Professional Documents
Culture Documents
The Principles of Act of Prevention in Construction Contract
The Principles of Act of Prevention in Construction Contract
The Principles of Act of Prevention in Construction Contract
International8. In that context, we can That assumption in turn has led to a A picture therefore emerges of an industry
consider the differing approaches taken in number of challenges to any effort made that has appreciated the potential impact
the drafting and interpretation of land- by the express terms to limit a contractor’s of the prevention principle, has dealt with
based and offshore construction contracts. right to rely on acts of prevention of an it in the drafting of its standard forms, and
–3– –4–
although we suggest that would be an
“The willingness to avoid the unsatisfactory outcome. There is no
impact of the prevention principle reasonable justification for the prevention
principle to be applied in different ways in
has driven an approach to different contracts.
interpretation that assumes that Our view is that it is the approach in
the contracting parties intended land-based construction that should
be preferred because of the strength of
to provide a complete code for the the underlying principle that a party to a
allocation of the risks of delay.” contract should not be able to rely on its
own wrong to the detriment of the other
contracting party. As it was put in Keating
In any event, the approach taken by on Offshore Construction and Marine
Leggatt J in Zhoushan appears to suggest Engineering Contracts14:
an opposing approach to that taken in the
land-based cases above. The willingness to “…the inability – absent clear words to
avoid the impact of the prevention principle the contrary – of party A to hold a party
has driven an approach to interpretation B to a stipulation if party A itself has
that assumes that the contracting parties prevented party B from complying with
intended to provide a complete code for the that stipulation is a basic presumption
allocation of the risks of delay. Therefore, compatible with ordinary rules of
if the contractor is delayed by anything construction. It is “obvious”. It is no
that is not a permissible delay, it is a different to the rebuttable presumption
In that context, the commonly held belief to the vessel. In those circumstances it At 34-35 he held: Notably, while article IV.3 of the contracts contractor’s risk. That approach has been when construing a contract, for example,
is that the builder cannot be prevented was alleged that the prevention principle (quoted at para 7 above) requires the followed in a number of partially reported that absent clear words a party will not
from delivering the vessel on time by virtue would apply, rendering time at large (and “There is accordingly a tripartite buyer’s supervisor to give prompt shipbuilding arbitrations13. give up their common law rights. The
of instructions because it has the power defeating the termination). Hamblen J classification of delays to the delivery of notice to the Yard of any construction suggestion that the modern shipbuilding
to refuse to make changes to the design rejected that analysis on the basis that the vessel. or workmanship which does not or will We are therefore in an awkward position in world is so different from other
and can ignore defects or punches issued there was an alternative mechanism ... not conform to the requirements of the jurisprudence where: commercial and construction spheres
by the purchaser as long as the builder through which a claim for an extension of the contract, the Yard is only obliged to that such an obvious starting point from
I think it plain that these three categories (1) it is accepted that the prevention
obtains the approval of class. time could be made. correct such nonconformity if it agrees which to construe a contract might be
of delay are intended to cover the whole principle applies in theory; but
field. It is natural to expect, and the with the buyer. To make the position even excluded is, it is suggested, wrong.”
There was therefore some surprise Thus, a trend began where judges and clearer, the clause continues:
expressed when Hamblen J concluded tribunals avoided implementing the wording of the definition in article VIII.4 (2) there is no appetite to apply it, and The path to an alignment of approaches
that the prevention principle applied to principle by seeking to find that the makes clear, that – once excluded delays contracts are construed to contain a
“In any circumstances, the BUILDER might be possible if there was a challenge
shipbuilding contracts generally in Adyard contract provided an adequate and are taken out of the picture and deemed complete code.
shall be entitled to proceed with the to the current assumption that the effect of
Abu Dhabi v SD Marine Services11: complete regime for the allocation of risk not to be delays at all – any delay which
construction of the VESSEL even if the application of the prevention principle
between the parties. is not a “permissible” delay is a “non- As a result, there has been no force
there exists discrepancy in the opinion was to set aside the whole of the machinery
“(1) In a basic shipbuilding contract, permissible” delay, and vice-versa.” driving a re-think of the standard forms of
between the BUYER and the BUILDER, of the contract relating to time, liquidated
which simply provides for a Builder to The key case after Adyard was Zhoushan contract as there was in the land-based
As a consequence, the judge found that without prejudice to the BUYER’s right to damages, and termination for delay by
complete the construction of a vessel Jinhaiwan Shipyard Co Ltd v Golden construction industry, even though it
any breach of contract that is not a caught submit the issue for determination by the setting time “at large”.
and to reach certain milestones within Exquisite Inc12. In that case, Leggatt J obviously would not be difficult to add to
by the definition of permissible or excluded CLASSIFICATION SOCIETY or arbitration
specific periods of time, the Builder is considered an amended SAJ form of the basic shipbuilding contract (usually The foreword to Keating on Offshore
delay must be a non-permissible delay for in accordance with the provisions hereof.
