Download as pdf or txt
Download as pdf or txt
You are on page 1of 13

11-1

11. Groundwater
The Groundwater Assessment examined the for the detailed design may vary from the
effects of the Project on groundwater quality, current design and this would need to be
availability and compliance with the State considered as well.
Environment Protection Policy (Groundwaters
Exposure of potential acid sulphate soils was
of Victoria).
identified as a risk to groundwater quality,
There are multiple groundwater aquifers in the however appropriate management measures
study area, ranging from less than 30 metres would reduce this to a low risk.
below the surface, to depths of 700 metres.
Effects on recharge/discharge processes were
Only the shallow watertable aquifers are assessed and, through incorporation of Water
considered relevant to the Project, as it is Sensitive Road Design principles, would be
unlikely that any construction or operation reduced to a low risk.
activities would impact on deep aquifers.
The risk that preferential groundwater
Excavation during construction intercepting seepage paths would be created, along the
shallow groundwater and the requirement to potentially relocated Gippsland Water
dewater was the key impact pathway of pipelines if groundwater is intercepted, would
concern. be managed through incorporating trench cut
offs which would reduce this to a low risk.
For most of the length of the proposed
duplication alignment, the road would be All residual risks of impact to groundwater are
constructed above the existing surface level, considered to be negligible to low.
requiring fill. In areas where there is shallow
groundwater and the proposed duplication
alignment would be constructed below the The EES evaluation objective relevant to
existing surface level, i.e. requiring groundwater is:
excavation, it is possible that groundwater
To protect catchment values, surface water and
would be intercepted.
groundwater quality, stream flows and floodway
Broad scale mapping produced by DSE/DPI capacity, as well as avoid impacts on protected
suggests that there are potential terrestrial beneficial uses.
Groundwater Dependant Ecosystems (GDEs)
This section discusses the groundwater environment
in the study area. These occur where the
within the project area, including the occurrence and
watertable aquifer is close to the ground
quality of groundwater. The potential impacts from
surface in low lying areas, such as the
the Project on groundwater have been assessed and
floodplains and morass of Blind Joes Creek
proposed management measures have been
(western outskirts of Rosedale), and also near
identified to minimise these impacts. More
prior streams and drainage lines between
specifically, this section:
Nambrok Creek and the western outskirts of
Kilmany. Impacts to potential GDEs as a result Characterises the groundwater in the study area
of dewatering during construction would be in terms of location, behaviour, and quality,
investigated further and managed through including its protected beneficial uses under the
implementation of a groundwater State Environment Protection Policy
management plan. (Groundwaters of Victoria).
Because the extent of excavation is limited Identifies potential effects of road construction
and the maximum depth of excavation would and operation activities on groundwater and any
be no more than three metres, it is expected potential effects of groundwater quality on road
that dewatering during construction would be construction and integrity.
limited and associated risks to groundwater,
Identifies measures to avoid, mitigate and
including impacts to potential GDEs, could be
manage any potential effects including any
adequately managed through implementation
relevant design features of the road or techniques
of a groundwater management plan.
for construction.
Depth to the shallow watertable aquifer has
Identifies residual effects of road construction
been derived from regional mapping for the
and operation activities on groundwater in the
purposes of this assessment. Depth to the
project area.
shallow watertable aquifer would need to be
more accurately determined through detailed This section is based on a Groundwater Assessment
investigations to inform the groundwater Report completed by GHD Pty Ltd (2011d), included
management plan. The extent of cut required in Appendix F.
11-2

11.1 Legislation and Policy


The legislation and government policies related to groundwater are discussed in Table 11-1.
Table 11-1 Relevant groundwater legislation and government policies
Legislation/Policy Description

Victorian

Extraction, use or disposal of groundwater for the Project would require approval under the Water
Water Act 1989 Act (1989). It is not yet known if this would be required for the Project, and as this would be
confirmed during the detailed design phase of the Project.

