Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Risk Assessment as per DEFL Pure & Residual Matrices & Pipeline Works Risk Assessment v1.

Pipeline Works Risk Assessment v1. DOCUMENT NUMBER: DEFL-HSEQ-


with respect to AS/NZS ISO 31000 20220310
REVISION NO.: 3
Design Engineering (Fiji) Pte Limited
HSEQ MANAGEMENT SYSTEM
DOCUMENT NAME: RISK ASSESSMENT FORM
DOCUMENT NUMBER: DEFL-HSEQ-20220310 PAGE NUMBER: 1 OF 1
REVISION NO.: 3 DATE OF REVIEW: 24/03/2022

Project & subject of risk assessment: Under Wharf Suspended Pipeline Installation

No. of persons
Action or controls adopted or in place at the specific site to control or reduce risks. Hierarchy

Effectiveness
Final

of Control, C
Control No. 5 (as PPE) is applicable to all mitigation measures as is mandatory to Terminal entry.

Eval'n with
Likelihood

R1=R0 x C
Eval'n w/o
Source of hazard / danger (Hazard scenario) Risk Further controls or actions required (include

R0= P x S

controls:
No. Hazard parameter Other controls as header may be indicated in the cells below, i.e., in order of preference [1]

Controls
per shift

Severity
(Properly describe a possible scenario) Rating action party and close out date)
Elimination; [2] Substitution; [3] Engineering (including isolation), [4] Administrative, & [5] Personal
(A/B/C)
Protective Equipment.

(P)

(S)
1. Not using the proper means of transportation 1. Ensuring the use of most appropriate form of transport for a particular load 1. Full-time supervision by TOTAL &
for the long and heavy pipes 2. Considering how best to protect large, heavy, or unusual loads. Contractorpersonnel.
2. Cases where the heavy load are not securely 3. Ensure loads are secure and weight is distributed evenly - this is essential, even if you're just 2. Continuous reminder is required.
fastened carrying a ladder on the roof of a vehicle. 3. Consistent follow-up required.
3.Weights are not evenly distributed 4. Consider whether you need goods-in-transit or marine insurance to protect goods being 4. All entities must participate well.
4.Traffic may be a problem due to lack of time transported. This may be paid for by the buyer or seller of goods, depending on the terms of trade
management resulting in the project not starting you agree.
on time for that day 5. Always take appropriate security measures. For example, for high-value goods you could consider
5. Load is securely fastened but the belt is not using a vehicle-tracking system.
suitable for the load 6. Make sure suitable packaging, labeling and containers are used. It's common for goods to be
6. Ignoring the use of warning signs when damaged in transit and good protection and effective packaging will help reduce this risk.
transporting 7. Using 3x supports which can cater for the pipes. The pipes are to be supported at 3 positions 2 at
7. Not using the assigned pallets or supports its end and one at the middle.
which can fit in pipes to prevent sliding 8. Put suitable warning signs on vehicles - for example, to indicate an overhanging, wide, long,
8. Wrong cutting positions for bracket insertions orhazardous load.
9. Utilities and services falling in path of work 9. Certified/ tested and load rated belts to be used for fastening purposes.
10. Disobedience of instructions 10. Ensure work is actioned as per approved details only which is done after extensive on-site
BREAKDOWN 11. Working on pontoon assessments
(COMPLETION TIMELINE 12. Working during curfew period (Non 11.Supervisor to be strict and stringent with workers in the team
1 RISK)/ DAMAGE TO 3rd arrangement for key personnel for work 4 3 2 6 12. Materials/Tools/Equipment to always be secured to avoid any loss (falling into ocean) 2 12 C
PARTY/ MATERIAL LOSS progression) 13. Communication and arrangements to be made with FPCL, and other key personnel for the
AND DAMAGE 13. Arrests during curfew availability outside business hours.
14. Tanker and bunker operations 14. Curfew pass approval to be prepared for all personnel working during curfew
15. Covid cases at the ports 15. Communication of tanker and bunker to be checked with FPCL/FPTL before work mobilization
16. Unforeseen scenarios and obstructions 16. Strict adherence to protocols by FPCL/FPTL for working on the wharf during a suspected COVID
17. Material shortage for pipeline, fittings, case with regards to PPE
valves,or bracket 17. No further action to be taken unless FPCL authorizes continuation with a detailed analysis of the
18. Defective, damaged, and situation prior to further engagement
unavailableequipment 18. All material BOQ to be updated after tasks are completed where materials are utilized
19. Unstable design mechanisms for working 19. All equipment to be tested and tagged before being used on site. Materials with a SOP for use
aids must be followed for example gensets.
20. Key personnel engaged elsewhere outside of 20. All designs to be first tested with designed loads before field implementation
the wharf 21. Appointments to be communicated in advance for works involving personnel for the task
21. Quality of work 22. Ensure that all work is done to the best of quality to avoid rework, and to be verified by field
representatives from the engineer to the contract, TFPL and AEFL supervisors.

