C - TS4CO - 2021: There Are 2 Correct Answers To This Question

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 51

C_TS4CO_2021

1 Which default values can you configure for the product cost collector?
✘✘✘

There are 2 correct answers to this question.

c ✘
Costing variant for preliminary costing
Variance variant
c ✘
Results Analysis (RA) key
Results Analysis (RA) version

2 Which statement best describes the Query Browser for reporting?

Please choose the correct answer.

It is a design studio app that comes as standard SAP Fiori content.


c ✘
It is a strategic analytical tool in SAP S/4HANA.
It is a desktop browser that integrates with SAP S/4HANA.
It is available as an additional license product in SAP S/4HANA.

3 What are some of the characteristics of SAP Core Data Services (CDS) views?

There are 3 correct answers to this question.

c ✘
CDS views have no latency.
CDS views are considered system modifications.
c ✘
CDS views support authorizations.
CDS views duplicate data for reporting efficiencies.
c ✘
CDS views have ready-to-use content.

4 You want to determine which operations of the routing should be considered in a

There are 2 correct answers to this question.

By assigning a cost center to the work center in the operation


By defining a usage key in the header of the routing
c ✘
By marking the Relevance to Costing indicator in the operation
c ✘ By marking the cost indicator in the control key assigned to the operation

5 What are some of the characteristics of internal order planning?



There are 2 correct answers to this question.


Tolerance limits are defined.
Availability control is checked.
c ✘
Multiple versions are allowed.
c ✘
Costs are entered.

6 Which process can you use to credit internal orders during period-end closing?

Please choose the correct answer.

Assessment
Distribution
Indirect activity allocation
c ✘
Periodic reposting

7 You want to run an assessment cycle in Profitability Analysis to allocate cost cent

Which of the following objects is part of the assessment cycle?


Please choose the correct answer

Template
Cycle iteration
PA transfer structure
c ✘
Tracing factor

8 You define rules in a status profile and assign the profile to your internal order ty

There are 3 correct answers to this question.

c ✘
To permit or forbid specific transactions
c ✘
To define the user status
c ✘
To set the initial status as Created or Released
To activate the CO partner update
To define users for the order

9 Which objects do you use when you assign costs and revenue to the value fields i

Please choose the correct answer.

c ✘
Transfer structure

Allocation structure
Allocation template
Overhead group

10 You want to set up integrated planning for your internal orders. What do you nee

There are 2 correct answers to this question.

Set the relevant indicator in the controlling area.


Set the relevant indicator in the planning profile of the order type.
c ✘
Set the relevant indicators in the CO version.
c ✘
Set the relevant indicator in the internal order master record.

11 How can you define the overhead rate in a costing sheet?

There are 2 correct answers to this question.

c ✘
As percentage rate
As equivalence number
As lot-based surcharge
c ✘
As quantity-based surcharge

12 What parameters can you set up when defining order types?

There are 2 correct answers to this question.

c ✘
Allow revenue postings.
Set up work lists.
Define document type.
c ✘
Define default parameters for master record fields.

13 You want to maintain a cost component structure. What can you determine for ea

There are 3 correct answers to this question.

c ✘
Assignment of cost component to calculation base for overheads in costing
c ✘
Relevance of cost component to results analysis
Relevance of cost component to goods manufactured
c ✘
Relevance of cost component to inventory valuation

Assignment of cost component to cost component group


14 To which object do you assign a costing sheet?

Please choose the correct answer.

Costing variant
Cost component structure
Transfer control
c ✘
Valuation variant

15 Which objects can statistical key figures be applied to?

There are 2 correct answers to this question.

Functional areas
c ✘
Profit centers
General ledger accounts
c ✘
Cost centers

16 How can you populate local variables in Profitability Analysis reports?

Please choose the correct answer.

c ✘
By user entry during report execution
By user exit
By Business Add-In
By populating from user parameters

17 ✘
Which statement best describes a cost center standard hierarchy?

Please choose the correct answer.

