Caso Puente Megaplaza

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

Design and Construction of a

Honduran Replacement Bridge


Li Zhenqiang The Megaplaza Interchange comprises two
Senior Engineer
Beijing, People’s Republic of China 131-ft-long (40 m) single-span bridges in an
and eastern suburb of San Pedro Sula, Honduras. The
Chief Engineer, Conhsa-Payhsa Group design used precast, prestressed concrete girders
San Pedro Sula, Honduras
to construct the bridges over the 131 ft (40 m)
span. A new design concept consisting of precast
concrete folded-plate abutments was used. The
precast, prestressed concrete girders required only
a transport truck and two cranes to erect each
68 ton (62 Mg) girder. In this paper, the authors
Rigoberto Ramírez C., P.E. present the design and construction highlights of
Structural Engineer the project.
Conhsa-Payhsa Group
San Pedro Sula, Honduras

T
he Megaplaza Interchange project comprises two
131-ft-long (40 m) single-span bridges in an eastern
suburb of San Pedro Sula, Honduras, a major city
near the Caribbean coast of Central America and on the
border of Guatemala. The bridges are part of a north-south,
secondary-circulating, main thoroughfare and were built
Juan Carlos Argüello, P.E. to overpass a major roadway, Prime 1A, a west-east route
Project Manager through San Pedro Sula (Fig. 1). The transportation project
Conhsa-Payhsa Group was constructed in eight months, from June 2003 to Febru-
San Pedro Sula, Honduras
ary 2004, with no significant interruption to daily traffic on
Prime 1A.

Design Background
The original design of the bridge (Design A) was com-
pletely finished in October 2002 and was offered for public
bid (Fig. 2). According to construction documents, the owner

70 PCI JOURNAL
received five competing bids from local
contractors. The project owners dem-
onstrated responsibility to the public
and leadership in contract administra-
tion through their use of a competitive
bid process for this transportation infra-
structure project. The Conhsa-Payhsa
Group submitted the winning bid and
was awarded the contract.
The owner had one stipulation re-
garding construction of the replace-
ment overpass bridges: Interference
with the heavy traffic on the Prime
1A roadway passing under the bridges
must not occur during construction. To
accommodate this mandate, the gird-
ers were delivered to the project site by
truck and erected at night (between the
low-traffic-volume hours of 10:00 p.m.
and 6:00 a.m.) or on Sundays. Even Fig. 1. West view of completed Megaplaza Interchange Bridge in San Pedro Sula,
with this site access restriction, the Honduras.
construction schedule dictated project
completion in only eight months.
The Conhsa-Payhsa Group per-
formed a value engineering analysis,
working with the owner and the con-
struction managers, with the objective
of finding ways to cut construction
time. Some of the joint decisions in-
cluded reducing bridge length from
150 ft to 131 ft (46 m to 40 m) and in-
creasing the main span from 108 ft to
131 ft (33 m to 40 m). Bridge design
improvements required modifying the
profile grade line and increasing the
vertical clearance limits (Fig. 3).
The most challenging aspect of the
bridge design was the 131-ft-long
(40 m) girders. Engineers were cre-
ative in developing a structural design
that incorporated precast, prestressed Fig. 2. Elevation detail of Megaplaza Interchange Bridge Design A.
concrete. As an alternative solution, Note: 25.4 mm = 1 in.
a change was proposed to the design
configuration: Use a completely pre-
cast concrete system for the super-
structure design. The new precast
concrete design was proposed to the
construction supervisor who, in turn,
proposed it to the owner. The com-
pletely precast concrete system was
ultimately accepted by the project
partners, and the contractor directed
the municipality of San Pedro Sula
to develop the necessary construction
documents for Design B. Construction
began in June 2003.
The volumes of concrete required
to construct the superstructures of the
bridges are shown in Table 1. Fig. 3. Elevation detail of Megaplaza Interchange Bridge Design B.
Note: 25.4 mm = 1 in.
July–August 2006 71
Table 1. Concrete Volume of Superstructure of Design B.
Total Concrete Volume
Designation Element Amount
Precast (m³) Cast-in-Place (m³)
Girder 6 139.22
Diaphragm 72 11.52 5.76
Deck panel 20 42.40
Wearing surface 54.12
Curb 10 6.50
Barrier 10 18.80
Barrier column 10 0.70 2.78
TOTAL 219.14 (78%) 62.66 (22%)
Note: 1.308 m3 = 1 yd3.

