Professional Documents
Culture Documents
Trar Algon East Kil Many Groundwater
Trar Algon East Kil Many Groundwater
11. Groundwater
The Groundwater Assessment examined the for the detailed design may vary from the
effects of the Project on groundwater quality, current design and this would need to be
availability and compliance with the State considered as well.
Environment Protection Policy (Groundwaters
Exposure of potential acid sulphate soils was
of Victoria).
identified as a risk to groundwater quality,
There are multiple groundwater aquifers in the however appropriate management measures
study area, ranging from less than 30 metres would reduce this to a low risk.
below the surface, to depths of 700 metres.
Effects on recharge/discharge processes were
Only the shallow watertable aquifers are assessed and, through incorporation of Water
considered relevant to the Project, as it is Sensitive Road Design principles, would be
unlikely that any construction or operation reduced to a low risk.
activities would impact on deep aquifers.
The risk that preferential groundwater
Excavation during construction intercepting seepage paths would be created, along the
shallow groundwater and the requirement to potentially relocated Gippsland Water
dewater was the key impact pathway of pipelines if groundwater is intercepted, would
concern. be managed through incorporating trench cut
offs which would reduce this to a low risk.
For most of the length of the proposed
duplication alignment, the road would be All residual risks of impact to groundwater are
constructed above the existing surface level, considered to be negligible to low.
requiring fill. In areas where there is shallow
groundwater and the proposed duplication
alignment would be constructed below the The EES evaluation objective relevant to
existing surface level, i.e. requiring groundwater is:
excavation, it is possible that groundwater
To protect catchment values, surface water and
would be intercepted.
groundwater quality, stream flows and floodway
Broad scale mapping produced by DSE/DPI capacity, as well as avoid impacts on protected
suggests that there are potential terrestrial beneficial uses.
Groundwater Dependant Ecosystems (GDEs)
This section discusses the groundwater environment
in the study area. These occur where the
within the project area, including the occurrence and
watertable aquifer is close to the ground
quality of groundwater. The potential impacts from
surface in low lying areas, such as the
the Project on groundwater have been assessed and
floodplains and morass of Blind Joes Creek
proposed management measures have been
(western outskirts of Rosedale), and also near
identified to minimise these impacts. More
prior streams and drainage lines between
specifically, this section:
Nambrok Creek and the western outskirts of
Kilmany. Impacts to potential GDEs as a result Characterises the groundwater in the study area
of dewatering during construction would be in terms of location, behaviour, and quality,
investigated further and managed through including its protected beneficial uses under the
implementation of a groundwater State Environment Protection Policy
management plan. (Groundwaters of Victoria).
Because the extent of excavation is limited Identifies potential effects of road construction
and the maximum depth of excavation would and operation activities on groundwater and any
be no more than three metres, it is expected potential effects of groundwater quality on road
that dewatering during construction would be construction and integrity.
limited and associated risks to groundwater,
Identifies measures to avoid, mitigate and
including impacts to potential GDEs, could be
manage any potential effects including any
adequately managed through implementation
relevant design features of the road or techniques
of a groundwater management plan.
for construction.
Depth to the shallow watertable aquifer has
Identifies residual effects of road construction
been derived from regional mapping for the
and operation activities on groundwater in the
purposes of this assessment. Depth to the
project area.
shallow watertable aquifer would need to be
more accurately determined through detailed This section is based on a Groundwater Assessment
investigations to inform the groundwater Report completed by GHD Pty Ltd (2011d), included
management plan. The extent of cut required in Appendix F.
11-2
Victorian
Extraction, use or disposal of groundwater for the Project would require approval under the Water
Water Act 1989 Act (1989). It is not yet known if this would be required for the Project, and as this would be
confirmed during the detailed design phase of the Project.
The Environment Protection Act 1970 (EP Act) regulates the discharge of emissions to the
groundwater environment by a system of licences and works approvals.
Environment Protection Act Any discharge into groundwater during the construction of the Project would be in accordance with
1970 the requirements of the EP
Act. The requirement for discharging of groundwater would be confirmed by the construction
contractor(s).
The SEPP (Groundwaters of Victoria) sets out segments of groundwater, based on salinity. Each
State Environment Protection segment has beneficial uses that must be protected. The background groundwater quality in the
Policy (Groundwaters of study area is variable, ranging from Segment A through C. The SEPP (Groundwaters of Victoria)
Victoria) specifies that groundwater quality must be protected to preserve the identified beneficial uses.
The Project must not adversely impact on the beneficial uses of the groundwater in the study area.
