BILL OF

QUANTITIES
Item Description Unit Qty Rate Amount

WORK BELOW LOWEST FLOOR FINISH

Excavation Works

A Excavate oversite to remove top soil for


preservation average 100 mm deep M2 229 6.80 1,557.20

Excavate trenches to receive foundations


starting from ground level maximum depth

B Not exceeding 0.25 m M3 1 11.40 11.40

C Not exceeding 1.00 m M3 2 17.70 35.40

D Not exceeding 2.00 m M3 82 19.80 1,623.60

E Not exceeding 2.00 m, curved on plan M3 16 21.30 340.80

F Extra over for excavation in rock for strip


foundation starting from original ground level M3 10 33.60 336.00

G Allow for keeping the surface of the site and


the excavation free from surface water ITEM 2,183.89 2,183.89

H Disposal of excavated material, on site, in


permanent spoil heap, average distance 200
metres from site M3 330 8.00 2,640.00

J Filling to excavation with excavated material M3 195 4.75 926.25

K Filling to make up level average depth not


exceeding 250mm thick with broken bricks M3 30 66.50 1,995.00

L 50mm thick sand blinding laid on hardcore M2 195 3.50 682.50

Polythene Damp-Proof Membrane As


Described (Measured Nett, Rate To
Include For Laps and Joints)

M 0.25 mm thick polythene damp-proof


membrane laid under concrete bed M2 195 5.90 1,150.50

To Collection (RM) 13,482.54

BQ/1
Item Description Unit Qty Rate Amount

WORK BELOW LOWEST FLOOR FINISH


(CONT'D)

Concrete Works

Lean Concrete (Grade 15) As Described

A Blinding laid under strip footing not exceeding


100 mm thick M3 4 391.80 1,567.20

Plain In-Situ Concrete (Grade 30) As


Described In

B Strip foundation M3 22 485.00 10,670.00

C Slab 150 mm to 300 mm thick M3 166 485.00 80,510.00

Sawn Formwork As Described To

D Faces and edges of foundation 250 mm to


500 mm high M 166 29.50 4,897.00

Brickworks

Well Burnt Clay Bricks Bedded And Jointed In


Cement And Sand (1:3) Mortar Reinforced
With And Including "Exmet" Reinforcement
At Every Fourth Course Complete With
Approved Bonding Tie With One End Cast
Into Concrete And The Other End Built Into
Brickwork

E 113 mm thick brickwall M2 29 30.00 870.00

F 225 mm thick brickwall M2 81 45.00 3,645.00

To Collection (RM) 102,159.20

BQ/2
Item Description Unit Qty Rate Amount

WORK BELOW LOWEST FLOOR FINISH


(CONT'D)

COLLECTION

From Page BQ/1 13,482.54

From Page BQ/2 102,159.20

From Page BQ/3 281.60

To Main Summary (RM) 115,923.34

BQ/4