The Environment Protection Act 1970 (EP Act) regulates the discharge of emissions to the
groundwater environment by a system of licences and works approvals.
Environment Protection Act Any discharge into groundwater during the construction of the Project would be in accordance with
1970 the requirements of the EP
Act. The requirement for discharging of groundwater would be confirmed by the construction
contractor(s).
The SEPP (Groundwaters of Victoria) sets out segments of groundwater, based on salinity. Each
State Environment Protection segment has beneficial uses that must be protected. The background groundwater quality in the
Policy (Groundwaters of study area is variable, ranging from Segment A through C. The SEPP (Groundwaters of Victoria)
Victoria) specifies that groundwater quality must be protected to preserve the identified beneficial uses.
The Project must not adversely impact on the beneficial uses of the groundwater in the study area.

Consideration of potential ongoing impacts on


11.2 Study Area groundwater from the road after construction.
The groundwater assessment study area A detailed description of the reports reviewed and
encompasses the same area as the EES project area data that was accessed for the groundwater
(a corridor extending 100 metres north and south of assessment is included in Appendix F.
the road reserve boundary, widened in some areas
around Flynn and Kilmany, to encompass alignment 11.4 Existing Conditions
options considered). However, the study area also
considers the greater groundwater catchment area 11.4.1. Groundwater Depth
as relevant (refer to Figure 11-1 for the Within the study area there are multiple aquifers at
Groundwater Management Units (GMUs) in proximity varying levels. In some areas the depth to
to the Project). groundwater is up to 700 metres, and in other areas
it is much closer to the surface (less than 30 metres
11.3 Methodology below the surface). It is the shallow aquifers which
are most relevant to the Project as the likelihood of
To assess the groundwater environment within the
impacting on the deep aquifers is very remote.
study area, the following tasks were completed:
There are four groundwater management units
Review of existing reports on groundwater in the
(GMUs) in the study area: Sale, Denison, Rosedale
study area.
and Stratford. These GMUs are designated for
Review of the GMUs in the study area. management of the groundwater resources in the
area. Figure 11-1 shows the GMU boundaries in the
Review of existing groundwater bore information
study area. Table 11-2 provides a summary of the
from the State Groundwater Management System
GMUs in the study area.
(GMS).
A GMU may be a Groundwater Management Area
Analysis of the geology of the study area and
(GMA) or a Water Supply Protection Area (WSPA). A
examining the relationships aquifers on a local
WSPA is an area declared under the Water Act 1989
and regional scale.
to protect the groundwater resources through the
Interpretation of processes of groundwater development of a management plan. Within WSPAs,
recharge and discharge, as well as interactions caps or moratoriums on the issue of additional
between surface water and groundwater. extraction licenses are often present. An
unincorporated area is a region falling outside of a
Identification of beneficial uses of groundwater
GMA or WSPA.
within the study area.
The shallow aquifers between Rosedale and
Participation in environmental risk assessment
Traralgon East are outside of a designated GMU, i.e.
process.
unincorporated. This is likely due to the poor quality
Consideration of potential impacts on of groundwater (due to high salinity) in these areas,
groundwater during construction of the Project. resulting in a lack of groundwater use.
11-3

Table 11-2 Groundwater Management Units within the study area


GMU Type Depth Limit (metres) Aquifer Comment

Denison WSPA 0 – 25 metres Quaternary Relevant

Likely to be too deep to interact with the


Sale WPSA 25 – 200 metres Boisdale Formation
Project
50 -150 metres (Zone 1)
Latrobe Valley Coal Too deep/outside likely influence of
Rosedale GMA 25 – 350 metres (Zone 2)
Measures Project
200 – 350 metres (Zone 3)

Too deep/outside likely influence of


Stratford GMA >350 metres Latrobe Group
Project

Princes Highway, approaching Flynn’s Creek Road, westbound


11-4

Figure 11-1 Groundwater Management Units


11-5

11.4.2. Existing Groundwater Use


There are currently 14 licenced groundwater bores
within the study area. These bores are used to
supply irrigation water for dairy farms as well as
other industrial and commercial uses. Figure 11-2
shows the location of these bores.
There is potential for additional, unlicensed
groundwater bores in the study area for purposes
such as stock watering, or domestic use, as an
extraction licence is not required for these uses.