It is grouped together with alternative hierarchies to represent decision con


It represents an organizational unit in SAP S/4HANA where the costs and re
It enables you to assign the same attributes to similar cost centers within a
c ✘
It is a structure to which all the cost centers within a controlling area are as
18 ✘

What values flow from Sales and Distribution billing to costing-based Profitability

There are 2 correct answers to this question.

c ✘
Revenue
Maintenance overhead costs
Accrued production overhead
c ✘
Sales deductions

19 ✘ Which views can you use to analyze the costing results within the costing run too

There are 3 correct answers to this question.

c ✘
Analysis report
c ✘
Material list report
c ✘
Costing levels report
Variance report
Work in progress report

20 How does SAP S/4HANA determine if a characteristic value is valid in Profitability

Please choose the correct answer.

c ✘
By defining the characteristic value in the check table
By defining the characteristic value in the field catalog
By defining the characteristic value as a key figure
By defining the characteristic value as a value field

21 ✘ What can you do with statistical internal orders?

Please choose the correct answer.

Settle costs to a cost center.


c ✘
Simultaneously post to a cost center.
Transfer posting to another internal order.
Apply overhead rates to the internal order.

22 What are the prerequisites for automatic generation of the settlement rule to a m

There are 2 correct answers to this question.


The material in the sales order item is a service.
The sales order item is a cost object.
c ✘
The sales order item is assigned to a project.
c ✘
Profitability Analysis (CO-PA) is activated.

23 ✘ Which cost objects can only be controlled by period?

There are 2 correct answers for this question.

Production order
c ✘
Product cost collector
Process order
c ✘
Cost object hierarchy

You use a production order with Product Cost by Period and you entered a resu
24 variances in Product Cost by Period?

Please choose the correct answer.

Variances = Actual costs - Delivery value


c ✘
Variances = Actual costs - Delivery value - WIP
Variances = Target costs - Delivery value
Variances = Target costs - Delivery value - WIP

25 Where can you find actual transaction data of account-based CO-PA in SAP S/4HA

Please choose the correct answer.

CE1XXXX
c ✘
ACDOCA
BSEG
COEJ

26 For which of the following situations would you need to implement the transfer price

Please choose the correct answer.

Parallel price calculation and invoicing are needed to facilitate intercompany


Parallel accounting is needed in order to be compliant with different account
c ✘
Parallel valuation views of the same logistical flows are needed to differentia
Parallel costing is needed in order to calculate separate costs of goods manu

27 What are some of the unique attributes of an assessment cycle in Controlling?

There are 2 correct answers to this question.

c ✘
They transfer primary and secondary costs.
They transfer only primary costs.
They use the original cost element during transfer.
c ✘
They use a secondary cost element during transfer.

28 At what level do you create the structure of the operating concern?

Please choose the correct answer.

c ✘
Client level
Sales organization level
Controlling area level
Company code level

29 To which objects do you assign the elements of the cost component split to ensur

Please choose the correct answer.

Segments
G/L accounts
c ✘
Value fields
Controlling areas

30 ✘ You want to use a template for activity and process assignment to your material

Please choose the correct answer.

Assign a template to an operation in the routing of the material


c ✘
Use the template allocation function in the material cost estimate and the c
Assign a template directly to costing view 1 of the material master record
Use the costing sheet of the costing view 1 in the template determination ta
31 ✘

Which of the following objects can be selected in templates for activity-based cos

There are 2 correct answers to this question.

Internal order
c ✘
Cost center/activity type
c ✘
Business process
WBS element

You want to configure different cost centers in your company. Which setting
32 ✘
attributes to similar cost centers?

Please choose the correct answer.

Functional area
Activity type
c ✘
Cost center category
Cost center type

33 Which of the following statements are applicable to automatic account assignmen

There are 2 correct answers to this question.

It takes precedence over validation and substitution.


It can be defined for postings on general ledger accounts of secondary costs
c ✘
It can be overwritten in the application.
c ✘
It can be defined for postings on general ledger accounts of primary costs t

34 Which criteria do you use to specify the G/L account for the work in process (WIP

There are 3 correct answers for this question.

