Method Statement For Block Work: Project Title Project No. Client Consultant Main Contractor Title
Method Statement For Block Work: Project Title Project No. Client Consultant Main Contractor Title
M/s. National Engineering Bureau M/s. Majed Al Kazem M/s. Gulf Asia Contracting Co. LLC
Proposed (B+G+P+9 Floor+ Roof)
PROJECT TITLE Residential Buildings on Plot No. 6312126 & 6319922 at Dubai Hills Estate,
Dubai, U.A.E.
PROJECT NO. 21-1891
CLIENT M/s. Majed Al Kazem
CONSULTANT M/s. National Engineering Bureau
MAIN CONTRACTOR M/s. Gulf Asia Contracting Co. LLC, Dubai.
TITLE:
CONSULTANT
NAME DESIGNATION SIGNATURE DATE
APPROVAL
APPROVAL STATUS:
Code 2 Revise and resubmit; Work may proceed subject to incorporation of comments indicated.
CONTENTS
CONSULTANTS: CLIENT: CONTRACTOR:
Dubai Hills Residential
Development Proposed
(B+G+P+9 Floor+ Roof)
Residential Buildings on Plot No. 6312126 &
6319922 at Dubai Hills Estate, Dubai, U.A.E.
M/s. Mimar Engineering Consultant M/s. Musabbeh Rashid Musabbeh Al Fattan Al Falasi M/s. Gulf Asia Contracting Co. LLC
Title: Method statement for Block work Document No: 02700-MDS-STR-GAC-ME-7871-022 Rev 00
1. PURPOSE
2. REFERENCES
3. ACCESS/EGRESS
4. PERSONAL RESPONSIBILITY
5. METHOD DESCRIPTION
6. QUALITY CONTROL
7. PLANT & EQUIPMENTS
8. ATTACHMENTS
8.1 INSPECTION & TESTING PLAN
8.2 SAFETY AND RISK ASSESSMENT
1. PURPOSE
The purpose of this Method Statement is to describe the measures and ways of
completing block work on this project. The works shall be carried out in compliance
with the drawings and project specifications.
CONSULTANTS: CLIENT: CONTRACTOR:
Dubai Hills Residential
Development Proposed
(B+G+P+9 Floor+ Roof)
Residential Buildings on Plot No. 6312126 &
6319922 at Dubai Hills Estate, Dubai, U.A.E.
M/s. Mimar Engineering Consultant M/s. Musabbeh Rashid Musabbeh Al Fattan Al Falasi M/s. Gulf Asia Contracting Co. LLC
Title: Method statement for Block work Document No: 02700-MDS-STR-GAC-ME-7871-022 Rev 00
2. REFERENCES:
Project Specifications
Material Approval
Drawings Issued for Construction
Approved Shop Drawings
DM approved Drawings
Project Quality plan
Project Safety Plan
3. ACCESS/EGRESS:
Adequate access and egress should be provided to the site. Access will be through
designated entrance and exit pathways only.
4. PERSONNEL RESPONSIBILITIES:
Project Manager
Construction Manager
Project Engineer
Site Engineer
QA/QC Engineer
Safety officer
Surveyor
Site Foreman
Skilled crews
Helpers
5. METHOD DESCRIPTION
5.1 General
M/s. Mimar Engineering Consultant M/s. Musabbeh Rashid Musabbeh Al Fattan Al Falasi M/s. Gulf Asia Contracting Co. LLC
Title: Method statement for Block work Document No: 02700-MDS-STR-GAC-ME-7871-022 Rev 00
a. Store masonry units on elevated platform or pallet in a dry and firm level ground
b. Away from vehicular traffic to avoid contamination.
c. Blocks to be stored as near as possible to the work, keeping re-handling
minimum.
d. Store sand materials where grading and other required characteristic can be
maintained and avoid contamination or inclusion of other materials is prevented.
e. Store cementations materials on elevated platform, under cover, and in dry
locations.
f. Store masonry accessories including metal items in an enclosed and dry location
to prevent corrosion and accumulation of dirt.
g. Block shall be handled properly to prevent damage.
5.3 Methodology:
a. The masonry units will be supplied by the approved manufacturer and will comply
the requirement of ASTM C140.
b. The masonry walls shall be as shown on approved drawing and schedule.
c. Setting out of Block work shall be made as per drawing and inspected by
consultant.
d. For site batching of mortar mix, mixer machine shall be used.
e. It is good to have dampen the masonry units before laying, and to lay the mortar
beds in shorter lengths to reduce rapids loss of water from the mortar through
evaporation before the next course is being laid.
f. As the masonry blocks is being erected, lay stainless mesh reinforcement in the
mortar joints at every 2nd layer.
g. Stiffener column shall be provided in the middle of block work for increasing the
strength and stability.
M/s. Mimar Engineering Consultant M/s. Musabbeh Rashid Musabbeh Al Fattan Al Falasi M/s. Gulf Asia Contracting Co. LLC
Title: Method statement for Block work Document No: 02700-MDS-STR-GAC-ME-7871-022 Rev 00
a. Block Mortar shall have mix proportion complying with ASTM 270 as specified in
Volume 2 Part I Section 8, Masonry in the division of 2.3
b. Mixing shall be carried out by means of manual mixer and a measuring box shall
be used to ensure compliance with the design mix.
c. Freshly mix mortar shall be protected at all times to avoid contamination and
prevent excessive evaporation.
6. QUALITY CONTROL
6.1 Inspection
M/s. Mimar Engineering Consultant M/s. Musabbeh Rashid Musabbeh Al Fattan Al Falasi M/s. Gulf Asia Contracting Co. LLC
Title: Method statement for Block work Document No: 02700-MDS-STR-GAC-ME-7871-022 Rev 00
8. Attachments.