No further controls required.


CAUGHT IN MECHANICAL 1. Caught during grinding/ cutting/ drilling
2 12 1 1 1 1. Ensure long sleeve shirts are fastened properly when doing any grinding/ cutting operation. 1 1 C
EQUIPMENT operation due to lose long sleeve shirts

1. Caught in dark work section. 1. Ensure hard hats with flashlights are worn No further controls required.
2. Caught between beams 2. Allow an effective work duration plan taking into consideration the tide levels.
3 CAUGHT UNDER WHARF 3. High tide times. 5 3 1 3 3. Adequate planning with hired boat service providers for worker movement outside normal 1 3 C
4. Confined space works during rising tides business operation hours
1. High boat speed resulting in losing control 1. Experience personnel to be operating the boat. No further controls required.
2. Third party losing control and colliding with 2. Use paddles whenever possible. [minimize use of engine]
4 BOAT COLLISION boat or pontoon. 5 1 2 2 3. Wear reflective vests so third-party personnel are aware of presence. 2 4 C

Page 1 of 7 19/04/21 5:28 PM


Risk Assessment as per DEFL Pure & Residual Matrices & Pipeline Works Risk Assessment v1. DOCUMENT NUMBER: DEFL-HSEQ-
with respect to AS/NZS ISO 31000 20220310
REVISION NO.: 3

1. Foreign tasks involved not identified for 1. Full-time supervision by TOTAL &
example fuel discharge, x-ray of containers, Contractorpersonnel.
1. Daily information to be exchanged between contractor and FPCL/FPTL regarding bunker and 2. Continuous reminder is required.
fumigation, biosecurity breaches
discharge operations at the wharf 3. Consistent follow-up required.
2.Traffic queues of container and forklifts due to
2. Any operational activity which may hinder project work to be informed to the contractor. 4. All entities must participate well.
CONFLICTING ACTIVITIES ongoing work by contractors
3. Information to be sent to key FPCL/FPTL personnel on time before the working day
5 WITHIN FPTL/FPCL 3. Delay of personnel on site N/A 2 1 2 1 2 C
4. Arrangements to be made for special provisional access outside normal working hours for wharf
OPERATIONS 4. Delay in submission of documents
access.
5. Working during curfew period
5. Work in designated areas only with proper barricading, signages and traffic control management.
6. Planned disruptions (fire drills and evacuation
All works which can be done offsite to be actioned accordingly, and not done on site.
drills)
7. Working in undesignated areas.
1. Electrocution through standing on wet surface 1. Ensure cord wires and power tools are thoroughly checked and certified for operation prior to use 1. Full-time supervision by TOTAL &
by faulty power tools and wires. on site. Contractorpersonnel.
2. Naked and damaged cord wires for operation. 2. Compulsory use system of circuit breakers. 2. All entities must participate well.
3. Faulty power tools. 3. Ensure rubber soled shoes are worn.
CONTACT WITH 4. Power tools being in contact with water and 4. Always keep power tools in a separate box so that contact with water is kept to a minimum.
6 5 3 3 9 2 18 B
ELECTRICITY operational without prior knowledge.
5. Damage done to existing cables