Results analysis profit center


Results analysis method
c ✘
Results analysis cost element
c ✘
Results analysis category
c ✘
Results analysis version

35 Which functionalities can create primary cost component splits?


There are 2 correct answers to this question.

c ✘
Settlement of internal orders
Business processes price calculation
c ✘
Execution of the assessment cycles
Cost center/activity type price calculation

36 ✘ Why would you use manual cost allocation in Controlling?

There are 2 correct answers to this question.

c ✘
To run simple allocations of actual data
To allocate costs using an allocation cycle
c ✘
To correct secondary postings
To run simple allocations of plan data

37 Which scenarios can be covered by the costing run?

There are 2 correct answers to this question.

c ✘
Standard cost estimate of all the materials in all plants of a controlling area
c ✘
Current cost estimate of all the materials in all controlling areas
Inventory cost estimate of all the materials in one plant
Product cost collector cost estimate in one plant

38 In a standard system delivery, how many characteristics can be added to an oper

Please choose the correct answer.

c ✘
0-70
71-100
101-150
Over 150

39 Which settings can you configure per order type for the budget and availability co

There are 2 correct answers to this question.

c ✘
Budget tolerance limits

Budget data entry layout


Design budget manager
c ✘
Budgeting on cost element level

40 Which of the following statements best describe Product Cost by Order?

There are 2 correct answers to this question.

It is recommended for products with a long production time.


It is used when you perform repetitive manufacturing.
c ✘
It is used when controlling by individual production lots or discrete quantitie
c ✘
It is used when full cost traceability is needed.

41 ✘ When you define assessment cycles for the period-end closing in overhead cost a

Please choose the correct answer.

Costing sheet
Template
Settlement rule
c ✘
Allocation structure

42 How does the system derive the requirement type from the material master data?

There are 2 correct answers to this question.

Strategy group -> planning strategy -> requirements class -> requirements
MRP group requirements class -> planning strategy -> requirements type
c ✘
Strategy group -> planning strategy -> requirements type
c ✘
MRP group -> strategy group -> planning strategy -> requirements type

43 Where do you activate commitment management for internal orders?

There are 2 correct answers for this question.

In the company code


In the budget profile
c In the controlling area
c ✘
In the order type

44 Which statements are relevant to the cost of sales accounting method in profitab

There are 2 correct answers to this question.

It presents revenues, primary expenses, changes in stock, WIP, and capital


c ✘
It presents the costs and revenues information in a format that is ideal for c
c ✘
It aims to match revenues for goods and services against sales-related expe
It aims to summarize activity and situational change for a given organizatio

45 You want to understand why costs are collected on sales order item level. What d

There are 3 correct answers to this question.

Valuation variant
c ✘
Requirements class
c ✘
Account assignment category
Costing type
c ✘
Requirement type

46 What are some of the characteristics of Profit Center Accounting in SAP S/4HANA

There are 2 correct answers to this question.

c ✘
It is integrated in the universal journal.
It is possible to derive the profit center from the segment in configuration.
c ✘
It can be used with period and/or cost of sales accounting.
It can be used in the settlement rule for internal orders.

47 How does SAP S/4HANA capture costs?

There are 2 correct answers to this question.

Only primary costs are captured in general ledger accounts.


c ✘
All primary and secondary costs are captured by creating them as cost elem
Secondary costs are captured as secondary cost elements, and NOT as gene
c ✘
Primary and secondary costs are captured in general ledger accounts.
48 You need to analyze different planning scenarios for cost centers. With which obj

Please choose the correct answer.

Operating concern
Cost center group
c ✘
CO version
Company code

49 ✘ Which of the following values can be calculated using results analysis?

There are 3 correct answers to this question.

c ✘
Work in progress
c ✘
Cost of sales
Gross margin
c ✘
Reserves for unrealized costs
Cost of goods manufactured

50 ✘

You are implementing SAP S/4HANA and you want to run analytical reports off a

Please choose the correct answer.

Reporting can be either broad and deep for analysis, or speedy and simple,
Reporting on data in real time is difficult, and complex to design.
Reporting analytical data is always done in a business warehouse system.
c ✘
Reporting on data is available in real-time at every level of detail.