entitled to the whole of that period of contract and, after a lengthy analysis of the based on the SAJ) a catch all provision Construction and Marine Engineering
time to complete the contract work. various terms dealing with time which were which there is no relief. which ensures the contractual mechanisms
It is therefore plain that the buyer’s Contracts15, by Hamblen LJ and Sir Vivian
distributed in different places throughout supervisor has no power to delay the apply to all types of acts of prevention by Ramsey, indicates that there may be some
(2) In the event that the Buyer interferes Dealing with the prevention principle the owner.
the contract, concluded that there were construction of the vessel. …” judicial appetite for such a move:
with the work so as to delay its specifically in the context of delays
three categories of delay defined by the
completion in accordance with the allegedly caused by the conduct of the
express terms: It is important to note that this judgment “…There is also a very interesting analysis
buyers’ supervisors he held at 46:
agreed timetable, this amounts to was given in the context of an appeal of an “There is no reasonable of the principle of prevention and time
an act of prevention and the Builder (1) “permissible delay” being delays for arbitrator’s award on a matter of law. The at large, which has been developed
is no longer bound by the strict which the builder could obtain an
“I of course recognise the force of the
judge did not therefore have to determine
justification for the prevention from nineteenth century decisions. It
general presumption on which the Yard
requirements of the contract as to extension of time;
relies. When considering what reasonable the facts and whilst it is not clear whether a principle to be applied in different raises for consideration whether the
time. different approach would have been taken principle is correct. The proposition that
(2)
“non-permissible delays” being delays parties would be likely to have intended,
had there been a determination that an act
ways in different contracts.” an act of prevention by the employer
(3) The instruction of variations to for which the builder could not obtain however, it is necessary to descend from
generality and look closely at the specific of prevention by the employer had caused can, in the absence of an extension of
the work can amount to an act of an extension to time; and critical delay to the delivery of the vessel, time provision for that eventuality, lead
prevention.” consequences which would ensue if Time At Large
a particular interpretation is adopted. there is no indication from the analysis to the replacement of the agreed time
(3) various other types of delay which the itself that would suggest that it would have for completion by a reasonable time
Significantly, however, Hamblen J did not judge called “excluded” delays as they When the implications of a breach by the At present it is difficult to see how the
buyer of article IV are examined, I do not been. is startling. In Chapter 7, the authors
need to apply the prevention principle in were, under a separate term of the differing approaches between land-based
think it safe to assume that reasonable question whether that proposition is
Adyard. In that case the builder argued contract, effectively permissible delays. and offshore construction contracts will
commercial parties would have intended consistent with existing case law….”
that the extension of time mechanism be resolved. One possibility is that it is
broke down where the parties were unable that such a breach could permit the Yard determined that (as some commentators
To understand how such an approach
to agree to reasonable adjustments to to postpone the delivery of the vessel. have argued) the prevention principle
might be possible it is appropriate to look
the delivery date arising from changes should not apply to shipbuilding contracts,
first at the development of the orthodox
13 (see for example London Arbitration 15/18 (22 Jun 2018), London Arbitration 2/19 (17 Jan 2019), and London Arbitration 9/19 (14 Mar 2019) in the Lloyd’s Maritime Law Newsletter)
11 [2011] EWHC] 848 (Comm) at paragraph 242 14 2nd Edition at para 7-110
12 [2015] 1 Lloyd’s Rep. 283 15 2nd Edition
–5– –6–
Also, although Coulson LJ’s judgment marked “(1)”, but does not establish, or
in North Midland clearly supports the afford any support to, the second part of
orthodox approach, his conclusion that the passage which I have marked “(2)”.”
Lord Pearson agreed with Lord Denning’s
judgment in the Court of Appeal in Trollope There is therefore some doubt cast in the
merits further analysis. Lord Pearson in highest authority on the application of
fact held as follows: the prevention principle that time should
be set at large with the effect that the
“ On the other hand, the majority of the contractual completion date is replaced
Court of Appeal, Lord Denning M.R. and by an obligation to complete within a
Phillimore L.J., decided in favour of the reasonable time.
He reached that conclusion relying, in part, Shortcomings of the Orthodox Approach respondents. Lord Denning M.R. decided
on Peak Construction (Liverpool) Limited
Some criticism of the impact of the
first on a point of construction or perhaps Conclusion
v McKinney Foundations Limited19 from on a rule of law which he derived from
which he quoted the following passage: orthodox approach can be found in Dodd v Churton25. I will set out a passage Given that it has now been confirmed that
Leggatt J’s observations in Zhoushan and from the judgment of Lord Denning, the prevention principle is an implied term
“The employer, in the circumstances the introduction to Keating on Offshore inserting “(1)” and “(2)” to divide it into two in North Midland, a possible route forward
postulated, is left to his ordinary remedy; Construction Contracts21 provided by parts: would be for the implied term to have a less
that is to say, to recover such damages as Hamblen LJ and Sir Vivian Ramsey. In fact,
draconian effect.
