Contract Account
(For the period 01-04-2021 to 31-03-2022)
74,37,500 1,88,300
To labour engaged By materials at site
3,61,700
To Direct Expenditure By work in progress A/C
28,27,500 28,27,500
BALANCE- SHEET
(As On 31st March 2022)
Particulars Amount Particulars Amount
Wages Accrued 2,40,000 Work in Progress
1,88,62,500
Direct Expense Accrued 24,000 (-) Cash Received from 8,62,500
Contractee 1,80,00,000
Materials In Stores 54,900
Materials at Site 1,88,300
Plant at Site 11,00,000