51 ✘
Which customizing do you use for calculating work in progress (WIP)?
There are 3 correct answers for this question.

c Assignment table
Allocation structure table
c Update table
c Posting rule table
Settlement profile table

52 Which of the following statements best describe Product Cost by Period?


There are 2 correct answers to this question.

c ✘ It is used when the focus of controlling is on a stable and continuous produc


It is used for joint production with process orders.
c ✘ It is used in conjunction with a product cost collector.
It is used to analyze work in process based on actual costs.

53 How can you configure the transfer price solution in SAP S/4HANA?

There are 2 correct answers to this question.

c ✘ Use separate ledgers for each valuation.


Use separate currency types within the same ledger for each valuation.
Use separate segments for each valuation.
c ✘ Use separate accounts for each valuation.

54 Which of the following statements are applicable to SAP S/4HANA embedded ana

There are 2 correct answers to this question.

c ✘ It is part of the core SAP S/4HANA license and uses the same technical stac
c ✘ It uses core data services (CDS) views to create virtual data models (VDMs)
It is used by dedicated BI users who need to go beyond the capabilities of S
It is part of SAP S/4HANA Strategic Analytics tools stack that uses virtual da

55 You want to create a new standard cost estimate based on the quantity structure

Please choose the correct answer.

Costing type
Costing version
Transfer control
c ✘ Reference variant

56 You want to use a template to consider overhead during product costing. How do

Please choose the correct answer.


Using a special procurement type and an overhead group
c ✘ Using an origin group and an overhead group
Using an overhead group and an overhead key
Using a profit center and an overhead key

57 Which receiver must be allowed in the settlement profile of a product cost collect

Please choose the correct answer.

c ✘ Material
Cost center
Business process
Order

58 You use a ledger, an additional standard ledger and an extension ledger. You pos

For which ledger(s) are separate line items posted in the universal journal?

Please choose the correct answer.

All ledgers
The standard ledgers
c ✘ The leading and extension ledgers
The leading ledger only

59 You want to derive the profitability segment for a line item in the universal journ

There are 2 correct answers to this question.

c ✘ The type of the corresponding general ledger account must be primary cost
The type of the corresponding general ledger account must be balance shee
c ✘ Costing-based Profitability Analysis must be active.
Account-based Profitability Analysis must be active.

60 For which revenue-carrying cost objects does the system perform results analysi

There are 3 correct answers to this question.

Cost center
Business processes
c ✘ Internal order
c ✘ Work breakdown structure
c ✘ Customer service orders

61 What action do you perform to use the Cost-Based Percentage of Completion (PO

Please choose the correct answer.

c ✘ Running the results analysis


Costing of an order
Billing of a sales order during production
Setting to profitability analysis

62 You want to enable WIP calculation in Product Cost by Period. What do you need

Please choose the correct answer.

Profitability Analysis (PA) transfer structure


c ✘ Valuation variant
Settlement profile
Variance variant

You have implemented Product Cost by Sales Order in conjunction with cost-bas
63 order item, you have the following:

- Plan revenue = 3000

- Plan costs = 2000

- Actual revenue = 1200

- Actual costs = 1000

What data does the system calculate during results analysis?

Please choose the correct answer.

Revenue = 1200; Cost of sales = 1000; Capitalized revenue (revenue in exc


Revenue = 1500; Cost of sales = 1000; Revenue surplus = 300
Revenue = 1200; Cost of sales = 1000; Revenue surplus = 200
c ✘ Revenue = 1500; Cost of sales = 1000; Capitalized revenue (revenue in exc

64 Which of the following steps are part of the procedure to update the standard pri

There are 2 correct answers to this question.


c ✘ Release the cost estimate.
c ✘ Mark the cost estimate.
Split the costs.
Archive the cost estimates.

65 How do you maintain number intervals/ranges in Controlling?

Please choose the correct answer.

By posting key
By document type
By company code
c ✘ By business transactions

66 What can you configure in the settlement profile?

There are 2 correct answers to this question.

c ✘ Define document management parameters.


