Professional Documents
Culture Documents
GOLDEN SCOP PHOTOS Construction Complete Checklist PDF
GOLDEN SCOP PHOTOS Construction Complete Checklist PDF
(MMBS)
Need 9927 and
Section B - Equipment-MMBS (NA Section if Expansion Cabinet is utilized) 9712 Examples.
Internal cabling is dressed and secured. (Make sure cables terminated to the Alpha ASMI unit are neatly routed and
secured)
Velcro must be
used for all fiber
cables and bend
radius is not
exceeded
Position of ASMI
must be correct
based on cabinet
configuration
because it affect
thermals.
BBU is properly racked and grounded.
ASIA Ground
GPS cable is properly connected per Installation MOP.
GPS Cable at
Splitter. Install per
MOP
Excess fiber and DC Cabling spooled and secured neatly with velcro straps.
Cables should be
spooled in cable
management tray
or GPS tray.
Installation above
ASMI violates
thermals because
of missing blank
plate
Section C - Fiber Distribution Box
Junction box is
Third breaker rail is properly installed when applicable (Make sure the power cables are labeled)
delivered with rail
installed.
Should be either 6
or 4 AWG
Should be 1/0
AWG
Should be updated
with door
Fiber Assignment Sheet (graphic) is attached inside position,
and corrected as necessary to show correct termination of fiber at
patch panel. Existing DC Distribution Schedule has been updated with new RRUs.
breaker amperage,
technology, sector,
and equipment
being powered
Termination details
in MOP
All exposed conduits are rigid galvanized steel (RGS). Conduit fittings are threaded. Final connections to cabinets are with
liquid tight flexible metallic conduit in lengths not to exceed 6 feet. Attachments to cabinets are made with metallic
gasketed threaded hubs or condulets. (Please show the entire length of the conduit run from one cabinet to the next. Also,
make sure all conduit are supported properly)
Cabinet anchor bolts are installed per Installation MOP. (Please show all 4 cabinet anchor bolts)
Expansion /top hat cabinet - Properly grounded (Ground lugs must be two hole lugs w/inspection windows and no-ox
applied b/w the lug and cabinet)
There should be no
open knockouts
There should not
be any gaps
between connector
and cabinet.
Equipment doors open fully, equipment and personnel access routes are clear.
Should be 4
rectifiers.
Internal cabling is dressed and secured. (Make sure the cabling in cabinets are neat and secured properly)
ASIA Ground
BBU (Base Band Unit) is properly installed and grounded (Show the ASMI units grounded properly)
ASIA Ground
GPS Connected
Verify FYGM
Grounding
Excess fiber spooled and secured neatly with velcro straps.
Cables should be
spooled in cable
management tray
or GPS tray.
Installation above
ASMI violates
thermals because
of missing blank
plate
AC circuit breaker at PPC is correctly sized and AC circuit directory has been updated
All exposed conduits are rigid galvanized steel (RGS). Conduit fittings are threaded. Final connections to cabinets are with
liquid tight flexible metallic conduit in lengths not to exceed 6 feet. Attachments to cabinets are made with metallic
gasketed threaded hubs or condulets. (Please show the entire length of the conduit run from one cabinet to the next. Also,
make sure all conduit are supported properly)
TOP HAT Cabinet Expansion Cabinet
Must be secured
within 18" from
cabinet and 36"
after.
Flex should be no
longer than 6' per
run and everything
else must be rigid.
Section E - Equipment- GPS (NA Section if new GPS not installed)
Fiber/power transition (cable bundles) are properly supported within 18" of breakout enclosure (Show at both ends of the
hybrid)
Breakout Cylinder properly mounted in accordance with Installation MOP (Please show breakout cylinder at both ends of
the hybrid cable)
Back of Antenna/RRU. View of full sector array showing jumpers properly supported maintaining proper bend radius. All
equipment properly mounted and grounded for all technologies.
Grounding
Antenna(s) are installed properly with specific hardware. Antenna make, model, quantity and physical location are accurately as
represented in the drawings and RFDS. (Please show both antenna attached to the mounting brackets w/ the torque marks)
Power/Fiber cables are installed and color coded per intstall MOP at MMBTS, RRUs, and any intermediate points (i.e. wall
penetrations, pulls boxes, etc.) (Make sure the fiber octis ports are in a locked position)
Verify tower top jumpers are supported at no greater than 18" intervals from the connectors & every 24" thereafter.
(Please show the path of the cables supported properly from the antenna)
Fiber Jumper interface is properly installed and secured (IP/MPO, MFC, ODC)
Sector verify ground wire lugs are two-hole, long barrel, and are sized for the ground wire. No-Ox or other anti-corrosive
has been applied between the lug and ground bar.. (Show the ground lug at the ground bar being to the antenna)
Sector verify ground lugs are crimped per the vendors recommendation with no deeply nicked or broken wire strands, and
that the wire insulation termination is within 1/8" of the barrel. (Show the ground lug at the ground bar crimped properly)
Antenna Azimuth information has been verified against RFDS with AAT upload in SV task 4134 [465] (+/- 3 degrees)
(Provide photos of the AAT tool attached to the antenna and a screenshot of the measurements)
Provide
documentation also
when using the
Sunsight Equipment
Antenna Downtilt & Roll information has been verified against RFDS with AAT upload in SV task 4134 [465] (+/- 1 degrees)
(Provide photos using the AAT tool showing the tilt and roll or using a 2ft smart level)
Fiber tests are verified complete and passing after RF review contained in SV task 4134 [465] (Provide the PDF of the End
to End Power Meter Test and the Fiber Scoping Test)
Upload to
Talonview in PDF
format
Section AMOB – Alpha/Beta/Gamma
AMOB OVERALL DOOR CLOSED (Make sure the AMOBs are labeled)
AMOB GROUND
INSIDE AMOB FIBERS N POWERS AND GPS PROPERLY ROUTED AND CONNECTED (Make sure the cables are properly
routed and supported)
Verify FYGM is
installed in AMOB
Dressed properly
and not close to
the door locking
mechanism so that
it does not get
pinched
INSIDE AMOB FIBERS N POWERS AND GPS PROPERLY ROUTED AND CONNECTED (Make sure the cables are properly
routed and supported)
INSIDE AMOB FIBERS N POWERS AND GPS PROPERLY ROUTED AND CONNECTED (Make sure the cables are properly
routed and supported)