay
Y– –
X–
Trip c.bs. A, B, C
Dead Bus
zone
Or
Blind
zone Circuit
breaker
Line
Fault
Y
Line CBF
protection
X
CBF
Y
1. X and Y protection operates and trips CBF isolating bus from fault is outside
line protection zone and line protection will not operate.
2. After a time delay the X and Y CBF protection in conjunction with the bus
initiates a trip to clear the breaker at the remote end of the line.
236 POWER SYSTEM PROTECTION AND COMMUNICATIONS
OR CB Trip
Line protection
220 kV source
Terminal station
220 kV lines
220 kV Buses
Terminal station
F2
F1
66 kV feeders
• the available phase settings for the relay are 1000 A, 1600 A, 2100 A
and 3000 A.
• the available neutral settings for the relay are 250 A, 400 A, 525 A
and 750 A.
• Equivalent fault currents seen by the back up protection (with
safety margins) for faults on the 220 kV bus or on the tertiary of
the transformer are as follows:
Fault Location Fault Level Safety Margin
220 kV Bus 3Φ = 3648A (R,Y, B) 3648/2100 = 1.74
Φ-Φ = 0A (R ) –
3158A (Y) 1.5
3158A (B) 1.5
Φ-g = 3657A (R) 1.74
595A (Y) –
595A (B) –
2467A (N) 4.7
Transformer 3Φ = 3884A (R,Y, B) 1.85
Tertiary Φ-Φ = 1942A (R ) –
3884A (Y) 1.85
1942A (B) –
Φ-g = Not Applicable
Introduction
configuration tools that will make it easy for the user to adopt the relay for
its application in the substation. This is especially important for peer-to-
peer communications based protection and control functions.
The material is organized in seven chapters. After Introduction of
the International Electrotechnical Committee and its objectives, the
initiatives taken by the Electric Power Research Institute are identified
followed by development of Intelligent Electronic Devices and the
development of Multifunction Microprocessor based relays. A separate
chapter is dedicated to communication principles where various
terminologies and architectures are identified. Numerous terminologies
are described so that the student or power network operator can have an
Engineering book that is easily understandable and which can be referred
to easily. Various architectures are considered that may very well be
appropriate for different scenarios. A separate chapter is included on
Protocols. In this chapter issues such as how communications processors
communicate to each other within the entire power network are identified
in detail. The application part of this book covers design and
implementation of Universal Middleware to support real-time
communication services over substation communication networks.
Intended to link various power networks via LAN & WAN
communication and information embedded power networks, this book is
authored from both university and power network operator’s perspective.
This book is aimed at the audience of application, design and Research &
Development Engineers in Power System Communications as well as
university graduate and continuous education students.
CHAPTER
Communication Principle
2.1 TERMINOLOGIES
2.1.1 System Automation and System Integration
System automation is the control of power system apparatus operations to
take the place of the human functions of observation, decision and action.
Substation automation refers to using Intelligent Electronic Device (IED)
data within the substation and control commands from remote users to
control the power system devices within the substation.
System integration is the act of communicating data to and from or
between IEDs in the Instrumentation and Control (I & C) system and remote
users. Substation integration refers to combining data from the IEDs that
are local to a substation so there is a single point of contact in the substation
for all the I & C data. This single point of contact then mediates remote
and local substation control. Since true substation automation relies on
substation integration, the terms are often used interchangeably. There is
often a need for multiple single points of contact to serve multiple user
connections or provide redundancy. The single point of contact is an I&C
device acting as a client/server, programmable logic platform, gateway,
router, dial-out device, communication switch, time synchronization
broadcaster, or a combination of these.
2.1.2 Substation Controller
Products from many industries are used to perform substation automation.
RTUs, port switches, meters, bay modules, and protocol gateways from
the Supervisory Control and Data Acquisition (SCADA) industry; PLCs
from the process control industry, relays and communication processors
from the protection industry, and PCs from the office environment.
COMMUNICATION PRINCIPLE 247
Application
Presentation
Session
Transport
Network
Data link
Physical
Layer Levels
• Application—Provides a set of interfaces for applications to use
to gain access to networked services.
• Presentation—Converts application data into a generic format
for network transmission and vice versa.
• Session—Enables two parties to hold ongoing communications,
called sessions, across a network.
• Transport—Manages the transmission of data across a network.