1. Contact/ inhaling dust during wheat 1. Keep working during discharge times at a minimum. 1. Full-time supervision by TOTAL &
discharging operation. 2. Have a brief idea on the discharging operation timetable. Liaise with FPCL to get their Contractorpersonnel.
2. Contact/ inhaling cement dust during operational activities. 2. All entities must participate well.
discharging operation. 3. Wear appropriate PPE including long sleeve shirt and trousers.
3. Contact/inhaling fumigation fumes sprayed on 4. Use dust mask during work times
containers 5. Use gas mask whenever doing welding operations in closed environments (high chance of
CONTACT WITH
7 4. Welding fumes in confined areas under wharf. 5 5 2 10 gas entrapment) 2 20 B
HAZARDOUS SUBSTANCE
5. Contact with fumes and flames during grinding 6. Deployed forced ventilation using fans
and cutting operation
6.Inhalation of vapor when refueling IC engine
operated equipment with petroleum

1. Direct sunlight reflection from water to the eye, 1. Plan daily work according to the activities at the wharf. Tentative planning and arrangement 1. Full-time supervision by TOTAL &
resulting in temporary blindness. should be made one day prior. Allowance to be made if works are to cancel, where will the work then Contractorpersonnel.
2. Motion sickness affects the balancing eventuate. 2. All entities must participate well.
mechanism in the ears due to prolong exposure 2. Wear hearing aid in under any work sections where noise is a major factor.
to noise. 3. Be familiar with the normal operating conditions of the workplace.
3. High blood pressure and fatigue. 4. Use of new power tools which are smooth running.
4. Less effective communication means. 5. Taking breaks when doing drilling operations.
5. Vibration from power tools resulting in numbing 6. Minimize drilling at places where unstable concrete abutments are present.
of hands and at the same time fall of unstable 7. Ensure that the ports operational activities are adhered to daily. This reduces communication
CONTACT WITH nearby concrete sections. breakdowns and possible hindrances which may arise between its operations.
8 RADIATION, NOISE AND 6. Fatigue which leads to general reduced 5 3 1 3 8. Ensure the ports and terminal staffs are aware of the work being carried out by the project 1 3 C
VIBRATION efficiency. team.
7. Vibration from heavy operational activities at 9. Utilize equipment’s with dampeners to reduced vibration
ports vicinity can cause damages to unstable 10. Take rests between certain periods and check on nearby surroundings for any
concrete structures present overhead. conspicuouschanges that might have occurred during operations of work.
8. X-ray scanning of containers on wharf deck 11. Utilize walkie-talkies or cellular devices
9. Communication by shouting

1. Not wearing a functional life safety vest. 1. Working with a partner or team. At least 2 people need to be always in sight with each other. 1. Full-time supervision by TOTAL &
2. Not having knowledge on the use of life safety Nobody is to work alone at any time. Contractorpersonnel.
vest. 2. Waterproof communication devices. 2. All entities must participate well.
3. Risk of falling into water – effect of trips and 3. Wearing functional life jackets.
slips. 4. Having good knowledge on the use of life jackets, in dangerous scenarios.
4. Contact with contaminated water or fumes 5. Suitable footwear may be required to reduce the risk of slipping.
5. Heat stress. 6. Guard rails to prevent falling into water are required.
6. Impact with near floating or partially 7. Working when tides are stable.
9 DROWNING 5 2 3 6 1 6 C
submerged objects when into water. 8. Use boats that are seaworthy
7. Rough tides. 9. Notify of under wharf works to FPCL to advise boats moving in harbor not to create large wakes
8. Boat having damages that will cause instability
and possibly sinking
9. Large wake generation from boats moving in
the harbor

