06

C1 FB1
C2
FB3
FB2
FB2
FB1 C3 FB2 C4 FB2

C5
FB2
FB2
FB3
FB1

FB1 C7
FB1 BEAM AT FLOOR LEVEL
C6
MB1
MIDLANDING SLAB

FB2
MB BEAM AT MIDLANDING
LEVEL / HIDDEN BEAM
FB2
C8
C9 FB1 C10 MB1

FB1 FB1
FB1
GENERAL NOTE

1). LAPPING OF BEAM MUST BE


DONE AT BEAM-COLUMN JUNTION.
OR UPTO L/4 FROM FACE OF COLUMN
2). LAP LENGTH = 50D
3). DEVELOPMENT LENGTH = 45d
4). CONCRETE COVER = 25 mm
5). GRADE OF CONCRETE = M25
C11 FB1 C12 FB1 C13 6). GRADE OF STEEL = FE500.

TOP EXTRA BAR AT MIDDLE SUPPORT

TOP EXTRA BAR AT END SUPPORT


TOP MAIN BAR
STIRRUPS
TOP MAIN BAR

0.25L1 0.3L1 0.3L1 CANTILEVER BEAM BAR

TOP EXTRA BAR AT END SUPPORT


1.5L3
Ld

Ld BOTTOM CURTAIL BAR BOTTOM CURTAIL BAR


0.15L1 0.15L1 0.15L2 0.15L2 STIRRUPS
L1 L2 L3
COLUMN COLUMN COLUMN
BOTTOM MAIN BAR
BOTTOM MAIN BAR

TYPICAL BEAM DETAIL


SCHEDULE OF FLOOR BEAM
BEAM BEAM SIZE BOTTOM REINFORCEMENT TOP REINFORCEMENT
NO FULL LENGTH CURTAILED FULL LENGTH EXTRA TOP STIRRUPS REMARKS
BxD
STR.BARS BARS STR.BARS AT SUPPORT
FB1 9" x 15" 2 - TOR 12 1 - TOR 12 2 - TOR 12 1 - TOR 12 2 legged 8 mm @ 6" c/c FLOOR BEAM

FB2 9" x 15" 2 - TOR 12 1 - TOR 12 2 - TOR 12 2 - TOR 12 2 legged 8 mm @ 6" c/c FLOOR BEAM

FB3 6" x 15" 2 - TOR 12 1 - TOR 12 2 - TOR 12 1 - TOR 12 2 legged 8 mm @ 6" c/c FLOOR BEAM
MID LANDING
MB 9" x 15" 2 - TOR 12 1 - TOR 12 2 - TOR 12 1 - TOR 12 2 legged 8 mm @ 6" c/c BEAM
MID LANDING BEAM
MB1 9" x 6" 2 - TOR 12 ---- 2 - TOR 12 ---- 2 legged 8 mm @ 6" c/c / HIDDEN BEAM

RCC DESIGN BY- PROJECT : - RESIDENTIAL BANGLOW


ER.AKSHAY LAWARE E
CLIENT : - MR. VIKAS GORDE WL Consultants
(STRUCTURAL CONSULTANT)
AT. KELWAD . Architect & Engineer's
TITTLE :-
N S C:\Users\hp\Desktop\IMG-20210307-WA0006.jpg

Address- Karmavir nagar, Rahata


JOB NO. DWG NO. DATE DRAWN BY SIGN Mail - wlconsultant@gamil.com
FLOOR BEAM STEEL DETAIL W
Contact - 7218931284 / 9404289396.
22/10/2021 ER.RAHUL WAGHE.