LAPORAN HASIL KERJA MINGGUAN

LHKM
NAMA PROYEK : Kantor Soepomo - Jakarta
NOMOR : 02/LHKM/SUP/13/VI/2020 PERIODE TANGGAL : 12-Jul 2020 s.d. 18-Jul 2020
MINGGU KE : 3 BULAN JUL 2020 LAMP. DOKUMEN : 1. Absen & KTP Harian 2. Foto Pengukuran Opname Item Pekerjaan
3. Video dan LHK 4. Tiket Kasbon dan Kupon Lunas Barang

PRESTASI SEBELUMNYA PRESTASI SEKARANG PRESTASI SAMPAI SEKARANG


BOBOT KETERA
NO URAIAN ITEM PEKERJAAN VOL SAT
(%) NGAN
28-Jun s.d. 4-Jul 5-Jul s.d. 11-Jul 5-Jul s.d. 11-Jul
Bobot Progress Bobot Bobot
Vol Progress (%) Vol Vol Progress (%)
(%) (%) (%) (%)
Mdr Edi (lantai 3)
1 Herbel (HB) 1268.56 M2 10.76% 929.39 73.26% 7.89% 0.00 0.00% 0.000% 929.39 73.26% 7.89% Bagus
2 Hebel + Langsir 339.76 M2 3.75% 39.73 11.69% 0.44% 30.96 9.11% 0.342% 70.69 20.81% 0.78% Bagus
3 Kolom Praktis (KP) 957.7 M1 10.16% 484.20 50.56% 5.14% 0.00 0.00% 0.000% 484.20 50.56% 5.14% Bagus
4 Ring Balok (RB) 568.3 M1 6.51% 315.36 55.49% 3.61% 0.00 0.00% 0.000% 315.36 55.49% 3.61% Bagus
5 Plaster Aci (PA) (Semen Pasir) 116 M2 1.48% 0.00 0.00% 0.00% 0.00 0.00% 0.000% 0.00 0.00% 0.00% Bagus
6 Plaster Aci (PA) (Mortar) 2537.12 M2 30.14% 1,209.59 47.68% 14.37% 37.70 1.49% 0.448% 1,247.29 49.16% 14.82% Bagus
7 Plester Bagian Dalam (Mortar) 1602.6 M2 14.62% 199.02 12.42% 1.82% 0.00 0.00% 0.000% 199.02 12.42% 1.82% Bagus
8 Aci Bagian Dalam (Mortar) 1369.7 M2 11.62% 476.00 34.75% 4.04% 0.00 0.00% 0.000% 476.00 34.75% 4.04% Bagus
9 Finish Sponengan 872.68 M1 1.85% 0.00 0.00% 0.00% 33.00 3.78% 0.070% 33.00 3.78% 0.07% Bagus
10 Finish Openingan 589.91 M1 7.51% 0.00 0.00% 0.00% 22.40 3.80% 0.285% 22.40 3.80% 0.29% Bagus
11 Coran site mix 22.9 M2 1.46% 22.90 100.00% 1.46% 0.00 0.00% 0.000% 22.90 100.00% 1.46% Bagus
12 Pasang Bekisting (coran) 11.06 M1 0.05% 11.06 100.00% 0.05% 0.00 0.00% 0.000% 11.06 100.00% 0.05% Bagus
13 Langsir Matrial (coran) 19.1 M2 0.10% 19.10 100.00% 0.10% 0.00 0.00% 0.000% 19.10 100.00% 0.10% Bagus
100.00% 38.90% 1.14% 40.05%