Page 2 of 7 19/04/21 5:28 PM


Risk Assessment as per DEFL Pure & Residual Matrices & Pipeline Works Risk Assessment v1. DOCUMENT NUMBER: DEFL-HSEQ-
with respect to AS/NZS ISO 31000 20220310
REVISION NO.: 3
1. Even though welding generally uses low 1. All workers who may enter dangerous areas, either on a regular basis or in an emergency, 1. Full-time supervision by TOTAL &
voltage, there is still a danger of electric shock. should be trained on rescue procedures, personal protective equipment, use of safety Contractorpersonnel.
The environmental conditions of the welder (such equipment, and proper procedures for entering and exiting a confined space: 2. All entities must participate well.
as wet or cramped spaces) may make the 2. The worker inside the confined space should be equipped with a safety harness, a lifeline, and
likelihood of a shock greater. appropriate personal protective clothing, including a self-contained breathing apparatus.
2. The intense heat and sparks produced by 3. Gas cylinders and welding power sources should be in a secure position outside of the
welding, or the welding flame, can cause fires or confined space.
ELECTRICAL HAZARDS
10 explosions if combustible or flammable materials 12 3 2 6 4. A trained helper must be stationed outside of the confined space and equipped with appropriate 2 12 C
FOR WELDING
are nearby. gear (including a fire extinguisher and personal protective equipment), to assist or rescue the worker
inside the confined space if necessary.
5. If the standby person notices any indications of intoxication or decreased alertness from the
“inside” worker, the inside worker should be removed from the area immediately.

1.Failure of airline connection, 1. Compressor to be positioned in an open area or have exhaust fume discharged to open air. 1. Full-time supervision by TOTAL &
2. Tripping over arising’s 2. Where available – vibration suppressing breakers to be selected and used. Contractorpersonnel.
3. Air supply hoses to have a connector restraint fitted and maintained. 2. All entities must participate well.
ELECTROCUTION/ELECTRI 4. Electric conductors to be sited along protected routes or suspended from a secure point
C SHOCK, HOSE ‘WHIP’, 5. Prolonged breaking-out operations to be limited to 2-hour cycles
11 TRIPPING, HEARING 12 3 4 12 6. Work equipment may be operated only by trained, authorized people 1 12 B
DAMAGE, WHOLE BODY 7. Issue PPE – eye protection, hearing protection, respirator, safety footwear,
VIBRATION, vibration-suppressing gloves, safety helmet, overalls
8. Safety instructions to be explained to workers by means of toolbox talks.

1. Full-time supervision by TOTAL &


1. Trip by manual and power tools. 1. Wearing good grip shoes. Contractorpersonnel.
2. Trip by cord wires 2. Ensure work surface is dry and that there is minimum contact with water 2. All entities must participate well.
3 Slippery boat surfaces 3. All power/ manual tools and cord wires are to be properly and systematically kept.
4. Slippery pontoon surface. 4. Avoid working in conditions when waves are rough.
FALL ON SAME LEVEL 5. Unstable boat or pontoon position which can 5. Keep appropriate manpower so that stability of working platform is acceptable.
12 12 2 2 4 1 4 C
[SLIP & TRIP] be due to rough waves and or improper team 6. Proper team coordination is to be done when moving on working platform.
coordination resulting in unbalancing of pontoon 7. Do not overload the boat and or pontoon
and or boat. 8. Ensure guard rails are installed on the pontoon
6. Rough tides 9. Avoid working during rough tide sessions.
7. Large wakes generated by boats in harbor 10. Notify of under wharf works to FPCL to advise boats moving in harbor not to create large wakes

1. Full-time supervision by TOTAL &


Contractorpersonnel.
1. Preventative checks and certification of all power tools and welding plant before use on site.
1. Fire and or explosion due to faulty power tools 2. All entities must participate well.
2. Avoid power tools and welding plant meeting water.
or welding plant.
3. Stop work if any major accidents are reported within the premises and evacuate the work area.
2. Use of Concrete cutter, grinder would generate
4. Have an evacuation plan in place?
sparks encouraging chance of fires in presence
5. Provision of gas meters and monitoring all warnings on site for quick response in case of
of flammable gases/ vapor.
emergencies
13 FIRE / EXPLOSION 3. Fire and or explosion due to faulty boat engine. 12 2 2 4 1 4 C
6. Preventative checks on boat engine before use on site by a trained boat operator
4. Boat collision due to lost control.
7. Keep boat speed at a minimum when mobilizing on site
5. Accident within the FPCL premises.
8. Stop work if any major accidents are reported within the FPCL premises and evacuate the work
6. Placement/movement of poorly contained
area.
dangerous goods (explosive) is near the work
9. Effective communication with the FPCL engineering department personnel.
area proximity
10. Proper site assessment before and periodically during works

