Professional Documents
Culture Documents
An Illustration of The Two-Stage Process For A Traditional Costing System
An Illustration of The Two-Stage Process For A Traditional Costing System
Applying the two-stage allocation process requires the following four steps:
Using the information given in Example 4.1 our initial objective is to assign all
manufacturing overheads to production and service cost entries. This require the
preparation of an overhead analysis sheet, which is shown in Exhibit 4.1.
If you look at Example 4.1 you will see that the indirect labour and indirect
material costs have been directly traced to cost centres.
The remaining costs in Example 4.1 cannot be traced directly to the cost centres
and must be allocated to the cost centre using appropriate allocation bases.
The term ‘first-stage allocation bases’ is used to describe allocations at this point.
The following list summarizes commonly used first stage allocation bases:
Step 2- Reallocating the costs assigned to service cost centres to production cost
centres
The next step is to reallocate the costs that have been assigned to service cost
centres to production cost centre.
Service department, sometimes called support department (i.e. service cost
centres) are the departments that exist to provide services of various kinds to
other units within organization.
The enterprise company has two services centres. They are materials procurement
and general factory support.
50% of the value of materials is issued to machine centre X, resulting in 50% of
the total costs of materials procurement being allocated to this centre
Step 3- Computing separate overhead rates for each production cost centre
The calculations (i.e. step 3) using the information given in Exhibit 4.1 are as follows:
Machine centre X= 4 300 000 / 2 000 000 machine hours = ₤2.15 per machine hour
Machine centre Y= 3 800 000 / 1 000 000 machine hours = ₤3.80 per machine hour
Assembly department = 3 600 000/2 000 000 direct labour hours =₤1.80 per direct labour hour
Step 4- Assigning cost centre overhead to products or other chosen cost object
The final step is to allocate the overheads to products passing through the
production centres.
If a product spends ten hours in machine cost centre A., overheads of ₤21.50 (10
x ₤2.15) will be allocated to the product.
Product A ₤
Direct costs (100 units X ₤100) 10 000
Overhead allocations
Machine centre A (100 units x 5 machine hours x ₤2.15) 1 075
Machine centre B (100 units x 10 machine hours x ₤3.80) 3 800
Assembly (100 units x 10 direct labour hours x ₤1.80) 1 800
Total cost 16 675
Cost per unit (₤16675/100 units)= ₤166.75
Product B ₤
Direct costs (200 units X ₤200) 40 000
Overhead allocations
Machine centre A (200 units x 10 machine hours x ₤2.15) 4 300
Machine centre B (200 units x 10 machine hours x ₤3.80) 15 200
Assembly (200 units x 20 direct labour hours x ₤1.80) 7 200
Total cost 66 700
Cost per unit (₤66700/200 units)= ₤333.50
For decision making, non-manufacturing costs should also be taken into account.
In addition some of the costs that have been assigned to the products may not be
relevant for certain decisions.
For example, if you look at the overhead analysis sheet in Exhibit 4.1 you will
see that property taxes, depreciation of machinery and insurance of buildings and
machinery have been assigned to cost centres, and thus included in the costs
assigned to products. If these costs are unaffected by a decision to discontinue a
product they should not be assigned to products when undertaking product
discontinue reviews.
If cost information is used to determine selling prices these costs may need to be
assigned to products.
The actual overheads for an accounting period have been allocated to the
products. However, the use of actual figures can be problematic.
Information on product costs is required more quickly if it is to used for monthly
profit calculations and inventory valuations or as a basis for setting selling prices.
Consider Example 4.2. the monthly overhead rates of ₤2 and ₤5 per hour are not
represent of typical, normal production conditions.
Example 4.2
The fixed overheads for the Euro Company are ₤24 million per annul, and
monthly production varies from 400 000 to 1 000 000 direct labour hours. The
monthly overhead rate for fixed overheads will therefore fluctuate as follow:
NON-MANUFACTURING OVERHEADS
Example 4.3
The same basic cost assignment procedures that are used by manufacturing
organizations can be applied were there is a need to track the cost of the service
provided to each individual customer. Where a job-order costing system is
inappropriate, cost information is required for profitability analysis by products,
services, departments, etc. Organizations may choose to assign only direct cost to
cost objects using a direct costing system.
Alternatively, they may also use only the first stage of two-stage overhead
allocation procedure to assign indirect costs to departments that are synonymous
with the products/services that are sold by the organization.