11.4.3. Groundwater Quality


The deep aquifers (greater than 30 metres below the
surface) in the study area are used throughout the
Gippsland Basin region for irrigation and industrial
uses. The salinity of these aquifers is generally low
and below 1,000 mg/L Total Dissolved Solids (TDS).
The shallow aquifers within the study area (less than
30 metres below the surface) have a salinity level of
between 1,000 mg/L to 4,500 mg/L TDS. Generally,
the higher salinity aquifers are located towards the
eastern and western ends of the study area, as
shown in Figure 11-3.
In the Macalister Irrigation District (MID), located to
the northeast of the study area, Southern Rural
Water operates a public groundwater pump network
of 19 bores. This pump network is used to manage
salinity in the groundwater and prevent land from
water logging and salinisation.
A summary of groundwater quality information from
45 bores within the study area is provided in Flynn’s Creek crossing, looking eastward
Table 11-3.

Table 11-3 Groundwater quality summary from bores within the study area
Analyte Unit Minimum Maximum Average

Total Dissolved Solids mg/L 143 7365 1071.3

Chloride mg/L 55 3900 527.4


Carbonate mg/L 7 23 15.3

Bicarbonate mg/L 0 507 118.6

Total Alkalinity mg/L 68 79 71.75

Sulphate mg/L 1 357 76.5

Nitrate mg/L 0.2 0.7 0.24

Calcium mg/L 2 63 15.75

Magnesium mg/L 1 288 41.85

Sodium mg/L 36 2245 320.8

Potassium mg/L 1 20 5.2

Iron mg/L 0.6 54 11.7

Hardness mg/L 27 1328 211.7

pH pH units 6.62 10.2 7.6

Electrical Conductivity µS/cm 267 12300 1917.3


11-6

Figure 11-2 Existing licenced groundwater bores in the study area


11-7

Figure 11-3 Groundwater salinity (Watertable Aquifer)


11-8

11.4.4. Beneficial Uses have a groundwater salinity of below 1,000 mg/L


The SEPP (Groundwaters of Victoria) defines TDS and commonly below 500 mg/L TDS. These
beneficial uses of groundwater, based on the aquifers are therefore in Segment A. The salinity of
existing groundwater quality. A summary of the shallow aquifers ranges from less than 1,000 mg/L
groundwater segments and corresponding beneficial (Segment A) to over 4,500 mg/L (Segment C).
uses is provided in Table 11-4. The deep aquifer
systems throughout the Gippsland Basin generally

Table 11-4 Groundwater beneficial uses for each segment


Segment

A1 A2 B C D
Use
0-500 501-1,000 1,001-3,500 3,501-13,000 >13,000
TDS TDS TDS TDS TDS

Maintenance of ecosystems

Potable water
Desirable

Acceptable

Potable mineral water supply

Agriculture, parks and gardens

Stock watering

Industrial water use

Primary contact recreation (eg. swimming/bathing)

Buildings and structures

Note: TDS had units of mg/L.

11.4.5. Groundwater Dependent of GDEs within the study area. This mapping shows
Ecosystems that there is the potential for GDEs consisting of
Groundwater Dependent Ecosystems (GDEs) are vegetation in areas where the groundwater level is
ecosystems that rely on groundwater to meet all or within 10 metres of the surface. Figure 11-4 shows
some of their water requirements. The Department the DPI mapping of GDEs within the study area.
of Primary Industries (DPI) has completed mapping