Page 3 of 7 19/04/21 5:28 PM


Risk Assessment as per DEFL Pure & Residual Matrices & Pipeline Works Risk Assessment v1. DOCUMENT NUMBER: DEFL-HSEQ-
with respect to AS/NZS ISO 31000 20220310
REVISION NO.: 3
1. The intense heat of welding and sparks can 1. A fire inspection should be performed before leaving the work area and for at least 30 minutes 1. Full-time supervision by TOTAL &
cause burns. Eye injuries can result from contact after the operation is completed. Fires extinguishers should be nearby. Contractorpersonnel.
with hot slag, metal chips, sparks, and hot 2. To prevent trips and falls, keep welding areas clear of equipment, machines, cables, and 2. All entities must participate well.
electrodes. In addition, excessive exposure to hoses, and use safety lines or rails.
heat can result in heat stress or heat stroke. 3. Adequate ventilation is essential for working in confined spaces.
2. Visible Light, and Ultraviolet and Infrared
Radiation
The intense light associated with arc welding can
cause damage to the retina of the eye, while
infrared radiation may damage the cornea and
result in the formation of cataracts. Invisible
HEAT GENERATED FROM ultraviolet light (UV) from the arc can cause “arc
14 12 3 2 6 2 12 C
WEDING eye” or “welder’s flash” after even a brief
exposure (less than one minute).
3. The arc can reflect off surrounding materials
and burn co-workers who work nearby.
4. Exposure to ultraviolet light can also cause
skin burns like sunburn and increase the
welder’s risk of skin cancer.

Generally, welding fumes and gases come from: 1. Arc welding should never be performed within 200 feet of degreasing equipment or solvents. 1. Full-time supervision by TOTAL &
1. The base material being welded or the filler 2. Dry gloves should always be worn to protect against electric shock. Contractorpersonnel.
material that is used 3. The welder should also wear rubber-soled shoes and use an insulating layer, such as a dry board 2. All entities must participate well.
2. Coatings and paints on the metal being or a rubber mat, for protection on surfaces that can conduct electricity.
welded, or coatings covering the electrode 4. The piece being welded and the frames of all electrically powered machines must be grounded.
3. Shielding gases supplied from cylinders 5. The insulation on electrode holders and electrical cables should be kept dry and in good condition.
4. Chemical reactions which result by the action Electrodes should not be changed with bare hands, with wet gloves, or when standing on wet floors
of ultraviolet light from the arc and heat or grounded surfaces.
5. Process and consumables used 6. Welding or cutting should be performed only in areas that are free of combustible materials,
6. Contaminants in the air, for example vapors including trash, wood, paper, textiles, plastics, chemicals and flammable dusts, liquids.
from cleaners and degreasers 7. Use continuous mechanical ventilation and a respirator whenever you weld or perform thermal
GASES AND FUMES FROM cutting in a confined space
15 12 3 2 6 2 12 C
WELDING OPERATIONS 8. All pipes, ducts, and power lines connected to the space, but not necessary to the operation,
should be disconnected or shut off. All shutoff valves and switches should be tagged and locked out
so they cannot be restarted accidently.
9. Observe the welding area to ascertain whether there are sources of heat, naked flames,
flammable liquids, or combustible materials in the vicinity.
10. If conditions are hot and humid, an assessment should take account of how long welding is to be
carried out and when breaks may be taken.

