Professional Documents
Culture Documents
Auld - Design of Underground Plugs
Auld - Design of Underground Plugs
Auld - Design of Underground Plugs
1gD} 98 siveuBeR OZ 1 s60is Ng api sa}su0N eT | i T T a“ [ple : + i] ji i 1 | I | tae L a | 1 Ag eg 4 ' \ ! 1 7 To | / ' 1 | a aia ! | _ 4 OEEStrata end contact zone 4 grouting 12No holes per ring Service pipes to be fitted with glands ot each end Dawatrng pipe aye one ' I . LSS |e oatsom sine with een eee ants ontl| NOT debris gril. outbye ene Penmaes contest eft 3950 \ ited wth valve vate 1 \ . an (b) SECTION A-A Buikneod door with man access tube, Fabricated tn aNe segments trom 65mm thiek, Grade 63 steel Segments to be bolted together underground end cil joints fully protile welded ya, Sump with debris gril222 Auld National Coal Board North Selby Mine, England, 1982 (temporary consolidation plug) Cementation Mining Ltd are currently (December 1982) sinking two shafts at North Selby for the National Coal Board Selby project. Both shafts have reached the stage of sinking through the Ackworth Rock, which is a Coal Measures sandstone and an aquifer, No, 1 shaft sump (Fig.9) standing at —540.2 m (1772 ft) below surface level [hydrostatic pressure 5.4 N mm”? (783 lb in”*)]. The previous sump level in No. 1 shaft stood 13.8m (45 ft) above the present sump level and strata cover grouting was carried out from that level. During the period of strata cover grouting, problems of grout standpipe installation were experienced due to the poor rock conditions and deterioration and heave of the sump took place. The length of cover grouting was also long (over 40 m) whereas the preferred maximum length is approximately 30 m. To enable the wall of the cover grouting cone to be less prone to leakage at the lower level of treatment and to guarantee satisfactory grout standpipe installation, it was decided to sink to the — 540.2 level and install a concrete plug. This would be closer to the zone of strata requiring the major grout treatment and, by casting the grout standpipes into the plug, a pressure pad for the next cover of strata grouting could be provided. Due to the potential water inflows for sinking below the plug, it was necessary to install a pump lodge (Fig. 9) for stage pumping to surface. No choice of position was available for the pump lodge other than immediately below the last cast section of the shaft wall. At the time of placing the plug, shaft water inflow to the sump was approximately 11 litres s~! (150 gal min“). Fig. 10 shows the framework for supporting the grout pipes and the water control rising mains during casting of the plug. The concrete mix design for the plug is given in Table 3. Minimal heat of hydration existed in the concrete mass due to using the cement replacement material (Cemsave) and additional heat removal occurred through the rising mains and grout pipes. The Grade 55 concrete was the same as the shaft lining concrete. However, designing the plug on the basis of the seven-day cube test results 2 55 = 36.7N mm”? (5317 lb in) allowed pressurizing of the plug for water stopping, at the earliest opportunity. The benefit of the 28 day strength was taken for the wall bearing resistance. The recommendations given in the design calculation section for cylindrical plugs were followed for the plug design. Neglecting the bearing resistance of the tapered plug, the calculated punching shear stress for the concrete to rock interface was 0.89 N mm”? (129 Ib in~) and the pressure gradient 5.4/17.3 = 0.31 N mm? m™! (13.7 Ib in“? ft"'). Grouting up of the plug started from the bottom through 50 mm grout pipes installed in the rising mains. These pipes were grouted in, leaving the bottom free for injection into the gravel bed, and also secured by high-pressure flanges bolted together at the top of the rising mains. The bottom injection was phased to follow backwall injection of the shaft wall above the plug, and controlled using the standpipes as ‘tell-tales’ before closing off for final pressurizing. The shaft water make was reduced to approximately 0.45 litres s“! (6 gal min=') before final tightening up, this amount being predominantly from behind the shaft lining above the pump lodge. The pump lodge was restricted to a position close to the plug and remained aDesign of underground plugs 223 1200+ 200 overbreo Punp Lodge (a) section THROUGH SHAFT Strate grouting | Nandnnet bu | O12 3k Se (b) PLAN AT PUMP LODGE LEVEL Fig. 9. National Coal Board, North Selby Mine, England. Section through shaft, showing temporary consolidation plug (a) and plan at pump lodge level (b). Design and construction by Cementation Mining Ltd (1982). Information published by permission of the National Coal Board.224 Auld potential source for strata water to penetrate the shaft if it could not be scaled off by grouting. To enable the plug to be subsequently broken out without damaging the shaft wall, the bottom surface of the wall was painted with a bond breaking agent Setcrete 11 (Cementation Chemicals Ltd), the hanging rod ends were sleeved and two water bars incorporated, the inner one protected and the outer one sacrificial for plug sealing. Conclusions and recommendations ‘The first objective of this paper was to review underground plug design for the purpose of bringing the subject to prominence and more up to date, As an additional objective, design rationalization was attempted on the basis of current practice. The author considers the first objective to have been achieved. However, much more work needs to be carried out to quantify, in greater detail, strata leakage resistance in relation to plug length before