Please select the codename that you used for the first MOCK EXAM. This is a 100-item test covering
lessons on Drilling & Blasting and Mine Safety & Health . All the best!
Name *
Jay Bahulay
Blasting Engineer/Foreman
Chief Shotfirer
Shotfirer
Asst. Blaster
explosion
blast
detonation
deflagration
volcano eruption
Correct answer
deflagration
Energy Factor
Blasting Factor
Blasting Efficiency
Explosive Efficiency
Correct answer
Explosive Efficiency
You have blasted a 10m x 10m x 15m bench by an existing copper pit. 1/1
Allowing 15% overbreak, calculate how many truck loads each taking 75
cu.m. of space per loading will be required to move loose rock to the mill.
Assume 35% voids. *
15 units
20 units
21 units
22 units
An explosive material containing substantial amounts of oxidizers 1/1
dissolved in waste, surrounded by an immiscible fuel. *
Glycerin
Fuel oil
Ammonia
Emulsion
Energy Factor
Blasting Factor
Blasting Efficiency
Explosive Efficiency
Carbon
Aluminum
TNT
Sodium Nitrate
Correct answer
Sodium Nitrate
A smooth blasting method in which cracks for the final contour are 0/1
created by blasting prior to the drilling of the rest of the holes for the
blast pattern. *
Perimeter blasting
Pre-splitting
Smooth blasting
Secondary blasting
Correct answer
Pre-splitting
ammonium nitrate
sodium nitrate
calcium nitrate
Correct answer
Plain detonator
Electric detonator
Electronic detonator
Detonating cord is a thin, flexible plastic tube usually filled with 1/1
pentaerythritol tetranitrate(PETN) with a VOD of approximately _____
m/s, any common length of detonation cord appears to explode
instantaneously. *
4500
5600
6400
7200
Which of the following refers to the total number of lost time incidents 1/1
per million man-hours worked? *
severity rate
all of these
frequency rate
accident rate
incident rate
60.55 kbars
69.11 kbars
70.15 kbars
71.33 kbars
Cushion blasting
Perimeter blasting
Presplitting
Line drilling
Which of the following refers to the Fire Safety Code of the Philippines? * 1/1
RA 1899
RA 4274
PD 7076
PD 1561
PD 1185
Cushion blasting
Presplitting
Smooth blasting
Bench blasting
The explosive cartridge into which the detonator has been inserted. * 1/1
ANFO
permissible explosive
gelatin dynamite
g y
primer cartridge
Used for small blasting operation and involves small holes 2-3inch (50- 1/1
75mm) in diameter *
Presplitting
Line drilling
Cushion blasting
Smooth blasting
Primer
Dynamite stick
Blasting cap
Booster
Detonator
Correct answer
Booster
Maximum hole depth is usually 50 feet (15m). Depth between 20 and 40 1/1
feet (6 and 12) are recommended. *
Presplitting
Line drilling
Smooth blasting
Cushion blasting
It covers horizontal cut-and-fill, square set, open, shrinkage will drilled 1/1
holes 1.5 x 2.5 m deep normal to the face being advanced and parallel to
the free faces. *
Conventional Stoping
Longhole Stoping
Sublevel Stoping
Are suited for rectangular shaft where hand mucking is practiced. * 0/1
Centre cut
Burn cut
Sump cut
Wedge cut
Correct answer
Sump cut
10-20 in.
6-18 in.
12-24 in.
5-10 in.
Correct answer
6-18 in.
Are series of closely spaced holes, some are loaded and some unloaded 0/1
that, when fired, it pulverize and eject a cylinder of rock to create an
opening where the remaining burden can be broken *
Michigan Cuts
Cornish cuts
Shatter cuts
Correct answer
Four to six holes converge, not to a point as with the centre cut, but to 1/1
line forming a wedge-shaped rather than a pyramidal opening when
blasted. *
V-Cut
Drag Cut
Pyramid Cut
Burn Cut
A licensed blaster who will conduct the actual handling of explosives and 1/1
monitor its movement from the satellite magazine towards the blasting
site. He implements the approved blasting proposal for the particular
blast area & make revisions to suit the actual site configuration. Install
primers, initiation lines/connectors, & column charges into the blastholes.