Define a number range for settlement documents.
Determine an overhead key.
c ✘ Determine whether settlement is required.

67 Which parameters can you enter when you create a costing run?

There are 3 correct answers to this question.

c ✘ Costing variant
Valuation variant
Production version
c ✘ Transfer control
c ✘ Costing version

68 What does the internal order settlement profile define?

There are 3 correct answers for this question.


c ✘ Whether settlement is necessary
c ✘ The valid receivers
Whether commitment management is necessary
The template allocation
c ✘ The accounting document type

69 In the material master record there are three planned prices. What do you use th

Please choose the correct answer.

To valuate goods movement


To valuate the materials in cost estimates
To valuate material stocks
c ✘ To update the standard price during the release of a standard cost estimate

70 You want to set up budget availability control for your projects and internal order

There are 2 correct answers to this question.

The availability of funds on period level


The availability of funds using overall plan value
c ✘ The availability of funds according to tolerance limits
c ✘ The availability of funds in object currency

71 What can you manage via the account assignment category?

There are 2 correct answers to this question.

c ✘ Valuated sales order stock


Separate sales order stock
Costing variant
c ✘ Product cost by sales order

72 Which attributes can you configure in the activity type master record?

There are 3 correct answers to this question.

Company code
c ✘ Price indicator

c ✘ Valid cost center categories


c ✘ Activity type category
CO version

73 Which parameters are controlled by the costing type in a costing variant?

There are 2 correct answers to this question.

c ✘ Save with date key


c ✘ Price updates
Price for materials
Costing sheet

74 In the Product Cost by Order component, what does the system calculate depend

Please choose the correct answer.

Both WIP and variances or only variances


WIP at target costs or variances
WIP at planned costs or variances
c ✘ WIP at actual costs or variances

75 You want to create alternative plan versions for your controlling area, in addition

There are 2 correct answers to this question.

c ✘ To store parallel valuation


To store different plan data
c ✘ To store actual-plan variance
To store different budget data


76 How does SAP S/4HANA select line-item-based data for costing-based Profitabilit

Please choose the correct answer.

It selects actual data from table ACDOCA and plan data from table COSP.
It selects actual data from table CE2XXXX and plan data from table CE3XXX
c ✘ It selects actual data from table CE1XXXX and plan data from table CE2XXX
It selects actual data from table ACDOCA and plan data from table ACDOCP
77 At which level do you define the valuation method for results analysis?

Please choose the correct answer.

Company code
Sales organization
Operating concern
c ✘ Controlling area

78 In which module do you process profit center allocations in SAP S/4HANA?

Please choose the correct answer.

General Ledger Accounting


Product Cost Accounting
c ✘ Profit Center Accounting
Cost Center Accounting

79 Which objects can you plan in cost center accounting?

There are 3 correct answers for this question.

c ✘ Secondary cost accounts


c ✘ Non-operating expense accounts
c ✘ Statistical key figures
Balance sheet accounts
Activity prices

80 How can you configure cycles for period-end allocation?

There are 2 correct answers for this question.

Create cycles that iterate with each other


Use different allocation rules within one segment
c ✘ Define allocation for the same cost center in multiple segments
c ✘ Assign several segments to a cycle


81 You post a billing document in Sales and Distribution (SD). What data flows to Pr

There are 3 correct answers to this question.

c ✘ Payment discount
Accruals
Order quantity
c ✘ Revenues
c ✘ Sales deductions

82 What are some of the objectives of Profitability Analysis?

There are 2 correct answers to this question.

c ✘ Provide the company with information on the performance of its market seg
Provide the company with a detailed view of its financial statements by resp
c ✘ Allow the company to determine if the sales force achieved their contributio
Allow the company to determine standard costs and revenues according to

You have implemented Product Cost by Sales Order in conjunction with revenue
83 order item, you have the following:

- Plan revenue = 3000

- Plan costs = 2000

- Actual revenue = 1200

- Actual costs = 1000

What data does the system calculate during results analysis?

Please choose the correct answer.