Princes Highway road reserve, south side, between Traralgon and Flynn
11-9

Figure 11-4 Groundwater Dependent Ecosystems


11-10

11.5 Impact Assessment 11.5.3. Existing Groundwater Use


A search of the Victorian Groundwater Management
The impact and risk assessment presented in the System identified stock and domestic, and licensed
following Sections were conducted on the proposed bores within the study area. An audit of bores prior
alignment only. to construction would identify other bores not
present on the GMS.
11.5.1. Dewatering
Cuts below water table along the proposed If the Project is likely to impact on a bore (or farm
duplication alignment, requiring dewatering (during dam), replacement may be required and would be
construction and/or operation phases) would subject to consent from Southern Rural Water.
potentially pose the greatest risk to the groundwater Potential impacts from construction dewatering or
environment. However, less than 10% of the construction water supply activities are likely to be
31 kilometres duplication is proposed to be below temporary with the duration dependent upon
the surface, and much of the cut is proposed to be construction progress. Mitigation measures would
less than 2 metres depth. The deepest cut would be available to reduce the risk of construction
approach 3 metres, however even this may not dewatering impacts. With increasing distance from
intersect the watertable or require significant the construction works, the risk of adverse impact to
dewatering. Therefore the likelihood of impact to other groundwater users is low. Ceasing pumping
groundwater would be low, and the consequences activities would likely result in groundwater levels
localised and short-term. recovering to pre-pumping levels.

11.5.2. Groundwater Quality Dewatering requirements for construction would be


The background groundwater quality in the study confirmed during the detailed design of the Project.
area is variable, ranging from Segment A through C. Groundwater bore locations and operational status
The SEPP (Groundwaters of Victoria) specifies that within the construction corridor would be confirmed
groundwater quality must be protected to preserve prior to construction and landholders would be
the identified beneficial uses. Therefore, the consulted regarding any potential impacts to
potential impacts of the construction and operation groundwater bores.
of the Project must be managed to protect the
existing beneficial uses of the groundwater in the
study area.
It is possible that construction and operational
activities could result in the contamination of
groundwater, impacting on groundwater quality
through:
Spillage, improper handling, storage and
application of hazardous materials during
construction.
Disposal of fluids or waste to groundwater.
Aquifer re-injection to mitigate drawdown and
related impacts, e.g. settlement.
Exposure of acid sulfate soils through dewatering
(refer to Section 10 for discussion of impacts and
mitigation for acid sulfate soils).
Incompatibilities with construction materials, e.g.
leaching from imported backfill.
Establishing hydraulic connection between two
aquifers of differing water quality which were
previously hydraulically isolated.
Spillage, road run-off during operation of the
Project.
The likelihood of these events occurring is low, as
the VicRoads standard environmental management
procedures address these risks. In addition, runoff
generated during operation of the road would be
captured in the road drainage system, largely
preventing the runoff from entering the groundwater Princes Highway near Nambrok Road (‘Nambrok curves’)
environment.
11-11

11.5.4. Groundwater Dependant environmental issues associated with the


Ecosystems (GDE) construction and operation of the Project. The
A GDE requires access to groundwater to meet all or methodology for this risk assessment has been
some of their water requirements. If the availability described in Section 4.6. A risk assessment report
of groundwater to a GDE is reduced, there is that explains the process in detail and contains the
potential for the ecosystem to be impacted. GDEs complete project risk register has also been included
are most likely to occur near waterways, where as Appendix P. The risk assessment was conducted
groundwater levels may be nearer to the surface on the proposed alignment only.
such as at Sheepwash Creek, Flynns Creek, Blind
Table 11-5 shows a summary for groundwater of:
Joes Creek and Nambrok Creek, as well as drainage
lines and minor waterways. Some excavation would The impact pathways identified.
be required near these waterways, with bridges to
A description of the consequence.
be constructed over the waterways (except for
Nambrok Creek). The depth of the cut and the In assessing the impact to groundwater, the
depth of groundwater in these areas is not majority of risks associated with the Project have
accurately known. This would be confirmed during been assigned a low likelihood of occurring, as much
detailed design and geotechnical testing prior to of the Project would be constructed above the
construction. Impacts on GDEs from dewatering existing grade and therefore there would be limited
activities during construction would be managed opportunity for direct interaction with the
through the development of a Groundwater groundwater environment. Management measures
Management Plan. As outlined in Table 11-6 the risk have been identified to protect and maintain
to GDEs from this project is considered negligible as groundwater availability and quality. Overall, it is
it is expected that there will be minimal changes to concluded that the risk to the groundwater
the groundwater/surface water environment. environment as a result of the construction and
operation of the Project would be low.
11.6 Risk Assessment
An environmental risk assessment was undertaken
on the preferred alignment to identify key

