ACCOMPLISHMENT REPORT

JUNE 10, 2022

BATAAN:
CABLING TEAM: 2 TEAMS
POLE ERECTION:

Site Name: SAN PEDRO ST BRGY SAN PEDRO PDB HERMOSA BATAAN
TEAM LEADER : JOFER FERREROS
Site ID: 19301
Date started: Jun 9, 2022
Cabling Team:
24FOC: 900/4382 -0/4382
LCP: 0/6 - 0/6
NAP: 0/25 - 0/25
72F CLOSURE: 0/1 - 0/1
Activity: CABLE LAYING
Remarks: on hold by sir Lorenzo, there's no slot in OLT

Site Name: BRGY RD BRGY BALSIC HERMOSA BATAAN


TEAM LEADER : JOFER FERREROS
Site ID: 2580
Date started: Jun 9, 2022
Cabling Team: 1 team / 9pax
24FOC: 700/6270- 0/6270
LCP: 0/4- 0/4
NAP: 0/16 - 0/16
CLOSURE: 0/1 - 0/1
POLE ERECTION: 0/3 - 0/3
Activity: CABLE LAYING
Remarks: 2 BRANCHING DONE

Site Name: BRGY RD BRGY BACONG HERMOSA BATAAN


TEAM LEADER : John Paul Quiñano
Site ID: 19324
Date started: Jun 9, 2022
Excavation Team: 1 team
24FOC: 1000/2586- 0/2586
LCP: 0/3- 0/3
NAP: 0/11 - 0/11
CLOSURE: 0/1 - 0/1
POLE ERECTION: 0/3 - 0/3
Activity: CABLE LAYING
Remarks: MAIN CABLE LAYING

DEPLYOMENT PLAN
Date: JUNE 11, 2022
Date started: JUNE 9, 2022

Site Name: BRGY RD BRGY BALSIC HERMOSA BATAAN


Cabling Team: 1team/9 pax
Team Leader: JOFER FERREROS
Activity: Cable Laying

Site Name: BRGY RD BRGY BACONG HERMOSA BATAAN


Cabling Team: 1team/9 pax
Team Leader: John Paul Quiñano
Activity: Cable Laying