Revenue = 1200; Cost of sales = 800; Reserve = 200


Revenue = 1200; Cost of sales = 1000; Reserve = 200
c ✘ Revenue = 1200; Cost of sales = 800; WIP = 200
Revenue = 1200; Cost of sales = 1000; WIP = 200

84 You are executing an indirect activity allocation. What do you post to the sender

Please choose the correct answer.


c ✘ You post quantity and cost to both the sender and receiver.
You post both quantity and cost to the receiver, and cost only to the sender
You post both quantity and cost to the sender, and cost only to the receiver
You post cost only to both the sender and receiver.

You perform a settlement with a primary cost account which is different from the
85 is a valid receiver for the settlement?

Please choose the correct answer.

WBS element
Internal order
Cost center
c ✘ Fixed asset

You have activated budget availability control for an internal order and entered
86 internal order in the current year.

How is that possible?

There are 2 correct answers to this question.

The cost element is exempted from budget availability control


c ✘ The purchase order was entered in a different year than the budget.
c ✘ The purchase order has NOT generated a budget document yet.
The difference of 1000 is within the tolerance limits defined in the configura

87 You are creating new activity type and want to maintain plan prices for a cost cen

There are 3 correct answers to this question.

c ✘ Price indicator
c ✘ Valid cost center categories
c ✘ Activity type category
CO Version
Company code

88 What are some of the characteristics of planning for internal orders?

There are 2 correct answers to this question.


Availability control can check against plan values.
c ✘ You can plan multiple versions.
c ✘ You can enter costs and revenues.
You can define tolerance limits for plan overspend.

101 What business structure is used to manage earnings from foreign markets?

c CO-PA profitability analysis


Company Code
Segment
Benefits Center

102 Which of the following describes the purpose of CO

Capital detail analysis


c Operating profit and expense report
External statutory reports

103 What technical characteristics of SAP allows changing the technical configuration of one clie

c transportation
organizational structure
configuration

104 What is the upper level of CO

c ✘ PA

105 In a SAP S/4 System, what configurations must be consistent to connect the Companies to a
c ✘ Fiscal Year
Company Code Currency
c ✘ Operating Chart of Accounts
c ✘ Special periods of the fiscal year

106 Which of the following options controls the version of the Control Society
c ✘ Ability to send plan data to other processes
Ability to plan balance
c ✘ Ability to publish real data
Ability to plan all cost centers
c ✘ Ability to calculate the price

107 Which of the Organizational Structures is directly connected with the Company CO

Commercial area
Plant, Purchasing
Organization
c ✘ Company code

108 When defining a controlling area, you must choose which of the following options

c ✘ Cross company code setup


Standard hierarchy of profit centers
c ✘ Control Zone Currency
c ✘ Standard hierarchy of cost centers

109 Which of the following components can be activated in a CO Company

Benefits Center
C ✘ Commitments
Production Order
Coins
C ✘ Cost centers

110 What key characteristics are activated in an Operating Company

c ✘ PA Company Currency
Area Control
c ✘ CO-PA based on costs
Company Code

111 The first step to activate the SAP System is to define what?
c ✘ Organizational Units
transactional data
ABAP programs
Master data

https://en.daypo.com/practice-2-1.html#test
t cost collector?

reporting?

AP Fiori content.

AP S/4HANA.

Services (CDS) views?

g should be considered in a product cost calculation. How do you do this?

e operation

he operation
signed to the operation

planning?
ring period-end closing?

nalysis to allocate cost center costs during period-end closing for your organization.

le to your internal order type. What do you use the status profile for?

evenue to the value fields in costing-based CO-PA?


al orders. What do you need to do?

the order type.

ter record.

at can you determine for each cost component?

for overheads in costing sheet


nalysis reports?

d hierarchy?

to represent decision control and responsibility units.


