During reverse integration, the company acquires or partners with supply chain organizations who
supply raw materials, parts, or components for products. Future integration is a process in which the
company operates itself on the supply chain to reach the consumer, the end customer by opening retail
outlets or distribution centers.
SECTION B – PROBLEMS
Problem 1 (20 points)
The times required to complete each of eight jobs in a two-machine flow shop are shown in the table
that follows. Each job must follow the same sequence, beginning with Printing machine and moving to
Binding machine .
a) Determine a sequence that will minimize makespan time.
b) Construct a chart of the resulting sequence, and find the total idle time.
Period 1 2 3 4 5 6 7 8
Gross requirements 0 50 0 10 40 20 30 5
Week
0 1 2 3 4 5 6 7 8
Gross requirement
Scheduled receipts
On Hand Inventory
Net Requirement
Planned receipts
Planned orders