Human Resources Management - Answers

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Tutorial (8)

Human Resources Management

1. Answer D
Explanation: When someone is given the job of project manager, they will have formal,
reward, and penalty power. But just having the position does not make the project manager
either a technical or project management expert.

2. Answer B
Explanation: Though the sponsor may help plan some of the activities (choice A) it is not the
sponsor's exclusive duty. Some project constraints (choice C) come from the sponsor, but
they should be considered necessary. The project management plan (choice D) is created by
the team and approved by the sponsor and other management. Since the project objectives are
stated in the project charter and it is the sponsor who issues the project charter, choice B is
the correct answer.

3. Answer D
Explanation: Problem solving normally takes more time, but it gets buy-in from everyone,
generating a more lasting solution.

4. Answer C
Explanation: Delaying the issue is called withdrawal.

5. Answer B
Explanation: The project schedule remains preliminary until resource assignments are
confirmed.

6. Answer A
Explanation: Time is shown on a schedule or bar chart. The responsibility assignment matrix
maps specific resources against the work packages from the WBS. On a resource histogram,
the use of resources is shown individually or by groups over time.

7. Answer A
Explanation: The responsibility assignment matrix maps who will do the work. The resource
histogram (choice B) shows the number of resources used in each time period. In its pure
form, a bar chart (choice C) shows only activity and calendar date. An organizational chart
(choice D) shows who reports to whom.

HR Management Page 1
8. Answer B
Explanation: Did you remember that in a matrix organization, the functional manager
controls the resources.

9. Answer A
Explanation: Theory Y is the belief that people can direct their own efforts. Know the
difference between Theory X and Theory Y for the exam.

10. Answer C
Explanation: The job of the project manager includes providing or obtaining project-specific
training for team members. This kind of training is a direct cost of the project.

11. Answer B
Explanation: Reward and expert are the best sources of power. Reward is not listed as a
choice.

12. Answer B
Explanation: The act of both parties giving something defines compromise.

13. Answer D
Explanation: Those having the problem should resolve the problem. Having had to crash the
critical path several times implies that team D has already dealt with these problems. In this
case, the two team leaders need to meet. The extent of this situation requires the project
manager's involvement as
well.

14. Answer D
Explanation: It is the sponsor's role to prevent unnecessary changes and to set priorities
between projects. The situation described in this question implies that such work is not being
done, and the project manager must therefore go to the root of the problem: the sponsor.

15. Answer A
Explanation: Self-fulfillment, or self-actualization, is the highest point in Maslow's hierarchy
of needs.

16. Answer B

HR Management Page 2
Explanation: Notice the phrasing of this question, "most likely NOT do" Expect to see
questions worded on the exam in ways that can cause you to misinterpret them. You will also
see questions about things we forget to do in the real world. "Who has time;' you might say,
"to determine if each problem is really solved?" One could respond with, "Who has time not
to do this? Who has time to deal with the same problem twice?" The final steps of problem
solving include: implement a decision, review it, and confirm that the decision solved the
problem.

17. Answer B
Explanation: Both parties are giving up something. This is a compromise.

18. Answer A
Explanation: As project managers spend 90 percent of their time communicating, the correct
choice must be A.

19. Answer C
Explanation: The staffing management plan describes when resources will be brought onto
and taken off the project.

20. Answer C
Explanation: What information should be sent to whom, and when information should be sent
is included in a communications management plan. How the team will ensure the satisfaction
of the needs for which is created is a quality management plan. Details about independent
estimates are covered in the procurement management plan. Plans for when and how human
resources will be brought into and taken off the project team is documented in the staffing
management plan.

HR Management Page 3

You might also like