1. Sustaining body injuries while 1. Incorporate traffic control (flags man) where necessary 1. Full-time supervision by TOTAL &
barricading/coning off work area inside/outside 2. Profound teamwork and communication Contractorpersonnel.
terminal 3. Ensure proper lifting procedures are adhered 2. All entities must participate well.
2. Caught up/near miss incident with active 4.Everyone to be vigilant and responsible for fellow college while barricading near road/traffic
traffic/turning vehicles 5. Ensure there is enough water breaks and resting times implemented by team leader or supervisor
3. Extremely sunny weather 6. Proper PPE is worn by all workers at work site based on work being done e.g., welding
4. Continuous work operations by workers gloves,lifting harness, face shields, tinted eyewear, ear plugs
5. Heavy movements manually using hands 7. Workers to always be attentive to work under strict supervision
6. Hot surface from welding/grinding 8. Proper lighting setup of worksite (floodlight), torches and helmet lights
7. Sharp edges 9. Barricade work sites to notify unnecessary movement is restricted
8. Low visibility of light under the wharf 10. Supervisor or team leader to be always stringent with workers to ensure full attention is with
NEAR MISS/ BODY 9. Other workers and public personnel movement work and not elsewhere
16 beneath wharf 12 1 1 1 11. Proper safety cages for hydrotest equipment are in place 1 1 C
INJURIES
10. Distractions to workers 12. Thermal relief valve is used
11. Destructive and non-destructive tests 13. Calibrated pressure gauges are utilized for the pressure test
(hydrotests, MPT, UT and RT) 14. Licensed fitter to perform pressure test
12. Vibratory equipment 15. Hydrotest to be planned for cold weather days
13. Dust/chip generation from cutting activities 16. All radioactive testing to be communicated to FPCL
17. Adequate resting periods for workers after vibratory equipment usage
18. Prolonged activities to have different sets of teams to be on standby for resting reasons

Page 4 of 7 19/04/21 5:28 PM


Risk Assessment as per DEFL Pure & Residual Matrices & Pipeline Works Risk Assessment v1. DOCUMENT NUMBER: DEFL-HSEQ-
with respect to AS/NZS ISO 31000 20220310
REVISION NO.: 3
1. Preventative checks on machines/ vehicle engine before dispatching to site. No further controls required.
1. Oil and fuel leakage from generator/ vehicle
17 SPILLAGE AND LEAKAGE 12 1 1 1 2. Preventative checks on boat engine before dispatching to site. 1 1 C
2. Oil and fuel leakage from boat engine.
3. Refilling to be done when engine is turned off
1. Struck by deteriorating concrete abutments on 1. Minimize working near deteriorating concrete conditions. 1. Full-time supervision by TOTAL &
beams and piles. 2. Carefully analyze the sections before working in such areas. Contractorpersonnel.
2. Objects ejected when using power tools. 3. Use of hard hats and clear safety glasses is a must i.e., PPE is compulsory 2. All entities must participate well.
3. Mounted brackets fall due to less 4. Be gentle and considerate when using power tools.
manpowerand mechanical support upon 5. Identify the mass of the brackets before installation so that enough manpower is provided.
installation process. 6. Ensure bracket is properly mounted with bolts, nuts and tightened properly.
4. Pipes falling due to less or weak supports 7. Pipes are to be lifted when the mechanical supports are properly fixed.
STRUCK BY FALLING/ when doing the lifting process. 8. Pipes are to be lifted with certified and tested chain blocks or lifting slings taking into
18 5 3 3 9 2 18 B
FLYING OBJECTS 5. Pipes rolling from the mounted bracket consideration the maximum load ratings.
supports even after successful lifting operation. 9. Once pipes are successfully lifted and placed to its suit location, ensure that there is zero
6. Fall of materials from ports area near relief provision or chance for it to roll from its original position. Ensure U bolts are installed and tightened
pools due to operations. before releasing any supports.
7. Fall of heavy suspended loads 10. Ensure appropriate personnel are aware of the works carried out under wharf.
11. No personnel to be always present under any suspended Loat

1. Have a proper traffic management plan showing the work section and the locations of sign boards No further controls required.
1. Inappropriate or excessive speed and signals to be placed when different work is done at certain locations
2. No clear communication between the “STOP” 2. Training the personals properly when it comes to signaling and guiding traffic
and “GO” sign workers guiding traffic, may create 3. High level of visibility should be available at the workstations
confusion among drivers leading to accidents 4. Utilize speed breakers at locations of exposure of bridge beam gaps
3. Vehicle factors – such as braking, handling 5. Adhere to FPCL/FPTL traffic rules (movements and limits)
Traffic accidents /
19 and maintenance 12 1 1 1 1 1 C
collisions
4. Adaptation to FPTL/FPCL traffic movement
5. Poor road user eyesight
6. Emission of harmful gas from vehicles
affecting health of the workers