• Network—Handles addressing message for delivery, as well as
translates logical network addresses and names into their physical
counterparts.
• Data Link—Handles special data frames between the network
layer and the physical layer.
COMMUNICATION PRINCIPLE 249
2.1.10 Switches
A switch is an intelligent multiplexing device that monitors the data link
layer of the OSI network model (Fig. 2.1). If a data packet is incomplete or
indecipherable, the switch ignores it and does not broadcast it. If a data
packet is intact, the switch rebroadcasts it to another port, based on the
addressing data included in the packet and the addresses associated with
each port of the switch. New switches can operate on the Network (Layer 3)
or Transport (Layer 4) packet information.
2.1.11 Router
A router is an intelligent device used to connect two networks together. It
can be a complex model, with many features. It operates at the Network
layer of the OSI network model (Fig. 2.1). In another term, as used in the
communications industry it refers to a device that routes data in transit
between source and destination. The router intelligently transmits messages
received on one communications port to another communications port.
The destination port for the message is dynamically determined via the
content of the message. This is used to efficiently route SER and other
messages through multiple substation controllers without affecting
substation automation.
2.1.12 Servers
A server collects data from all of the local devices and creates a substation
database. Often a local human machine interface graphics package uses
data from this database. Servers function at the Application layer of the
OSI model (Fig. 2.1).
2.1.13 Dial-out
A dial-out device initiates conversations or triggers paging from the
substation to a remote user. Use for dial-out include ensuring connection
security, eliminating the need for a dedicated communications connection,
and performing unsolicited indication of a disturbance with fault location.
2.1.14 Communications Switch
A communications switch is the single point of contact for remote users to
dial in and make a direct connection to all substations IEDs individually. A
single communications connection form inside or outside the substation is
switched between several IEDs. The user initiates a dynamic conversation
with specific IED and the port switch merely ‘passes through’ the
conversation.
250 POWER SYSTEM PROTECTION AND COMMUNICATIONS
2.1.22 Tier-to-Tier/Peer-to-Peer
Some substation controllers accommodate substations of varying size as
well as redundant designs by supporting peer-to-peer and tier-to-tier
functionality. Peer-to-peer refers to the direct transfer of data between
devices functioning in a similar capacity. Tier-to-tier refers to devices that
can transfer data while connected in such a way that one is the client and
the other the server.
2.1.23 Substation Hardened
The inverse of the failure rate of a device, or mean time between failure
(MTBF) compares reliability of devices. Most devices that were traditionally
used for automation in the past, such as RTUs and PLCs were designed to
be operated in controlled environments like control rooms and generation
facilities. The average MTBF or RTUs and PLCs is 11 and 17 years
respectively. This low MTBF reflects a design philosophy based on frequent
replacement and maintenance. Protection devices are designed to be more
reliable, fail less frequently, be in service longer, and cost less to maintain
than PLCs and RTUs. The device MTBF can be used to predict how available
an automation system will be and how frequently the maintenance staff
will be replacing failed devices [1-2].
2.2 ARCHITECTURES
2.2.1 Types of Connections
Direct connect and multidrop are two types of data link connections
available to create networks. In a direct connection, there are only two
devices connected via network media, which can be metallic, wireless or
fiber. Each interface consists of a separate transmit and receive connection
at each device. Since there are only two devices, each of them can constantly
control the connection on which they are transmitting and both can know
implicitly to which other device they are connected. Several individual
direct connections to many IEDs would allow each of them to communicate
simultaneously. Many direct connections originating from one device is
called a star network topology (Fig. 2.2).
252 POWER SYSTEM PROTECTION AND COMMUNICATIONS
Network
controller
Relays/IEDs
Network
controller
Relays/IEDs
Network
controller
Relays
receive messages from the switch at the same time. Ethernet has now
completed the transformation both electrically and logically in a star
network architecture.