General Planning repetition and precast concrete forming Bridge Design


standardization and did not lend itself
The original interchange was skewed to the inherent efficiencies offered by The total length of each bridge is
(about 86 degrees) and composed of precast concrete manufacturing. 135 ft (41 m), with a total bridge
two separate, parallel, and independent After studying these original plans, width of 42.8 ft (13.1 m) and a clear-
bridges over the roadway, Prime 1A, in the authors concluded that, with only ance (from road surface to soffit of the
San Pedro Sula (Fig. 4a). The owner minor modifications, the most efficient bridge) of 18.4 ft (5.6 m). The depth
offered a simple plan for the new over- and economical structural solution of the bridge superstructure varies
pass, calling for two parallel bridges, would be a rectangular plan. Conse- from 6.7 ft (2.0 m) at midspan to 5.7 ft
also skewed 86 degrees, similar to quently, the owner agreed to the modi- (1.7 m) at the ends. A schematic dia-
the original structure. In the owner- fied replacement plan design because gram of the bridges is shown in Fig. 5.
supplied plan, the skewed structural ge- it offered advantages in quality and Because the longitudinal and trans-
ometry resulted in a lack of component scheduling (Fig. 4b). verse bridge girder geometries are

Fig. 4a. Design A plan view. Note: 25.4 mm = 1 in.

72 PCI JOURNAL
Fig. 4b. Design B plan view. Note: 25.4 mm = 1 in. Note: 1 mm × 0.03937 = 1 in.

critical to any good bridge design, it Precast Concrete Girder Design suitable shape and size. The design
was carefully determined that 7.2 ft of the beams for the Megaplaza Inter-
(2.2 m) center-to-center girder spacing Girder Geometry: The most impor- change Bridges called for a variable
across the bridge width was required tant aspect in the design of the precast depth along their length.
with a bridge section composed of six concrete bridge beams is the selection Each girder for the Megaplaza In-
transverse precast concrete girders. of a beam profile and cross section of terchange Bridge has a clear span
The bridge surface geometry called for
a 1.5% slope from the bridge centerline
to each side. Structural design is based
on HS-20 loading per the American
Association of Highway Transportation
Officials load-resistant factor design.
Precast, prestressed concrete girders
were fabricated by the Conhsa-Payhsa
Group and transported to the project
site by truck.

Description of
Superstructure
Each of the Megaplaza Interchange
Bridges consists of a superstructure
system that contains two basic pre-
cast concrete components and a cast-
in-place concrete slab on top. In the
completed structure, the entire bridge
cross section, shown in Fig. 6, has full-
thickness integral decks. Fig. 5. Schematic drawing of Megaplaza Interchange Bridges’ superstructure.