He is responsible for the location of blasting barricades, traffic guards
and clearing of the affected areas. *
Blasting Engineer/Foreman
Chief Shotfirer
Shotfirer
Asst. Blaster
mudcapping
block holing
master shooting
bootleg
Correct answer
block holing
Does not involve drilling equipment but much bigger explosive charges. 1/1
The charge is primed and laid on surface of boulder and sealed/plastered
with clay. *
Blistering
Seismic Blasting
Pop Blasting
borehole pressure
detonating pressure
Pop Blasting
Blister Blasting
Seismic Blasting
It is the operation of drilling and blasting for hard toes that are formed 1/1
after loading of the blasted muck. *
secondary blasting
primary blasting
correctional blasting
cushion blasting
It consist of creating and blasting holes at any location with considering 1/1
environmental and stability concerns. *
Conventional Blasting
Pre-splitting
Line Drilling
Smoothwall Blasting
Typical powder factor for surface blasting in a high rock breakage 0/1
difficulty. (kg/cu.m.) *
0.1 – 0.18
0.18 – 0.34
0.34 – 0.57
0.57 – 1.14
Correct answer
0.34 – 0.57
It is the pounds of explosive per cubic meter (kg/m3) of rock; * 1/1
Energy factor
Explosive factor
Powder factor
Tonnage factor
The Rule of Thumb for bench blasting is that the hole depth-to-burden 1/1
ratio should be between _________. *
1-0 to 1.5
1.5 to 4.0
4.0 to 4.5
4.5 to 5.0
It is the distance between the rows of blastholes parallel to the major 0/1
free face. *
burden
spacing
sub-drill
collar distance
Correct answer
burden
Manufacturer’s License
Purchaser’s License
Possession License
Are not loaded and acts as a free face/void for the broken material. * 1/1
Reamer
Shothole
Easer
An iron or steel weight held on a wire rope that is dropped from a height 1/1
into large boulders to break them into smaller fragments. *
Headache ball
Break ball
Blast ball
Crash ball
96% AN and 4% FO
95% AN and 5% FO
97% AN and 3% FO
4% AN and 96% FO
Correct answer
96% AN and 4% FO
A term used to express the frequency of ground vibrations and airblast. * 0/1
Decibels
Hertz
VOD
Seismicity
Correct answer
Hertz
the wire connecting the electrical power source with the leg wires or 1/1
connecting wires of a blasting circuit. *
detonating wire
lead wire
copper wire
safety fuse
A cord which burns at definite speed and is commonly used to initiate a 1/1
plain or simple detonator or blasting cap is called? *
detonating cord
safety fuse
gun cotton
signal cap
A liquid fuel that can be combined with pulverized ammonium nitrate 1/1
prills to make a dense blasting mixture. *
Nitroglycerin (NG)
Nitromethane
Nitropropane
Nitrostarch
Primary Explosive
Secondary Explosive
Tertiary Explosive
Blasting Agent
The holes at the sides of a tunnel or drift round that determine the width 1/1
of the opening. *
Rib holes
Round
Relievers
Sill pillars
Nobel Philippines
Correct answer
Class A Explosive
Class B Explosive
Class C Explosive
Class D Explosive
Ammonia Gelatin
Permissible Explosives
Quarigel
Hydrogel
Semi-gelatinous permitted explosive with high weight strength & 1/1
medium density. Ideal for mechanized coal mines with thick seams. *
Ajax
Morcol
Dynagex
A3 Monobel
Slurries
Emulsions
Rig
Mounting
Drill bit
Correct answer
CO
CO2
NO
N2O
NO2
Weight of the explosive per unit length of borehole at a specified hole 1/1
diameter, expressed in pounds per foot. *
Package Density
Bulk Density
Loading Density
Specific Density
RA 9516
RA 1885
RA 8371
RA 9005
It is referred to as the change in loss? * 0/1
risk
incident
accident
injury
Correct answer
risk
aluminum
iron
carbon
potassium
copper
Which of the following does not belong in the group: * 0/1
line drilling
cushion blasting
secondary blasting
pre splitting
Correct answer
secondary blasting
12 hours
15 hours
24 hours
48 hours
The employer shall allow at least _________ period for orientation of 1/1
newly hired employees which shall be in the form of lecture and/or actual
observation of the working place where they will be assigned; *
one week
two weeks
three weeks
one month
12 hours
24 hours
48 hours
72 hours
In underground mining rules, the manager shall never allow the storage 1/1
of flammable liquids or materials within __________ radius of any main
entrance to the underground mine. *
25 meters
50 meters
30 meters
15 meters
5 meters
6 meters
8 meters
10 meters
Fractured and broken roof or back of mine workings shall be provided 1/1
with closely installed laggings of at least __________ thick and shall be
tightly blocked. *
2.5 cm
3.5 cm
4 cm
5 cm
6 cm
Extra precautions such as barricade and the like shall be taken when a 1/1
raise or other opening is within __________ of connection with a level or
other openings. *
6 meters
7 meters
8 meters
9 meters
10 meters
All ladders shall project at least _____ centimeters above every platform 0/1
of the ladderways unless convenient and sufficient handholds are
provided. *
50
60
70
80
75
Correct answer
60
All ladders shall be installed so far as practicable at an angle not greater 1/1
than seventy (70) degrees from the horizontal and shall have substantial
and adequate landing platform for every _______ vertical distance from
each other. If installed greater than seventy (70) degrees from the
horizontal, it shall have substantial and adequate landing platform for
every four and a half (4.5) meters vertical distance from each other. *
4.5 meters
5.5 meters
6.5 meters
9 meters
Manway compartments supported by square sets and exceeding 0/1
_________ in height shall be provided with center and cross bracings. *
20 meters