Relays/IEDs
SCADA Engineering
master station
Ethernet RS232
HUB
Route WAN Terminal
server
Terminal
server
Substation
UCA HMI
gateway
RS485 Ethernet
Ethernet
RS232
Legacy IED IED Laptop Data
Front
IED computer concentrator
RS485 RS485
RS485 Back 2 Back 2
Noninstrusive
eavesdrop
data link
Communication processor
Expert
Metering nodes
master
Met
Multidrop subnetwork
Subsystem Peer-to-Peer
connections
Distributed
HMI
controller
Ethernet
switch
FIGURE 2.8 Station LAN and multiple segment process LAN design
Station
LAN Distributed
HMI
controller
Ethernet
switch
Ethernet
IED
HUB
Sending Receiving
IED IED
GOOSE
Receiving
IED
IED
Distributed
HMI controller To Internet
To WAN
Ethernet
switch
Router
Ethernet Ethernet
switch switch
Protocols
CT
VT
Digital rela
y
SCADA Engineering
master station
RS232
Ethernet Terminal
Router WAN
HUB server
Terminal
server
UCA Substation
gateway HMI
As mentioned earlier, some forms of PLC have been in use for quite
long time now. However, a new perspective has been formed in the recent
years with the proliferation of companies developing low-cost chipsets,
which enable new high-speed short-distance applications. In addition,
companies have high hopes for developing ways of communicating
Broadband Internet connections over long distances using the utility
powerline network. There are many existing and evolving high-speed PLC
technologies with further research work proceeding aggressively.
However, the fact that powerlines are inherently limited to transmission
at the highest 400 Hz brings some concerns [37]. In addition, the high
electronically contaminated structure of the powerline and the high signal
attenuation at the frequencies of interest makes it challenging to achieve
dependable results. Hence, there is still a long way to go!
The user can quite often make choices in any given layer. The
ensemble of choices made to implement a protocol is termed a profile. The
rules designed by a protocol profile are designed to organize operating
issues in the following areas:
• Framing
• Error control
• Sequence control
• Transparency
• Line control
• Time-out control
• Start-up control.
There are literally thousands of combinations of protocol agreements
that can be created with the large domain of existing pieces. The main
protocols that have found widespread use in the substation environments
are [18, 10]:
• MODBUS: A popular master-slave protocol with industrial users,
which has also become popular in substations. It issues simple
READ/WRITE commands to addresses inside an IED.
• Distributed Network Protocol (DNP): An increasingly popular
master-slave protocol mainly in North America. DNP can run over
multiple media, such as RS-232 and RS-485 and can issue multiple
types of READ/WRITE messages to an IED.
• IEC-870-5-101: It is considered as the European partner to DNP.
It differentiates itself from DNP with its slightly different
messaging structure and the ability to access object information
from the IED.
• UCA: It is the Utility Communications Architecture designed to
satisfy every possible requirement in substation equipment.
accepted standard [19, 20]. IEC 61850 is a super subset of UCA 2.0 while
offering some additional features. IEC 61850 was published as standard
around the year 2003[23]. The following sections will detail the work done
by the IEC and EPRI groups towards standardization.
Possibilities:
· IEC 870-5
· DNP
· Profibus
· Other
TCP UDP
Protocol stacks OSI
IP
Data Data
Data on the wire
As shown in Fig. 3.5, the UCA comprises the data object models
(forming the highest level), the service interfaces to these models (defining,
retrieving, reporting and logging of process data, controlling devices, file
transfer) and the communication profiles.
The direct data acquisition and control of field devices is an area,
which has been undergoing significant transition. Traditionally, the end
field devices were directly connected to Remote Terminal Units (RTUs),
which provided a network interface and performed initial processing of
the acquired data.
The introduction of the microprocessor technology has allowed for
the direct network access to the devices as well as more processing being
performed at the end device by leading to the development of Intelligent
Electronic Devices (IEDs).
The cost of integrating the end devices has been increasing rapidly
since the end devices (IEDs) became more and more complex in time due
to the advancements in the technology. Within the UCA framework, the
device object model is referred to the definition of the data and control
functions made available by the device, along with the associated
algorithms and capabilities [19, 26, 27].
Number of efforts has been initiated to develop detailed object
models of common field devices, including definitions of their associated
PROTOCOLS 271
illustrates how the UCA Version 2.0 is implemented for field [27]. A device
is conformant to the UCA specifications only if it incorporates the following
three distinct specifications:
• The appropriate UCA object mode
• One or more UCA profiles
• The appropriate mapping of the Common Application Serivces
used in the Object Model to the application layer protocol.