July–August 2006 73
signed at 9000 psi (62 MPa). On av-
erage, the concrete strength at the
time of prestressing strand release was
6300 psi (43 MPa). Typical concrete
compressive strength gain curves of
9000 psi (62 MPa) are shown in Table
2 Chart. The concrete design follows:
• Cement content: 1060 lb/yd3
(630 kg/m3);
• Water-cementitious materials
ratio (w/cm): 0.29;
• Tested slump of fresh concrete:
from 5 in. to 6 in. (125 mm to
150 mm);
• Maximum aggregate size: 0.4 in.
(10 mm); and
• Water-reducing and concrete-
Fig. 6. Basic precast concrete components of Megaplaza Interchange Bridge set–retarding admixtures.
superstructure. Note: 25.4 mm = 1 in.
Diaphragms
Composite diaphragms were placed
of 131 ft (40 m) and total length of determine the strand distribution of 26 ft (8.0 m) apart along the length
134 ft (40.8 m). The girders vary in the girder (Fig. 8). A total 47 strands, of the girders (Fig. 11). Two types
depth from 6 ft (1.8 m) at midspan to 5 ft 0.5 in. (13 mm) in diameter, were of diaphragms were used with the in-
(1.5 m) at both ends, with 2.5-ft-wide used in each girder. Forty-five strands tegral deck construction. One type
(760 mm) and 2.2-ft-wide (660 mm) were placed in the bottom flange, was the partially precast concrete dia-
top and bottom flanges, respectively. distributed in three rows of fifteen phragm slabs, fabricated by second-
The Conhsa-Payhsa Group developed strands each. Each row of prestressing ary concrete placements at the precast
and standardized the girder section strand is separated by a vertical space concrete facility. The gap between the
(Fig. 7). The basic design concepts of 1.6 in. (40 mm). diaphragm slabs was later filled with
for the girders and the ramps for the As shown in Fig. 9 and 10, strands cast-in-place concrete to a final mono-
Megaplaza Interchange project are the in each girder bottom flange are ar- lithic configuration. The diaphragms on
following: ranged in three rows as follows: Eight both exterior sides of the bridge were
• The ramps at both ends were strands in the top row are unbound for designed to support both the precast
backfilled at a 6% slope, and the their complete length (to reduce the concrete curb and the guard barrier pan-
girders were designed with slop- total compressive force in the bottom els. Vehicular barriers were assembled
ing top flanges to accommodate flange and to accommodate long-line by putting a small cast-in-place concrete
water runoff. Girder geometry prestressing beds); in the bottom row, column between two precast concrete
in longitudinal profile is a pen- four strands are unbound for a distance guard barrier panels (Fig. 10, 12).
tagon shape, with a 1.5% slope of 5 ft (1.50 m) at each end to reduce
in the top flange on each side; end cracking; and to minimize crack- Precast Concrete Deck Panels
• A reduction in the volume of ing, five strands in the middle row are The bridge deck was a composite
precast and cast-in-place con- unbound at each end for a distance of mixture of cast-in-place concrete on
crete for the superstructure was 10 ft (3 m). the top and a precast concrete deck
attained by sloping the girder There are only two prestressed panel in the bottom for an average total
top flanges. This also reduced 0.5-in.-diameter (13 mm) strands in depth of about 8 in. (200 mm). Twenty
the weight of bridge girders; each girder top flange. Each top flange precast, prestressed concrete deck pan-
• The heights of the ramps were re- has four 0.8-in.-diameter (22 mm) mild els were used on each overpass.
duced about 1 ft (0.3 m) and the steel reinforcing bars. Placement of two The precast, prestressed con-
length was also reduced about prestressed strands in the top flange is crete bridge deck panels were 34.3 ft
33 ft (10 m), reducing the total necessary to eliminate cracking in the (10.4 m) long and 6.3 ft (1.9) wide,
volume of ramp fill material by top flange and to control accurate posi- and each contained eight preformed
about 3140 yd3 (2400 m3); and tioning of the mild steel reinforcement holes to allow steel reinforcing bars to
• Web thickness of the girder is cage in the top flanges. Reinforcing project from the top of the longitudinal
5.9 in. (150 mm) for the middle and concrete placement in a precast girders into the deck topping. A cast-in-
section, with a girder span-to- concrete plant setting provide optimal place concrete topping reinforced with
depth ratio of approximately 22. quality control. 0.5-in.-diameter (13 mm) steel bars
Prestressing Strand Distribution: Concrete Design: The girder con- was placed on top of the bridge super-
The objectives of the study were to crete compressive strength was de- structure and averaged 4 in. (100 mm)

74 PCI JOURNAL
Fig. 7. Section drawing of the Megaplaza Interchange Bridge. Note: 25.4 mm = 1 in.

July–August 2006 75
Fig. 8. Size and location of prestressing strands in the Megaplaza Interchange Bridge. Note: 25.4 mm = 1 in.
76 PCI JOURNAL
thick on top of the deck panels and 8 in.
(200 mm) thick over the diaphragms.
The connection system between the
deck and the girders consisted of eight
openings on each panel for shear stud
connectors. The inside dimension of
each panel opening is 2 ft (0.60 m) long
and 1.8 ft (0.56 m) wide. After the cast-
in-place concrete for the topping was
placed, every structural aspect of the
superstructure of the bridge integrated
into a monolithic structure, including
the diaphragms and parapets (Fig. 5, 6).
Precast Concrete Curb and
Guard Barriers