Table 11-5 Groundwater risks


Risk
Impact Pathway Consequence Description
No

Cuts below water table along alignment, requiring Dewatering drawdown impact to other groundwater users (e.g.
GW1
dewatering (construction and/or operation) irrigators, stock and domestic users)

Cuts below water table along alignment, requiring Groundwater dewatering discharge degrades surface water
GW2
dewatering (construction and/or operation) quality
Cuts below water table along alignment, requiring Dewatering /depressurisation consolidates compressible
GW3
dewatering (construction and/or operation) materials causing settlement and land instability

Cuts below water table along alignment, requiring Dewatering drawdown adversely affects surface water recharge
GW4
dewatering (construction and/or operation) and GDEs

Dewatering alters hydraulic gradients resulting in existing


Cuts below water table along alignment, requiring contamination plumes potentially being dislocated/moved
GW5
dewatering (construction and/or operation)
Interruption of existing groundwater remediation efforts

Cuts below water table along alignment, requiring Potential generation of acid plumes/mobilisation of heavy
GW6 dewatering (construction and/or operation). metals/aggressive groundwater, leading to attack on
Dewatering exposes acid sulphate soils (ASS) submerged steel /concrete structures (piles, services)

Contamination of groundwater from construction Impact to groundwater quality/ breach of SEPP (Groundwater
GW7 activities (e.g. spillage, dust suppression, construction of Victoria)
waste discharge) Impact to worker safety

Contamination of groundwater from operational


Impact to groundwater quality/ breach of SEPP (Groundwater
GW8 activities (road runoff, traffic accidents, stormwater,
of Victoria).
spillage)

New or increased groundwater accessions, altered groundwater


Ponding and retention of water associated with
GW9 flow patterns, new or exacerbated waterlogging and salinity
highway drainage (operation)
impacts

Construction earthworks removing impervious layers Site recharge enhanced increasing groundwater levels (water
GW10 (across site, floodplains, river crossings and logging, groundwater displacement) and or introducing
embankments) contaminants

Preferential groundwater seepage paths created and alter


GW11 Project pipelines constructed in saturated materials
seepage migration routes
11-12

Risk
Impact Pathway Consequence Description
No

Construction works create impervious ground surface


GW12 Reduced recharge to groundwater system
layers

Alignment of road passes through existing groundwater


bore location [east and west of Kilmany] or severs Requirement to compensate groundwater user, install
GW13 access for stock or irrigation infrastructure replacement bore (observation, stock, irrigation etc.)
Temporary loss of production
Use of groundwater for construction water supply

detail in Section 21. In some instances, additional


11.7 Environmental Management Project specific environmental management
Measures measures have been proposed to reduce risks.
VicRoads has a standard set of environmental Management measures specific to each identified
management measures which are typically groundwater risk, and the residual risk rating after
incorporated into their construction contracts for environmental management measures have been
road works and bridge works. These measures have applied, are outlined in Table 11-6.
been used as the starting point for the assessment
of construction related risks and are described in