he can prove flow from the contractor’s Sir Vivian Ramsey’s discomfort with the “(1) It is well settled that in building
breach […] Edmund Davies and Phillimore orthodox position can be traced back to his contracts — and in other contracts As the judicial criticism noted above makes
LLJ expressed similar views in their comments in Bluewater Energy Services v too — when there is a stipulation for clear, it is not obvious or necessary that
concurring judgments”. Mercon22: work to be done in a limited time, if an act of prevention should dissolve the
one party by his conduct — it may parties’ agreed extension of time and
Finally, Coulson LJ reached the conclusion “The principle is of some antiquity and be quite legitimate conduct, such liquidated damages regimes which, after
in North Midland, already set out above, has a surprising effect of the contractual as ordering extra work — renders it all, were agreed for the benefit of both
that “the application of the prevention obligations as to the time of completion” impossible or impracticable for the parties.
principle would mean that, on the other party to do his work within the
happening of that event, time was set at Stronger criticism can be found in
stipulated time, then the one whose Instead the implied term could simply
large” relying on the authorities above and Coleman J’s judgment in Balfour Beatty v
conduct caused the trouble can no permit an extension of time to the extent
the speeches given in the House of Lords Chestermount:
longer insist upon strict adherence to that critical delay was caused by an act of
in Trollope & Colls Limited v North West the time stated. He cannot claim any prevention not otherwise covered by the
Metropolitan Regional Hospital Board20. “The remarkable consequences of
penalties or liquidated damages for express terms of the contract.
the application of this principle could
therefore be as if…the contractor fell non-completion in that time.”
Coulson LJ noted that, when the case was Such an approach would take the sting out
in the Court of Appeal, Lord Denning MR well behind the clock and overshot the
“(2) T
he time becomes at large. The work of the prevention principle, as perceived
held: completion date…if the architect then
must be done within a reasonable by the offshore construction industry,
approach before considering some of the This was developed in Dodd v Churton17 by gave an instruction for the most trivial
time — that is, as a rule, the stipulated and encourage the differences between
shortcomings of that approach noted in Lord Esher MR in the Court of Appeal who “…. It is well settled that in building variation, representing perhaps only a
time plus a reasonable extension for the approach taken for on and offshore
other authorities. held: contracts - and in other contracts too day’s extra work, the employer would
the delay caused by his conduct.” construction projects to be reconciled.
- when there is a stipulation for work to thereby lose all right to liquidated
The Orthodox Approach “If the building owner has ordered extra be done in a limited time, if one party by damages for the culpable delay…what Then he said:
work beyond that specified by the original his conduct - it may be quite legitimate might be a trivial variation instruction
The first mention of the concept of time contract which has necessarily the time conduct, such as ordering extra work - would destroy the whole liquidated “That was established by Dodd v Churton.”
being “at large” as a consequence of an act requisite for finishing the work, he is renders it impossible or impracticable damages regime…”
of prevention appears to come from Holme thereby disentitled to claim the penalties for the other party to do his work within “Now Dodd v Churton does establish the
v Guppy16 in which Parke B in the Court of for non-completion provided by the the stipulated time, then the one whose It can also be seen that the cases relied first part of that passage, which I have
Exchequer held: contract. The reason for that rule is that conduct caused the trouble can no longer on in the development of the orthodox
otherwise a most unreasonable burden insist upon strict adherence to the time approach are not as clear-cut as they
“Then it appears that they were disabled would be imposed upon the Contractor.” stated. He cannot claim any penalties or have been presented. For example, Peak
from by the act of the defendants from liquidated damages for non-completion v McKinney23 was relied on by the judge
the performance of that contract. There In Multiplex v Honeywell Control Systems18. in that time.” in Multiplex, Jackson J commenting that
are clear authorities that if the party be Jackson J (as he then was) concluded: Phillimore LLJ expressed a view that was
prevented by the refusal of the other And went on to state that, “In the House consistent with the orthodox approach.
contracting party from completing the “In the field of construction law, one of Lords, Lord Pearson agreed with that However, Phillimore LLJ in fact said:
contract within the time limited he is consequence of the prevention principle section of Lord Denning’s judgment (see
not liable in law for the default ... It is is that the employer cannot hold the 607 E-H). Lord Guest, Lord Diplock and “I was somewhat startled when Mr.
clear, therefore, that the plaintiffs were contractor to a specified completion date, Lord Cross agreed with the speech of Gardam said in the course of his
excused from performing the agreement if the employer has by act or omission Lord Pearson.” argument that the moment any part of
contained in the original contract and prevented the contractor from completing the delay which has occurred can be
there is nothing to show that they entered by that date. Instead, time becomes at The orthodox approach rests on the attributed to the employer, then any
into a new contract by which to perform large and the obligation to complete jurisprudential foundation above. agreement as to liquidated damages
the work in four months and a half ending by the specified date is replaced by an However, a deeper dive into the case law disappears. Mr. Rankin conceded that
at a later period. The plaintiffs were implied obligation to complete within demonstrates that there is some dissent the summary of the effect of the cases…
therefore left at large. Consequently they a reasonable time. The same principle from other authorities and even some was correct save only in regard to
are not to forfeit anything for the delay.” applies as between main contractor and uncertainty within the examples relied subparagraph (d), which he suggested
sub-contractor.” on above as the basis of the orthodox went too far. I think his concession
approach. was right”.
–7– –8–