A total of 16 precast concrete com-


ponents were used for the curb and Fig. 9. The 151-ft-span (46 m) girders during fabrication of the Megaplaza
the guard barriers on each side of Interchange Bridge.
the bridge. The curbs and the barri-
ers were supported on the girder dia-
phragms. Thus, the span lengths of diaphragms cantilevered transverse- After modification, a 13-ft-long (4 m)
the barrier and curb elements were ly 4.5 ft (1.4 m) on both sides of the double-tee steel form was adopted by
governed by the spacing of the dia- bridge. Precast, prestressed concrete the precaster to fabricate the curbs.
phragms (Fig. 13). curbs were used. Their size and shape This scheme produced economies in
The diaphragms were placed every depended on the steel forms from the precast concrete process and the
26.2 ft (8.0 m) along the girder, and the which the double tees were fabricated. production schedule.

Fig. 10. Precast concrete girder with inter-diaphragms for the Megaplaza Interchange Bridge at precast concrete assembly facility.

July–August 2006 77
Each bridge has five pieces of the 4.7 in. (120 mm) thick. The columns ture act monolithically. Small circu-
precast concrete barrier panels and six of the barriers, which were designed to lar precast concrete elements (11.8 in.
cast-in-place small columns on each resist lateral loads, were cast in place [300 mm] diameter and 19.7 in.
side of the bridge. The barrier panels between two barrier panels and con- [500 mm] high) were placed on the
are rectangular and contain a folded nected to the barriers and the curbs. tops of the column to provide an
plate at the top. Each panel is 4.3 ft This aspect of the construction was aesthetically pleasing structure
(1.3 m) high, 25.2 ft (7.7 m) long, and one of the keys to making the struc- (Fig. 13, 14).

Table 2. Compressive Strength Data for 62 MPa Concrete.


Beam No. Date of Production Compressive Strength (MPa)
1 Day 3 Days 7 Days 28 Days 60 Days
B-4 November 27, 2003 41.52 46.28 50.69 61.59 67.59
B-5 December 3, 2003 37.86 47.10 49.76 63.66 66.34
B-6 December 5, 2003 41.45 48.76 49.24 66.97 70.34
B-7 December 11, 2003 43.03 48.76 50.55 71.86 77.79
B-8 December 13, 2003 41.17 46.28 48.76 63.45 71.03
Average MPa 41.00 47.00 50.00 66.00 71.00
Note: 1 MPa = 145 psi.

Table 2 Chart. Typical strength gain curve for concrete used in Megaplaza Interchange Bridge, 62 MPa. Note: 1MPa = 145 psi.

78 PCI JOURNAL
Bridge Substructure
The majority of the Megaplaza In-
terchange project substructure is con-
structed of precast, prestressed con-
crete elements.

Pile Foundations
A total of 15 precast, prestressed
concrete piles were used at each end
of the bridge: 2 vertical piles and 13
battered piles. The piles each had a
20-in.-diameter (500 mm) circular
cross section with a 12-in.-diam-
eter (300 mm) circular-spun hollow
core and a total length of about 85 ft
(26 m) (Fig. 15).
Structural analysis, substrata soils
data, and the designer’s past experi-
ence dictated that the piles be driven
to a minimum depth of 66 ft (20 m)
below the surface of the road to achieve
sufficient capacity. Above the surface Fig. 11. Close-up of Megaplaza Interchange Bridge girders shows transverse
of the road, the piles are as high as 16 diaphragms.
ft (4.8 m). The piles were driven into
place with a diesel-powered hammer.
The hammer weight was dropped from
a height of 10 ft (3 m) at a rate of 59
blows per minute.
The superstructure included 42.7-ft-
long (13.0 m), 4.3-ft-wide (1.30 m)
pile caps utilizing a single 2.3-ft-deep
(0.70 m) precast concrete box unit. The
unit was assembled using precast, pre-
stressed concrete panels and reinforc-
ing steel cages that were fabricated
and partially assembled in a precast
concrete manufacturing plant about
9.3 miles (15 km) away from the bridge
construction site.
Supported on 15 piles, the precast
concrete pile cap box unit served as
stay-in-place formwork for the place-
ment of the cast-in-place concrete
within the box unit. The precast con-
crete box elements were designed to
act monolithically with the cast-in- Fig. 12. Megaplaza Interchange Bridge girder with side diaphragms at precast
place concrete to form the completed concrete manufacturing plant.
structure (Fig. 16).
used on many bridge projects. Option top slab. Two precast, prestressed
Abutment
B was a folded-plate retaining wall concrete wall panels are used for the
The type of abutment used for a with drainage ports (spillthrough). retaining abutments above the folded-
project may significantly affect the Precast, prestressed concrete plate retaining wall, and the upper
cost of the bridge, particularly on a folded-plate retaining walls are sup- panels are supported on the pile cap
single-span bridge. During prelimi- ported on a cast-in-place foundation. (Fig. 17, 18).
nary design considerations, two con- The folded-plate walls are assembled In comparing the concrete quantities
crete design options were considered. using precast, prestressed concrete flat required under abutment Options A and
Option A was a fully cast-in-place re- slab units, and cast-in-place concrete B, it was apparent that Option B provid-
taining wall, a typical abutment design is used for the joints and the inclined ed the more economical structure, using
July–August 2006 79
struction was employed successfully on
the Megaplaza Interchange project.