UCA documents
Vendor documents Standardized
IEC 870-6-503: services,
Vendor product
Vendor product Selection of TASE.2 TASE.2 services mapping to
information,
specification building blocks and protocol application
user
layer
require-
ments
Specific
IEC 870-802: object types
TASE.2 TASE.2 object
TASE.2 Service Specific mapping to be
Services models
interface of objects supported
supported
Software Product
implem- design
entation
The number of UCA based IEDs for protection and control available
on the market is continuously growing and they are starting to appear in
installations around the world. However, the significant amount of
conventional microprocessor based protective relays installed earlier in
the substations need to be considered. There are some significant differences
between the UCA based IEDs and conventional microprocessor based
protective relays. This requires good understanding of the fundamentals
of communications based substation protection devices and at the same
time the availability of proper configuration tools that will make it easy
for the user to adapt the relay for its application in the substation [28].
3.4.2 lEC 61850 Project
IEC 61850 is based on the need and the opportunity for developing standard
communication protocols [30] to permit interoperability of IEDs from
PROTOCOLS 273
Station
FCT.A FCT.B
level
Bay
Bay unit
level
Application
ACSI
Neutral Abstract
interface communication
service interface
Specific
interfaces
AL 1 AL 2 AL n
Application layer 7
Layers 1.6
Communication stacks
Process
Application view
Binding
Logical node obejct
Objects
According to
Data objects Data objects
7-4 and 7-3
Communication view
Network
that are not yet modelled in IEC 61850. With the rules contained in EIC
61850 on how to model extensions, the data contained in these specific
extensions can be made available over the communication network in a
predefined way assuring interoperability [25].
With the plug and play capabilities embedded in the standard and
the immediate prove of concept in pilot projects, IEC 61850 promises to be
a great step forward in the development and acceptance of substation
automation systems world-wide. This will finally bring the real benefits of
automation and integration to utilities that were originally promised years
ago [25]. A non-proprietary, standard, high-speed protocol offering
sufficient services was required to enable a robust, integrated substation
communications network without protocol converters.
The introduction of IEC 61850 and the Utility Communications
Architecture has made it possible and justifiable to integrate station IEDs
through standardization. Using the standardized high-speed
communications between IEDs, the utility engineers can eliminate, many
expensive stand-alone devices and use the sophisticated functionality and
the available data to their full extend [25, 35].
3.4.3 DNP-3[153]
DNP-3 (Distributed Network Protocol) is a set of communications protocols.
It plays an important role in SCADA (Super Control and Data Acquisition)
system, where it is used for communications between system components.
The protocol was specifically developed for facilitating communication
between data acquisition and control devices.
DNP3 is an open, intelligent, robust, and efficient modern SCADA
protocol. It can:
• request and respond with multiple data types in single messages,
• segment message into multiple frames to ensure excellent error
detection and recovery,
• include only changed data in response message,
• assign priorities to data items and request data items periodically
based on their priority.
• respond without request (unsolicited),
• support time synchronization and a standard time format,
• allow multiple masters and peer-to-peer operations, and
• allow user definable objects including file transfer.
DNP-3 Provides Multiplexing, Data Fragmentation and More:
• DNP-3 is a layer 2 protocol. This means that it provides for
multiplexing, data fragmentation, error checking, link control, and
PROTOCOLS 277
with destination address. All IEDs on the bus receive the message but only
the matching address IED responses. In SPAusNet, only a handful of
analogue circuits is used for SCADA communication between RTU and
Control Centre. SP AusNet Digital Network SDH/PDH (circuit switch) is
used to provide all communications requirements for Protection, Controls
and SCADA. It also builds a separate Ethernet GigaBit network (where
possible) to provide corporate, engineering access to IEDs at Terminal and
Zone substations. Future development will be Operational IP network to
provide SCADA on IP.
CHAPTER
Middleware
4.1 INTRODUCTION
Power system utilities have to increase the efficiency and effectiveness of
their communications and control systems to become faster, flexible and
more productive. The best solution to achieve this is to make more efficient
use of the information and telecommunication systems. The progressing
deregulation of the sector has been possessing new demands to integrate,
consolidate and disseminate real-time information quickly and accurately
within all kinds of company systems. Therefore, there is a further need to
utilise the data provided by the Substation Automation (SA) system to
extend it by enhancing information processing and management on system
level. Furthermore, coordination of the SA and network control levels is
also crucial.
Over the last years, there have been significant standardization
efforts in order to prepare standards for power system control equipments
and control systems. Interoperability between vendors and systems is the
key for standardization. The new IEC standard IEC 61850 is expected to
solve some of the problems. However, the existing standard remote control
protocols are not well suited for transmitting between the substations and
system control system. Hence, there is a need for improving the
coordination of communication protocols at station level and for remote
control, which will improve the vertical integration, and the cost benefit of
SA.