A where the costs and revenues are incurred and reported.
milar cost centers within a controlling area.
a controlling area are assigned.
costing-based Profitability Analysis?

s within the costing run tool?

value is valid in Profitability Analysis?

f the settlement rule to a market segment for a sales order item?


od and you entered a results analysis key and variance key. How does the system calculate

-based CO-PA in SAP S/4HANA?

o implement the transfer price solution in SAP S/4HANA?

to facilitate intercompany reconciliation.


ant with different accounting principles.
are needed to differentiate between legal and profit center valuation.
arate costs of goods manufactured for different accounting principles.

ent cycle in Controlling?

ing concern?

st component split to ensure the transfer of costing to costing-based CO-PA?

signment to your material cost estimate. What do you need to do?

the material
l cost estimate and the costing run
material master record
emplate determination table
lates for activity-based costing?

company. Which setting in the cost center master data will you use to assign the same

tomatic account assignment in SAP S/4HANA?

counts of secondary costs type.

counts of primary costs type. primary cost

or the work in process (WIP) settlement?

ent splits?
ants of a controlling area
trolling areas

cs can be added to an operating concern?

e budget and availability control?


ct Cost by Order?

tion time.

n lots or discrete quantities is needed.

closing in overhead cost accounting, which object can you assign to the cycle segment?

m the material master data?

nts class -> requirements type


y -> requirements type

-> requirements type

nternal orders?
ounting method in profitability management?

n stock, WIP, and capitalized activities.


a format that is ideal for conducting margin analyses.
against sales-related expenses.
ge for a given organizational unit over a period of time.

es order item level. What do you need to check in the configuration?

ccounting in SAP S/4HANA?

egment in configuration.

accounts.
eating them as cost elements.
ements, and NOT as general ledger accounts.
al ledger accounts.
ost centers. With which object do you differentiate the planning scenarios?

results analysis?

run analytical reports off a single data model. Which statement best describes reporting in SAP S/4HANA?

s, or speedy and simple, but not both.


plex to design.
ess warehouse system.
level of detail.

k in progress (WIP)?

ct Cost by Period?
ble and continuous production process.

ual costs.

AP S/4HANA?

er for each valuation.

AP S/4HANA embedded analytics?

s the same technical stack and user interface.


rtual data models (VDMs) for reporting.
yond the capabilities of Strategic Analytics Tools for reporting.
stack that uses virtual data models for reporting.

d on the quantity structure of the existing standard cost estimate. Which object do you use?

ng product costing. How do you assign the template to your material?


ile of a product cost collector?

extension ledger. You post a general journal entry without indicating a ledger group.

he universal journal?

item in the universal journal using SAP S/4HANA standard configuration. What requirements must be fulfi

unt must be primary cost/revenue or secondary cost.


unt must be balance sheet.

em perform results analysis?


centage of Completion (POC) method?

Period. What do you need to configure?

conjunction with cost-based POC results analysis in your organization. For a particular sales

d revenue (revenue in excess of billings) = 200


urplus = 300
urplus = 200
d revenue (revenue in excess of billings) = 300

to update the standard price of the material?


sting run?
prices. What do you use them for?

a standard cost estimate

projects and internal orders. What can you check using budget availability control?

master record?
n a costing variant?

e system calculate depending on the order status?

ontrolling area, in addition to version "0". What would you use additional CO versions for?

or costing-based Profitability Analysis reports?

data from table COSP.


n data from table CE3XXXX.
n data from table CE2XXXX.
data from table ACDOCP.
results analysis?

ns in SAP S/4HANA?

ple segments
SD). What data flows to Profit Center Accounting?

rmance of its market segments.


ancial statements by responsibility units.
achieved their contribution margin goals.
d revenues according to the period accounting method.

conjunction with revenue-based results analysis in your organization. For a particular sales

do you post to the sender and receiver?


receiver.
d cost only to the sender.
cost only to the receiver.

which is different from the cost account you used to post the original expense. Which object

nternal order and entered an overall budget of 10000. Actuals of 10000 were posted for this

ility control
than the budget.
ocument yet.
s defined in the configuration.

in plan prices for a cost center. Which attribute must you configure in the activity type master record?

ternal orders?
eign markets? 1

hnical configuration of one client to another 1

o connect the Companies to a CO Company in an n:1 environment 3

ntrol Society 3
with the Company CO 1

he following options 3

1
ting in SAP S/4HANA?
irements must be fulfilled?
pe master record?