Girder Precast
CONCRETE Operations
A total of 12 girders were produced
in the 295 ft (90 m) long-line prestress-
ing bed. Both pieces (the girder itself
and the five diaphragms on each side
of the girder) were fabricated at the
same time using two different con-
crete placements. The girders, utilizing
thirty-seven 0.5-in-diameter (13 mm)
prestressing strands, were designed to
accommodate the ultimate capacity of
the prestressing beds.
Girder forms and stiffeners were
made of both steel and wood. A total
of three pieces of steel plate form were
used in the middle 118 ft (36 m) of the
girder. Wooden molds were used at
Fig. 13. Precast concrete curb and vehicular guard barriers of the Megaplaza the girder ends. The diaphragm molds
Interchange Bridge. were made of steel plates. Molds were
securely anchored to the concrete floor
of the long-line prestressing bed and
were adjusted to prevent form defor-
mation. Fabrication time for the two
girder pieces ranged from seven to
nine days, and they were steam cured
for an average of ten hours at about
175 °F (80 °C) (Fig. 9, 19).

Transporting and
Erecting Girders
Since the bridge is located approxi-
mately 9.3 miles (15 km) via main
roads from Bufalo—a southern Hon-
duran city containing a certified pre-
cast, prestressed concrete fabrication
plant—girder transport methods had a
significant impact on the type of struc-
ture chosen, method of construction,
and cost of the bridge.
Girders were delivered from the
plant to the job site by truck. Transpor-
tation of the one-piece girders, which
weighed almost 68 ton (62 Mg), re-
quired trucks that were 198 ft (58 m)
long and equipped with three axles and
a lowboy trailer in the front with two
Fig. 14. Megaplaza Interchange Bridge superstructure detail. Note: 25.4 mm = 1 in.
axles and a lowboy trailer in the back
with four axles (Fig. 20, 21).
Erection equipment for the precast
about 60% less concrete than Option concrete folded-plate wall panel with concrete elements consisted of both
A, assuming that all other construction spillthrough is an economical abutment a 99 ton (90 Mg) crane and a 68 ton
costs remained the same. The precast design. This rarely used abutment con- (60 Mg) crane for the girders and an-
80 PCI JOURNAL
other 44-ton-capacity (40 Mg) crane
for erecting the rest of the elements.
All of the concrete pieces were erect-
ed at night, between 10:00 p.m. and
2:00 a.m., to avoid interfering with rush
hour traffic on the main roads and to
minimize the potential for accidents.