Heterogenous software systems, computing and communication
components form the basis of future computing platforms, which are also
280 POWER SYSTEM PROTECTION AND COMMUNICATIONS
Gateway
OI
Substation network
Lead Master
Controller
(optional)
Substation bus
Protection unit
Bay controller
PC To network
control Station
centre level
Interbay
bus
Process
bus
Process
CD drive CTS/PTS Power transformers level
A bay refers to an area where a power system device such as feeder breaker,
and all of the I & C devices associated with it are located. These power
system IEDs include protective relays, meters, fault recorders, load tap
changers, VAR controllers, Remote Terminal Units (RTUs) and
Programmable Logic Controllers (PLCs).
3. Station level: Substation controller refers to devices that perform
data acquisition and control of IEDs and contain local I/O. They contain
data for the entire station. RTUs, PLCs, bay controllers, and Human
Machine Interface (HMI) software running on a personal computer are all
possible substation controllers.
4. Enterprise level: This is a generic term for all of the end users, or
clients of power system data inside and outside of the substation. These
applications acquire data from station level and unit-level devices.
For example, the three-fold purpose of a utility’s system integration
task can be summarised as follows. Transfer sensor measurements and
information created from this data among IEDs, between IEDs and a
substation controller and to end user clients directly from the IEDs and the
substation controller.
4.2.1.2 Example Communication Architectures of Power Systems
The communications architecture needs to be capable of data acquisition
and control to and from each IED in the substation. The following sections
detail the types of architectures used in substations.
4.2.1.2.1 Multidrop Network Architecture
The most common communication architecture used today is the multidrop
network or bus network shown in Fig. 4.3. As it can be seen from Fig. 4.2,
all devices are connected to the same physical wiring bus. Network master
is responsible for controlling the communications by issuing permission
commands to IEDs sharing the cable. An IED can only communicate when
it receives the virtual token and then passes the token when it is finished.
The most important advantage concerned with this kind of architecture is
that simple and fast peer-to-peer connections are possible. However, there
are major disadvantages as well such as the fact
Substation
that it does not allow simultaneous data polling of IEDs. The long-term
trend is away from multidrop networks and towards star networks.
4.2.1.2.2 Star Network Architecture
Many direct connections originating from one device is called a star network
topology as shown in Fig. 4.4. Any protocol, including those designed for
multidrop applications, can be used for direct communications in a star
topology. In this architecture, slow communicating devices can coexist with
more complex fast communication relays. Therefore star network supports
a wide range of IED capabilities.
Communications
Publisher Subscriber
2 2
Publish Unsubscribe ( )
Sending host
Ethernet hub
Another subnet
Sending host
Another subnet
Ethernet hub
Another
subnet
Sending host
Another subnet
Desired QoS
parameters
delay,
bandwidth,
reliability,
etc.
QoS signalling
Client
Host
Host
QoS techniques
signalling queuing, etc.
IDL IDL
stub skeleton
ORB ORB
Network
TCP/IP TCP/IP
Client
TCP/IP
6. Up-call 7. Return
Server
Data
(12800 bits)
APPL APPL
APPLICATION PROFILES
DEFINITION DEFINITION
Applicants Profiles
Atlantic Ocean
In
Corba_server IED1
Fig. 4.16 shows the two components of the system reaction time for
the case when UDP is used as the transport protocol:
Communication Management
control interface
Communication Diagnostics
protocol stack and test
Real-
time
OS Application framework
Software
work has already been carried out in this field since 1999. However, the
project can become unique in the sense that the IEC 61850 is not to be
implemented over a standard CORBA middleware but over an extended
version of the standard CORBA middleware. In other words, the main
phase of research comes in when the standard CORBA middleware is
extended to form an effective platform for performance sensitive real-time
power system operations. The main emphasis is on satisfying the
middleware requirements such as the ones detailed in Section 4.3.
Next step is to implement the IEC 61850 on the newly designed
middleware. Such an implementation is necessary since the designed
middleware will not deal with specific object functionality but with how
interfaces are specified, used and managed across the substation
automation network. Thus, we can provide an effective platform for
performance sensitive substation automation applications while also
meeting the interoperability requirements. Last step of the work can be
programming a programmable communications processor with the overall
code. The programmed communication processor can be referred to as
Universal Communications Processor (UCP) and FPGA technology could
well be used for this purpose [55-60].