Table 11-6 Groundwater environmental management measures and residual risk rating
Risks Residual Risk
Environmental Management Measures
Addressed Rating
VicRoads would conduct pre-construction geotechnical and hydrogeological investigations.
An assessment of groundwater level would be conducted in areas of cut.
A groundwater management plan and monitoring program would be developed and
implemented to address potential impacts to groundwater if encountered. The groundwater
management plan would include controls to prevent erosion and sedimentation associated
with groundwater management.
The construction contractor(s) would evaluate the options and financial implications for
management of waste groundwater in order to demonstrate the application of the waste
hierarchy. Alternative options for management or reuse of saline or potentially
contaminated groundwater may be considered based on EPA Victoria advice at the time of
management / reuse / disposal.
Measures to mitigate groundwater draw down impacts would include:
o Minimise dewatering required by micro-review of gradelines.
o Preconstruction investigations of groundwater (occurrence and quality),
particularly in proposed areas of cut, and establishment of baseline
conditions.
o Detailed design of cuts and ground support. Alteration of the
construction technique to reduce the need for dewatering. A variety of
engineering options are available, e.g. use of sheet piles / contiguous
GW1 piles. Negligible
o Careful design of the dewatering methodology, e.g. multiple closely
spaced bores may create a localized cone of depression.
o Increased construction effort, e.g. reducing the duration over which
dewatering may be required;
o Careful timing of the works to periods where water levels may be at their
lowest.
o Re-injection of the pumped groundwater between the excavation site
and impacted part to impart hydraulic control (aquifer recharge).
o Non-continuous pumping that may allow water level recovery during
pumping quiescence.
o Supplying any affected parties with an alternate water supply, e.g.
carting water, deepening the pump intake setting depth.
o Replacement of existing bores that are adversely impacted by
construction.
o Implementing a groundwater monitoring program.
Sufficient contingency must be incorporated into water treatment plans, monitoring
programs (environmental, safety) to cope with the ingress, management, treatment and
disposal of contaminated groundwater water that may be unexpectedly encountered.
Comply with section 1200.08 Erosion and Sediment Control of the VicRoads contract
GW2 specification. Negligible
As per GW1.
GW3 As per GW1. Low
11-13

Risks Residual Risk


Environmental Management Measures
Addressed Rating
A site specific investigation would be conducted during detailed design to identify likelihood
of subsidence.
As per GW1.
Contaminated materials would be managed as per the measures for geology and soils risks
G1 to prevent groundwater contamination.
GW4 Negligible
If required, an alternate water supply would be established to maintain environmental
water requirements, e.g. treated stormwater / road drainage could be redirected as a
replenishing or alternate water supply.
As per GW1.
GW5 Contaminated materials would be managed as per the measures for geology and soils risks Negligible
G1, G2, G3 and G4.
As per GW1.
Contaminated materials would be managed as per the measures for geology and soils risks
G1, G2, G3 and G4.
Minimise the dewatering influence near PASS materials (as per GW1).
Soil sampling and laboratory analysis would be conducted as part of the detailed design
GW6 phase confirm the presence of ASS. Low
Groundwater levels and quality would be monitored in all aquifers adjoining PASS materials.
Performance standards and action triggers would be established for:
- implementing remedial actions. Impacted or at risk areas / assets remediation can be
undertaken through pH adjustment, e.g. lime dosing.
- considering the need for artificial recharge.
Comply with section 1200.11 Fuels and Chemicals of the VicRoads contract specification.
GW7 Contaminated materials would be managed as per the measures for geology and soils risks Negligible
G1, G2, G3 and G4.
Contaminated materials would be managed as per the measures for geology and soils risks Negligible
GW8
G1, G2, G3 and G4.
Water Sensitive Road Design measures would be evaluated in the detailed design phase, as
GW9 Low
described in VicRoads Integrated Water Management Guidelines (August 2011).
A groundwater management plan and monitoring program would be developed and
implemented to address potential impacts to groundwater, if encountered.
Earthwork surface finish specifications specified to mitigate enhanced accessions
(preferential pathways for infiltration and groundwater movement).
GW10 Site would be rehabilitated with vegetation / grasses. Negligible
Grading would be conducted for erosion control.
Allowance would be made for subsidence with backfilled excavations.
Temporary access tracks would be removed and ground conditions rehabilitated.
As per GW1.
GW11 Apply pipeline construction measures (trench cut offs- or breakers) that mitigate risk Low
process, if groundwater is encountered.
As per GW1 and GW10.
GW12 Negligible

Confirm of bore locations (and operational status) within construction corridor and conduct
landholder consultation.
Construction groundwater supplies would be from licensed bores and subject to the
GW13 Southern Rural Water approvals process and/or groundwater trading rules / local Negligible
management rules.
Audit of landholders would be conducted of identified water supplies that may be impacted,
e.g. dams or bores.

You might also like