Professional Documents
Culture Documents
Project Management Framework - Answers
Project Management Framework - Answers
1. Answer A
The project is temporary and unique. The project is completed when the defined project objective have
been met.
2. Answer A
3. Answer B
In a weak matrix, the functional manager has the power. Functional and Tight matrix are made-up
Terms.
4. Answer D
Project Constrains include Scope, Time, Quality, Risk, Resources and customers satisfaction. These
constrains must be balanced and controlled throughout the project life cycle.
5. Answer D
Explanation: The main drawback of the projectized organization is that at the end of the project, the
team is dispersed but they do not have a functional department ("home") to which to return.
6. Answer A
Explanation: In a functional organization, the project manager has the least support for the project and
has little authority to assign resources. Choices C and D are roles in a weak matrix organization.
7. Answer C
Explanation: Because a project done in a matrix organization involves people from across the
organization, communications are more complex.
8. Answer B
Explanation: In a functional organization, the functional manager is the team member's boss
and probably also the project manager's boss.
9. Answer A
Explanation: Choice D implies that the whole project repeats every month. Generally, the
only things that might repeat in a project are some activities. The whole project does not
repeat.
11. Answer A
Explanation: Application area knowledge is the best answer. The other choices are all
examples of application area knowledge.
12. Answer B
Explanation: There are many things the project manager could do. Choice A is not the best
choice, as the other project manager might not be an experienced mentor. His advice might
not be adequate to help this project manager. Choice C is reactive, while a project manager
should be proactive. Choice D is not the best choice. It would be helpful, but does not
specifically address the issues in this situation. If the PMO is contacted, the project manager
can receive the knowledge of many project managers, historical information from many
projects, and have the assistance of someone whose job it is to help.
13. Answer C
Explanation: Because the question talks about priorities among projects, this cannot be the
role of the
project manager (choice A), the project management team (choice B), or the project team
(choice D).
14. Answer D
15. Answer C
16. Answer A
17. Answer D
Explanation: The best answer is stakeholders, as their input is critical for collecting all the
lessons learned on each project. The term "stakeholders" includes all the other groups.
18. Answer C
19. Answer B
Explanation: Did you select choice C? If so, you missed the word "unrelated." Programs are
groups of related projects.
20. Answer B
Explanation: Lessons learned help to avoid future pitfalls and use the good ideas of past
projects. This leads to improvements in future projects.