Professional Documents
Culture Documents
Belimo EV Case Study
Belimo EV Case Study
Problems
Improper water balancing due to rush in opening a
few years ago
1
AHU-BF-2 Photos
Fouling
2
Testing & Commissioning Procedures
Energy Valve
Maintain the manual balancing valve at its original
75%
M V
position, i.e. 75%
(1) T
Position Control
R AHU Set the EV to position control just working like a
T
XX normal control valve
S
Run this mode for a period of time & collect data
Flow Control
R AHU Turn the manual balancing valve to 100% open
T
XX Run this mode for a period of time and collect
S
another set of data
3
Phase 1 – Position Control
Findings
Control valve was responding to the DDC setpoint perfectly as both the valve position feedback curve and the DDC setpoint
curve were lying on the same line.
Valve cycling time was a little fast due to the DDC output signal from close-to-open or open-to-close occurred in every 30 mins.
Original design flow rate of the AHU was 11.5 l/s, but the measured maximum flow rate was approx. 40% only. However, the
return air temperature setpoint can still be maintained meaning that improper balancing was happening or the AHU, piping, and
control valve were oversized.
4
Phase 2 – Flow Control
DDC
Water
Setpoint
flow rate
Valve position
feedback
Findings
Flow control of the energy valve was enabled.
The activation of flow control changed the flow as the new control point responding to the DDC setpoint whereas the valve
position was becoming the dependent of the flow. Because of the equal percentage characteristics of the valve, the water flow
curve and DDC setpoint curve are different.
Design flow rate of the AHU was changed from 11.5 l/s down to 5.7 l/s, and the measured maximum flow rate was approx. 60%
of the new design flow. Again, return air temperature setpoint was still be maintaining even with lesser flow.
5
16.5
17.5
18.5
19.5
20.5
16
17
18
19
20
21
11/25/13 12:00:00 AM CST
11/25/13 2:10:00 AM CST
11/25/13 4:20:00 AM CST
11/25/13 6:30:00 AM CST
11/25/13 8:40:00 AM CST
11/25/13 10:50:00 AM CST
11/25/13 1:00:00 PM CST
11/25/13 3:10:00 PM CST
11/25/13 5:20:00 PM CST
11/25/13 7:30:00 PM CST
11/25/13 9:40:00 PM CST
11/25/13 11:50:00 PM CST
11/26/13 2:00:00 AM CST
11/26/13 4:10:00 AM CST
11/26/13 6:20:00 AM CST
11/26/13 8:30:00 AM CST
11/26/13 10:40:00 AM CST
11/26/13 12:50:00 PM CST
11/26/13 3:00:00 PM CST
11/26/13 5:10:00 PM CST
11/26/13 7:20:00 PM CST
11/26/13 9:30:00 PM CST
11/26/13 11:40:00 PM CST
11/27/13 1:50:00 AM CST
11/27/13 4:00:00 AM CST
11/27/13 6:10:00 AM CST
11/27/13 8:20:00 AM CST
11/27/13 10:30:00 AM CST
11/27/13 12:40:00 PM CST
11/27/13 2:50:00 PM CST
11/27/13 5:00:00 PM CST
11/27/13 7:10:00 PM CST
11/27/13 9:20:00 PM CST
11/27/13 11:30:00 PM CST
11/28/13 1:40:00 AM CST
11/28/13 3:50:00 AM CST
11/28/13 6:00:00 AM CST
11/28/13 8:10:00 AM CST
11/28/13 10:20:00 AM CST
11/28/13 12:30:00 PM CST
11/28/13 2:40:00 PM CST
11/28/13 4:50:00 PM CST
Findings
Water
flow rate
Even with very little water flow, return air temperature was
maximum flow rate was further dropped to approx. 30% of
6
Test Result
1 Nov 12 Nov 6 Dec
2013 2013 2013 Calculations
(from position control to flow control only)
7
Case Study Prince of Wales Hospital
Problems
The building and its many facilities have been operating
for more than 30 years, aging problem is obvious
8
Test Result
3 Jul 8 Jul 30 Jul
2014 2014 2014 Calculations
(from position control to flow control+DT manager)
9
Case Study MIT Hayden Library
Problems
The Hayden Library built in 1949 with total floor area of
approx. 14,000 m2. It’s air conditioning system contains
of numerous of FCU and 6 AHU.
Expectations
Resolve the low delta T syndrome
10
Field Test Result
11
Payback Period (MIT Hayden Library)
US Dollar
Operation & maintenance costs 0 0 0 -10000
-20000
Existing pumps energy saving
10,000 10,000 10,000
per annual Break Even
-30000
13.6 months
Existing chillers energy saving
30,000 30,000 30,000 -40000
per annual
-50000
Total (2,000) 40,000 40,000 Month
12