the design procedure can be regarded as being completely rationalized. The philosophies of design included in the paper are based predominantly on the excellent work of Garrett and Campbell Pitt which was reported in 1958 and 1961. In addition to the normally accepted punching shear stress concept of design for plug interaction with the surrounding rock, they proposed a bearing stress concept which was related to the surface roughness and also carried out tests on both experimental and service plugs to quantify plug length in relation to leakage resistance. This is the only published work known to the author which relates to the latter factor. However, the work carried out by Garrett and Campbell Pitt is specifically applicable to the gold mines of South Africa where hard rocks of the quartzite type are encountered at deep levels and high water pressures are experienced (Fig. 4). The quoted data is not directly applicable to any other rock conditions, particularly those of the softer sandstone, limestone, marls and coal measures experienced in the UK (Fig. 4), where the aquifers are closer to the surface and the hydro- static pressures are much less. A study of the Garrett and Campbell Pitt work was essential in the paper to form the basis for applying their principles to other rock conditions, in line with modern construction Codes of Practice, as it appears that very little forward progress has been made in the subject of plug design during the last two decades. Considering the two parallel plug length design theories, one based on punching shear stress and the other on bearing stress, which have been proposed for resistance to horizontal thrust at the concrete to rock interface, it would appear that they are incompatible. Fig. 10. National Coal Board, North Selby Mine, England. General arrangement elevation of temporary consolidation plug (a) and sections A~A(b), B-B(c) and C-C(d) showing supporting framework for cast in grout stand pipes and water control rising mains. Design and construction by Cementation Mining Ltd. Information published by permission of the National Coal Board.226 Auld Comparing Equations 1c and 84, giving / = pb/4p,, and! = pb/2p,, respectively, using the value for py, = 3.75p,. from Table 1 indicates that the length based on permissible punching shear stress, as given by Equation 1c, will always be the longer by a factor of 1.875. Based on the concept of length being a priority for resistance to leakage, the bearing stress concept can be neglected in the design of parallel plugs. It should, however, be pointed out that although the permissible shear stress concept is recommended for determining length, in order to assist sealing by increasing the leakage resistance, the acutal strength will be greater because of the bearing action. ‘As already mentioned in the design calculations section, the two tapered plug design theories based on different bearing stress concepts are also not compatible. In this case, the longer length is given by the Garrett and Campbell Pitt rough surface-bearing resistance philosophy, as opposed to the smooth-faced wedge principle, and the former is therefore the recommended approach based on the longer length required for leakage resistance. With regard to the permissible stresses quoted in Table 1, the values of p., p, and p, are realistic for the current types of concrete now being used underground. The factor of safety equal to 4 used in connection with the p,, and p,, values at the concrete to rock interface is also probably realistic. However, care should always be taken to study rock strength and condition to confirm the values. It is interesting to note that the permissible shear stress values for the interface, which are quoted by South African practice (see p. 207), are less than the values recommended in Table 1. Although the South African values are not related directly to concrete or rock strengths, nor the rock condition, they result in longer plug lengths which err on the safe side for leakage resistance. On this basis, it can be seen that the stronger, and better quality, concretes now being employed in underground construc- tion will give shorter plug design lengths for strength but could have inherent leakage problems if sufficient length is not provided. At the present time it is not possible to define the exact length which is needed for sealing in relation to any particular ground conditions, The pressure gradient concept of Garrett and Campbell Pitt (1958, 1961) would appear to be a practical means for quantifying the resistance of rock to the passage of water through specific lengths but insufficient data is available as yet for general application of the principle. The allowable pressure gradient of 9.14 N mm? m7! (404 Ib in-? ft"), which the South Africans would accept for normally grouted rock, should not be adopted in the UK as it is based on plug to rock interface grouting pressures of 2 to 2} times hydrostatic. Such high pressures would not be adopted in the UK, values of 1.25 to 1.5 being more representative. Comparing the pressure gradients from the case studies with the Garrett and Campbell Pitt data in Fig, 4, the Sherburn Mine emergency plug value of 0.013 N mm~? m=! (0.59 Ib in™? ft”) is much less than that given by graph A [0.23 N mm~?m“? (20.8 Ib in” ft~)] showing it possessed a satisfactory leakage resistance without grouting. For the proposed precautionary plug the pressure gradient of 0.45 N mm~? m=! (19.9 Ib in”? ft!) was much less than that given by graph B [3.64 N mm~? m™! (161 Ib in”? ft)]. This indicates that although leakage would occur before grouting