40 meters
30 meters
45 meters
Correct answer
45 meters
45 meters
50 meters
60 meters
55 meters
Trolley wires shall be sectionalized by proper switches at intervals not to 1/1
exceed _____________; switches shall also be installed in all branch lines
near the beginning. *
100 meters
150 meters
200 meters
300 meters
Shafts and winzes shall be provided with ladderways and handrails when 1/1
the inclination from the horizontal exceeds twenty ____ degrees. *
35
30
45
20
When men are working at the bottom of the shaft or winze, the cage, 1/1
skip bucket or other conveyance shall not be lowered directly to the
bottom but always stopped about ________ above until a signal is given to
lower them. *
3 meters
4 meters
3.5 meters
4.5 meters
5 meters
An underground and surface mine which employs a total of net less than 0/1
150 and 250 employees respectively is classified as an: *
Class A
Class B
Class C
Class D
Correct answer
Class A
It shall be prohibited to stay nearer than _____meters from the shaft 1/1
collar while waiting to board the cage. *
It shall be prohibited to work at the bottom of the shaft unless protected 0/1
by an adequate covering extending over the whole area of the shaft, with
sufficient space left for the passage of any sinking cage, skip or other
means of conveyance. The clearance of cover from the shaft bottom
shall be maintained at ___________ and twenty-seven (27) meters for
vertical and inclined shafts, respectively. *
15 meters
18 meters
25 meters
27 meters
Correct answer
18 meters
In the course of shaft or winze sinking and before drilling is commenced, 1/1
the ground shall be thoroughly washed over within _____ of any hole to
be drilled. If the ground to be examined is under water, it shall be drained
so as to expose the presence of all misfires and pockets. *
one meter
three meters
four meters
five meters
When hoisting of men is done through a shaft or winze or raise over 1/1
_____________ deep, proper safety device shall be installed to prevent
overwinding. *
15 meters
17 meters
20 meters
23 meters
35 meters
An underground and surface mine which employs a total of not more ···/1
than 50 and 75 employees respectively is classified as an: *
Class A
Small Scale
Class C
Large Scale
No correct answers
Safety catches or dogs of cages shall be inspected and drop tested with 1/1
load equivalent to its full capacity at least once every _________. *
one month
three months
six months
nine months
Mines employing _____ or more men underground at any one time shall 1/1
maintain a mine rescue organization capable of sustaining operation
during an emergency until outside help or assistance is available. *
50
75
100
150
250
When operating near power lines, the drilling machine and its mast or 1/1
derrick shall not be posted closer than 6 meters horizontally and
_________ vertically from such lines. *
1.5 meters
3 meters
3.5 meters
4 meters
4.5 meters
A Class “C” mine shall have at least: * 1/1
20 meters
25 meters
30 meters
35 meters
40 meters
Correct answer
30 meters
Trucks shall not be parked closer than 20 meters behind or in front or 1/1
_______ beside other trucks. *
2 meters
5 meters
10 meters
4 meters
6 meters
5 - 10 years
15 years
10 years
10 – 15 years
Correct answer
10 years
Width of a permanent two (2) lanes haulage road shall not be less than 1/1
______________ times the width of the widest hauling truck. *
two
three
four
five
Distance from the hydraulic monitor to the face shall not be less than the 0/1
height of the face. When working a dense ground liable to cause falls of
large lumps, distance shall be at least ___ times the height of the face. *
1.1
1.2
1.5
1.4
Correct answer
1.2
* ···/1
Option 1
No correct answers
20 kilograms
30 kilograms
40 kilograms
50 kilograms
Correct answer
50 kilograms
Underground magazines shall not be located within the radius of ____ 0/1
from shafts or other underground magazines *
50 meters
100 meters
150 meters
200 meters
Correct answer
100 meters
____________shall mean those that will prevent the injured from reporting 1/1
to work on the working day following the day of injury and thereafter. *
Prime cartridges shall be exploded or utilized within ______ hours after 1/1
these are prepared. *
12
24
48
72
Two-way radios shall be turned off within _________ from electrical 0/1
blasting cables or when entering an explosive magazine area. *
50 meters
100 meters
150 meters
200 meters
Correct answer
100 meters
Drilling shall not be done in or within ____ of old holes or bootlegs as 0/1
some explosives may still remain at the bottom or crevices of the hole. *
10 cemtimeter
15 centimeters
20 centimeters
30 centimeters
Correct answer
15 centimeters
The days lost per million man-hours worked. * 0/1
Correct answer
20 minutes
30 minutes
40 minutes
15 minutes
Correct answer
30 minutes
Every mining company shall have a properly trained central fire fighting 1/1
brigades and fire drill shall be conducted at least once in ___________. *
3 months
6 months
9 months
12 months
In a mine with 2,000 employees where 100 were on sick leave and 1/1
another 100 were on vacation leave for a particular month, there were 18
lost time accidents. Assuming the employees worked for 25 days (for 8
hrs) and no one worked overtime, what was the accident frequency rate
per million manhours? *
60
45
30
none of these
55
The total fatal and non-fatal lost time accidents per million man-hours 0/1
work. *
Correct answer
45 truckloads
48 truckloads
50 truckloads
52 truckloads
Correct answer
52 truckloads