CORBA enables running application analysis, monitorization and
simplifies system evolution. CORBA, nowadays, is the best suitable
platform for distributed systems construction due to its ability:
• To provide a good mixture of performance
• To provide resource consumption
• To provide a good support in the early phases of systems
engineering life cycles.
The research aims for making a standard middleware for substation
automation system by extending the standard CORBA middleware to meet
certain requirements as detailed earlier on. Thus, while keeping some of
the benefits it provides, the developers have tries to enhance it to end up
with a middleware platform speficifically designed to meet the
requirements of a substation automation network. Hence, the designed
communications processor is of universal type since it can include a
universal middle ware and the IEC 61850 universal standard.
Layer 7 Application
Layer 6 Presentation
Layer 5 Session
Layer 4 Transport
Layer 3 Network
Layer 1 Physical
Idle
Layer 3 Layer 1
Correct request Release confirm
Layer 1
Failure indicate
Resources
pending
Layer 1
Resource confirm Release
pending
Layer 1
Failure indicate
Link Layer 1
pending Release indicate
Layer 1 Layer 1
Link confirm Link Release request
established
Layer 3
Data request
Protocol stack
Interrupt Interrupt
Access Access
service service
function function
routine routine
Hardware
Diag.
Configuration Performance and test
manager monitor manager
Usage Fault
monitor monitor
Diag./Test
Objects and/or Data stores application
5
Information Embedded
Power Systems
NAT NAT
RTU RTU RTU RTU RTU RTU RTU RTU RTU RTU
Wide Area
Network
Power utility
Power system control centre
RTU 1 RTU 2
I2
V1
Wide area
Measurement network Display
data
P3
Mainframe
RTU 3
6
Fiber Optic Network
Infrastructure as Next Generation
Power System Communications
6.1 BACKGROUND
Power system communication has from high-speed substation control and
protection data communication to wide area power system monitoring
and measurement data transmission, the increasing incorporation of
computer network throughout the utility as well as the forces of
deregulation are compelling power system communications into new
realms with new requirements and challenges. Expanding network services
such as real time wide area control and Flexible AC Transmission System
(FACTS) device coordination are also driving the need for evermore
bandwidth in the network backbone.
These need will grow further as new real-time service, protection
and control applications become more feasible and pervasive. Electric
utilities often employ several types of communication media for different
functions. With more and more bandwidth required by the power system
data communication, the current transmission media cannot meet all the
high capacity and quality of service requirement. This chapter reviews
current power system communication media and discusses fiber optic
network infrastructure for the next generation power system
communications.
The power system is using several media for its protection, control,
and information sharing function. The most common ones include: Power
Line Carrier (PLC), microwave, pilot wire and wireless.
PLC operates by transmitting radio band of frequency signals
between 10 kHz to 490 kHz over the transmission lines. PLC with power
324 POWER SYSTEM PROTECTION AND COMMUNICATIONS
output of order 150 W can be used up to 240 km. Normally, PLC carriers
only one channel of 4 kHz bandwidth. The frequency range is limited by
government regulations. The PLC is the most common communication
media used in the USA. However, it has some disadvantage such as
bandwidth limit. It is subject to lightening switching surges, and networks
reconfiguration.
Another media is microwave. Microwave operates in the 150 MHz
to 20 GHz frequency range. This bandwidth can carry a lot of
communication channels for a variety of information. The disadvantages
of microwave is that the transmission length is limited to sight path between
antennas. Microwave is subject to atmospheric attenuation and distortion.
The combined latency using modem plus analog microwave is around 100
milliseconds between two adjacent antennas.
Pilot wire is normally a telephone wire either owned by utility
companies or leased from telephone companies. This type of
communication has a bandwidth from 0-4 kHz. Overhead lines may
experience interference from power lines while the underground is subject
to damages for many obvious reasons.
Wireless is one of the modern methods of communication. Low orbit
satellite communication system provides an existing option to transmit
information covering a very large range. The delay is a problem, which
depends on the distance. For example, the latency for low orbit satellite at
10 km above the earth is about 300 ms one-way. Another disadvantage is
the cost of installation.