1. Crane or Hiab has been set up on soft When preparing any work method statement for a lifting operation, it is important that the statement: 1. Full-time supervision by TOTAL &
orsloping ground. 1. Can be easily understood by persons involved in the lift Contractorpersonnel.
2. Crane or Hiab has been overloaded making 2. Only include information that is directly related to the lift 2. Continuous reminder is required.
itunstable. 3. No person enters the zone where a suspended load may fall 3. Consistent follow-up required.
3. Safety-systems have been ignored or 4. All lifting operations are undertaken by a competent person 4. All entities must participate well.
overridden for example the use of hydraulic 5. Where applicable, a pre-lift briefing is undertaken with all crane crew members to review the
supports. relevant risk
4. Crane or Hiab contacts power lines 6. Tag lines are used to prevent the pendulum motion of a load, unless their attachment presents
5. Not using the recommended load rating lifting additional risk
belts to lift the assigned load 7. Loads are carried as near to the support surface as practicable.
6. Unskilled Hiab truck or crane operator 8. Loads do not exceed defined working load limits of plant and equipment.
7. Being within the turning circle of the Hiab 9. Operators of lifting plant conduct a pre-start check of all plant and equipment to be used
truck or underneath the crane load 10. A crane or hoist shall not to be left unattended unless the following actions, where applicable,
8. Ignoring the use of personal protective have been taken:
equipment for example the use of hardhats, - All loads have been removed from the hook
safety harness and reflective vests -The hook has been raised to a position where it is safely clear of other operations, hooked back or
STRUCK BY LOAD/ 9. No hook locker for Hiab otherwise appropriately secured
20 DAMAGE TO UTILITIES/ 12 3 4 12 11. Check for operator and vehicle certificates. 2 24 B
BODY INJURIES. 12. Ensuring proper load chart is standardized with respect to distance away from crane and angle
load
13. Ensuring proper communication for example the use of hand signals or walkie talkie
14. Barricading the crane operation area with the appropriate warning tapes
15. Loads are carried as near to the support surface as practicable
16. Reliable and tested communication method is in place between all personnel involved in lifting
operations
17. Appropriate/ functional hook locker to be installed.
18. Duty of care taken to transfer equipment to pontoons and pipe floaters
19. No personnel to to be manually assisting with lifting once load is on the crane
20. No personnel to be under the load at any time
21. Area where load is rested must not be damaged during movement. No impact generated
movements during transfer.
22. Ensure harness is used when hook is to be attached to any large item by personnel

1. Adhere to TSUNAMI sirens. No further controls required.


2. STOP WORK and follow the evacuation plan effectively.
21 TSUNAMI 1. Rough and high tides from TSUNAMI 12 1 1 1 1 1 C
3. Assemble at the appropriate assembly site.

Page 5 of 7 19/04/21 5:28 PM


Risk Assessment as per DEFL Pure & Residual Matrices & Pipeline Works Risk Assessment v1. DOCUMENT NUMBER: DEFL-HSEQ-
with respect to AS/NZS ISO 31000 20220310
REVISION NO.: 3
1. Welding and fabrication consumables through 1. Having a separate bin to dispose all consumables and recess materials. No further controls required.
welding works 2. Hydrotested water to be released safely (non-hazardous dye used)
WASTE AND SCRAP 2. Improper disposal of used welding rods,
22 [ENVIRONMENTAL grinding and cutting discs 12 1 1 1 1 1 C
HAZARD] 3. Improper disposal of cut steel due to
modifications.
4. Hazardous dye used for hydrotest
Entered HSEQ
Initiator: Co-assessor(s): Validated by: Re-evaluated after project completion by:
Database by:

Name(s):
HSEQ :Ravikesh Singh Engineer: Amitesh
Chand

Date:

Signature(s):

Page 6 of 7 19/04/21 5:28 PM


Risk Assessment as per DEFL Pure & Residual Matrices & Pipeline Works Risk Assessment v1. DOCUMENT NUMBER: DEFL-HSEQ-
with respect to AS/NZS ISO 31000 20220310
REVISION NO.: 3

Page 7 of 7 19/04/21 5:28 PM

You might also like