of the contact zone it would not leak after grouting the interface. The North Selby temporary consolidation plug was also in this category, possessing a greatly reduced pressure gradient [0.31 N mm? m7 (13.7 Ib in™? ft”})] than given by graph B.Design of underground plugs 227 It would appear that the Garrett and Campbell Pitt pressure gradient of 3.64 N mm=?m~ (161 Ib in ft”) could be used as an upper limit in the UK for plugs with the contact zones and strata grouted. However, much lower pressure gradients will result in the ability to seal off leakage more easily. Each plug scheme will generally be an individual design tailored to the particular situation. The above recommendations for pressure gradients should be used with caution and the rock leakage resistance in situ, which is associated with each design, must be investi- gated as thoroughly as possible prior to preparing any scheme. Successful plug design therefore, will rely heavily on the mining contractor’s experience and knowledge. Current concrete mix designs, using plasticizers for high workability, are much more easy to place and provide much tighter contact with the surrounding rock. Improved sealing will be achieved and leakage resistance much greater. Increased pressure gradients should be capable of being withstood by shorter lengths of plug and therefore, in future, the quantifying of such data by experiment and in situ monitoring is essential to progress and improve underground plug design. Understanding of plug mechanisms of resistance to horizontal thrust, when confined by the surrounding rock, can be enhanced by further studies into rock stresses resulting from excavations. Modification of these stresses during interface pressure grouting and the accompanying plug stressing needs to be investigated. Finally study of the effects of end pressures on such a combined stress system would lead to knowledge of how stresses are dissipated throughout the whole and possibly a clearer picture of the interface ultimate behaviour under load would emerge. Future research and experiment are therefore imperative to advance the state of the art of plug design. Acknowledgements The author wishes to thank Mr J.C. Black, Managing Director of Cementation Mining Ltd, for permission to publish the paper. Illustrations and details are included from the Selby New Mine Project and the author is indebted to Mr C.T. Massey, Deputy Director (Mining) - Selby Project, of the National Coal Board for his permission to use this infor- mation. Details of the Sherburn Mine incident are published by courtesy of British Gypsum Ltd, and thanks are due to Mr W.S. Gibson, Chief Mining Engineer, British Gypsum Ltd, and Mr R. Hird, the Mine Manager at the time of the incident, for their permission to include such data. Further thanks are extended to Mrs M. Mordue, who typed the manuscript. References Auld, F.A. (1979) Design of concrete shaft linings, in Proceedings of the Institution of Civil Engineers, Part 2, Vol. 67, Sept., pp. 817-32. Auld, FA. (1982a) Ultimate strength of concrete shaft linings and its influence on design, Proceedings of the Symposium on Strata Mechanics, Newcastle upon Tyne, Elsevier Scientific Publishing Company, Amsterdam, pp. 134-40.228 Auld Auld, F.A. (1982b) Concrete in underground works, Concrete Society Technical Report No. 105, The Concrete Society, London. Auld, F.A. (1982c) Concrete in underground works in The Concrete Society North West Region Symposium, Concrete in the Energy Industry. British Ready Mixed Concrete Association (1978) Register of Commercial Test Houses, 4th edn, British Ready Mixed Concrete Association Ltd, London British Standards Institution (1969a) BS 449:Part 2:1969, Specification for the use of structural steel in building, Part 2, Metric units, British Standards Institution, London. British Standards Institution (1969b) CP 114:1969, The Structural use of reinforced concrete in buildings, British Standards Institution, London. British Standards Institution (1970) BS 1881:Part 4:1970, Methods of testing concrete, Part 4, Methods of testing concrete for strength, British Standards Institution, London. British Standards Institution (1972) CP 110:Part 1:1972, The structural use of concrete, Part 1, Design, materials and workmanship, British Standards Institution, London. British Standards Institution. (1976) BS 5337:1976, Code of practice for the structural use of concrete {for retaining aqueous liquids, British Standards Institution, London. Comite Europeen du Beton — Federation Internationale de la Precontrainte (1970) International recommendations for the design and construction of concrete structures. Principles and Recommendations, FIP Sixth Congress, Prague. Fligge, W. (1967) Stresses in Shells, p. 24, Springer-Verlag, Berlin. Garrett, W.S, and Campbell Pitt, L.T. (1958) Tests on an experimental underground bulkhead for high pressures, Journal of the South African Institution of Mining and Metallurgy 59, 123-43. Garrett, W. S, and Campbell Pitt, L. T. (1961) Design and construction of underground bulkheads and water barriers, Paper presented to the Seventh Commonwealth Mining and Metallurgical Congress, Johannesburg. Jaeger, J.C. and Cook, N.G.W. (1979) Fundamentals of Rock Mechanics, 3rd edn, Chapman and Hall, London. pp. 86-8. Lancaster, F.H. (1964) Report on Research into Underground Plugs, Transvaal and Orange Free State Chamber of Mines Research Report No. 27/64. Manning, G.P. (1961) Reinforced Concrete Design, 2nd edn. Longmans, Harlow. Timoshenko, $.P, and Gere, J.M. (1961) Theory of Elastic Stability, 2nd edn, p. 49, McGraw-Hill Kogakusha Ltd, Tokyo.