All the above media may be using different communication networks
such as circuit-switched networks, packet-switched networks, and cell-
switched networks [73–80].
Fiber optic technologies have developed rapidly over the last 15-20
years. All-Optical cross connects and All-Optical Add-drop multiplexers
enable the evolution from simple point-to-point WDM links to full
networks. Fig. 6.3 shows detailed fiber optic network architecture.
Consisting of N-full duplex ports, where each of which can connect to any
other device, an OXC is a large photonic switch. An OADM is a 2 × 2
degenerate form of the NN × OXC. An OADM extracts and reinserts certain
light paths for local use and routes the others through.
End user
OXC
OXC Router
OXC OXC End user
Long distance OEO
OXC OXC
mesh network
(100s–100s km) OXC Router End user
Metro distance
network OXC
(10s–100s km) OXC Router
End user
Physical Layer
The layer at which signals are exchanged is known as the physical layer.
Based on fiber optic along the distribution feeders or single mode fiber
installed in the substation, is the feature of the physical layer. While bit
rates can be OC-48 (2.5 Gbs)/OC–192 (10 Gbps) or higher, transmitting
options are based on laser.
FIBER OPTIC NETWORK INFRASTRUCTURE AS NEXT GENERATION...... 331
Substation
server Level 2
Substation
Switch
Level 1
Control IED Control IED Substation
Control IED
User User
SMTP/FTP... application TFTP/NFS... application
TCP UDP
Internet protocol
Network layer
UDP [146] [148] [149] does not add much service to the underlying
IP. A mechanism of sending packets called datagrams is simply provided
by IP. The arrival of data neither the order of arrival nor important are
guaranteed. For large volume and non-critical data transmission like stream
audio and video UDP is normally used.
The TCP [146] [148] [149] offers connection-oriented byte-stream
service to the data transmission. The features are very important for power
system data transmission, since when data sent to the control centre or a
command is issued through the network, each bit will be very critical for
the correct information interpretation.
Reliability facilities to the IP protocol such as error detection and
correction, flow control, resequencing and duplicated segments
management, are added by TCP [146] [148] [149].
CHAPTER
Conclusions
and integrates 60,000 gates excluding on chip memory of DNP-2. The DNP
has a peak performance of around 50 MCPS.
Its use of object models of devices and device components is the
main difference in UCA from the previously designed and used protocols.
The common data formats; identifiers, controls for substation and feeder
devices can be defined with the use of object models of devices and device
components. The models specify standardized behaviour for most common
device functions and allow for significant vendor specialization for future
innovation.
The IEC 61850 protocol identifies all the known functions in a
substation automation system and splits them into sub-functions or
so-called logical nodes. A logical node is a sub-function located in a physical
node, which exchanges data with other separate logical entities. In IEC
61850, all logical nodes have been grouped according to their most common
applications area, a short textual description of the functionally, a device
function number if applicable and the relationship between logical nodes
and functions. The introduction of UCA and IEC61850 has made it
justifiable and possible to integrate station IEDs through standardization.
Utility Engineers can eliminate, many expensive stand-alone devices and
use the sophisticated functionality and the available data to their full extent,
using the standardized high-speed communications between IEDs.
74. Wook Hyun Kwon, Beon Jin Chung, “Real-Time Fiber Optic Network
for an Integrated Digital Protection and Control System”, IEEE
Transaction on Power Delivery, Vol. 7, No. 1. January 1992,
pp. 160–66.
75. Veeraraghavan, M., Karri, R., “Architecture and Protocols that enable
New Applications on Optical Network”, IEEE Communication
Magazine, Vol. 39, Issue 3, March 2001, pp. 118–27.
76. Tellez, J., Meriem, T.B., “Management Solutions for WDM
Networking”, IEEE International Conference on Network (ICON 2000)
Proceedings, 2000, pp. 120–24.
77. Bala, Rajagopalan, Pendarakis, D., “IP Over Optical Network:
Architecture Aspect”, IEEE Communication Magazine, Vol. 38, Issue
9, September 2000, pp. 94–102.
78. Harold Kirkham, Alan, R. Johnson, “Design Consideration for a Fiber
Optic Communications Networks for Power Systems”, IEEE
Transaction on Power Delivery, Vol. 9, No. 1, January 1994, pp. 510–18.
79. K. Washburn, J.T. Evans, “TCP/IP—Running Successful Network”,
Addison Wesley Publishing Company, 1998.