CONCLUSION
The new 134-ft-long (40.8 m) gird-
er used in the Megaplaza Interchange
project has a variable section, in both
the longitudinal and transverse direc-
tions, that is unique in Honduras for
bridge construction of this span length. Fig. 15. The 20-in.-diameter (500 mm) Megaplaza Interchange Bridge piles in final
This girder geometry is well suited for position.
the project, with ideal structural behav-
ior for the application, because defor-
mation and cracking are minimized.
Long-line prestressing methods
consisting of fixed-bed technologies
were well suited for production of pre-
stressed concrete girders with 131 ft
(40 m) spans.
For the 131-ft-long (40 m) girder,
the use of 9000 psi (62 MPa) compres-
sive strength concrete was suitable for
an economical and efficient bridge
design and construction. The precast
concrete girders were cast in fixed steel
forms with maximum depth of 72 in.
(1830 mm) and web thickness of 5.9 in. Fig. 16. Precast concrete pile cap during erection at Megaplaza Interchange Bridge
(150 mm). site.
An all-precast concrete superstruc-
ture system was proposed for the Mega-
plaza Interchange Bridge. Diaphragms,
deck panels, curbs, and barriers were
all made of precast concrete, signifi-
cantly reducing time of construction.
An innovative structural solution
used precast folded-plate and precast
concrete panels at the bridge abutments,
permitting a reduced section and re-
duced earthmoving quantities. At the
present time, similar and identical struc-
tural designs are being used for other
bridges constructed in the city of San
Pedro Sula.

Acknowledgments
The success of this project is due to
the energy and talent of many people,
each of whom played a significant
part. These individuals include vari-
ous researchers, designers, manufactur- Fig. 17. Schematic of folded precast concrete plate retaining wall shows location of
ers, suppliers, and builders who played drainage ports (spillthrough) in the Megaplaza Interchange Bridge.
July–August 2006 81
Fig. 18. Plan details of pile foundation and pile section drawing for the Megaplaza Interchange Bridge. Note: 25.4 mm = 1 in.

82 PCI JOURNAL
important roles in bringing about a suc- ASP-Geotec, Tegucigalpa, Honduras:
cessful conclusion to the Megaplaza In- Amilcar Girón, Eddie Rivera,
terchange Bridge project. All are grate- Leonel Castillo, and Luis Rodríguez.
fully acknowledged by the authors. The Conhsa-Payhsa Group; San Pedro
authors also appreciate the constructive Sula, Honduras.
comments from PCI Journal reviewers Coordination and Administration:
regarding this technical paper. José Raúl Durón.
Design and Structural Analysis:
Conhsa-Payhsa Group, Engineering
Department; San Pedro Sula,
credits Honduras
Owner: Alcaldía Municipal M.S.P.S, Precast Concrete Producer: Gloria
San Pedro Sula, Honduras: Oscar Vásquez and Sabino Rivera.
Kilgore, Osmín Bautista, Ramón Concrete Research and Quality
Medina, and Marlon Diaz. Control: Hector Bustillo.
General Contractor: Conhsa-Payhsa, Erection and Construction: Rafael
Fig. 19. Unbonded strands for the
San Pedro Sula, Honduras. Garzona and Carlos Lara.
Megaplaza Interchange Bridge during
General Supervision: Consorcio Transportation: Oscar Vásquez. prestressing operations.

Fig. 20. Precast concrete girders for the Megaplaza Interchange Bridge in transit.

Fig. 21. A 131-ft-long (40 m) girder of the Megaplaza Interchange Bridge is erected.

July–August 2006 83
Preguntas a contestar:

1.- ¿Cual alternativa le parece más eficiente para el diseño del paso desnivel del
puente megaplaza?

2.- ¿Se podría diseñar una viga AASHTO para un claro en el caso de la alternativa A?
¿En caso de que no se pudiera diseñar que elemento propondría?

3.- ¿Se podría diseñar una viga AASHTO para un claro en el caso de la alternativa B?
¿En caso de que no se pudiera diseñar que elemento propondría?

4.- ¿Cuantas vigas tiene la alternativa B y que peralte tienen?

5.- ¿Qué porcentaje de la obra del puente es concreto prefabricado y concreto en sitio?

6.- ¿Qué elemento estructural del puente tiene el mayor volumen de concreto y cuál es
su valor?

7.- ¿Cuál es la resistencia a la compresión de los elementos prefabricados y colados en


sitio?

8.- ¿Cuánto es el claro del puente, según se diseño?

9.- ¿Qué tipo de cimentación se utilizo en el puente y porque piensa que se utilizo?

10- ¿Qué comentarios tiene con respecto al diseño final? ¿Que comentarios positivos y
por mejorar tiene usted con respecto a esta obra?

You might also like