Table 11-3 Groundwater quality summary from bores within the study area
Analyte Unit Minimum Maximum Average
A1 A2 B C D
Use
0-500 501-1,000 1,001-3,500 3,501-13,000 >13,000
TDS TDS TDS TDS TDS
Maintenance of ecosystems
Potable water
Desirable
Acceptable
Stock watering
11.4.5. Groundwater Dependent of GDEs within the study area. This mapping shows
Ecosystems that there is the potential for GDEs consisting of
Groundwater Dependent Ecosystems (GDEs) are vegetation in areas where the groundwater level is
ecosystems that rely on groundwater to meet all or within 10 metres of the surface. Figure 11-4 shows
some of their water requirements. The Department the DPI mapping of GDEs within the study area.
of Primary Industries (DPI) has completed mapping
Princes Highway road reserve, south side, between Traralgon and Flynn
11-9
Cuts below water table along alignment, requiring Dewatering drawdown impact to other groundwater users (e.g.
GW1
dewatering (construction and/or operation) irrigators, stock and domestic users)
Cuts below water table along alignment, requiring Groundwater dewatering discharge degrades surface water
GW2
dewatering (construction and/or operation) quality
Cuts below water table along alignment, requiring Dewatering /depressurisation consolidates compressible
GW3
dewatering (construction and/or operation) materials causing settlement and land instability
Cuts below water table along alignment, requiring Dewatering drawdown adversely affects surface water recharge
GW4
dewatering (construction and/or operation) and GDEs
Cuts below water table along alignment, requiring Potential generation of acid plumes/mobilisation of heavy
GW6 dewatering (construction and/or operation). metals/aggressive groundwater, leading to attack on
Dewatering exposes acid sulphate soils (ASS) submerged steel /concrete structures (piles, services)
Contamination of groundwater from construction Impact to groundwater quality/ breach of SEPP (Groundwater
GW7 activities (e.g. spillage, dust suppression, construction of Victoria)
waste discharge) Impact to worker safety
Construction earthworks removing impervious layers Site recharge enhanced increasing groundwater levels (water
GW10 (across site, floodplains, river crossings and logging, groundwater displacement) and or introducing
embankments) contaminants
Risk
Impact Pathway Consequence Description
No
Table 11-6 Groundwater environmental management measures and residual risk rating
Risks Residual Risk
Environmental Management Measures
Addressed Rating
VicRoads would conduct pre-construction geotechnical and hydrogeological investigations.
An assessment of groundwater level would be conducted in areas of cut.
A groundwater management plan and monitoring program would be developed and
implemented to address potential impacts to groundwater if encountered. The groundwater
management plan would include controls to prevent erosion and sedimentation associated
with groundwater management.
The construction contractor(s) would evaluate the options and financial implications for
management of waste groundwater in order to demonstrate the application of the waste
hierarchy. Alternative options for management or reuse of saline or potentially
contaminated groundwater may be considered based on EPA Victoria advice at the time of
management / reuse / disposal.
Measures to mitigate groundwater draw down impacts would include:
o Minimise dewatering required by micro-review of gradelines.
o Preconstruction investigations of groundwater (occurrence and quality),
particularly in proposed areas of cut, and establishment of baseline
conditions.
o Detailed design of cuts and ground support. Alteration of the
construction technique to reduce the need for dewatering. A variety of
engineering options are available, e.g. use of sheet piles / contiguous
GW1 piles. Negligible
o Careful design of the dewatering methodology, e.g. multiple closely
spaced bores may create a localized cone of depression.
o Increased construction effort, e.g. reducing the duration over which
dewatering may be required;
o Careful timing of the works to periods where water levels may be at their
lowest.
o Re-injection of the pumped groundwater between the excavation site
and impacted part to impart hydraulic control (aquifer recharge).
o Non-continuous pumping that may allow water level recovery during
pumping quiescence.
o Supplying any affected parties with an alternate water supply, e.g.
carting water, deepening the pump intake setting depth.
o Replacement of existing bores that are adversely impacted by
construction.
o Implementing a groundwater monitoring program.
Sufficient contingency must be incorporated into water treatment plans, monitoring
programs (environmental, safety) to cope with the ingress, management, treatment and
disposal of contaminated groundwater water that may be unexpectedly encountered.
Comply with section 1200.08 Erosion and Sediment Control of the VicRoads contract
GW2 specification. Negligible
As per GW1.
GW3 As per GW1. Low
11-13
Confirm of bore locations (and operational status) within construction corridor and conduct
landholder consultation.
Construction groundwater supplies would be from licensed bores and subject to the
GW13 Southern Rural Water approvals process and/or groundwater trading rules / local Negligible
management rules.
Audit of landholders would be conducted of identified water supplies that may be impacted,
e.g. dams or bores.