80. Amanullah Maung Than Oo, Kalam, A. and Zayegh, A., “Fiber Optic
Network Infrastructure.” As Next Generation Power System
Communications, JIEEE, November 2005, Jordan.
81. Qui, Bin, “Next Generation Information Communication
Infrastructure End Case Studies for Future Power Systems,” Ph.D.
Dessertation, Electrical and Computer Engineering, Virginia
Polytechnic Institute or State University, April 2002.
82. Hauer, J., Hughes, F.J., Trudenowski, D., et al., “A Dynamic
Information Manager for Networked Monitoring of Large Power
Systems”, EPRI Report WO 8813-01, October, 1998.
83. Liu, C.C., Heydt, G.T., Phadke, A.G., et al., “The Strategic Power
Infrastructure Defense (SPID) Systems”, IEEE Control System
Magazine, Vol. 20, Issue 4, August 2000, pp. 40–52.
84. Adamiak, M., Premerlani, W., “The Role of Utility Communications
in a Deregulated Environment”, Proceeding of the Hawaii’s International
Conference on System Sciences, Maui, Hawaii, January 1999, pp. 1–8.
85. “SCADA Communications”, Training Course, Institution of
Engineers, Australia, Western Australia Divison, 1996.
86. Newbury, John, Miller, William, “Potential Metering Communication
Services Using the Public Internet”, IEEE Transaction on Power
Delivery, Vol. 14, No. 2, October 1999, pp. 1202–07.
350 POWER SYSTEM PROTECTION AND COMMUNICATIONS
100. Mittelstadt, W.A., Krause, P.E., “The DOE Wide Area Measurement
System (WAMS) Project-Demonstration of Dynamic Information
Technology for the Future Power System”, EPRI Conference on the
Future of Power Delivery, April 1996.
101. Pao-Hsiang His, Shi-Lin Chen, “Distribution Automation
Communication Infrastructure”, IEEE Transactions on Power Delivery,
Vol. 13, No. 3, July 1998, pp. 728–34.
102. Qiu, B., Gooi, H.B., “Internet-based SCADA Display Systems (WSDS)
for Access via Internet.” IEEE Transaction on Power System, Vol. 15,
Issue 2, May 2000, pp. 681–86.
103. Fromm, W., Halinka, A., “Accurate Measurement of Wide-Range
Power System Frequency Changes for Generation Protection”, IEE
Conference Publication, No. 434, 1997, pp. 53–57.
104. Hauer, J.F., Cresap, R.L., “Measurement and Modelling of Pacific
AC Intertie Response to Random Load Switching”, IEEE Transactions
on Power Apparatus and Systems, Vol. PAS-100, No. 1, January 1981,
pp. 353–57.
105. Novosel, D., Vu, K.T., Eric Udren, Hart, “Practical Protection and
Control Strategies during Large Power System Disturbance”,
Transmission and Distribution Conference, 1996, pp. 560–65.
106. Martinez, J., Dortolina, C., “Dynamic Simulation Studies on Electric
Industrial System for Designing and Adjusting Load Shedding
Schemes”, Industrial and Commercial Power System Technical Conference,
Annual Meeting, 1994, pp. 23–29.
107. Chuvychin, V.N., Gurov, N.S., Venkata, S.S., Brown, R.E., “An
Adaptive Approach to Load Shedding and Spinning Reserve Control
During Underfrequency Conditions”, IEEE Transactions on Power
Systems, Vol. 11, Issue 4, November 1996, pp. 1805–10.
108. Moya, O., “Power System Computer Controlled Load Shedding”,
Electric Power System Research, April 1996, pp. 165–71.
109. Thang, W.Y., Boussion, J.Y., Peruzzo, B., Hubner, R., ”An Approach
for an Open Control System for Substations”, 14th International
Conference and Exhibition on Electricity Distribution, Part 1:
Contirbutions, IEE, Vol. 4, 1997, pp. 8/1–5.
110. Jay Murphy, R., “Power System Disturbance Monitoring”, IEEE
Proceeding of the International Symposium of Signal Processing and its
Applications, ISSPA, Vol. 1, Piscataway, NJ, 1996, pp. 282–85.
111. ACTLEM, “Power Quality Monitoring Systems for Utilities and
Industry”, http://www.actlem.com/
352 POWER SYSTEM PROTECTION AND COMMUNICATIONS